Contract ID: | 120288 | Estimate Number: | 0013 | Contract No: | 810370 | |||
Residency: | DUNCAN (07100) | Estimate Type: | Progressive | Account No: | 736700 | |||
Project Number(s): | BRO-134D(079)CI | ||||||||||||
Primary Job Piece No: | 27474(04) | ||||||||||||
Contract Description: | BRIDGE AND APPROACHES COUNTY ROAD (EW-190): OVER MUD AND COTTONWOOD CREEK, 0.7 MILES WEST OF SH-89. PROJECT LENGTH = 0.376 MILES | ||||||||||||
Primary County: | JEFFERSON | ||||||||||||
Name of Road: | COUNTY ROAD (EW-190) | ||||||||||||
Prime Contractor: | OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) | ||||||||||||
P.O. BOX 3817 | |||||||||||||
EDMOND , OK 73083 | |||||||||||||
Surety Company: | LIBERTY MUTUAL INSURANCE COMPANY | ||||||||||||
Date Let: | 08/16/2012 | NTP Effective Date: | 02/18/2013 | Pay Period: | 05/16/2013 TO 07/31/2013 |
Date Awarded: | 09/10/2012 | Date Work Began: | 12/10/2012 | Original Contract Time: | 150 |
Date Contract Executed: | 09/27/2012 | Date Time Stopped: | Current Time Charged: | 132.00 | |
Date NTP Issued: | 10/02/2012 | Completion Date: | Current Time Allowed: | 150.00 | |
General Liability Expires: | 05/01/2014 | Workman's Comp Expires: | 07/01/2014 | Percent Time Used: | 88.00 % |
Specification Year: | 2009 | Date Approved: | |||
Current Contract Amount: | $1,049,375.54 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $1,049,375.54 | Participating: | $988,913.25 | $972,617.65 | $16,295.60 | ||
Percent Complete: | 93.80 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $65,058.10 | Total Earnings: | $988,913.25 | $972,617.65 | $16,295.60 | ||
Unearned Balance: | $65,058.10 | Stockpiled Materials: | $60.21 | $60.21 | $0.00 | ||
Gross Earnings: | $988,973.46 | $972,677.86 | $16,295.60 | ||||
Other Adjustments: | $-4,656.02 | $-582.12 | $-4,073.90 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $984,317.44 | $972,095.74 | $12,221.70 |
Contract ID: | 120288 | Estimate Number: | 0013 | Primary JP: | 27474(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
27474(04) | 0017 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0017 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0017 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0017 | PC BR ITM FABS (AML) | Stockpiled Material Initial Payment | 0001 | $21,559.07 |
27474(04) | 0017 | PC BR ITM FABS (AML) | Stockpiled Material Adjustment | 0006 | $-21,559.07 |
27474(04) | 0018 | RSTL FABS (AML)(IA) | Stockpiled Material Initial Payment | 0006 | $1,144.00 |
27474(04) | 0018 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0009 | $-1,144.00 |
27474(04) | 0024 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0009 | $-1,228.65 |
27474(04) | 0024 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0008 | $-3,784.73 |
27474(04) | 0024 | RSTL FABS (AML)(IA) | Stockpiled Material Initial Payment | 0006 | $5,013.37 |
27474(04) | 0025 | Stockpiled Material Closure | 0008 | $-1,234.79 | |
27474(04) | 0025 | Stockpiled Material Adjustment | 0004 | $-1,734.81 | |
27474(04) | 0025 | Stockpiled Material Initial Payment | 0002 | $2,969.60 | |
27474(04) | 0026 | Stockpiled Material Closure | 0008 | $-6,139.06 | |
