Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    10/17/2012
Contract ID: 120183   Estimate Number: 0003     Contract No: 810000
Residency: ANTLERS (02100)   Estimate Type: Progressive     Account No: 404200

Project Number(s): SSR-245A(001)SR, SSR-245A(002)SR
Primary Job Piece No: 29031(04)
Contract Description: RESURFACE (ASPHALT) US-259: BEGIN 8.656 NORTH OF THE END OF CONCRETE PAVEMENT IN BROKEN BOW (6TH STREET) AND EXTEND NORTH. PROJECT LENGTH = 12.00 MILES
Primary County: MCCURTAIN              
Name of Road: US-259              
Prime Contractor: THE CUMMINS CONSTRUCTION CO., INC.              
    P. O. BOX 748              
    ENID , OK   73702              
Surety Company: HARTFORD ACCIDENT & INDEMNITY COMPANY              

Date Let: 05/17/2012 NTP Effective Date: 07/16/2012 Pay Period: 10/01/2012  TO  10/15/2012
Date Awarded: 06/04/2012 Date Work Began: Original Contract Time: 75
Date Contract Executed: 06/15/2012 Date Time Stopped: Current Time Charged: 82.00
Date NTP Issued: 06/21/2012 Completion Date: Current Time Allowed: 75.00
General Liability Expires: 09/01/2013 Workman's Comp Expires: 01/01/2013 Percent Time Used: 109.33 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $2,685,984.80 Total to Date Prev to Date This Estimate
Bid Amount: $2,685,984.80 Participating: $0.00 $0.00 $0.00
Percent Complete: 68.94 % Non Participating: $1,881,935.19 $872,783.97 $1,009,151.22
Funds Available: $834,325.53 Total Earnings: $1,881,935.19 $872,783.97 $1,009,151.22
Unearned Balance: $834,325.53 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $1,881,935.19 $872,783.97 $1,009,151.22
Other Adjustments: $-25,025.92 $-13,901.18 $-11,124.74
Liq Dam/Disincentive: $-5,250.00 $0.00 $-5,250.00
TOTAL: $1,851,659.27 $858,882.79 $992,776.48

Estimate Adjustment Detail

Contract ID: 120183   Estimate Number: 0003     Primary JP: 29031(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Time extension for delayed start. Pending 0 14.0 $0.00


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0003 --7.0 $750.00 $-5,250.00
Subtotals For Liquidated Damages $-5,250.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
29031(04) 0002 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0003 5,633.64 $-0.96 $-5,415.06
29032(04) 0009 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 3,797.17 $-0.72 $-2,738.52
29032(04) 0009 SUPERPAVE, TYPE S4(PG 76-28 OK) * HMA Deduction as per Sec. 411 0002 -60.00 $85.10 $-5,106.00
29032(04) 0009 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0002 6,038.08 $-0.72 $-4,354.66
29032(04) 0009 SUPERPAVE, TYPE S4(PG 76-28 OK) * HMA Deduction as per Sec. 411 0002 -20.00 $85.10 $-1,702.00
29032(04) 0009 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0003 5,940.16 $-0.96 $-5,709.68
Subtotals For Line Item Adjustments $-25,025.92
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120183   Estimate Number: 0003     Primary JP: 29031(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SSR-245A(001)SR Project:    29031(04) Category:    0100/ROADWAY - SSR-245A(001)SR
0001 TACK COAT 407(B) 0250 GAL 7,063.000 7,063.000 4,150.000 4,183.330 $3.25 $13,487.50 $13,595.82
0002 SUPERPAVE, TYPE S4(PG 76-28 OK) 411(C) 5950 TON 5,297.000 5,297.000 5,633.640 5,633.640 $85.10 $479,422.76 $479,422.76
0003 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 1,977.000 1,977.000   0.000 $75.75 $0.00 $0.00
0004 COLD MILLING PAVEMENT 412 5267 SY 250.000 250.000   248.880 $13.00 $0.00 $3,235.44
Subtotals For Category     0100/ROADWAY - SSR-245A(001)SR    $492,910.26 $496,254.02
Fed/State Project Number:    SSR-245A(001)SR Project:    29031(04) Category:    0300/TRAFFIC - SSR-245A(001)SR
0005 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 70,624.000 70,624.000   0.000 $0.33 $0.00 $0.00
0006 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 4.000 4.000   0.000 $150.00 $0.00 $0.00
0007 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.400 0.650 $8,400.00 $3,360.00 $5,460.00
Subtotals For Category     0300/TRAFFIC - SSR-245A(001)SR    $3,360.00 $5,460.00
Subtotals For Project SSR-245A(001)SR /29031(04) $496,270.26 $501,714.02


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SSR-245A(002)SR Project:    29032(04) Category:    0100/ROADWAY - SSR-245A(002)SR
0008 TACK COAT 407(B) 0250 GAL 19,660.000 19,660.000 2,425.000 9,266.670 $3.25 $7,881.25 $30,116.68
0009 SUPERPAVE, TYPE S4(PG 76-28 OK) 411(C) 5950 TON 16,059.000 16,059.000 5,940.160 15,775.410 $85.10 $505,507.62 $1,342,487.40
0010 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 6,962.000 6,962.000   0.000 $75.75 $0.00 $0.00
0011 COLD MILLING PAVEMENT 412 5267 SY 1,250.000 1,250.000 -78.140 1,171.860 $6.50 $-507.91 $7,617.09
Subtotals For Category     0100/ROADWAY - SSR-245A(002)SR    $512,880.96 $1,380,221.17
Fed/State Project Number:    SSR-245A(002)SR Project:    29032(04) Category:    0300/TRAFFIC - SSR-245A(002)SR
0012 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 182,816.000 182,816.000   0.000 $0.33 $0.00 $0.00
0013 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 4.000 4.000   0.000 $150.00 $0.00 $0.00
Subtotals For Category     0300/TRAFFIC - SSR-245A(002)SR    $0.00 $0.00
Subtotals For Project SSR-245A(002)SR /29032(04) $512,880.96 $1,380,221.17