| Contract ID: | 120264 | Estimate Number: | 0007 | Contract No: | 810219 | |||
| Residency: | HEAVENER (02200) | Estimate Type: | Progressive | Account No: | 400200 | |||
| Project Number(s): | BRFY-164B(143) | ||||||||||||
| Primary Job Piece No: | 26232(04) | ||||||||||||
| Contract Description: | BRIDGE AND APPROACHES US-271: OVER HURD CREEK 2.4 MILES SOUTH OF SH-2. PROJECT LENGTH = 0.325 MILES | ||||||||||||
| Primary County: | PUSHMATAHA | ||||||||||||
| Name of Road: | US-271 | ||||||||||||
| Prime Contractor: | PARADIGM CONSTRUCTION & ENGINEERING, INC | ||||||||||||
| P.O. BOX 700239 | |||||||||||||
| TULSA , OK 74170-0239 | |||||||||||||
| Surety Company: | MID-CONTINENT CASUALTY COMPANY | ||||||||||||
| Date Let: | 07/19/2012 | NTP Effective Date: | 12/03/2012 | Pay Period: | 02/16/2013 TO 02/28/2013 |
| Date Awarded: | 08/06/2012 | Date Work Began: | 11/12/2012 | Original Contract Time: | 180 |
| Date Contract Executed: | 08/21/2012 | Date Time Stopped: | Current Time Charged: | 87.00 | |
| Date NTP Issued: | 08/24/2012 | Completion Date: | Current Time Allowed: | 180.00 | |
| General Liability Expires: | 02/11/2014 | Workman's Comp Expires: | 07/01/2013 | Percent Time Used: | 48.33 % |
| Specification Year: | 2009 | Date Approved: | |||
| Current Contract Amount: | $1,809,840.70 | Total to Date | Prev to Date | This Estimate | |||
| Bid Amount: | $1,809,840.70 | Participating: | $640,390.46 | $603,584.81 | $36,805.65 | ||
| Percent Complete: | 48.14 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
| Funds Available: | $938,531.46 | Total Earnings: | $640,390.46 | $603,584.81 | $36,805.65 | ||
| Unearned Balance: | $938,531.46 | Stockpiled Materials: | $232,305.16 | $245,037.65 | $-12,732.49 | ||
| Gross Earnings: | $872,695.62 | $848,622.46 | $24,073.16 | ||||
| Other Adjustments: | $-1,386.38 | $-1,386.38 | $0.00 | ||||
| Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
| TOTAL: | $871,309.24 | $847,236.08 | $24,073.16 | ||||
| Contract ID: | 120264 | Estimate Number: | 0007 | Primary JP: | 26232(04) | |||
| CHANGE ORDER HISTORY | |||||
| Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
| No change orders have been created for this contract. | |||||
| STOCKPILE PAYMENT HISTORY | |||||
| Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
| 26232(04) | 0018 | Class C Conc Paved ditches | Stockpiled Material Initial Payment | 0003 | $3,373.92 |
| 26232(04) | 0020 | 18" RCP Pipe | Stockpiled Material Initial Payment | 0003 | $497.25 |
| 26232(04) | 0021 | 24" RCP | Stockpiled Material Initial Payment | 0003 | $2,530.89 |
| 26232(04) | 0022 | 18" CGSP | Stockpiled Material Adjustment | 0005 | $-412.79 |
| 26232(04) | 0022 | 18" CGSP | Stockpiled Material Adjustment | 0003 | $-391.07 |
| 26232(04) | 0022 | 18" CGSP | Stockpiled Material Initial Payment | 0003 | $4,171.39 |
| 26232(04) | 0023 | 96" CGSP | Stockpiled Material Initial Payment | 0003 | $15,617.16 |
