Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    10/01/2012
Contract ID: 120181   Estimate Number: 0005     Contract No: 810014
Residency: SAND SPRINGS (08400)   Estimate Type: Progressive     Account No: 432800

Project Number(s): BRO-119D(129)CO
Primary Job Piece No: 22750(04)
Contract Description: BRIDGE AND APPROACHES COUNTY ROAD (EW-60): OVER LAGOON CREEK 2.0 MILES NORTH AND 1.0 MILES WEST OF THE SH-51/SH-99 JCT. PROJECT LENGTH = 0.283 MILES
Primary County: CREEK              
Name of Road: COUNTY ROAD (EW-60)              
Prime Contractor: BELK BRIDGE, INC.              
    4 RIVER RIDGE ROAD              
    BROKEN ARROW , OK   74014              
Surety Company: OHIO CASUALTY INSURANCE COMPANY              

Date Let: 05/17/2012 NTP Effective Date: 09/04/2012 Pay Period: 09/16/2012  TO  09/30/2012
Date Awarded: 06/04/2012 Date Work Began: 07/10/2012 Original Contract Time: 120
Date Contract Executed: 06/15/2012 Date Time Stopped: Current Time Charged: 79.00
Date NTP Issued: 06/20/2012 Completion Date: Current Time Allowed: 120.00
General Liability Expires: 08/27/2013 Workman's Comp Expires: 09/01/2013 Percent Time Used: 65.83 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $620,757.75 Total to Date Prev to Date This Estimate
Bid Amount: $620,757.75 Participating: $463,545.67 $268,129.17 $195,416.50
Percent Complete: 71.07 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $179,590.08 Total Earnings: $463,545.67 $268,129.17 $195,416.50
Unearned Balance: $179,590.08 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $463,545.67 $268,129.17 $195,416.50
Other Adjustments: $-22,378.00 $-5,559.00 $-16,819.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $441,167.67 $262,570.17 $178,597.50

