Contract ID: | 120234 | Estimate Number: | 0001 | Contract No: | 810002 | |||
Residency: | PERRY (04100) | Estimate Type: | Progressive | Account No: | 404400 | |||
Project Number(s): | SSR-152C(190)SR | ||||||||||||
Primary Job Piece No: | 27600(04) | ||||||||||||
Contract Description: | RESURFACE (ASPHALT) US-77: FROM SH-164, EXTEND EAST. PROJECT LENGTH = 5.36 MILES. | ||||||||||||
Primary County: | NOBLE | ||||||||||||
Name of Road: | US-77 | ||||||||||||
Prime Contractor: | HASKELL LEMON CONSTRUCTION CO. | ||||||||||||
P. O. BOX 75608 | |||||||||||||
OKLAHOMA CITY , OK 73147-0608 | |||||||||||||
Surety Company: | WESTERN SURETY COMPANY | ||||||||||||
Date Let: | 05/17/2012 | NTP Effective Date: | 10/25/2012 | Pay Period: | 06/18/2012 TO 07/31/2012 |
Date Awarded: | 06/04/2012 | Date Work Began: | 07/27/2012 | Original Contract Time: | N/A |
Date Contract Executed: | 06/14/2012 | Date Time Stopped: | Current Time Charged: | N/A | |
Date NTP Issued: | 06/18/2012 | Completion Date: | Current Time Allowed: | N/A | |
General Liability Expires: | 07/01/2013 | Workman's Comp Expires: | 07/01/2013 | Percent Time Used: | N/A |
Specification Year: | 2009 | FIXED COMPLETION DATE: | 10/31/2012 | Date Approved: | |
Current Contract Amount: | $1,764,920.00 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $1,764,920.00 | Participating: | $0.00 | $0.00 | $0.00 | ||
Percent Complete: | 0.19 % | Non Participating: | $3,429.00 | $0.00 | $3,429.00 | ||
Funds Available: | $1,761,491.00 | Total Earnings: | $3,429.00 | $0.00 | $3,429.00 | ||
Unearned Balance: | $1,761,491.00 | Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||
Gross Earnings: | $3,429.00 | $0.00 | $3,429.00 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $3,429.00 | $0.00 | $3,429.00 |
Contract ID: | 120234 | Estimate Number: | 0001 | Primary JP: | 27600(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 120234 | Estimate Number: | 0001 | Primary JP: | 27600(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: SSR-152C(190)SR | Project: 27600(04) | Category: 0200/ROADWAY | ||||||||
0001 | UNCLASSIFIED BORROW (TOPSOIL) | 202(D) 4781 | CY | 400.000 | 400.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0002 | EARTHWORK | 202(H) 0185 | LSUM | 1.000 | 1.000 | 0.000 | $25,000.00 | $0.00 | $0.00 | |
0003 | SOLID SLAB SODDING | 230(A) 2806 | SY | 500.000 | 500.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0004 | AGGREGATE BASE TYPE A | 303(A) 2100 | CY | 300.000 | 300.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0005 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 411(B) 5945 | TON | 500.000 | 500.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
0006 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 411(C) 5960 | TON | 16,800.000 | 16,800.000 | 0.000 | $79.25 | $0.00 | $0.00 | |
0007 | COLD MILLING PAVEMENT | 412 5267 | SY | 155,000.000 | 155,000.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
0008 | CLASS A CONCRETE | 509(B) 1328 | CY | 18.000 | 18.000 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0009 | REINFORCING STEEL | 511(A) 0332 | LB | 1,300.000 | 1,300.000 | 0.000 | $1.00 | $0.00 | $0.00 | |
0010 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 3.000 | 3.000 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0011 | VALVE BOXES ADJUST TO GRADE | 612(E) 0647 | EA | 1.000 | 1.000 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0012 | REMOVAL OF HEADWALL | 619(B) 0291 | EA | 2.000 | 2.000 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0013 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 150.000 | 150.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0014 | REMOVAL OF CURB | 619(B) 4791 | LF | 1,000.000 | 1,000.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0015 | REMOVAL OF BRICK CHATTER MEDIAN | 619(B) 5150 | SY | 226.000 | 226.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
0016 | REMOVAL OF PAVING BRICK ROADWAY | 619(B) 6118 | SY | 800.000 | 800.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
0017 | REMOVAL OF 6" CONCRETE DIVIDING STRIP | 619(B) 6132 | SY | 240.000 | 240.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
Subtotals For Category 0200/ROADWAY | $0.00 | $0.00 | ||||||||
Fed/State Project Number: SSR-152C(190)SR | Project: 27600(04) | Category: 0300/TRAFFIC | ||||||||
0018 | LOOP DETECTOR WIRE | 828(B) 8136 | LF | 800.000 | 800.000 | 762.000 | 762.000 | $4.50 | $3,429.00 | $3,429.00 |
0019 | TRAFFIC STRIPE(PAINT)(SYMBOLS) | 854(B) 8809 | EA | 5.000 | 5.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
0020 | TRAFFIC STRIPE(PLASTIC)(8" WIDE) | 855(A) 8814 | LF | 1,000.000 | 1,000.000 | 0.000 | $0.35 | $0.00 | $0.00 | |
0021 | TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 855(A) 8825 | LF | 1,700.000 | 1,700.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
0022 | TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) | 855(A) 8840 | LF | 110,000.000 | 110,000.000 | 0.000 | $0.35 | $0.00 | $0.00 | |
0023 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 18.000 | 18.000 | 0.000 | $35.00 | $0.00 | $0.00 | |
0024 | TRAFFIC STRIPE(PLASTIC)(WORDS) | 855(B) 8821 | EA | 9.000 | 9.000 | 0.000 | $225.00 | $0.00 | $0.00 | |
0025 | TRAFFIC STRIPE(PLASTIC)(SYMBOLS) | 855(B) 8824 | EA | 3.000 | 3.000 | 0.000 | $675.00 | $0.00 | $0.00 | |
0026 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.000 | $10,000.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC | $3,429.00 | $3,429.00 | ||||||||
Subtotals For Project SSR-152C(190)SR /27600(04) | $3,429.00 | $3,429.00 |