27474(04) | 0026 | Stockpiled Material Adjustment | 0004 | $-10,988.10 | |
27474(04) | 0026 | Stockpiled Material Initial Payment | 0002 | $17,127.16 | |
27474(04) | 0040 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0040 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0040 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0040 | PC BR ITM FABS (AML) | Stockpiled Material Initial Payment | 0001 | $21,559.07 |
27474(04) | 0040 | PC BR ITM FABS (AML) | Stockpiled Material Adjustment | 0006 | $-21,559.07 |
27474(04) | 0041 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0009 | $-1,235.65 |
27474(04) | 0041 | RSTL FABS (AML)(IA) | Stockpiled Material Initial Payment | 0006 | $1,235.65 |
27474(04) | 0047 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0008 | $-6,171.71 |
27474(04) | 0047 | RSTL FABS (AML)(IA) | Stockpiled Material Initial Payment | 0006 | $6,171.71 |
27474(04) | 0048 | Stockpiled Material Closure | 0008 | $-1,254.20 | |
27474(04) | 0048 | Stockpiled Material Adjustment | 0004 | $-1,715.38 | |
27474(04) | 0048 | Stockpiled Material Initial Payment | 0002 | $2,969.58 | |
27474(04) | 0049 | Stockpiled Material Closure | 0008 | $-6,667.27 | |
27474(04) | 0049 | Stockpiled Material Initial Payment | 0002 | $18,767.31 | |
27474(04) | 0049 | Stockpiled Material Adjustment | 0005 | $-12,100.04 | |
27474(04) | 0061 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0061 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0061 | PC BR ITM FABS (AML) | Stockpiled Material Closure | 0001 | $0.00 |
27474(04) | 0061 | PC BR ITM FABS (AML) | Stockpiled Material Adjustment | 0006 | $-21,498.84 |
27474(04) | 0061 | PC BR ITM FABS (AML) | Stockpiled Material Initial Payment | 0001 | $21,559.06 |
27474(04) | 0062 | RSTL FABS (AML)(IA) | Stockpiled Material Initial Payment | 0006 | $1,144.00 |
27474(04) | 0062 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0009 | $-1,144.00 |
27474(04) | 0068 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0006 | $-1,973.71 |
27474(04) | 0068 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0007 | $-922.49 |
27474(04) | 0068 | RSTL FABS (AML)(IA) | Stockpiled Material Initial Payment | 0006 | $5,013.37 |
27474(04) | 0068 | RSTL FABS (AML)(IA) | Stockpiled Material Adjustment | 0008 | $-2,117.17 |
27474(04) | 0069 | Stockpiled Material Closure | 0008 | $-1,254.20 | |
27474(04) | 0069 | Stockpiled Material Initial Payment | 0002 | $2,969.58 | |
27474(04) | 0069 | Stockpiled Material Adjustment | 0005 | $-1,715.38 | |
27474(04) | 0070 | Stockpiled Material Closure | 0008 | $-6,892.71 | |
27474(04) | 0070 | Stockpiled Material Adjustment | 0005 | $-12,577.67 | |
27474(04) | 0070 | Stockpiled Material Initial Payment | 0002 | $19,470.38 | Subtotals For Stockpile Payments | $60.21 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
27474(04) | 0003 | TEMPORARY SILT FENCE | * Missing Material Certification | 0002 | -1,899.00 | $1.42 | $-2,696.58 |
27474(04) | 0003 | TEMPORARY SILT FENCE | * Missing Material Certification | 0003 | 1,899.00 | $1.42 | $2,696.58 |
27474(04) | 0004 | TEMPORARY SILT DIKE | * Missing Material Certification | 0002 | -90.00 | $8.35 | $-751.50 |
