Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    11/04/2013
Contract ID: 120160   Estimate Number: 0020     Contract No: 711168
Residency: ALTUS (05200)   Estimate Type: Progressive     Account No: 400500

Project Number(s): NHY-009N(098)
Primary Job Piece No: 16063(45)
Contract Description: GRADE, DRAIN, AND SURFACE US-183: FROM 1.5 MILES NORTH OF THE SH-9 WEST JUNCTION, EXTEND NORTH. PROJECT LENGTH = 3.049 MILES.
Primary County: KIOWA              
Name of Road: US-183              
Prime Contractor: THE CUMMINS CONSTRUCTION CO., INC.              
    P. O. BOX 748              
    ENID , OK   73702              
Surety Company: HARTFORD ACCIDENT & INDEMNITY COMPANY              

Date Let: 04/19/2012 NTP Effective Date: 08/06/2012 Pay Period: 07/01/2013  TO  10/31/2013
Date Awarded: 05/07/2012 Date Work Began: 08/13/2012 Original Contract Time: 180
Date Contract Executed: 05/16/2012 Date Time Stopped: 06/06/2013 Current Time Charged: 180.00
Date NTP Issued: 05/18/2012 Completion Date: 06/06/2013 Current Time Allowed: 180.00
General Liability Expires: 09/01/2014 Workman's Comp Expires: 01/01/2014 Percent Time Used: 100.00 %
Specification Year: 2009     Date Approved:

Bid Amount: $7,121,528.84 Total to Date Prev to Date This Estimate
Funds Available (Bid + Positive C/O): $7,130,028.84 Participating: $6,922,720.29 $6,906,643.99 $16,076.30
Percent Complete: 97.05 % Non Participating: $0.00 $0.00 $0.00
Unearned Balance: $210,377.79 Total Earnings: $6,922,720.29 $6,906,643.99 $16,076.30
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $6,922,720.29 $6,906,643.99 $16,076.30
Other Adjustments: $-3,069.24 $-3,069.24 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $6,919,651.05 $6,903,574.75 $16,076.30

Estimate Adjustment Detail

Contract ID: 120160   Estimate Number: 0020     Primary JP: 16063(45)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Remobilization to correct drainage Approved 06/18/2013 0.0 $8,500.00
002 Smoothness Incentive Pending 0 0.0 $127,004.43


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
16063(45) 0002 UNCLASSIFIED EXCAVATION Fuel Price Adjustment 0011 6,916.00 $-0.04 $-312.05
16063(45) 0002 UNCLASSIFIED EXCAVATION Fuel Price Adjustment 0019 1,301.10 $-0.06 $-86.03
16063(45) 0003 UNCLASSIFIED BORROW Fuel Price Adjustment 0009 500.02 $-0.01 $-7.56
16063(45) 0003 UNCLASSIFIED BORROW Fuel Price Adjustment 0010 772.80 $-0.04 $-34.87
16063(45) 0010 LIME * SUBSTANDARD ITEM 0003 0.00 $0.00 $-906.15
16063(45) 0010 LIME * Material Discrepancy Adjustments 0020 0.00 $0.00 $-906.15
16063(45) 0010 LIME * SUBSTANDARD ITEM 0020 0.00 $0.00 $906.15
16063(45) 0011 LIME STABILIZED SUBGRADE * Material Discrepancy Adjustments 0002 -12,670.89 $2.00 $-25,341.78
16063(45) 0011 LIME STABILIZED SUBGRADE * Material Discrepancy Adjustments 0003 12,670.89 $2.00 $25,341.78
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0005 7,213.75 $-0.02 $-189.36
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0006 1,341.88 $-0.02 $-35.22
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0007 3,734.17 $-0.02 $-98.02
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0008 4,983.94 $-0.02 $-130.83
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0009 1,158.20 $-0.02 $-30.40
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0010 655.83 $-0.02 $-17.22
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0013 1,877.10 $-0.02 $-49.27
16063(45) 0016 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0015 712.63 $-0.02 $-18.71
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0005 4,386.83 $-0.02 $-115.15
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0006 2,875.77 $-0.02 $-75.49
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0007 4,743.18 $-0.02 $-124.51
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0008 3,229.19 $-0.02 $-84.77
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0009 2,250.82 $-0.02 $-59.08
