Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    12/17/2012
Contract ID: 120308   Estimate Number: 0004     Contract No: 810215
Residency: CLAREMORE (08300)   Estimate Type: Progressive     Account No: 404800

Project Number(s): SBR-266N(002)SB, SBR-266A(003)SB
Primary Job Piece No: 29061(04)
Contract Description: BRIDGE REHABILITATION I-44/SH-66: I-44 OVER SH-66 0.6 MILE EAST OF TULSA CL, AND SH-66 OVER ABANDONDED TURNPIKE 0.8 MILE EAST OF TULSA CL.
Primary County: ROGERS              
Name of Road: I-44/SH-66              
Prime Contractor: PBX CORPORATION              
    P.O. BOX 644              
    SAPULPA , OK   74067              
Surety Company: WESTFIELD INSURANCE COMPANY              

Date Let: 07/19/2012 NTP Effective Date: 10/01/2012 Pay Period: 12/01/2012  TO  12/15/2012
Date Awarded: 08/06/2012 Date Work Began: 10/08/2012 Original Contract Time: 60
Date Contract Executed: 08/17/2012 Date Time Stopped: Current Time Charged: 58.00
Date NTP Issued: 08/22/2012 Completion Date: Current Time Allowed: 60.00
General Liability Expires: 10/05/2013 Workman's Comp Expires: 10/05/2013 Percent Time Used: 96.67 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $326,856.50 Total to Date Prev to Date This Estimate
Bid Amount: $326,856.50 Participating: $0.00 $0.00 $0.00
Percent Complete: 84.80 % Non Participating: $286,841.69 $232,230.83 $54,610.86
Funds Available: $49,681.81 Total Earnings: $286,841.69 $232,230.83 $54,610.86
Unearned Balance: $49,681.81 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $286,841.69 $232,230.83 $54,610.86
Other Adjustments: $-9,667.00 $-36,686.25 $27,019.25
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $277,174.69 $195,544.58 $81,630.11

Estimate Adjustment Detail

Contract ID: 120308   Estimate Number: 0004     Primary JP: 29061(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
29061(04) 0004 RAPID CURE JOINT SEALANT * Missing Material Certification 0002 -111.00 $25.00 $-2,775.00
29061(04) 0004 RAPID CURE JOINT SEALANT * Missing Material Certification 0004 111.00 $25.00 $2,775.00
29061(04) 0005 ELASTOMERIC MORTAR * Missing Material Certification 0002 -5.60 $800.00 $-4,480.00
29061(04) 0005 ELASTOMERIC MORTAR * Missing Material Certification 0004 5.60 $800.00 $4,480.00
29061(04) 0006 WATER REPELLENT (VISUALLY INSPECTED) * Missing Material Certification 0002 -112.50 $5.00 $-562.50
29061(04) 0006 WATER REPELLENT (VISUALLY INSPECTED) * Missing Material Certification 0004 112.50 $5.00 $562.50
29061(04) 0011 SEALER RESIN * Missing Material Certification 0002 -0.90 $50.00 $-45.00
29061(04) 0012 DECK AREA SEALED (FLOODCOATS) * Missing Material Certification 0002 -460.50 $20.00 $-9,210.00
29061(04) 0016 TRAFFIC STRIPE(PLASTIC)(4" WIDE) * Missing Material Certification 0004 -103.00 $4.00 $-412.00
29062(04) 0028 ELASTOMERIC MORTAR * Missing Material Certification 0003 -2.50 $800.00 $-2,000.00
29062(04) 0028 ELASTOMERIC MORTAR * Missing Material Certification 0004 2.50 $800.00 $2,000.00
29062(04) 0031 EPOXY RESIN, ABOVE WATER * Missing Material Certification 0001 -1.50 $77.00 $-115.50
29062(04) 0031 EPOXY RESIN, ABOVE WATER * Missing Material Certification 0004 1.50 $77.00 $115.50
29062(04) 0032 PNEUMATICALLY PLACED MORTAR * Missing Material Certification 0003 -33.33 $525.00 $-17,498.25
29062(04) 0032 PNEUMATICALLY PLACED MORTAR * Missing Material Certification 0004 33.33 $525.00 $17,498.25
Subtotals For Line Item Adjustments $-9,667.00
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120308   Estimate Number: 0004     Primary JP: 29061(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SBR-266N(002)SB Project:    29061(04) Category:    0200/BRIDGE "A" SBR-266N(002)SB
0001 CLSM BACKFILL 501(G) 6309 CY 5.000 5.000   11.620 $500.00 $0.00 $5,810.00
0002 APPROACH SLAB 504(A) 1304 SY 152.200 152.200   152.200 $300.00 $0.00 $45,660.00
0003 SAW-CUT GROOVING 504(B) 1305 SY 152.200 152.200   152.200 $14.00 $0.00 $2,130.80
0004 RAPID CURE JOINT SEALANT 504(G) 6390 LF 111.000 111.000 0.000 111.000 $25.00 $0.00 $2,775.00
0005 ELASTOMERIC MORTAR 504(H) 6389 CF 5.600 5.600 0.000 5.600 $800.00 $0.00 $4,480.00
0006 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 112.500 112.500 0.000 112.500 $5.00 $0.00 $562.50
0007 PREPARATION OF CRACKS, ABOVE WATER 520(A) 6058 LF 100.000 100.000   0.000 $25.00 $0.00 $0.00
0008 EPOXY RESIN, ABOVE WATER 520(C) 6060 GAL 0.700 0.700   0.000 $77.00 $0.00 $0.00
0009 PNEUMATICALLY PLACED MORTAR 521(A) 6210 SY 10.000 10.000   11.170 $525.00 $0.00 $5,864.25
0010 SEALER CRACK PREPARATION 523(A) 6550 LF 138.000 138.000   138.000 $3.00 $0.00 $414.00
0011 SEALER RESIN 523(B) 6560 GAL 0.900 0.900 0.000 0.900 $50.00 $0.00 $45.00
0012 DECK AREA SEALED (FLOODCOATS) 523(C) 6570 SY 460.500 460.500 0.000 460.500 $20.00 $0.00 $9,210.00
0013 (SP)CORROSION INHIBITOR(SURFACE APPLIED) 535 6130 SY 4.000 4.000   11.170 $62.00 $0.00 $692.54
0014 (PL)REPAIR BRIDGE ITEM (TYPE A) 540 4515 EA 1.000 1.000   1.000 $30,000.00 $0.00 $30,000.00
0015 (PL)REPLACE BRIDGE ITEM (TYPE A) 545 4815 EA 1.000 1.000   1.000 $8,000.00 $0.00 $8,000.00
Subtotals For Category     0200/BRIDGE "A" SBR-266N(002)SB    $0.00 $115,644.09
Fed/State Project Number:    SBR-266N(002)SB Project:    29061(04) Category:    0300/TRAFFIC CONTROL SBR-266N(002)SB
0016 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 425.000 425.000 435.000 435.000 $4.00 $1,740.00 $1,740.00
0017 (SP)CONST.ZONE IMPACT ATTEN. 871(B) 8705 SD 60.000 60.000 10.000 40.000 $25.00 $250.00 $1,000.00
0018 DELIVER PORTABLE LONGITUDINAL BARRIER 877(B) 8484 LF 500.000 500.000   480.000 $25.00 $0.00 $12,000.00
0019 RELOCATION OF PORTABLE LONGITUDINAL BARRIER 877(C) 8486 LF 1,500.000 1,500.000 480.000 1,440.000 $2.00 $960.00 $2,880.00
0020 ARROW DISPLAY(TYPE C) 880(A) 8812 SD 120.000 120.000 10.000 40.000 $10.00 $100.00 $400.00
0021 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 1.000 $26,308.00 $6,577.00 $26,308.00
0022 PORT.CHANGEABLE MESSAGE SIGN 882(A) 8306 SD 120.000 120.000 20.000 74.000 $10.00 $200.00 $740.00
Subtotals For Category     0300/TRAFFIC CONTROL SBR-266N(002)SB    $9,827.00 $45,068.00
Fed/State Project Number:    SBR-266N(002)SB Project:    29061(04) Category:    0640/CONSTRUCTION SBR-266N(002)SB
0023 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $26,000.00 $0.00 $26,000.00
Subtotals For Category     0640/CONSTRUCTION SBR-266N(002)SB    $0.00 $26,000.00
Subtotals For Project SBR-266N(002)SB /29061(04) $9,827.00 $186,712.09