27474(04) | 0004 | TEMPORARY SILT DIKE | * Missing Material Certification | 0003 | 90.00 | $8.35 | $751.50 |
27474(04) | 0006 | SOLID SLAB SODDING | * TEST CODE | 0013 | 0.00 | $0.00 | $-4,073.90 |
27474(04) | 0022 | CLASS AA CONCRETE | * TEST CODE | 0008 | 0.00 | $0.00 | $-582.12 |
27474(04) | 0030 | TYPE I-A FILTER BLANKET | * Missing Material Certification | 0006 | -46.28 | $30.24 | $-1,399.51 |
27474(04) | 0030 | TYPE I-A FILTER BLANKET | * Missing Material Certification | 0008 | 0.00 | $0.00 | $1,399.51 |
27474(04) | 0031 | 6" PERFORATED PIPE UNDERDRAIN ROUND | * Missing Material Certification | 0010 | -52.00 | $42.79 | $-2,225.08 |
27474(04) | 0031 | 6" PERFORATED PIPE UNDERDRAIN ROUND | * Missing Material Certification | 0011 | 52.00 | $42.79 | $2,225.08 |
27474(04) | 0032 | 6" NON-PERF.PIPE UNDERDRAIN RND. | * Missing Material Certification | 0010 | -34.00 | $8.18 | $-278.12 |
27474(04) | 0032 | 6" NON-PERF.PIPE UNDERDRAIN RND. | * Missing Material Certification | 0011 | 34.00 | $8.18 | $278.12 |
27474(04) | 0053 | TYPE I-A FILTER BLANKET | * Missing Material Certification | 0006 | -46.28 | $30.24 | $-1,399.51 |
27474(04) | 0053 | TYPE I-A FILTER BLANKET | * Missing Material Certification | 0008 | 0.00 | $0.00 | $1,399.51 |
27474(04) | 0074 | TYPE I-A FILTER BLANKET | * Missing Material Certification | 0006 | -45.72 | $30.24 | $-1,382.57 |
27474(04) | 0074 | TYPE I-A FILTER BLANKET | * Missing Material Certification | 0008 | 0.00 | $0.00 | $1,382.57 | Subtotals For Line Item Adjustments | $-4,656.02 | * = User applied Line Item Adjustments |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 120288 | Estimate Number: | 0013 | Primary JP: | 27474(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: BRO-134D(079)CI | Project: 27474(04) | Category: 0100/ROADWAY | ||||||||
0001 | CLEARING AND GRUBBING | 201(A) 0102 | LSUM | 1.000 | 1.000 | 1.000 | $12,600.00 | $0.00 | $12,600.00 | |
0002 | EARTHWORK | 202(H) 0185 | LSUM | 1.000 | 1.000 | 1.000 | $73,500.00 | $0.00 | $73,500.00 | |
0003 | TEMPORARY SILT FENCE | 221(C) 2801 | LF | 4,000.000 | 4,000.000 | 1,899.000 | $1.42 | $0.00 | $2,696.58 | |
0004 | TEMPORARY SILT DIKE | 221(F) 0100 | LF | 250.000 | 250.000 | 90.000 | $8.35 | $0.00 | $751.50 | |
0005 | TEMPORARY ROCK FILTER DAM TYPE 2 | 221(G) 0151 | CY | 15.000 | 15.000 | 0.000 | $73.50 | $0.00 | $0.00 | |
0006 | SOLID SLAB SODDING | 230(A) 2806 | SY | 14,000.000 | 14,000.000 | 10,313.670 | 10,313.670 | $1.58 | $16,295.60 | $16,295.60 |
0007 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 5.800 | 5.800 | 0.000 | $630.00 | $0.00 | $0.00 | |
0008 | TRAFFIC BOUND SURFACE COURSE TYPE E | 402(E) 0225 | TON | 1,904.000 | 1,904.000 | 1,857.090 | $22.21 | $0.00 | $41,245.97 | |
0009 | PRIME COAT | 408 5774 | GAL | 1,287.000 | 1,287.000 | 0.000 | $7.88 | $0.00 | $0.00 | |
0010 | CLASS C CONCRETE | 509(D) 0325 | CY | 15.000 | 15.000 | 0.000 | $255.71 | $0.00 | $0.00 | |
0011 | 48" R.C.PIPE CLASS III | 613(A) 0496 | LF | 46.000 | 46.000 | 46.000 | $156.93 | $0.00 | $7,218.78 | |
0012 | 24" CORR. GALV. STEEL PIPE | 613(B) 0690 | LF | 50.000 | 50.000 | 50.000 | $28.08 | $0.00 | $1,404.00 | |
