Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    04/02/2013
Contract ID: 120245   Estimate Number: 0004     Contract No: 810265
Residency: ANTLERS (02100)   Estimate Type: Progressive     Account No: 400200

Project Number(s): HSIPG-203F(008)TR
Primary Job Piece No: 29308(04)
Contract Description: STRIPING AND PAVEMENT MARKING US-69/US-70/US-70B/US-271B: MULTIPLE LOCATIONS IN DIVISION II.
Primary County: ATOKA              
Name of Road: US-69/US-70/US-70B/              
Prime Contractor: DIRECT TRAFFIC CONTROL INC.              
    P.O. BOX 602              
    MUSKOGEE , OK   74402-0602              
Surety Company: EMPLOYERS MUTUAL CASUALTY COMPANY              

Date Let: 07/19/2012 NTP Effective Date: 10/01/2012 Pay Period: 03/01/2013  TO  03/31/2013
Date Awarded: 08/06/2012 Date Work Began: 10/01/2012 Original Contract Time: 45
Date Contract Executed: 08/21/2012 Date Time Stopped: 03/25/2013 Current Time Charged: 98.00
Date NTP Issued: 08/24/2012 Completion Date: 03/25/2013 Current Time Allowed: 45.00
General Liability Expires: 07/01/2013 Workman's Comp Expires: 07/01/2013 Percent Time Used: 217.78 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $297,000.00 Total to Date Prev to Date This Estimate
Bid Amount: $297,000.00 Participating: $305,307.05 $163,928.75 $141,378.30
Percent Complete: 93.87 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $18,192.95 Total Earnings: $305,307.05 $163,928.75 $141,378.30
Unearned Balance: $18,192.95 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $305,307.05 $163,928.75 $141,378.30
Other Adjustments: $0.00 $0.00 $0.00
Liq Dam/Disincentive: $-26,500.00 $-18,500.00 $-8,000.00
TOTAL: $278,807.05 $145,428.75 $133,378.30

Estimate Adjustment Detail

Contract ID: 120245   Estimate Number: 0004     Primary JP: 29308(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Final Quantity Change Order Pending 0 0.0 $8,307.05


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0002 --10 $500.00 $-5,000.00
System Application of Liquidated Damages 0003 --27 $500.00 $-13,500.00
System Application of Liquidated Damages 0004 --16 $500.00 $-8,000.00
Subtotals For Liquidated Damages $-26,500.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120245   Estimate Number: 0004     Primary JP: 29308(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    HSIPG-203F(008)TR Project:    29308(04) Category:    0300/PAVEMENT MARKING
0001 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 856(A) 8530 LF 84,000.000 84,000.000 0.000 295,072.000 $0.33 $0.00 $97,373.76
0002 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) 856(A) 8535 LF 415,720.000 415,720.000 350,853.000 350,853.000 $0.35 $122,798.55 $122,798.55
0003 TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) 856(A) 8540 LF 7,431.000 7,431.000 8,670.000 9,875.000 $1.00 $8,670.00 $9,875.00
0004 TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) 856(A) 8548 LF 5,587.000 5,587.000 2,975.000 3,200.000 $2.00 $5,950.00 $6,400.00
0005 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) 856(A) 8555 LF 132.000 132.000 37.000 49.000 $6.00 $222.00 $294.00
0006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 857(F) 8006 LF 611,000.000 611,000.000   335,498.000 $0.13 $0.00 $43,614.74
0007 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 1.000 $14,951.00 $3,737.75 $14,951.00
Subtotals For Category     0300/PAVEMENT MARKING    $141,378.30 $295,307.05
Fed/State Project Number:    HSIPG-203F(008)TR Project:    29308(04) Category:    0640/CONSTRUCTION
0008 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $10,000.00
Subtotals For Project HSIPG-203F(008)TR /29308(04) $141,378.30 $305,307.05