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SBR-266A(003)SB Project:    29062(04) Category:    0200/BRIDGE "A" SBR-266A(003)SB
0024 CLSM BACKFILL 501(G) 6309 CY 5.000 5.000 5.790 9.630 $500.00 $2,895.00 $4,815.00
0025 APPROACH SLAB 504(A) 1304 SY 95.700 95.700 47.850 95.700 $325.00 $15,551.25 $31,102.50
0026 SAW-CUT GROOVING 504(B) 1305 SY 95.700 95.700 47.850 95.700 $14.00 $669.90 $1,339.80
0027 RAPID CURE JOINT SEALANT 504(G) 6390 LF 117.000 117.000 117.000 117.000 $25.00 $2,925.00 $2,925.00
0028 ELASTOMERIC MORTAR 504(H) 6389 CF 5.000 5.000 2.500 5.000 $800.00 $2,000.00 $4,000.00
0029 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 179.000 179.000 179.000 179.000 $5.00 $895.00 $895.00
0030 PREPARATION OF CRACKS, ABOVE WATER 520(A) 6058 LF 100.000 100.000   81.170 $25.00 $0.00 $2,029.25
0031 EPOXY RESIN, ABOVE WATER 520(C) 6060 GAL 2.000 2.000 0.000 1.500 $77.00 $0.00 $115.50
0032 PNEUMATICALLY PLACED MORTAR 521(A) 6210 SY 160.000 160.000 33.330 89.650 $525.00 $17,498.25 $47,066.25
0033 SEALER CRACK PREPARATION 523(A) 6550 LF 71.000 71.000 71.000 71.000 $3.00 $213.00 $213.00
0034 SEALER RESIN 523(B) 6560 GAL 1.400 1.400 1.400 1.400 $50.00 $70.00 $70.00
0035 (SP)CORROSION INHIBITOR(SURFACE APPLIED) 535 6130 SY 160.000 160.000 33.330 89.650 $62.00 $2,066.46 $5,558.30
Subtotals For Category     0200/BRIDGE "A" SBR-266A(003)SB    $44,783.86 $100,129.60
Subtotals For Project SBR-266A(003)SB /29062(04) $44,783.86 $100,129.60