0013 | 24" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5730 | EA | 2.000 | 2.000 | 2.000 | $203.46 | $0.00 | $406.92 | |
0014 | SPECIAL END SECTION OF 48" RCP ROUND | 613(O) 4383 | EA | 2.000 | 2.000 | 2.000 | $1,988.96 | $0.00 | $3,977.92 | |
Subtotals For Category 0100/ROADWAY | $16,295.60 | $160,097.27 | ||||||||
Fed/State Project Number: BRO-134D(079)CI | Project: 27474(04) | Category: 0200/BRIDGE "A" | ||||||||
0015 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 180.000 | 180.000 | 180.000 | $25.30 | $0.00 | $4,554.00 | |
0016 | GRANULAR BACKFILL | 501(F) 6352 | CY | 66.000 | 66.000 | 66.000 | $69.06 | $0.00 | $4,557.96 | |
0017 | PRESTRESSED CONCRETE BEAMS (TYPE II) | 503(A) 1311 | LF | 179.000 | 179.000 | 179.000 | $165.65 | $0.00 | $29,651.35 | |
0018 | CONCRETE RAIL (TR3) | 504(D) 6239 | LF | 176.000 | 176.000 | 176.000 | $90.97 | $0.00 | $16,010.72 | |
0019 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 500.000 | $3.94 | $0.00 | $1,970.00 | |
0020 | WEATHERING STEEL FIXED BEARING ASSEMBLY | 507(A) 6172 | EA | 3.000 | 3.000 | 3.000 | $1,269.87 | $0.00 | $3,809.61 | |
0021 | WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 507(B) 6176 | EA | 3.000 | 3.000 | 3.000 | $1,269.87 | $0.00 | $3,809.61 | |
0022 | CLASS AA CONCRETE | 509(A) 1326 | CY | 48.500 | 48.500 | 48.500 | $727.65 | $0.00 | $35,291.02 | |
0023 | CLASS A CONCRETE | 509(B) 1328 | CY | 60.400 | 60.400 | 60.400 | $689.15 | $0.00 | $41,624.66 | |
0024 | REINFORCING STEEL | 511(A) 1332 | LB | 20,160.000 | 20,160.000 | 20,160.000 | $1.00 | $0.00 | $20,160.00 | |
0025 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 160.000 | 160.000 | 160.000 | $31.77 | $0.00 | $5,083.20 | |
0026 | PILES, FURNISHED (HP 12X53) | 514(A) 6011 | LF | 731.000 | 731.000 | 731.000 | $36.52 | $0.00 | $26,696.12 | |
0027 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 160.000 | 160.000 | 160.000 | $11.00 | $0.00 | $1,760.00 | |
0028 | PILES, DRIVEN (HP 12X53) | 514(B) 6294 | LF | 731.000 | 731.000 | 558.840 | $11.00 | $0.00 | $6,147.24 | |
0029 | TYPE I-A PLAIN RIPRAP | 601(B) 1353 | TON | 777.000 | 777.000 | 797.550 | $37.96 | $0.00 | $30,274.99 | |
0030 | TYPE I-A FILTER BLANKET | 601(C) 1355 | TON | 184.000 | 184.000 | 181.530 | $30.24 | $0.00 | $5,489.47 | |
0031 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(H) 6204 | LF | 52.000 | 52.000 | 52.000 | $42.79 | $0.00 | $2,225.08 | |
0032 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(I) 6207 | LF | 150.000 | 150.000 | 34.000 | $8.18 | $0.00 | $278.12 | |
0033 | REMOVAL OF EXISTING BRIDGE STRUCTURE | 619(D) 1397 | LSUM | 1.000 | 1.000 | 1.000 | $6,325.00 | $0.00 | $6,325.00 | |
0034 | BEAM GUARDRAIL W-BEAM SINGLE | 623(A) 1418 | LF | 200.000 | 200.000 | 200.000 | $13.75 | $0.00 | $2,750.00 | |
0035 | GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 623(F) 5686 | EA | 4.000 | 4.000 | 4.000 | $1,430.00 | $0.00 | $5,720.00 | |
0036 | GUARDRAIL ANCHOR UNIT (TYPE B) | 623(F) 6030 | EA | 3.000 | 3.000 | 3.000 | $445.50 | $0.00 | $1,336.50 | |
0037 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.850 | $3,245.00 | $0.00 | $2,758.25 | |
