Oklahoma Department of Transportation
Final Estimate Affidavit

Contract ID: 120301   Estimate Number: 0005 , Final     Spec Year: 2009
Primary JP: 28262(04)   Residency: SAND SPRINGS (08400)     Contract No: 810085
Date Created: 12/20/2012   Contractor FEI: 730764097A     Account No: 404800

Project Number(s): E-SAP-257B(011)
Contract Description: BRIDGE AND APPROACHES SH-11: OVER RED EAGLE BRANCH CREEK, 9.2 MILES EAST OF JUNCTION SH-99. PROJECT LENGTH = 0.022 MILES.
Primary County: OSAGE              
Name of Road: SH-11              
Prime Contractor: MANHATTAN ROAD & BRIDGE COMPANY           Time Charged: 55.00
    5601 S. 122ND E. AVE.           Time Allowed: 60.00
    TULSA , OK   74146           Percent Time: 91.67 %

  Paid To Date: $679,467.60 Payable This Statement: $-656.89

CONTRACTOR AFFIDAVIT
STATE OF ___________________ )  
  )     §  
COUNTY OF __________________ )  
The undersigned contractor or duly authorized agent, of lawful age, being first duly sworn, on oath say that this claim is true and correct.
Affiant further states that the work, services or materials as shown by this claim have been completed or supplied in accordance with the plans, specifications, orders, requests and all other terms of the contract. Affiant further states that (s)he is duly authorized agent of the contractor for the purpose of certifying the facts pertaining to the giving of things of value to government personnel in order to procure the contract or obtain payment; that (s)he is fully aware of the facts and circumstances surrounding the making of the contract and has been personally and directly involved in the proceedings leading to the procurement of the contract and the filing of this claim; and, neither the contractor nor anyone subject to the contractor's direction or control has been paid, given or donated or agreed to pay, give or donate to any officer or employee of the State of Oklahoma any money or other thing of value, either directly or
indirectly, in procuring the contract or obtaining payment. The affiant further certifies that all laborers, mechanics, apprentices and trainees employed by him/her or by any subcontractor performing work under the contract on the project have been paid wages at rates not less than those required by the contract provisions, and that the work performed by each such laborer, mechanic, apprentice or trainee conformed to the classifications set forth in the contract or training program provisions applicable to the wage rate paid.
Affiant hereby agrees that Contractor will accept this estimate as full compensation for all money due Contractor by the Department of Transportation, and hereby relinquish all claims, either in contract or in tort, which have arisen or which might arise out of the construction of said project. That to the best of my knowledge and belief, all indebtedness for labor, materials, fuel, equipment, equipment rental, parts, supplies, insurance premiums, and claims for items not specifically mentioned, which are attributable to performance of the work on this project or which were incorporated therein in any manner, have been paid in full, and that there are not now any presently outstanding, unpaid claims for such indebtedness; that my position with the company is such, that if there were any such outstanding claims of the nature specified herein, I would ordinarily be aware of them.
Further affiant sayeth not.                                
MANHATTAN ROAD & BRIDGE COMPANY                               
 
_________________________________________________
Affiant Signature
 
_________________________________________________
Affiant Printed Name
                          PE Seal
_________________________________________________
Affiant Company Position
Subscribed and sworn to before me this ______ day of ____________, 20____
My Commission Number: ____________ My Commission Expires: ______________
   
_________________________________________________              
_________________________________________________
                    Professional Engineer Signature
              Oklahoma Department of Transportation
Corporate Seal
Notary Seal                  

Oklahoma Department of Transportation
Final Estimate Summary
Created:    12/20/2012
Contract ID: 120301   Estimate Number: 0005     Contract No: 810085
Residency: SAND SPRINGS (08400)   Estimate Type: Final     Account No: 404800

Project Number(s): E-SAP-257B(011)
Primary Job Piece No: 28262(04)
Contract Description: BRIDGE AND APPROACHES SH-11: OVER RED EAGLE BRANCH CREEK, 9.2 MILES EAST OF JUNCTION SH-99. PROJECT LENGTH = 0.022 MILES.
Primary County: OSAGE              
Name of Road: SH-11              
Prime Contractor: MANHATTAN ROAD & BRIDGE COMPANY              
    5601 S. 122ND E. AVE.              
    TULSA , OK   74146              
Surety Company: FIDELITY & DEPOSIT INSURANCE COMPANY OF MARYLAND              

