Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    08/16/2013
Contract ID: 120171   Estimate Number: 0006     Contract No: 810213
Residency: EL RENO (04200)   Estimate Type: Progressive     Account No: 404400

Project Number(s): SBR-255A(063)SB
Primary Job Piece No: 29274(04)
Contract Description: BRIDGE REPAIR I-44: OVER THE OKLAHOMA RIVER IN OKLAHOMA CITY.
Primary County: OKLAHOMA              
Name of Road: I-44              
Prime Contractor: GIBSON & ASSOCIATES, INC.              
    P.O. BOX 800579              
    BALCH SPRINGS , TX   75180-0579              
Surety Company: FEDERAL INSURANCE COMPANY              

Date Let: 07/19/2012 NTP Effective Date: 10/22/2012 Pay Period: 03/16/2013  TO  08/15/2013
Date Awarded: 08/06/2012 Date Work Began: 10/01/2012 Original Contract Time: 45
Date Contract Executed: 08/16/2012 Date Time Stopped: 12/19/2012 Current Time Charged: 54.00
Date NTP Issued: 09/14/2012 Completion Date: 12/19/2012 Current Time Allowed: 54.00
General Liability Expires: 06/30/2014 Workman's Comp Expires: 06/30/2014 Percent Time Used: 100.00 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $1,194,088.47 Total to Date Prev to Date This Estimate
Bid Amount: $785,150.40 Participating: $0.00 $0.00 $0.00
Percent Complete: 99.84 % Non Participating: $1,194,088.47 $1,086,401.33 $107,687.14
Funds Available: $1,898.48 Total Earnings: $1,194,088.47 $1,086,401.33 $107,687.14
Unearned Balance: $-407,039.59 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $1,194,088.47 $1,086,401.33 $107,687.14
Other Adjustments: $-1,898.48 $-45,776.37 $43,877.89
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $1,192,189.99 $1,040,624.96 $151,565.03

Estimate Adjustment Detail

Contract ID: 120171   Estimate Number: 0006     Primary JP: 29274(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Class B deck repair overrun Approved 01/08/2013 9.0 $163,465.30
002 Smoothness Bonus Approved 03/05/2013 0.0 $92,036.50
003 Final Quantity Change Order Approved 06/04/2013 0.0 $54,775.98
004 Wreck repair Approved 08/13/2013 0.0 $98,660.29


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0004 --2.0 $500.00 $-1,000.00
System Application of Liquidated Damages 0005 -2.0 $500.00 $1,000.00
Subtotals For Liquidated Damages $0.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
LD Adjustment (Prog. Est. Only) 0004 $1,000.00
LD Adjustment (Prog. Est. Only) 0005 $-1,000.00
Withhold to Funds Avail(Prog. Est. Only) 0005 $-44,000.00
Withhold to Funds Avail(Prog. Est. Only) 0006 $44,000.00
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
29274(04) 0001 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0004 352.87 $-1.19 $-421.33
29274(04) 0001 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0005 394.50 $-1.19 $-471.03
29274(04) 0008 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0003 446.48 $-1.19 $-533.10
29274(04) 0008 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0004 250.36 $-1.19 $-298.93
29274(04) 0008 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0005 43.53 $-1.19 $-51.98
29274(04) 8003 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0006 66.91 $-1.31 $-87.92
29274(04) 8012 SUPERPAVE, TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0006 26.02 $-1.31 $-34.19
Subtotals For Line Item Adjustments $-1,898.48


