Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    02/21/2014
Contract ID: 120180   Estimate Number: 0003     Contract No: 810039
Residency: ANADARKO (07300)   Estimate Type: Progressive     Account No: 400700

Project Number(s): STPY-216C(006)RW
Primary Job Piece No: 21717(08)
Contract Description: RIGHT-OF-WAY CLEARANCE US 277: BEGIN 0.04 MILES EAST OF US-62, EXTEND EAST. PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED. BOTH BIDEXPRESS AND WRITTEN BIDS WILL BE ACCEPTED.
Primary County: COMANCHE              
Name of Road: US-277              
Prime Contractor: M & M WRECKING, INC.              
    860 COUNTYLINE ROAD              
    BLANCHARD , OK   73010-4426              
Surety Company: MERCHANTS BONDING COMPANY              

Date Let: 05/17/2012 NTP Effective Date: 08/06/2012 Pay Period: 12/01/2012  TO  02/01/2014
Date Awarded: 06/04/2012 Date Work Began: 09/25/2012 Original Contract Time: 180
Date Contract Executed: 06/19/2012 Date Time Stopped: 02/01/2014 Current Time Charged: 538.00
Date NTP Issued: 07/13/2012 Completion Date: 02/01/2014 Current Time Allowed: 180.00
General Liability Expires: 01/23/2015 Workman's Comp Expires: 06/01/2014 Percent Time Used: 298.89 %
Specification Year: 2009     Date Approved: 02/21/2014

Bid Amount: $68,058.00 Total to Date Prev to Date This Estimate
Funds Available (Bid + Positive C/O): $68,058.00 Participating: $68,058.00 $36,342.97 $31,715.03
Percent Complete: 87.69 % Non Participating: $0.00 $0.00 $0.00
Unearned Balance: $8,380.00 Total Earnings: $68,058.00 $36,342.97 $31,715.03
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $68,058.00 $36,342.97 $31,715.03
Other Adjustments: $99,020.00 $0.00 $99,020.00
Liq Dam/Disincentive: $-107,400.00 $0.00 $-107,400.00
TOTAL: $59,678.00 $36,342.97 $23,335.03

Estimate Adjustment Detail

Contract ID: 120180   Estimate Number: 0003     Primary JP: 21717(08)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0003 --358 $300.00 $-107,400.00
Subtotals For Liquidated Damages $-107,400.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
LD Adjustment (Prog. Est. Only) 0003 $107,400.00
Subtotals For Contract Adjustments $107,400.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
21717(08) 0001 RIGHT-OF-WAY CLEARANCE * Material Discrepancy Adjustments 0003 0.00 $0.00 $-8,380.00
Subtotals For Line Item Adjustments $-8,380.00
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120180   Estimate Number: 0003     Primary JP: 21717(08)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STPY-216C(006)RW Project:    21717(08) Category:    0640/CONSTRUCTION
0001 RIGHT-OF-WAY CLEARANCE 619(G) 0094 LSUM 1.000 1.000 0.466 1.000 $68,058.00 $31,715.03 $68,058.00
Subtotals For Category     0640/CONSTRUCTION    $31,715.03 $68,058.00
Subtotals For Project STPY-216C(006)RW /21717(08) $31,715.03 $68,058.00