Subtotals For Category 0200/BRIDGE "A" | $0.00 | $258,282.90 | ||||||||
Fed/State Project Number: BRO-134D(079)CI | Project: 27474(04) | Category: 0201/BRIDGE "B" | ||||||||
0038 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 190.000 | 190.000 | 190.000 | $25.30 | $0.00 | $4,807.00 | |
0039 | GRANULAR BACKFILL | 501(F) 6352 | CY | 76.000 | 76.000 | 76.000 | $69.06 | $0.00 | $5,248.56 | |
0040 | PRESTRESSED CONCRETE BEAMS (TYPE II) | 503(A) 1311 | LF | 179.000 | 179.000 | 179.000 | $165.65 | $0.00 | $29,651.35 | |
0041 | CONCRETE RAIL (TR3) | 504(D) 6239 | LF | 188.100 | 188.100 | 188.000 | $90.97 | $0.00 | $17,102.36 | |
0042 | STRUCTURAL STEEL | 506(A) 1322 | LB | 580.000 | 580.000 | 580.000 | $3.94 | $0.00 | $2,285.20 | |
0043 | WEATHERING STEEL FIXED BEARING ASSEMBLY | 507(A) 6172 | EA | 3.000 | 3.000 | 3.000 | $1,269.87 | $0.00 | $3,809.61 | |
0044 | WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 507(B) 6176 | EA | 3.000 | 3.000 | 3.000 | $1,269.87 | $0.00 | $3,809.61 | |
0045 | CLASS AA CONCRETE | 509(A) 1326 | CY | 50.600 | 50.600 | 50.600 | $727.65 | $0.00 | $36,819.09 | |
0046 | CLASS A CONCRETE | 509(B) 1328 | CY | 68.000 | 68.000 | 68.000 | $689.15 | $0.00 | $46,862.20 | |
0047 | REINFORCING STEEL | 511(A) 1332 | LB | 24,120.000 | 24,120.000 | 24,120.000 | $1.00 | $0.00 | $24,120.00 | |
0048 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 160.000 | 160.000 | 160.000 | $32.13 | $0.00 | $5,140.80 | |
0049 | PILES, FURNISHED (HP 12X53) | 514(A) 6011 | LF | 801.000 | 801.000 | 801.000 | $36.34 | $0.00 | $29,108.34 | |
0050 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 160.000 | 160.000 | 160.000 | $11.00 | $0.00 | $1,760.00 | |
0051 | PILES, DRIVEN (HP 12X53) | 514(B) 6294 | LF | 801.000 | 801.000 | 795.980 | $11.00 | $0.00 | $8,755.78 | |
0052 | TYPE I-A PLAIN RIPRAP | 601(B) 1353 | TON | 703.000 | 703.000 | 526.040 | $37.96 | $0.00 | $19,968.48 | |
0053 | TYPE I-A FILTER BLANKET | 601(C) 1355 | TON | 166.000 | 166.000 | 159.770 | $30.24 | $0.00 | $4,831.44 | |
0054 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(H) 6204 | LF | 60.000 | 60.000 | 60.000 | $42.79 | $0.00 | $2,567.40 | |
0055 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(I) 6207 | LF | 150.000 | 150.000 | 57.000 | $8.18 | $0.00 | $466.26 | |
0056 | BEAM GUARDRAIL W-BEAM SINGLE | 623(A) 1418 | LF | 442.370 | 442.370 | 442.370 | $13.75 | $0.00 | $6,082.59 | |
0057 | GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 623(F) 5686 | EA | 4.000 | 4.000 | 4.000 | $1,430.00 | $0.00 | $5,720.00 | |
0058 | GUARDRAIL ANCHOR UNIT (TYPE B) | 623(F) 6030 | EA | 1.000 | 1.000 | 1.000 | $445.50 | $0.00 | $445.50 | |
Subtotals For Category 0201/BRIDGE "B" | $0.00 | $259,361.57 | ||||||||
Fed/State Project Number: BRO-134D(079)CI | Project: 27474(04) | Category: 0202/BRIDGE "C" | ||||||||
0059 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 180.000 | 180.000 | 180.000 | $25.30 | $0.00 | $4,554.00 | |
0060 | GRANULAR BACKFILL | 501(F) 6352 | CY | 66.000 | 66.000 | 66.000 | $69.06 | $0.00 | $4,557.96 | |