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120171   Estimate Number: 0006     Primary JP: 29274(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SBR-255A(063)SB Project:    29274(04) Category:    0200/BRIDGE 'A'
0001 SUPERPAVE, TYPE S4(PG 76-28 OK) 411(C) 5950 TON 650.000 747.370   747.370 $109.00 $0.00 $81,463.33
0002 COLD MILLING PAVEMENT 412 5267 SY 5,470.000 5,535.140   5,535.140 $3.30 $0.00 $18,265.96
0003 DIAMOND GRINDING CONCRETE PAVEMENT 425 5195 SY 5,470.000 4,996.440   4,996.440 $6.75 $0.00 $33,725.97
0004 RAPID CURE JOINT SEALANT 504(G) 6390 LF 510.000 512.000   512.000 $36.00 $0.00 $18,432.00
0005 ELASTOMERIC MORTAR 504(H) 6389 CF 84.000 127.370 6.250 127.370 $535.00 $3,343.75 $68,142.95
0006 ASPHALT MEMBRANE OVERLAY 505(D) 6080 SY 5,490.000 5,563.200 70.960 5,563.200 $15.50 $1,099.88 $86,229.60
0007 CLASS B BRIDGE DECK REPAIR 513(B) 6019 SY 150.000 20.550   20.550 $370.00 $0.00 $7,603.50
8001 PAVEMENT/BRIDGE SMOOTHNESS ADJUSTMENT 430 5010 LSUM 0.000 1.000   1.000 $47,023.00 $0.00 $47,023.00
Subtotals For Category     0200/BRIDGE 'A'    $4,443.63 $360,886.31
Fed/State Project Number:    SBR-255A(063)SB Project:    29274(04) Category:    0201/BRIDGE 'B'
0008 SUPERPAVE, TYPE S4(PG 76-28 OK) 411(C) 5950 TON 650.000 740.370   740.370 $109.00 $0.00 $80,700.33
0009 COLD MILLING PAVEMENT 412 5267 SY 5,470.000 5,540.590   5,540.590 $3.30 $0.00 $18,283.95
0010 DIAMOND GRINDING CONCRETE PAVEMENT 425 5195 SY 5,470.000 4,864.440   4,864.440 $6.75 $0.00 $32,834.97
0011 RAPID CURE JOINT SEALANT 504(G) 6390 LF 510.000 512.000   512.000 $36.00 $0.00 $18,432.00
0012 ELASTOMERIC MORTAR 504(H) 6389 CF 84.000 130.220   130.220 $535.00 $0.00 $69,667.70
0013 ASPHALT MEMBRANE OVERLAY 505(D) 6080 SY 5,490.000 5,563.200 70.960 5,563.200 $15.50 $1,099.88 $86,229.60
0014 CLASS B BRIDGE DECK REPAIR 513(B) 6019 SY 150.000 592.730 9.730 592.730 $370.00 $3,600.10 $219,310.10
8000 CLASS B BRIDGE DECK REPAIR 513(B) 6019 SY 0.000 405.230 9.730 405.230 $-12.00 $-116.76 $-4,862.76
8002 PAVEMENT/BRIDGE SMOOTHNESS ADJUSTMENT 430 5010 LSUM 0.000 1.000   1.000 $45,013.50 $0.00 $45,013.50
Subtotals For Category     0201/BRIDGE 'B'    $4,583.22 $565,609.39
Fed/State Project Number:    SBR-255A(063)SB Project:    29274(04) Category:    0300/TRAFFIC
0015 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 856(A) 8530 LF 3,280.000 0.000   0.000 $0.66 $0.00 $0.00
0016 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) 856(A) 8535 LF 1,525.000 4,792.000   4,792.000 $1.10 $0.00 $5,271.20
0017 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) 856(B) 8860 EA 18.000 18.000   18.000 $165.00 $0.00 $2,970.00
0018 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 857(A) 8839 LF 4,805.000 0.000   0.000 $0.26 $0.00 $0.00
0019 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 857(E) 8887 EA 1,000.000 1,196.000   1,196.000 $0.50 $0.00 $598.00
0020 (PL)TRUCK MOUNTED ATTENUATOR 876(A) 8482 SD 180.000 136.000   136.000 $7.70 $0.00 $1,047.20
0021 ARROW DISPLAY(TYPE C) 880(A) 8812 SD 180.000 340.000   340.000 $20.00 $0.00 $6,800.00
0022 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 1,440.000 2,108.000   2,108.000 $0.22 $0.00 $463.76
0023 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 2,160.000 3,536.000   3,536.000 $0.22 $0.00 $777.92
0024 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 1,440.000 3,468.000   3,468.000 $0.77 $0.00 $2,670.36
