Oklahoma Department of Transportation
Final Estimate Affidavit

Contract ID: 120246   Estimate Number: 0006 , Final     Spec Year: 2009
Primary JP: 29311(04)   Residency: CLINTON (05100)     Contract No: 810224
Date Created: 07/05/2013   Contractor FEI: 731564757     Account No: 400500

Project Number(s): HSIPG-205F(014)TR
Contract Description: STRIPING AND PAVEMENT MARKING I-40/US-62/US-183/US-270/US-283/SH-6/SH-3/SH-33: MULTIPLE LOCATIONS IN DIVISION V.
Primary County: BECKHAM              
Name of Road: MULTIPLE LOCATIONS              
Prime Contractor: DIRECT TRAFFIC CONTROL INC.           Time Charged: 76.00
    P.O. BOX 602           Time Allowed: 45.00
    MUSKOGEE , OK   74402-0602           Percent Time: 168.89 %

  Paid To Date: $289,311.55 Payable This Statement: $9.00

CONTRACTOR AFFIDAVIT
STATE OF ___________________ )  
  )     §  
COUNTY OF __________________ )  
The undersigned contractor or duly authorized agent, of lawful age, being first duly sworn, on oath say that this claim is true and correct.
Affiant further states that the work, services or materials as shown by this claim have been completed or supplied in accordance with the plans, specifications, orders, requests and all other terms of the contract. Affiant further states that (s)he is duly authorized agent of the contractor for the purpose of certifying the facts pertaining to the giving of things of value to government personnel in order to procure the contract or obtain payment; that (s)he is fully aware of the facts and circumstances surrounding the making of the contract and has been personally and directly involved in the proceedings leading to the procurement of the contract and the filing of this claim; and, neither the contractor nor anyone subject to the contractor's direction or control has been paid, given or donated or agreed to pay, give or donate to any officer or employee of the State of Oklahoma any money or other thing of value, either directly or
indirectly, in procuring the contract or obtaining payment. The affiant further certifies that all laborers, mechanics, apprentices and trainees employed by him/her or by any subcontractor performing work under the contract on the project have been paid wages at rates not less than those required by the contract provisions, and that the work performed by each such laborer, mechanic, apprentice or trainee conformed to the classifications set forth in the contract or training program provisions applicable to the wage rate paid.
Affiant hereby agrees that Contractor will accept this estimate as full compensation for all money due Contractor by the Department of Transportation, and hereby relinquish all claims, either in contract or in tort, which have arisen or which might arise out of the construction of said project. That to the best of my knowledge and belief, all indebtedness for labor, materials, fuel, equipment, equipment rental, parts, supplies, insurance premiums, and claims for items not specifically mentioned, which are attributable to performance of the work on this project or which were incorporated therein in any manner, have been paid in full, and that there are not now any presently outstanding, unpaid claims for such indebtedness; that my position with the company is such, that if there were any such outstanding claims of the nature specified herein, I would ordinarily be aware of them.
Further affiant sayeth not.                                
DIRECT TRAFFIC CONTROL INC.                               
 
_________________________________________________
Affiant Signature
 
_________________________________________________
Affiant Printed Name
                          PE Seal
_________________________________________________
Affiant Company Position
Subscribed and sworn to before me this ______ day of ____________, 20____
My Commission Number: ____________ My Commission Expires: ______________
   
_________________________________________________              
_________________________________________________
                    Professional Engineer Signature
              Oklahoma Department of Transportation
Corporate Seal
Notary Seal                  

Oklahoma Department of Transportation
Final Estimate Summary
Created:    07/05/2013
Contract ID: 120246   Estimate Number: 0006     Contract No: 810224
Residency: CLINTON (05100)   Estimate Type: Final     Account No: 400500

Project Number(s): HSIPG-205F(014)TR
Primary Job Piece No: 29311(04)
Contract Description: STRIPING AND PAVEMENT MARKING I-40/US-62/US-183/US-270/US-283/SH-6/SH-3/SH-33: MULTIPLE LOCATIONS IN DIVISION V.
Primary County: BECKHAM              
Name of Road: MULTIPLE LOCATIONS              
Prime Contractor: DIRECT TRAFFIC CONTROL INC.              
    P.O. BOX 602              
    MUSKOGEE , OK   74402-0602              
Surety Company: EMPLOYERS MUTUAL CASUALTY COMPANY              

Date Let: 07/19/2012 NTP Effective Date: 09/24/2012 Pay Period: 02/01/2013  TO  06/30/2013
Date Awarded: 08/06/2012 Date Work Began: 10/07/2012 Original Contract Time: 45
Date Contract Executed: 08/21/2012 Date Time Stopped: 01/22/2013 Current Time Charged: 76.00
Date NTP Issued: 08/24/2012 Completion Date: 01/22/2013 Current Time Allowed: 45.00
General Liability Expires: 07/01/2014 Workman's Comp Expires: 07/01/2014 Percent Time Used: 168.89 %
Specification Year: 2009        