| 26232(04) | 0024 | 18" PCES round | Stockpiled Material Initial Payment | 0003 | $1,027.65 |
| 26232(04) | 0025 | 24" PCES Round | Stockpiled Material Initial Payment | 0003 | $1,707.23 |
| 26232(04) | 0026 | A4 CET | Stockpiled Material Initial Payment | 0003 | $105.43 |
| 26232(04) | 0027 | A6 CET | Stockpiled Material Initial Payment | 0003 | $128.86 |
| 26232(04) | 0043 | Prestressed Conc Beams | Stockpiled Material Initial Payment | 0003 | $181,971.09 |
| 26232(04) | 0046 | Traffic Rail | Stockpiled Material Initial Payment | 0003 | $2,982.00 |
| 26232(04) | 0052 | Epoxy Steel for piers & abut | Stockpiled Material Initial Payment | 0003 | $7,216.63 |
| 26232(04) | 0052 | Epoxy Steel for piers & abut | Stockpiled Material Adjustment | 0007 | $-2,208.54 |
| 26232(04) | 0052 | Bridge Deck Epoxy Steel | Stockpiled Material Adjustment | 0007 | $-2,208.52 |
| 26232(04) | 0052 | Bridge Deck Epoxy Steel | Stockpiled Material Initial Payment | 0005 | $16,196.58 |
| 26232(04) | 0052 | APPROACH SLABS | Stockpiled Material Adjustment | 0007 | $-7,274.72 |
| 26232(04) | 0052 | APPROACH SLABS | Stockpiled Material Initial Payment | 0005 | $7,274.72 |
| 26232(04) | 0053 | HP 10 x 42 Pilings | Stockpiled Material Initial Payment | 0005 | $7,361.80 |
| 26232(04) | 0053 | HP 10 x 42 Pilings | Stockpiled Material Adjustment | 0006 | $-7,361.80 |
| 26232(04) | 0054 | Piles encasement | Stockpiled Material Initial Payment | 0003 | $220.66 |
| 26232(04) | 0054 | Piles encasement | Stockpiled Material Adjustment | 0007 | $-220.66 |
| 26232(04) | 0054 | 10" Pile Points Piles Driven | Stockpiled Material Initial Payment | 0005 | $820.05 |
| 26232(04) | 0054 | 10" Pile Points Piles Driven | Stockpiled Material Adjustment | 0007 | $-820.05 |
| 26232(04) | 0057 | 36" CGSP for Drill Shafts | Stockpiled Material Initial Payment | 0003 | $1,798.25 |
| 26232(04) | 0057 | 36" CGSP for Drill Shafts | Stockpiled Material Adjustment | 0006 | $-1,798.25 |
| 26232(04) | 0057 | Reinforcing Steel DS | Stockpiled Material Adjustment | 0006 | $-2,504.57 |
| 26232(04) | 0057 | Reinforcing Steel DS | Stockpiled Material Initial Payment | 0003 | $2,504.57 | Subtotals For Stockpile Payments | $232,305.16 |
| LIQUIDATED DAMAGES HISTORY | |||||||||
| Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
| No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ | |||||||
| CONTRACT ADJUSTMENTS HISTORY | ||
| Adjustment Description | Estimate Nbr | Adjustment Amount |
| No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
| LINE ITEM ADJUSTMENT HISTORY | |||||||
| Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
| 26232(04) | 0015 | SUPERPAVE, TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0005 | 645.15 | $-1.04 | $-674.02 |
| 26232(04) | 0017 | SUPERPAVE, TYPE S4(PG 64-22 OK) | Asphalt Binder Adjustment | 0005 | 596.62 | $-1.19 | $-712.36 | Subtotals For Line Item Adjustments | $-1,386.38 |
| MILESTONE INFORMATION | |||||||||
| Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
| 01 | INCENTIVE/DISINCENTIVE | 11/12/2012 | NOT ENTERED | 150.00 DYS | $1,000.00 | N | |||
| MILESTONE ADJUSTMENTS | |||||||||
| Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
| No milestones adjustments exist for this contract. | Subtotals For Milestones | $ | |||||||
| Contract ID: | 120264 | Estimate Number: | 0007 | Primary JP: | 26232(04) | |||
| Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
| Fed/State Project Number: BRFY-164B(143) | Project: 26232(04) | Category: 0100/ROADWAY | ||||||||
| 0001 | CLEARING AND GRUBBING | 201(A) 0102 | LSUM | 1.000 | 1.000 | 1.000 | $35,000.00 | $0.00 | $35,000.00 | |
| 0002 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 11,116.000 | 11,116.000 | 81.780 | 2,819.520 | $6.00 | $490.68 | $16,917.12 |
| 0003 | UNCLASSIFIED BORROW | 202(D) 0184 | CY | 1,951.000 | 1,951.000 | 4,142.200 | $8.00 | $0.00 | $33,137.60 | |
| 0004 | TYPE A-SALVAGED TOPSOIL | 205(A) 4229 | LSUM | 1.000 | 1.000 | 0.000 | 0.500 | $11,000.00 | $0.00 | $5,500.00 |
| 0005 | TEMPORARY SILT FENCE | 221(C) 2801 | LF | 1,870.000 | 1,870.000 | 1,450.000 | $1.75 | $0.00 | $2,537.50 | |
| 0006 | TEMPORARY SILT DIKE | 221(F) 0100 | LF | 238.000 | 238.000 | 168.000 | $12.00 | $0.00 | $2,016.00 | |
| 0007 | SOLID SLAB SODDING | 230(A) 2806 | SY | 18,642.000 | 18,642.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
| 0008 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 3.860 | 3.860 | 0.000 | $950.00 | $0.00 | $0.00 | |
| 0009 | AGGREGATE BASE TYPE A | 303(A) 2100 | CY | 3,200.000 | 3,200.000 | 1,799.500 | $40.00 | $0.00 | $71,980.00 | |
| 0010 | SEPARATOR FABRIC | 325 5271 | SY | 8,105.000 | 8,105.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
| 0011 | TRAFFIC BOUND SURFACE COURSE TYPE E | 402(E) 0225 | TON | 1,603.000 | 1,603.000 | 115.200 | $23.00 | $0.00 | $2,649.60 | |
| 0012 | TACK COAT | 407(B) 0250 | GAL | 1,733.000 | 1,733.000 | 286.000 | $8.00 | $0.00 | $2,288.00 | |
| 0013 | PRIME COAT | 408 5774 | GAL | 5,238.000 | 5,238.000 | 914.000 | $8.50 | $0.00 | $7,769.00 | |
| 0014 | SUPERPAVE, TYPE S3(PG 76-28 OK) | 411(B) 5935 | TON | 638.000 | 638.000 | 0.000 | $93.00 | $0.00 | $0.00 | |
| 0015 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 411(B) 5945 | TON | 1,697.000 | 1,697.000 | 645.150 | $83.00 | $0.00 | $53,547.45 | |
| 0016 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 411(C) 5950 | TON | 594.000 | 594.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
| 0017 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 411(C) 5960 | TON | 720.000 | 720.000 | 596.620 | $88.00 | $0.00 | $52,502.56 | |
| 0018 | CLASS C CONCRETE | 509(D) 0325 | CY | 71.600 | 71.600 | 0.000 | $450.00 | $0.00 | $0.00 | |
| 0019 | TEMPORARY SHEET PILING | 514(J) 6390 | LSUM | 1.000 | 1.000 | 0.000 | $15,000.00 | $0.00 | $0.00 | |
| 0020 | 18" R.C.PIPE CLASS III | 613(A) 0491 | LF | 82.000 | 82.000 | 0.000 | $35.00 | $0.00 | $0.00 | |