0025 CONSTRUCTION BARRICADES(TYPE III) 880(C) 8842 SD 720.000 1,836.000   1,836.000 $0.44 $0.00 $807.84
0026 WING BARRICADES 880(C) 8848 SD 360.000 272.000   272.000 $0.22 $0.00 $59.84
0027 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 2,880.000 6,188.000   6,188.000 $0.55 $0.00 $3,403.40
0028 (PL) CONSTRUCTION ZONE SEQUENTIAL LIGHTING SYSTEM 880(E) 8900 LSUM 1.000 1.000   1.000 $10,600.00 $0.00 $10,600.00
0029 DRUMS 880(F) 8878 SD 6,075.000 18,224.000   18,224.000 $0.44 $0.00 $8,018.56
0030 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 504.000 1,022.500   1,022.500 $60.00 $0.00 $61,350.00
0031 PORT.CHANGEABLE MESSAGE SIGN 882(A) 8306 SD 360.000 272.000   272.000 $7.70 $0.00 $2,094.40
Subtotals For Category     0300/TRAFFIC    $0.00 $106,932.48
Fed/State Project Number:    SBR-255A(063)SB Project:    29274(04) Category:    0640/CONSTRUCTION
0032 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $62,000.00 $0.00 $62,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $62,000.00
Fed/State Project Number:    SBR-255A(063)SB Project:    29274(04) Category:    0900/STATE NON PARTICIPATING
8003 SUPERPAVE, TYPE S4(PG 76-28 OK) 411(C) 5950 TON 0.000 66.910 66.910 66.910 $109.00 $7,293.19 $7,293.19
8004 COLD MILLING PAVEMENT 412 5267 SY 0.000 406.400 406.400 406.400 $3.30 $1,341.12 $1,341.12
8005 RAPID CURE JOINT SEALANT 504(G) 6390 LF 0.000 12.500 12.500 12.500 $36.00 $450.00 $450.00
8006 ELASTOMERIC MORTAR 504(H) 6389 CF 0.000 3.000 3.000 3.000 $535.00 $1,605.00 $1,605.00
8007 ASPHALT MEMBRANE OVERLAY 505(D) 6080 SY 0.000 406.400 406.400 406.400 $15.50 $6,299.20 $6,299.20
8008 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) 856(A) 8535 LF 0.000 302.000 302.000 302.000 $1.10 $332.20 $332.20
8009 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 0.000 41.000 41.000 41.000 $60.00 $2,460.00 $2,460.00
8010 MOBILIZATION 641 1399 LSUM 0.000 1.000 1.000 1.000 $42,160.00 $42,160.00 $42,160.00
8011 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 0.000 1.000 1.000 1.000 $5,113.60 $5,113.60 $5,113.60
Subtotals For Category     0900/STATE NON PARTICIPATING    $67,054.31 $67,054.31
Fed/State Project Number:    SBR-255A(063)SB Project:    29274(04) Category:    0901/STATE NON PARTICIPATING
8012 SUPERPAVE, TYPE S4(PG 76-28 OK) 411(C) 5950 TON 0.000 26.020 26.020 26.020 $109.00 $2,836.18 $2,836.18
8013 COLD MILLING PAVEMENT 412 5267 SY 0.000 157.000 157.000 157.000 $3.30 $518.10 $518.10
8014 RAPID CURE JOINT SEALANT 504(G) 6390 LF 0.000 12.500 12.500 12.500 $36.00 $450.00 $450.00
8015 ELASTOMERIC MORTAR 504(H) 6389 CF 0.000 3.000 3.000 3.000 $535.00 $1,605.00 $1,605.00
8016 ASPHALT MEMBRANE OVERLAY 505(D) 6080 SY 0.000 157.000 157.000 157.000 $15.50 $2,433.50 $2,433.50
8017 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) 856(A) 8535 LF 0.000 288.000 288.000 288.000 $1.10 $316.80 $316.80
8018 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 0.000 20.000 20.000 20.000 $60.00 $1,200.00 $1,200.00
8019 MOBILIZATION 641 1399 LSUM 0.000 1.000 1.000 1.000 $19,840.00 $19,840.00 $19,840.00
8020 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 0.000 1.000 1.000 1.000 $2,406.40 $2,406.40 $2,406.40
Subtotals For Category     0901/STATE NON PARTICIPATING    $31,605.98 $31,605.98
Subtotals For Project SBR-255A(063)SB /29274(04) $107,687.14 $1,194,088.47