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0010 779.44 $-0.02 $-20.46
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0012 3,010.37 $-0.02 $-79.02
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0013 2,085.98 $-0.02 $-54.76
16063(45) 0017 SUPERPAVE, TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0014 150.54 $-0.02 $-3.95
16063(45) 0018 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0013 5,429.18 $-0.03 $-162.88
16063(45) 0018 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0014 6,778.43 $-0.03 $-203.35
16063(45) 0018 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0015 620.76 $-0.03 $-18.62
16063(45) 0018 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0018 44.98 $-0.27 $-12.15
16063(45) 0019 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0013 2,217.50 $-0.03 $-66.53
16063(45) 0019 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0014 2,123.24 $-0.03 $-63.70
16063(45) 0019 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0015 304.26 $-0.03 $-9.13
16063(45) 0023 24" R.C.PIPE CLASS III * Missing Material Certification 0006 -40.00 $92.40 $-3,696.00
16063(45) 0023 24" R.C.PIPE CLASS III * Missing Material Certification 0008 40.00 $92.40 $3,696.00
16063(45) 0032 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) * Missing Material Certification 0010 -45,938.33 $0.40 $-18,375.33
16063(45) 0032 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) * Missing Material Certification 0012 45,938.33 $0.40 $18,375.33
16063(45) 0033 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) * Missing Material Certification 0010 -1,841.00 $0.75 $-1,380.75
16063(45) 0033 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) * Missing Material Certification 0012 1,841.00 $0.75 $1,380.75
16063(45) 0034 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 * Missing Material Certification 0007 -193.00 $0.50 $-96.50
16063(45) 0034 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 * Missing Material Certification 0008 193.00 $0.50 $96.50
16063(45) 0034 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 * Missing Material Certification 0010 -173.00 $0.50 $-86.50
16063(45) 0034 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 * Missing Material Certification 0012 -216.00 $0.50 $-108.00
16063(45) 0034 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 * Missing Material Certification 0013 389.00 $0.50 $194.50
16063(45) 0050 SHEET ALUMINUM SIGNS * Missing Material Certification 0015 -765.44 $16.50 $-12,629.76
16063(45) 0050 SHEET ALUMINUM SIGNS * Missing Material Certification 0016 765.44 $16.50 $12,629.76
16063(45) 0051 2" SQUARE TUBE POST * Missing Material Certification 0015 -900.00 $8.25 $-7,425.00
16063(45) 0051 2" SQUARE TUBE POST * Missing Material Certification 0016 900.00 $8.25 $7,425.00
16063(45) 0052 2 1/2" SQUARE TUBE POST * Missing Material Certification 0015 -84.00 $9.25 $-777.00
16063(45) 0052 2 1/2" SQUARE TUBE POST * Missing Material Certification 0016 84.00 $9.25 $777.00
16063(45) 0053 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0015 -88,734.00 $0.35 $-31,056.90
16063(45) 0053 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0016 88,734.00 $0.35 $31,056.90
16063(45) 0054 TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) * Missing Material Certification 0015 -1,604.00 $0.60 $-962.40
16063(45) 0054 TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) * Missing Material Certification 0016 1,604.00 $0.60 $962.40
16063(45) 0055 TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) * Missing Material Certification 0015 -1,096.00 $2.05 $-2,246.80
16063(45) 0055 TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) * Missing Material Certification 0016 1,096.00 $2.05 $2,246.80
16063(45) 0056 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) * Missing Material Certification 0015 -85.00 $3.10 $-263.50
