Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    11/30/2012
Contract ID: 120259   Estimate Number: 0002     Contract No: 810231
Residency: OKLAHOMA CITY (04600)   Estimate Type: Progressive     Account No: 502400

Project Number(s): CMC-255E(091)
Primary Job Piece No: 29332(04)
Contract Description: RESURFACE (ASPHALT) PARKING LOT: BEGIN AT THE SOUTHWEST QUADRANT OF THE INTERSECTION OF LINCOLN BOULEVARD AND N.E. 18TH STREET IN OKC, EXTEND WEST.
Primary County: OKLAHOMA              
Name of Road: PARKING LOT              
Prime Contractor: SILVER STAR CONSTRUCTION COMPANY, INC.              
    2401 S. BROADWAY              
    MOORE , OK   73160              
Surety Company: OHIO CASUALTY INSURANCE COMPANY              

Date Let: 07/19/2012 NTP Effective Date: 10/01/2012 Pay Period: 10/16/2012  TO  11/30/2012
Date Awarded: 08/06/2012 Date Work Began: 10/01/2012 Original Contract Time: N/A
Date Contract Executed: 08/16/2012 Date Time Stopped: 10/15/2012 Current Time Charged: N/A
Date NTP Issued: 08/24/2012 Completion Date: 10/15/2012 Current Time Allowed: N/A
General Liability Expires: 05/19/2013 Workman's Comp Expires: 05/19/2013 Percent Time Used: N/A
Specification Year: 2009 FIXED COMPLETION DATE: 10/15/2012 Date Approved:

Current Contract Amount: $186,588.88 Total to Date Prev to Date This Estimate
Bid Amount: $160,294.00 Participating: $0.00 $0.00 $0.00
Percent Complete: 100 % Non Participating: $190,042.86 $182,389.48 $7,653.38
Funds Available: $0.01 Total Earnings: $190,042.86 $182,389.48 $7,653.38
Unearned Balance: $-26,294.87 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $190,042.86 $182,389.48 $7,653.38
Other Adjustments: $-3,453.99 $-22,095.49 $18,641.50
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $186,588.87 $160,293.99 $26,294.88

Estimate Adjustment Detail

Contract ID: 120259   Estimate Number: 0002     Primary JP: 29332(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Additional Appropriations for Over/Underruns Approved 11/19/2012 0.0 $26,294.88


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Withhold to Funds Avail(Prog. Est. Only) 0001 $-20,667.61
Withhold to Funds Avail(Prog. Est. Only) 0002 $20,667.61
Withhold to Funds Avail(Prog. Est. Only) 0002 $-2,018.54
Subtotals For Contract Adjustments $-2,018.54


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
29332(04) 0002 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0001 1,195.88 $-1.19 $-1,427.88
29332(04) 0002 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0002 6.34 $-1.19 $-7.57
Subtotals For Line Item Adjustments $-1,435.45


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120259   Estimate Number: 0002     Primary JP: 29332(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    CMC-255E(091) Project:    29332(04) Category:    0100/ROADWAY
0001 AGGREGATE BASE TYPE A 303(A) 2100 CY 200.000 126.750   126.750 $92.80 $0.00 $11,762.40
0002 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 900.000 1,195.880 6.340 1,202.220 $107.40 $680.92 $129,118.43
0003 COLD MILLING PAVEMENT 412 5267 SY 8,800.000 8,800.000 2,141.450 10,519.070 $2.10 $4,497.05 $22,090.05
0004 REINFORCING STEEL 511(A) 0332 LB 2,500.000 2,500.000 20.040 2,371.200 $0.58 $11.62 $1,375.29
0005 8" CONCRETE DRIVEWAY 610(B) 5016 SY 200.000 200.000   194.110 $76.75 $0.00 $14,897.94
0006 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 600.000 712.390   712.390 $11.70 $0.00 $8,334.96
Subtotals For Category     0100/ROADWAY    $5,189.59 $187,579.07
Fed/State Project Number:    CMC-255E(091) Project:    29332(04) Category:    0400/TRAFFIC
0007 TRAFFIC STRIPE(PAINT)(4" WIDE) 854(A) 8800 LF 5,000.000 5,000.000 4,870.250 4,870.250 $0.37 $1,801.99 $1,801.99
0008 TRAFFIC STRIPE(PAINT)(ARROW) 854(B) 8803 EA 4.000 4.000 4.000 4.000 $12.50 $50.00 $50.00
0009 TRAFFIC STRIPE(PAINT)(SYMBOLS) 854(B) 8809 EA 20.000 20.000 14.000 14.000 $43.70 $611.80 $611.80
Subtotals For Category     0400/TRAFFIC    $2,463.79 $2,463.79
Subtotals For Project CMC-255E(091) /29332(04) $7,653.38 $190,042.86