Current Contract Amount: $289,311.54 Total to Date Prev to Date This Estimate
Bid Amount: $300,000.00 Participating: $304,811.55 $304,802.55 $9.00
Percent Complete: 100 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $-0.01 Total Earnings: $304,811.55 $304,802.55 $9.00
Unearned Balance: $10,688.45 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $304,811.55 $304,802.55 $9.00
Other Adjustments: $0.00 $0.00 $0.00
Liq Dam/Disincentive: $-15,500.00 $-15,500.00 $0.00
TOTAL: $289,311.55 $289,302.55 $9.00

Estimate Adjustment Detail

Contract ID: 120246   Estimate Number: 0006     Primary JP: 29311(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Final Quantity Change Order Approved 06/25/2013 0.0 $-10,688.46


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0003 --6.0 $500.00 $-3,000.00
System Application of Liquidated Damages 0004 --19 $500.00 $-9,500.00
System Application of Liquidated Damages 0005 --6.0 $500.00 $-3,000.00
Subtotals For Liquidated Damages $-15,500.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120246   Estimate Number: 0006     Primary JP: 29311(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    HSIPG-205F(014)TR Project:    29311(04) Category:    0300/TRAFFIC CONTROL
0001 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 222,600.000 62,293.000   62,293.000 $0.46 $0.00 $28,654.78
0002 TRAFFIC STRIPE(PLASTIC)(8" WIDE) 855(A) 8814 LF 8,230.000 6,378.000   6,378.000 $1.00 $0.00 $6,378.00
0003 TRAFFIC STRIPE(PLASTIC)(24" WIDE) 855(A) 8825 LF 1,020.000 1,235.000   1,235.000 $3.00 $0.00 $3,705.00
0004 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 44.000 45.000   45.000 $90.00 $0.00 $4,050.00
0005 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 1.000 23.000   23.000 $200.00 $0.00 $4,600.00
0006 TRAFFIC STRIPE(PLASTIC)(SYMBOLS) 855(B) 8824 EA 8.000 8.000   8.000 $2,000.00 $0.00 $16,000.00
0007 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 856(A) 8530 LF 130,075.000 300,212.000   300,212.000 $0.38 $0.00 $114,080.56
0008 TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) 856(A) 8540 LF 7,545.000 8,240.000   8,240.000 $0.80 $0.00 $6,592.00
0009 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) 856(A) 8555 LF 2,914.000 2,786.000 3.000 2,786.000 $3.00 $9.00 $8,358.00
0010 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) 856(B) 8860 EA 145.000 144.000   144.000 $70.00 $0.00 $10,080.00
0011 TRAFFIC STRIPE(MULTI-POLY.)(SYMBOLS) 856(B) 8870 EA 22.000 22.000   22.000 $200.00 $0.00 $4,400.00
0012 TRAFFIC STRIPE(MULTI-POLY.)(WORDS) 856(B) 8880 EA 41.000 19.000   19.000 $125.00 $0.00 $2,375.00
0013 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 857(F) 8006 LF 321,535.000 414,193.000   414,193.000 $0.15 $0.00 $62,128.95
0014 PAVEMENT MARKING REMOVAL(ARROWS) 857(F) 8007 EA 189.000 182.000   182.000 $25.00 $0.00 $4,550.00
0015 PAVEMENT MARKING REMOVAL(WORDS) 857(F) 8008 EA 30.000 30.000   30.000 $25.00 $0.00 $750.00
0016 PAVEMENT MARKING REMOVAL(SYMBOLS) 857(F) 8009 EA 24.000 24.000   24.000 $123.00 $0.00 $2,952.00
0017 PAVEMENT MARKERS CLASS A TYPE 1-B 858(A) 8899 EA 135.000 108.000   108.000 $4.00 $0.00 $432.00
0018 PAVEMENT MARKERS CLASS A TYPE 2-C 858(A) 8911 EA 250.000 223.000   223.000 $5.00 $0.00 $1,115.00
0019 PAVEMENT MARKERS CLASS A TYPE 2-D 858(A) 8914 EA 765.000 722.000   722.000 $5.00 $0.00 $3,610.00
0020 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $10,000.25 $0.00 $10,000.26
9000 CONSTRUCTION MISCELLANEOUS 104 0600 EA 0.000 31.000   0.000 $-500.00 $0.00 $0.00
Subtotals For Category     0300/TRAFFIC CONTROL    $9.00 $294,811.55
Fed/State Project Number:    HSIPG-205F(014)TR Project:    29311(04) Category:    0640/CONSTRUCTION
0021 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $10,000.00
Subtotals For Project HSIPG-205F(014)TR /29311(04) $9.00 $304,811.55


1 CURRENT QUANTITIES DO NOT MATCH THE QUANTITY PAID TO DATE