| 0021 | 24" R.C.PIPE CLASS IV | 613(A) 0583 | LF | 111.000 | 111.000 | 0.000 | $45.00 | $0.00 | $0.00 | |
| 0022 | 18" CORR. GALV. STEEL PIPE | 613(B) 0689 | LF | 310.000 | 310.000 | 74.000 | $25.00 | $0.00 | $1,850.00 | |
| 0023 | 96" CORR. GALV. STEEL PIPE | 613(B) 4819 | LF | 188.000 | 188.000 | 188.000 | $100.00 | $0.00 | $18,800.00 | |
| 0024 | 18" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5726 | EA | 2.000 | 2.000 | 0.000 | $850.00 | $0.00 | $0.00 | |
| 0025 | 24" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5730 | EA | 3.000 | 3.000 | 0.000 | $950.00 | $0.00 | $0.00 | |
| 0026 | TYPE A4 CULVERT END TREATMENT | 613(M) 7186 | EA | 5.000 | 5.000 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
| 0027 | TYPE A6 CULVERT END TREATMENT | 613(M) 7196 | EA | 5.000 | 5.000 | 0.000 | $1,500.00 | $0.00 | $0.00 | |
| 0028 | STANDARD BEDDING MATERIAL, CLASS C | 613(T) 1187 | CY | 46.800 | 46.800 | 0.000 | $44.00 | $0.00 | $0.00 | |
| 0029 | TRENCH EXCAVATION | 613(V) 1180 | CY | 73.100 | 73.100 | 0.000 | $10.00 | $0.00 | $0.00 | |
| 0030 | REMOVAL OF FENCE | 619(B) 4725 | LF | 2,217.000 | 2,217.000 | 0.000 | $2.50 | $0.00 | $0.00 | |
| 0031 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 11,778.000 | 11,778.000 | 4,805.160 | $6.00 | $0.00 | $28,830.96 | |
| 0032 | REMOVAL OF EXISTING STRUCTURES | 619(B) 4778 | EA | 4.000 | 4.000 | 1.000 | 1.000 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0033 | REMOVAL OF GUARDRAIL | 619(B) 4780 | LF | 400.000 | 400.000 | 400.000 | $3.00 | $0.00 | $1,200.00 | |
| 0034 | SAWING PAVEMENT | 619(C) 0924 | LF | 437.000 | 437.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
| 0035 | BEAM GUARDRAIL W-BEAM SINGLE | 623(A) 0932 | LF | 487.500 | 487.500 | 0.000 | $16.50 | $0.00 | $0.00 | |
| 0036 | GUARDRAIL END TREATMENT (GET) | 623(G) 8571 | EA | 4.000 | 4.000 | 0.000 | $2,400.00 | $0.00 | $0.00 | |
| 0037 | GUARDRAIL BRIDGE CONNECTION-TYPE A | 623(I) 8675 | EA | 4.000 | 4.000 | 0.000 | $1,500.00 | $0.00 | $0.00 | |
| 0038 | FENCE-STYLE SWF (5 BARBED WIRE) | 624(C) 4459 | LF | 972.000 | 972.000 | 0.000 | $4.00 | $0.00 | $0.00 | |
| 0039 | REMOVE AND RESET MAILBOX | 629(E) 5048 | EA | 2.000 | 2.000 | 0.000 | $125.00 | $0.00 | $0.00 | |
| Subtotals For Category 0100/ROADWAY | $2,990.68 | $339,025.79 | ||||||||
| Fed/State Project Number: BRFY-164B(143) | Project: 26232(04) | Category: 0200/BRIDGE "A" | ||||||||
| 0040 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 68.000 | 68.000 | 0.000 | $6.00 | $0.00 | $0.00 | |
| 0041 | GRANULAR BACKFILL | 501(F) 6352 | CY | 10.000 | 10.000 | 4.970 | 4.970 | $55.00 | $273.35 | $273.35 |
| 0042 | CLSM BACKFILL | 501(G) 6309 | CY | 80.000 | 80.000 | 0.000 | $125.00 | $0.00 | $0.00 | |
| 0043 | PRESTRESSED CONCRETE BEAMS | 503(A) 6123 | LF | 1,155.000 | 1,155.000 | 0.000 | $220.00 | $0.00 | $0.00 | |
| 0044 | APPROACH SLAB | 504(A) 1304 | SY | 187.400 | 187.400 | 0.000 | $180.00 | $0.00 | $0.00 | |