Date Let: 06/21/2012 NTP Effective Date: 07/07/2012 Pay Period: 09/16/2012  TO  12/20/2012
Date Awarded: 07/02/2012 Date Work Began: 07/07/2012 Original Contract Time: 60
Date Contract Executed: 07/05/2012 Date Time Stopped: 09/18/2012 Current Time Charged: 55.00
Date NTP Issued: 07/06/2012 Completion Date: 09/18/2012 Current Time Allowed: 60.00
General Liability Expires: 10/01/2013 Workman's Comp Expires: 10/01/2013 Percent Time Used: 91.67 %
Specification Year: 2009        

Current Contract Amount: $684,894.63 Total to Date Prev to Date This Estimate
Bid Amount: $684,792.80 Participating: $0.00 $0.00 $0.00
Percent Complete: 99.21 % Non Participating: $684,894.63 $685,551.52 $-656.89
Funds Available: $5,427.03 Total Earnings: $684,894.63 $685,551.52 $-656.89
Unearned Balance: $5,325.20 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $684,894.63 $685,551.52 $-656.89
Other Adjustments: $-5,427.03 $-5,427.03 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $679,467.60 $680,124.49 $-656.89

Estimate Adjustment Detail

Contract ID: 120301   Estimate Number: 0005     Primary JP: 28262(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Final Change Order Approved 12/19/2012 0.0 $101.83


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
28262(04) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0002 -100.00 $3.00 $-300.00
28262(04) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0003 -95.00 $3.00 $-285.00
28262(04) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0004 95.00 $3.00 $285.00
28262(04) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0004 100.00 $3.00 $300.00
28262(04) 0012 SEPARATOR FABRIC * Missing Material Certification 0003 -577.78 $4.50 $-2,600.01
28262(04) 0012 SEPARATOR FABRIC * Missing Material Certification 0004 577.78 $4.50 $2,600.01
28262(04) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0003 61.43 $-0.30 $-19.03
28262(04) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0003 55.50 $-0.30 $-17.19
28262(04) 0018 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0003 200.04 $-0.35 $-70.81
28262(04) 0029 CLASS AA CONCRETE * COMPRESSIVE STRENGTH 0004 -1.00 $5,320.00 $-5,320.00
Subtotals For Line Item Adjustments $-5,427.03
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 INCENTIVE/DISINCENTIVE 07/07/2012 08/21/2012 45.00 DYS $3,000.00 Y