0061 | PRESTRESSED CONCRETE BEAMS (TYPE II) | 503(A) 1311 | LF | 179.000 | 179.000 | 178.500 | $165.65 | $0.00 | $29,568.53 | |
0062 | CONCRETE RAIL (TR3) | 504(D) 6239 | LF | 176.000 | 176.000 | 176.000 | $90.97 | $0.00 | $16,010.72 | |
0063 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 500.000 | $3.94 | $0.00 | $1,970.00 | |
0064 | WEATHERING STEEL FIXED BEARING ASSEMBLY | 507(A) 6172 | EA | 3.000 | 3.000 | 3.000 | $1,269.87 | $0.00 | $3,809.61 | |
0065 | WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 507(B) 6176 | EA | 3.000 | 3.000 | 3.000 | $1,269.87 | $0.00 | $3,809.61 | |
0066 | CLASS AA CONCRETE | 509(A) 1326 | CY | 48.500 | 48.500 | 48.500 | $727.65 | $0.00 | $35,291.03 | |
0067 | CLASS A CONCRETE | 509(B) 1328 | CY | 60.400 | 60.400 | 60.400 | $689.15 | $0.00 | $41,624.66 | |
0068 | REINFORCING STEEL | 511(A) 1332 | LB | 20,160.000 | 20,160.000 | 20,160.000 | $1.00 | $0.00 | $20,160.00 | |
0069 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 160.000 | 160.000 | 160.000 | $32.13 | $0.00 | $5,140.80 | |
0070 | PILES, FURNISHED (HP 12X53) | 514(A) 6011 | LF | 831.000 | 831.000 | 831.000 | $36.27 | $0.00 | $30,140.37 | |
0071 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 160.000 | 160.000 | 160.000 | $11.00 | $0.00 | $1,760.00 | |
0072 | PILES, DRIVEN (HP 12X53) | 514(B) 6294 | LF | 831.000 | 831.000 | 795.560 | $11.00 | $0.00 | $8,751.16 | |
0073 | TYPE I-A PLAIN RIPRAP | 601(B) 1353 | TON | 1,020.000 | 1,020.000 | 682.350 | $37.96 | $0.00 | $25,902.01 | |
0074 | TYPE I-A FILTER BLANKET | 601(C) 1355 | TON | 270.000 | 270.000 | 180.250 | $30.24 | $0.00 | $5,450.76 | |
0075 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(H) 6204 | LF | 52.000 | 52.000 | 52.000 | $42.79 | $0.00 | $2,225.08 | |
0076 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(I) 6207 | LF | 150.000 | 150.000 | 60.000 | $8.18 | $0.00 | $490.80 | |
0077 | REMOVAL OF EXISTING BRIDGE STRUCTURE | 619(D) 1397 | LSUM | 1.000 | 1.000 | 1.000 | $6,325.00 | $0.00 | $6,325.00 | |
0078 | BEAM GUARDRAIL W-BEAM SINGLE | 623(A) 1418 | LF | 192.500 | 192.500 | 192.500 | $13.75 | $0.00 | $2,646.88 | |
0079 | GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 623(F) 5686 | EA | 4.000 | 4.000 | 4.000 | $1,430.00 | $0.00 | $5,720.00 | |
0080 | GUARDRAIL ANCHOR UNIT (TYPE B) | 623(F) 6030 | EA | 3.000 | 3.000 | 3.000 | $445.50 | $0.00 | $1,336.50 | |
Subtotals For Category 0202/BRIDGE "C" | $0.00 | $257,245.48 | ||||||||
Fed/State Project Number: BRO-134D(079)CI | Project: 27474(04) | Category: 0600/STAKING | ||||||||
0081 | CONSTRUCTION STAKING LEVEL II | 642(B) 0096 | LSUM | 1.000 | 1.000 | 0.750 | $10,237.50 | $0.00 | $7,678.14 | |
Subtotals For Category 0600/STAKING | $0.00 | $7,678.14 | ||||||||
Fed/State Project Number: BRO-134D(079)CI | Project: 27474(04) | Category: 0640/CONSTRUCTION | ||||||||
0082 | SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.750 | $3,554.25 | $0.00 | $2,665.69 | |
0083 | MOBILIZATION | 641 1399 | LSUM | 1.000 | 1.000 | 1.000 | $43,582.20 | $0.00 | $43,582.20 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $46,247.89 | ||||||||
Subtotals For Project BRO-134D(079)CI /27474(04) | $16,295.60 | $988,913.25 |