| 0045 | SAW-CUT GROOVING | 504(B) 1305 | SY | 711.100 | 711.100 | 0.000 | $5.00 | $0.00 | $0.00 | |
| 0046 | CONCRETE RAIL (TR4) | 504(D) 6245 | LF | 320.000 | 320.000 | 0.000 | $85.00 | $0.00 | $0.00 | |
| 0047 | STRUCTURAL STEEL | 506(A) 1322 | LB | 960.000 | 960.000 | 100.000 | 100.000 | $7.00 | $700.00 | $700.00 |
| 0048 | ELASTOMERIC BEARING PADS | 507(C) 6282 | EA | 60.000 | 60.000 | 0.000 | $85.00 | $0.00 | $0.00 | |
| 0049 | CLASS AA CONCRETE | 509(A) 1326 | CY | 94.700 | 94.700 | 0.000 | $450.00 | $0.00 | $0.00 | |
| 0050 | CLASS A CONCRETE | 509(B) 1328 | CY | 92.200 | 92.200 | 25.000 | 25.000 | $550.00 | $13,750.00 | $13,750.00 |
| 0051 | CLASS C CONCRETE | 509(D) 1331 | CY | 12.800 | 12.800 | 1.400 | 1.400 | $800.00 | $1,120.00 | $1,120.00 |
| 0052 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 41,890.000 | 41,890.000 | 3,950.000 | 3,950.000 | $1.00 | $3,950.00 | $3,950.00 |
| 0053 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 350.000 | 350.000 | 350.000 | $50.00 | $0.00 | $17,500.00 | |
| 0054 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 350.000 | 350.000 | 77.840 | 77.840 | $8.00 | $622.72 | $622.72 |
| 0055 | (PL)PILOT HOLES | 514(K) 6260 | LF | 308.000 | 308.000 | 116.790 | 116.790 | $100.00 | $11,679.00 | $11,679.00 |
| 0056 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 223.000 | 223.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
| 0057 | DRILLED SHAFTS 36" DIAMETER | 516(A) 6092 | LF | 59.000 | 59.000 | 65.100 | $600.00 | $0.00 | $39,060.00 | |
| 0058 | TYPE I-A PLAIN RIPRAP | 601(B) 1353 | TON | 760.000 | 760.000 | 144.230 | $40.00 | $0.00 | $5,769.20 | |
| 0059 | TYPE I-A FILTER BLANKET | 601(C) 1355 | TON | 435.000 | 435.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
| 0060 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(H) 6204 | LF | 84.000 | 84.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
| 0061 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(I) 6207 | LF | 30.000 | 30.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
| 0062 | REMOVAL OF EXISTING BRIDGE STRUCTURE | 619(D) 1397 | LSUM | 1.000 | 1.000 | 1.000 | $37,000.00 | $0.00 | $37,000.00 | |
| Subtotals For Category 0200/BRIDGE "A" | $32,095.07 | $131,424.27 | ||||||||
| Fed/State Project Number: BRFY-164B(143) | Project: 26232(04) | Category: 0300/TRAFFIC | ||||||||
| 0063 | (PL)REMOVAL OF EXISTING SIGNS | 805(A) 8724 | EA | 3.000 | 3.000 | 3.000 | $75.00 | $0.00 | $225.00 | |
| 0064 | (PL)REMOVE & RESET EXISTING SIGNS | 805(D) 8756 | EA | 7.000 | 7.000 | 0.000 | $175.00 | $0.00 | $0.00 | |
| 0065 | SHEET ALUMINUM SIGNS | 850(A) 8110 | SF | 4.500 | 4.500 | 0.000 | $50.00 | $0.00 | $0.00 | |
| 0066 | 2" SQUARE TUBE POST | 851(C) 8324 | LF | 112.000 | 112.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
| 0067 | GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 853 9069 | EA | 16.000 | 16.000 | 0.000 | $18.00 | $0.00 | $0.00 | |