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120301   Estimate Number: 0005     Primary JP: 28262(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    E-SAP-257B(011) Project:    28262(04) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201(A) 0102 LSUM 1.000 1.000   1.000 $65,000.00 $0.00 $65,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 2,577.000 2,577.000   2,577.000 $6.00 $0.00 $15,462.00
0003 UNCLASSIFIED BORROW 202(D) 0184 CY 1,106.000 1,106.000   1,106.000 $24.00 $0.00 $26,544.00
0004 TYPE A-SALVAGED TOPSOIL 205(A) 4229 LSUM 1.000 1.000   1.000 $5,600.00 $0.00 $5,600.00
0005 TEMPORARY SILT FENCE 221(C) 2801 LF 240.000 195.000   195.000 $3.00 $0.00 $585.00
0006 SOLID SLAB SODDING 230(A) 2806 SY 530.000 2,867.400   2,867.400 $3.25 $0.00 $9,319.05
0007 SEEDING METHOD A 232(A) 2813 AC 0.110 0.000   0.000 $1,000.00 $0.00 $0.00
0008 VEGETATIVE MULCHING 233(A) 2817 AC 0.110 0.000   0.000 $900.00 $0.00 $0.00
0009 MOWING 241 2832 AC 9.360 0.000   0.000 $80.00 $0.00 $0.00
0010 AGGREGATE BASE TYPE B 303(B) 2110 CY 88.000 123.100 -5.940 123.100 $50.00 $-297.00 $6,155.00
0011 STABILIZED SUBGRADE 307(K) 4300 SY 463.000 0.000   0.000 $17.50 $0.00 $0.00
0012 SEPARATOR FABRIC 325 5271 SY 502.000 570.560 -7.220 570.560 $4.50 $-32.49 $2,567.52
0013 TRAFFIC BOUND SURFACE COURSE TYPE E 402(E) 0225 TON 60.000 0.000   0.000 $26.00 $0.00 $0.00
0014 TACK COAT 407(B) 0250 GAL 93.000 49.200 -50.800 49.200 $3.00 $-152.40 $147.60
0015 PRIME COAT 408 5774 GAL 270.000 0.000   0.000 $7.00 $0.00 $0.00
0016 SUPERPAVE, TYPE S3(PG 70-28 OK) 411(B) 5940 TON 56.000 61.430   61.430 $144.00 $0.00 $8,845.92
0017 SUPERPAVE, TYPE S3(PG 64-22 OK) 411(B) 5945 TON 57.000 55.500   55.500 $135.00 $0.00 $7,492.50
0018 SUPERPAVE, TYPE S4(PG 70-28 OK) 411(C) 5955 TON 57.000 200.040   200.040 $146.00 $0.00 $29,205.84
0019 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 126.000 0.000   0.000 $146.00 $0.00 $0.00
0020 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
0021 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 320.000 320.000   320.000 $22.00 $0.00 $7,040.00
0022 SAWING PAVEMENT 619(C) 0924 LF 648.000 48.000   48.000 $3.00 $0.00 $144.00
0023 BEAM GUARDRAIL W-BEAM SINGLE 623(A) 0932 LF 650.000 800.000 -25.000 800.000 $17.00 $-425.00 $13,600.00
0024 GUARDRAIL END TREATMENT (31") 623(G) 8590 EA 4.000 4.000   4.000 $2,275.00 $0.00 $9,100.00
0025 DELINEATORS(TYPE 2, CODE 1) 853 9033 EA 14.000 18.000   18.000 $6.00 $0.00 $108.00
Subtotals For Category     0100/ROADWAY    $-906.89 $226,916.43
Fed/State Project Number:    E-SAP-257B(011) Project:    28262(04) Category:    0200/BRIDGE 'A'
0026 UNCLASSIFIED EXCAVATION 202(A) 1301 CY 2,510.000 2,510.000   2,510.000 $6.50 $0.00 $16,315.00
0027 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 1306 CY 85.000 85.000   85.000 $30.00 $0.00 $2,550.00
0028 SUBSTRUCTURE EXCAVATION ROCK 501(C) 1308 CY 39.000 39.000   39.000 $60.00 $0.00 $2,340.00
0029 CLASS AA CONCRETE 509(A) 1326 CY 525.000 525.000   525.000 $400.00 $0.00 $210,000.00
0030 REINFORCING STEEL 511(A) 1332 LB 149,440.000 149,440.000   149,440.000 $0.90 $0.00 $134,496.00
0031 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $25,000.00 $0.00 $25,000.00
Subtotals For Category     0200/BRIDGE 'A'    $0.00 $390,701.00
Fed/State Project Number:    E-SAP-257B(011) Project:    28262(04) Category:    0300/TRAFFIC
0032 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 2,400.000 1,496.000   1,496.000 $1.20 $0.00 $1,795.20
0033 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0034 PORT.CHANGEABLE MESSAGE SIGN 882(A) 8306 SD 120.000 142.000   142.000 $21.00 $0.00 $2,982.00
Subtotals For Category     0300/TRAFFIC    $0.00 $9,777.20
Fed/State Project Number:    E-SAP-257B(011) Project:    28262(04) Category:    0600/STAKING
0035 CONSTRUCTION STAKING LEVEL II 642(B) 0096 LSUM 1.000 1.000 0.100 1.000 $2,500.00 $250.00 $2,500.00
Subtotals For Category     0600/STAKING    $250.00 $2,500.00
Fed/State Project Number:    E-SAP-257B(011) Project:    28262(04) Category:    0640/CONSTRUCTION
0036 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $55,000.00 $0.00 $55,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $55,000.00
Subtotals For Project E-SAP-257B(011) /28262(04) $-656.89 $684,894.63