Estimate Adjustment Detail

Contract ID: 120181   Estimate Number: 0005     Primary JP: 22750(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
22750(04) 0004 TEMPORARY SILT FENCE * Missing Material Certification 0002 -200.00 $1.25 $-250.00
22750(04) 0004 TEMPORARY SILT FENCE * Missing Material Certification 0003 -260.00 $1.25 $-325.00
22750(04) 0004 TEMPORARY SILT FENCE * Missing Material Certification 0004 -400.00 $1.25 $-500.00
22750(04) 0004 TEMPORARY SILT FENCE * Missing Material Certification 0005 -200.00 $1.25 $-250.00
22750(04) 0005 TEMPORARY SILT DIKE * Missing Material Certification 0004 -28.00 $3.00 $-84.00
22750(04) 0017 SEALED EXPANSION JOINT * Missing Material Certification 0005 -33.50 $150.00 $-5,025.00
22750(04) 0019 STRUCTURAL STEEL * Missing Material Certification 0005 -686.00 $4.00 $-2,744.00
22750(04) 0020 WEATHERING STEEL FIXED BEARING ASSEMBLY * Missing Material Certification 0003 -4.00 $550.00 $-2,200.00
22750(04) 0020 WEATHERING STEEL FIXED BEARING ASSEMBLY * Missing Material Certification 0005 -8.00 $550.00 $-4,400.00
22750(04) 0021 WEATHERING STEEL EXPANSION BEARING ASSEMBLY * Missing Material Certification 0003 -4.00 $550.00 $-2,200.00
22750(04) 0021 WEATHERING STEEL EXPANSION BEARING ASSEMBLY * Missing Material Certification 0005 -8.00 $550.00 $-4,400.00
22750(04) 0027 DRILLED SHAFTS 54" DIAMETER * Material Discrepancy Adjustments 0002 -26.10 $600.00 $-15,660.00
22750(04) 0027 DRILLED SHAFTS 54" DIAMETER * Material Discrepancy Adjustments 0003 26.10 $600.00 $15,660.00
Subtotals For Line Item Adjustments $-22,378.00
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120181   Estimate Number: 0005     Primary JP: 22750(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BRO-119D(129)CO Project:    22750(04) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201(A) 0102 LSUM 1.000 1.000   1.000 $7,000.00 $0.00 $7,000.00
0002 EARTHWORK 202(H) 0185 LSUM 1.000 1.000   0.500 $50,000.00 $0.00 $25,000.00
0003 TYPE A-SALVAGED TOPSOIL 205(A) 4229 LSUM 1.000 1.000 0.000 0.500 $3,000.00 $0.00 $1,500.00
0004 TEMPORARY SILT FENCE 221(C) 2801 LF 1,500.000 1,500.000 200.000 1,060.000 $1.25 $250.00 $1,325.00
0005 TEMPORARY SILT DIKE 221(F) 0100 LF 200.000 200.000 0.000 28.000 $3.00 $0.00 $84.00
0006 SOLID SLAB SODDING 230(A) 2806 SY 7,900.000 7,900.000   0.000 $1.58 $0.00 $0.00
0007 VEGETATIVE MULCHING 233(A) 2817 AC 1.700 1.700   0.000 $700.00 $0.00 $0.00
0008 TRAFFIC BOUND SURFACE COURSE TYPE E 402(E) 0225 TON 781.000 781.000   0.000 $19.00 $0.00 $0.00
0009 CLASS C CONCRETE 509(D) 0325 CY 20.000 20.000   0.000 $100.00 $0.00 $0.00
0010 TYPE I PLAIN RIPRAP 601(A) 0297 TON 505.000 505.000   0.000 $29.00 $0.00 $0.00
0011 24" CORR. GALV. STEEL PIPE 613(B) 0690 LF 90.000 90.000   0.000 $15.00 $0.00 $0.00
0012 TYPE B4 CULVERT END TREATMENT 613(M) 7187 EA 4.000 4.000   0.000 $900.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY    $250.00 $34,909.00
Fed/State Project Number:    BRO-119D(129)CO Project:    22750(04) Category:    0200/BRIDGE 'A'
0013 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 88.000 88.000   88.000 $25.00 $0.00 $2,200.00
0014 UNCLASSIFIED BACKFILL 501(D) 6353 CY 90.000 90.000   0.000 $20.00 $0.00 $0.00
0015 PRESTRESSED CONCRETE BEAMS (TYPE III) 503(A) 1312 LF 728.500 728.500 490.500 728.500 $175.00 $85,837.50 $127,487.50
0016 SAW-CUT GROOVING 504(B) 1305 SY 552.000 552.000   0.000 $4.15 $0.00 $0.00
0017 SEALED EXPANSION JOINT 504(C) 6250 LF 33.500 33.500 33.500 33.500 $150.00 $5,025.00 $5,025.00
0018 CONCRETE RAIL (TR1) 504(E) 1380 LF 435.170 435.170 141.660 141.660 $85.00 $12,041.10 $12,041.10
0019 STRUCTURAL STEEL 506(A) 1322 LB 686.000 686.000 572.000 686.000 $4.00 $2,288.00 $2,744.00
0020 WEATHERING STEEL FIXED BEARING ASSEMBLY 507(A) 6172 EA 12.000 12.000 8.000 12.000 $550.00 $4,400.00 $6,600.00
0021 WEATHERING STEEL EXPANSION BEARING ASSEMBLY 507(B) 6176 EA 12.000 12.000 8.000 12.000 $550.00 $4,400.00 $6,600.00
0022 CLASS AA CONCRETE 509(A) 1326 CY 141.700 141.700 138.070 141.700 $350.00 $48,324.50 $49,595.00
0023 CLASS A CONCRETE 509(B) 1328 CY 101.400 101.400   101.400 $350.00 $0.00 $35,490.00
0024 REINFORCING STEEL 511(A) 1332 LB 45,400.000 45,400.000 31,540.000 45,400.000 $0.99 $31,224.60 $44,946.00
0025 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 597.000 597.000   597.000 $18.00 $0.00 $10,746.00
0026 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 597.000 597.000   432.010 $9.00 $0.00 $3,888.09
0027 DRILLED SHAFTS 54" DIAMETER 516(A) 6095 LF 156.000 156.000   123.820 $600.00 $0.00 $74,292.00
0028 TYPE I-A PLAIN RIPRAP 601(B) 1353 TON 1,170.000 1,170.000   496.580 $29.00 $0.00 $14,400.82
0029 TYPE I-A FILTER BLANKET 601(C) 1355 TON 165.000 165.000 22.950 139.840 $24.00 $550.80 $3,356.16
0030 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $8,000.00 $0.00 $8,000.00
0031 GUARDRAIL ANCHOR UNIT (TYPE II) 623(F) 6033 EA 4.000 4.000   0.000 $1,875.00 $0.00 $0.00
0032 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.750 $2,800.00 $700.00 $2,100.00
Subtotals For Category     0200/BRIDGE 'A'    $194,791.50 $409,511.67
Fed/State Project Number:    BRO-119D(129)CO Project:    22750(04) Category:    0600/STAKING
0033 CONSTRUCTION STAKING LEVEL II 642(B) 0096 LSUM 1.000 1.000   0.750 $4,000.00 $0.00 $3,000.00
Subtotals For Category     0600/STAKING    $0.00 $3,000.00
Fed/State Project Number:    BRO-119D(129)CO Project:    22750(04) Category:    0640/CONSTRUCTION
0034 SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000 0.250 0.750 $1,500.00 $375.00 $1,125.00
0035 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $15,000.00 $0.00 $15,000.00
Subtotals For Category     0640/CONSTRUCTION    $375.00 $16,125.00
Subtotals For Project BRO-119D(129)CO /22750(04) $195,416.50 $463,545.67