16063(45) 0056 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) * Missing Material Certification 0016 85.00 $3.10 $263.50
16063(45) 0057 TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) * Missing Material Certification 0015 -42.00 $70.00 $-2,940.00
16063(45) 0057 TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) * Missing Material Certification 0016 42.00 $70.00 $2,940.00
Subtotals For Line Item Adjustments $-3,069.24
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120160   Estimate Number: 0020     Primary JP: 16063(45)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    NHY-009N(098) Project:    16063(45) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201(A) 0102 LSUM 1.000 1.000   1.000 $15,000.00 $0.00 $15,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 56,089.000 56,089.000   46,172.100 $5.00 $0.00 $230,860.50
0003 UNCLASSIFIED BORROW 202(D) 0184 CY 7,265.000 7,265.000   3,151.000 $8.15 $0.00 $25,680.65
0004 TYPE A-SALVAGED TOPSOIL 205(A) 4229 LSUM 1.000 1.000   1.000 $9,200.00 $0.00 $9,200.00
0005 TEMPORARY SILT FENCE 221(C) 2801 LF 16,600.000 16,600.000   4,190.000 $1.10 $0.00 $4,609.00
0006 TEMPORARY SILT DIKE 221(F) 0100 LF 488.000 488.000   63.000 $9.15 $0.00 $576.45
0007 SOLID SLAB SODDING 230(A) 2806 SY 67,480.000 67,480.000   146,733.170 $1.10 $0.00 $161,406.49
0008 VEGETATIVE MULCHING 233(A) 2817 AC 13.970 13.970   0.000 $431.50 $0.00 $0.00
0009 MOWING 241 2832 AC 41.900 41.900   0.000 $71.00 $0.00 $0.00
0010 LIME 307(D) 4230 TON 1,817.000 1,817.000 0.000 1,163.680 $172.60 $0.00 $200,851.16
0011 LIME STABILIZED SUBGRADE 307(H) 4270 SY 100,921.000 100,921.000   99,301.840 $2.00 $0.00 $198,603.68
0012 TRAFFIC BOUND SURFACE COURSE TYPE E 402(E) 0225 TON 309.000 309.000   215.700 $32.60 $0.00 $7,031.82
0013 TACK COAT 407(B) 0250 GAL 31,216.000 31,216.000   13,850.000 $3.50 $0.00 $48,475.00
0014 PRIME COAT 408 5774 GAL 18,272.000 18,272.000   7,945.000 $5.50 $0.00 $43,697.50
0015 FABRIC REINFORCEMENT 409(A) 4242 SY 245.000 245.000   0.000 $1.10 $0.00 $0.00
0016 SUPERPAVE, TYPE S3(PG 70-28 OK) 411(B) 5940 TON 22,163.000 22,163.000   21,677.500 $67.14 $0.00 $1,455,427.35
0017 SUPERPAVE, TYPE S3(PG 64-22 OK) 411(B) 5945 TON 41,237.000 41,237.000   41,025.710 $60.74 $0.00 $2,491,901.63
0018 SUPERPAVE, TYPE S4(PG 70-28 OK) 411(C) 5955 TON 12,585.000 12,585.000   12,873.350 $72.10 $0.00 $928,168.54
0019 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 4,367.000 4,367.000   4,645.000 $68.15 $0.00 $316,556.76
0020 COLD MILLING PAVEMENT 412 5267 SY 2,224.000 2,224.000   3,955.590 $4.40 $0.00 $17,404.60
0021 RUMBLE STRIP-METHOD HMA-CON 413(A) 4861 LF 65,370.000 65,370.000   62,218.000 $0.09 $0.00 $5,599.62
0022 CLASS C CONCRETE 509(D) 0325 CY 10.000 10.000   0.000 $309.00 $0.00 $0.00
0023 24" R.C.PIPE CLASS III 613(A) 0492 LF 27.000 27.000   40.000 $92.40 $0.00 $3,696.00
0024 18" CORR. GALV. STEEL PIPE 613(B) 0689 LF 162.000 162.000   162.000 $41.20 $0.00 $6,674.40
0025 24" CORR. GALV. STEEL PIPE 613(B) 0690 LF 56.000 56.000   94.000 $56.65 $0.00 $5,325.10
0026 TYPE A4 CULVERT END TREATMENT 613(M) 7186 EA 3.000 3.000   3.000 $1,340.00 $0.00 $4,020.00
0027 TYPE B4 CULVERT END TREATMENT 613(M) 7187 EA 1.000 1.000   2.000 $1,390.00 $0.00 $2,780.00
0028 TYPE A6 CULVERT END TREATMENT 613(M) 7196 EA 3.000 3.000   3.000 $1,545.00 $0.00 $4,635.00
0029 TYPE B6 CULVERT END TREATMENT 613(M) 7197 EA 2.000 2.000   2.000 $1,390.00 $0.00 $2,780.00
0030 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $30,750.00 $0.00 $30,750.00
0031 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 23,007.000 23,007.000   23,831.730 $3.20 $0.00 $76,261.54
Subtotals For Category     0100/ROADWAY    $0.00 $6,297,972.79
Fed/State Project Number:    NHY-009N(098) Project:    16063(45) Category:    0300/TRAFFIC CONTROL
0032 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 857(A) 8839 LF 3,001.000 3,001.000 15,922.000 127,527.000 $0.40 $6,368.80 $51,010.80