| 0068 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 854(A) 8800 | LF | 18,462.000 | 18,462.000 | 10,202.000 | $0.15 | $0.00 | $1,530.30 | |
| 0069 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 9,748.000 | 9,748.000 | 0.000 | $0.65 | $0.00 | $0.00 | |
| 0070 | TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 855(A) 8825 | LF | 27.000 | 27.000 | 0.000 | $11.00 | $0.00 | $0.00 | |
| 0071 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 857(F) 8006 | LF | 1,600.000 | 1,600.000 | 630.000 | $0.75 | $0.00 | $472.50 | |
| 0072 | DELIVER PORTABLE LONGITUDINAL BARRIER | 877(B) 8484 | LF | 2,151.000 | 2,151.000 | 2,086.000 | $23.00 | $0.00 | $47,978.00 | |
| 0073 | RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 877(C) 8486 | LF | 805.000 | 805.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
| 0074 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 7,815.000 | 7,815.000 | 234.000 | 1,088.000 | $0.85 | $198.90 | $924.80 |
| 0075 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 1,380.000 | 1,380.000 | 338.000 | 2,449.000 | $0.50 | $169.00 | $1,224.50 |
| 0076 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 2,400.000 | 2,400.000 | 338.000 | 1,970.000 | $0.75 | $253.50 | $1,477.50 |
| 0077 | CONSTRUCTION BARRICADES(TYPE III) | 880(C) 8842 | SD | 1,380.000 | 1,380.000 | 286.000 | 1,024.000 | $2.25 | $643.50 | $2,304.00 |
| 0078 | WING BARRICADES | 880(C) 8848 | SD | 960.000 | 960.000 | 52.000 | 436.000 | $0.25 | $13.00 | $109.00 |
| 0079 | VERTICAL PANELS | 880(D) 8854 | SD | 1,500.000 | 1,500.000 | 286.000 | 594.000 | $0.50 | $143.00 | $297.00 |
| 0080 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 5,160.000 | 5,160.000 | 819.000 | 3,869.000 | $0.10 | $81.90 | $386.90 |
| 0081 | DRUMS | 880(F) 8878 | SD | 8,660.000 | 8,660.000 | 611.000 | 4,949.000 | $0.10 | $61.10 | $494.90 |
| 0082 | PORT.CHANGEABLE MESSAGE SIGN | 882(A) 8306 | SD | 480.000 | 480.000 | 26.000 | 211.000 | $6.00 | $156.00 | $1,266.00 |
| Subtotals For Category 0300/TRAFFIC | $1,719.90 | $58,690.40 | ||||||||
| Fed/State Project Number: BRFY-164B(143) | Project: 26232(04) | Category: 0600/STAKING | ||||||||
| 0083 | CONSTRUCTION STAKING LEVEL II | 642(B) 0096 | LSUM | 1.000 | 1.000 | 0.500 | $11,000.00 | $0.00 | $5,500.00 | |
| Subtotals For Category 0600/STAKING | $0.00 | $5,500.00 | ||||||||
| Fed/State Project Number: BRFY-164B(143) | Project: 26232(04) | Category: 0640/CONSTRUCTION | ||||||||
| 0084 | SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.250 | $3,000.00 | $0.00 | $750.00 | |
| 0085 | FIELD OFFICE | 640(A) 1426 | EA | 1.000 | 1.000 | 1.000 | $3,000.00 | $0.00 | $3,000.00 | |
| 0086 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $102,000.00 | $0.00 | $102,000.00 | |
| Subtotals For Category 0640/CONSTRUCTION | $0.00 | $105,750.00 | ||||||||
| Subtotals For Project BRFY-164B(143) /26232(04) | $36,805.65 | $640,390.46 | ||||||||