Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    03/18/2013
Contract ID: 120086   Estimate Number: 0004     Contract No: 710989
Residency: ADA (03100)   Estimate Type: Progressive     Account No: 400300

Project Number(s): NHY-017N(239)3P
Primary Job Piece No: 28215(04)
Contract Description: RESURFACE (ASPHALT) US-75: FROM 7.5 MILES NORTH OF THE ATOKA COUNTY LINE, EXTEND NORTH. PROJECT LENGTH = 2.09 MILES.
Primary County: COAL              
Name of Road: US-75              
Prime Contractor: JOB CONSTRUCTION CO., INC.              
    P. O. BOX 549              
    POTEAU , OK   74953              
Surety Company: MID-CONTINENT CASUALTY COMPANY              

Date Let: 02/16/2012 NTP Effective Date: 07/02/2012 Pay Period: 09/01/2012  TO  02/28/2013
Date Awarded: 03/05/2012 Date Work Began: 07/02/2012 Original Contract Time: 45
Date Contract Executed: 03/14/2012 Date Time Stopped: 01/31/2013 Current Time Charged: 54.00
Date NTP Issued: 03/22/2012 Completion Date: 01/31/2013 Current Time Allowed: 55.00
General Liability Expires: 11/25/2013 Workman's Comp Expires: 11/25/2013 Percent Time Used: 98.18 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $919,663.14 Total to Date Prev to Date This Estimate
Bid Amount: $812,724.80 Participating: $917,026.62 $913,008.13 $4,018.49
Percent Complete: 99.11 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $8,159.13 Total Earnings: $917,026.62 $913,008.13 $4,018.49
Unearned Balance: $-98,779.21 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $917,026.62 $913,008.13 $4,018.49
Other Adjustments: $-5,522.61 $-96,283.34 $90,760.73
Liq Dam/Disincentive: $0.00 $-4,000.00 $4,000.00
TOTAL: $911,504.01 $812,724.79 $98,779.22

Estimate Adjustment Detail

Contract ID: 120086   Estimate Number: 0004     Primary JP: 28215(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Overrun of Major Items Approved 01/28/2013 10.0 $48,696.01
002 Overrun of Asphalt Pay Items Approved 03/05/2013 0.0 $58,242.33


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0003 --8.0 $500.00 $-4,000.00
System Application of Liquidated Damages 0004 -8.0 $500.00 $4,000.00
Subtotals For Liquidated Damages $0.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Withhold to Funds Avail(Prog. Est. Only) 0003 $-97,937.65
Withhold to Funds Avail(Prog. Est. Only) 0004 $97,937.65
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
28215(04) 0003 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0001 663.63 $1.62 $1,079.06
28215(04) 0003 SUPERPAVE, TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0002 2,037.05 $-1.00 $-2,037.05
28215(04) 0003 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0002 3,127.95 $0.42 $1,332.51
28215(04) 0003 SUPERPAVE, TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0002 584.13 $-1.00 $-584.13
28215(04) 0003 SUPERPAVE, TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0004 -4,275.49 $1.00 $-4,275.49
28215(04) 0003 SUPERPAVE, TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0004 -1.00 $2,901.43 $-2,901.43
28215(04) 0004 SUPERPAVE, TYPE S5(PG 70-28 OK) Asphalt Binder Adjustment 0002 2,435.98 $0.47 $1,145.84
28215(04) 0004 SUPERPAVE, TYPE S5(PG 70-28 OK) Asphalt Binder Adjustment 0003 1,526.60 $0.47 $718.08
Subtotals For Line Item Adjustments $-5,522.61
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 120086   Estimate Number: 0004     Primary JP: 28215(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    NHY-017N(239)3P Project:    28215(04) Category:    0100/ROADWAY
0001 UNCLASSIFIED BORROW 202(D) 0184 CY 200.000 200.000 40.400 40.400 $22.00 $888.80 $888.80
0002 TACK COAT 407(B) 0250 GAL 2,037.000 4,999.000 0.500 4,999.500 $3.36 $1.68 $16,798.32
0003 SUPERPAVE, TYPE S4(PG 70-28 OK) 411(C) 5955 TON 3,614.000 3,791.580 0.000 3,791.580 $78.59 $0.00 $297,980.27
0004 SUPERPAVE, TYPE S5(PG 70-28 OK) 411(D) 5970 TON 3,614.000 3,962.580   3,962.580 $84.55 $0.00 $335,036.14
0005 COLD MILLING PAVEMENT 412 5267 SY 40,738.000 42,652.000   42,652.000 $2.54 $0.00 $108,336.08
0006 4" CONCRETE SIDEWALK 610(A) 0602 SY 129.000 161.250 -126.950 161.250 $300.00 $-38,085.00 $48,375.00
0007 TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 232.000 232.000   224.000 $80.00 $0.00 $17,920.00
0008 TACTILE WARNING DEVICE-RETROFIT 610(I) 4615 SF 120.000 120.000   144.000 $90.00 $0.00 $12,960.00
0009 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 33,106.000 33,106.000 384.000 35,124.000 $0.50 $192.00 $17,562.00
0010 TRAFFIC STRIPE(PLASTIC)(12" WIDE) 855(A) 8818 LF 740.000 740.000   228.000 $3.00 $0.00 $684.00
0011 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 8.000 8.000   7.000 $120.00 $0.00 $840.00
0012 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 5.000 5.000   5.000 $125.00 $0.00 $625.00
0013 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.100 1.000 $20,000.00 $2,000.00 $20,000.00
8001 4" CONCRETE SIDEWALK 610(A) 0602 SY 0.000 127.110 127.110 127.110 $273.35 $34,745.52 $34,745.52
8002 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000 1.000 1.000 $4,275.49 $4,275.49 $4,275.49
Subtotals For Category     0100/ROADWAY    $4,018.49 $917,026.62
Subtotals For Project NHY-017N(239)3P /28215(04) $4,018.49 $917,026.62