0033 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) 857(C) 8851 LF 14,700.000 14,700.000   1,841.000 $0.75 $0.00 $1,380.75
0034 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 857(E) 8887 EA 3,156.000 3,156.000   1,032.000 $0.50 $0.00 $516.00
0035 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 857(F) 8006 LF 6,600.000 6,600.000   11,591.000 $0.25 $0.00 $2,897.75
0036 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 3,690.000 3,690.000   5,620.000 $0.08 $0.00 $449.60
0037 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 2,850.000 2,850.000   5,246.000 $0.45 $0.00 $2,360.70
0038 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 5,100.000 5,100.000   8,272.000 $0.45 $0.00 $3,722.40
0039 CONSTRUCTION BARRICADES(TYPE II) 880(C) 8836 SD 900.000 900.000   0.000 $0.02 $0.00 $0.00
0040 CONSTRUCTION BARRICADES(TYPE III) 880(C) 8842 SD 540.000 540.000   5,713.000 $1.05 $0.00 $5,998.65
0041 WING BARRICADES 880(C) 8848 SD 720.000 720.000   1,752.000 $1.05 $0.00 $1,839.60
0042 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 2,880.000 2,880.000   15,136.000 $0.45 $0.00 $6,811.20
0043 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 14,820.000 14,820.000   0.000 $0.02 $0.00 $0.00
0044 DRUMS 880(F) 8878 SD 9,870.000 9,870.000   12,098.000 $1.03 $0.00 $12,460.94
0045 CHANNELIZER CONES 880(G) 8890 SD 13,350.000 13,350.000   14,340.000 $0.02 $0.00 $286.80
0046 FLAGGER 880(I) 8902 SD 8.000 8.000   0.000 $166.25 $0.00 $0.00
0047 PORT.CHANGEABLE MESSAGE SIGN 882(A) 8306 SD 56.000 56.000   0.000 $25.75 $0.00 $0.00
Subtotals For Category     0300/TRAFFIC CONTROL    $6,368.80 $89,735.19
Fed/State Project Number:    NHY-009N(098) Project:    16063(45) Category:    0301/TRAFFIC SIGNING AND STRIPING
0048 (PL)REMOVAL OF EXISTING SIGNS 805(A) 8724 EA 30.000 30.000   30.000 $46.35 $0.00 $1,390.50
0049 (PL)REMOVE & RESET EXISTING SIGNS 805(D) 8756 EA 2.000 2.000   2.000 $92.70 $0.00 $185.40
0050 SHEET ALUMINUM SIGNS 850(A) 8110 SF 819.520 819.520   769.940 $16.50 $0.00 $12,704.01
0051 2" SQUARE TUBE POST 851(C) 8324 LF 1,052.000 1,052.000   900.000 $8.25 $0.00 $7,425.00
0052 2 1/2" SQUARE TUBE POST 851(C) 8330 LF 116.000 116.000   84.000 $9.25 $0.00 $777.00
0053 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 856(A) 8530 LF 85,100.000 85,100.000   90,224.000 $0.35 $0.00 $31,578.40
0054 TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) 856(A) 8540 LF 1,050.000 1,050.000   1,604.000 $0.60 $0.00 $962.40
0055 TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) 856(A) 8548 LF 1,400.000 1,400.000   1,542.000 $2.05 $0.00 $3,161.10
0056 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) 856(A) 8555 LF 76.000 76.000   85.000 $3.10 $0.00 $263.50
0057 TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) 856(B) 8525 EA 38.000 38.000   42.000 $70.00 $0.00 $2,940.00
Subtotals For Category     0301/TRAFFIC SIGNING AND STRIPING    $0.00 $61,387.31
Fed/State Project Number:    NHY-009N(098) Project:    16063(45) Category:    0600/STAKING
0058 CONSTRUCTION STAKING LEVEL II 642(B) 0096 LSUM 1.000 1.000 0.100 1.000 $71,450.00 $7,145.00 $71,450.00
Subtotals For Category     0600/STAKING    $7,145.00 $71,450.00
Fed/State Project Number:    NHY-009N(098) Project:    16063(45) Category:    0640/CONSTRUCTION
0059 SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000 0.250 1.000 $10,250.00 $2,562.50 $10,250.00
0060 FIELD OFFICE 640(A) 1426 EA 1.000 1.000   0.000 $8,500.00 $0.00 $0.00
0061 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $337,425.00 $0.00 $337,425.00
0062 (SP)CONTRACTORS QUALITY CONTROL 643 0087 LSUM 1.000 1.000   1.000 $46,000.00 $0.00 $46,000.00
8000 MOBILIZATION 641 1552 LSUM 0.000 1.000   1.000 $8,500.00 $0.00 $8,500.00
Subtotals For Category     0640/CONSTRUCTION    $2,562.50 $402,175.00
Subtotals For Project NHY-009N(098) /16063(45) $16,076.30 $6,922,720.29