Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    09/05/2012
Contract ID: 120233   Estimate Number: 0001     Contract No: 810135
Residency: BUFFALO (06100)   Estimate Type: Progressive     Account No: 404600

Project Number(s): SSR-176B(178)SR
Primary Job Piece No: 27560(04)
Contract Description: RESURFACE (ASPHALT) US-281: BEGIN 2.4 MILES NORTH OF US-64, EXTEND NORTH. PROJECT LENGTH = 6.00 MILES
Primary County: WOODS              
Name of Road: US-281              
Prime Contractor: THE CUMMINS CONSTRUCTION CO., INC.              
    P. O. BOX 748              
    ENID , OK   73702              
Surety Company: HARTFORD ACCIDENT & INDEMNITY COMPANY              

Date Let: 06/21/2012 NTP Effective Date: 08/06/2012 Pay Period: 07/18/2012  TO  08/31/2012
Date Awarded: 07/02/2012 Date Work Began: 08/06/2012 Original Contract Time: 35
Date Contract Executed: 07/12/2012 Date Time Stopped: Current Time Charged: 26.00
Date NTP Issued: 07/18/2012 Completion Date: Current Time Allowed: 35.00
General Liability Expires: 09/01/2012 Workman's Comp Expires: 01/01/2013 Percent Time Used: 74.29 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $899,680.00 Total to Date Prev to Date This Estimate
Bid Amount: $899,680.00 Participating: $0.00 $0.00 $0.00
Percent Complete: 87.78 % Non Participating: $792,449.66 $0.00 $792,449.66
Funds Available: $109,898.47 Total Earnings: $792,449.66 $0.00 $792,449.66
Unearned Balance: $109,898.47 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $792,449.66 $0.00 $792,449.66
Other Adjustments: $-2,668.13 $0.00 $-2,668.13
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $789,781.53 $0.00 $789,781.53

Estimate Adjustment Detail

Contract ID: 120233   Estimate Number: 0001     Primary JP: 27560(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
27560(04) 0002 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0001 7,537.09 $-0.35 $-2,668.13
Subtotals For Line Item Adjustments $-2,668.13


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120233   Estimate Number: 0001     Primary JP: 27560(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SSR-176B(178)SR Project:    27560(04) Category:    0100/ROADWAY
0001 TACK COAT 407(B) 0250 GAL 5,430.000 5,430.000 1,875.000 1,875.000 $4.00 $7,500.00 $7,500.00
0002 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 7,600.000 7,600.000 7,537.090 7,537.090 $98.40 $741,649.66 $741,649.66
Subtotals For Category     0100/ROADWAY    $749,149.66 $749,149.66
Fed/State Project Number:    SSR-176B(178)SR Project:    27560(04) Category:    0300/TRAFFIC
0003 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 856(A) 8530 LF 89,500.000 89,500.000   0.000 $0.56 $0.00 $0.00
0004 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.900 0.900 $10,000.00 $9,000.00 $9,000.00
Subtotals For Category     0300/TRAFFIC    $9,000.00 $9,000.00
Fed/State Project Number:    SSR-176B(178)SR Project:    27560(04) Category:    0640/CONSTRUCTION
0005 MOBILIZATION 641 1552 LSUM 1.000 1.000 0.490 0.490 $70,000.00 $34,300.00 $34,300.00
Subtotals For Category     0640/CONSTRUCTION    $34,300.00 $34,300.00
Subtotals For Project SSR-176B(178)SR /27560(04) $792,449.66 $792,449.66