Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    05/20/2013
Contract ID: 120078   Estimate Number: 0013     Contract No: 711060
Residency: ATKINS NORTH AMERICA, INC. (AKA PBS & J) (03010)   Estimate Type: Progressive     Account No: 404300

Project Number(s): BTOP-267N(003)
Primary Job Piece No: 28128(34)
Contract Description: SAFETY IMPROVEMENTS (FIBER OPTIC CABLE) I-40: BEGIN AT THE SH-99 INTERCHANGE, EXTEND EAST TO HENRYETTA. PROJECT LENGTH = 40.5 MILES.
Primary County: SEMINOLE              
Name of Road: I-40              
Prime Contractor: ROHL NETWORKS, LP              
    2875 JUPITER PARK DRIVE, STE. 900              
    JUPITER , FL   33458              
Surety Company: TRAVELERS INDEMNITY COMPANY              

Date Let: 03/15/2012 NTP Effective Date: 06/04/2012 Pay Period: 02/01/2013  TO  05/15/2013
Date Awarded: 04/02/2012 Date Work Began: 06/18/2012 Original Contract Time: 140
Date Contract Executed: 04/12/2012 Date Time Stopped: Current Time Charged: 211.00
Date NTP Issued: 05/09/2012 Completion Date: Current Time Allowed: 197.00
General Liability Expires: 01/19/2014 Workman's Comp Expires: 01/19/2014 Percent Time Used: 107.11 %
Specification Year: 2009     Date Approved: 05/17/2013

Current Contract Amount: $1,385,705.01 Total to Date Prev to Date This Estimate
Bid Amount: $1,286,282.96 Participating: $1,281,628.61 $1,290,402.29 $-8,773.68
Percent Complete: 89.28 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $148,576.40 Total Earnings: $1,281,628.61 $1,290,402.29 $-8,773.68
Unearned Balance: $49,154.35 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $1,281,628.61 $1,290,402.29 $-8,773.68
Other Adjustments: $148,000.00 $0.00 $148,000.00
Liq Dam/Disincentive: $-192,500.00 $-233,750.00 $41,250.00
TOTAL: $1,237,128.61 $1,056,652.29 $180,476.32

Estimate Adjustment Detail

Contract ID: 120078   Estimate Number: 0013     Primary JP: 28128(34)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Change in quantities and additional work and pay items Approved 02/05/2013 4.0 $99,422.05
002 Add Pay item omitted from Original contract Pending 0 0.0 $-8,562.82
003 adjustment of days as compensation of scope change Approved 05/06/2013 129.0 $0.00


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0008 --10 $750.00 $-7,500.00
System Application of Liquidated Damages 0009 --15 $750.00 $-11,250.00
System Application of Liquidated Damages 0010 --15 $750.00 $-11,250.00
System Application of Liquidated Damages 0011 --15 $750.00 $-11,250.00
System Application of Liquidated Damages 0012 --14 $750.00 $-10,500.00
System Application of Liquidated Damages 0013 -55.0 $750.00 $41,250.00
Subtotals For Liquidated Damages $-10,500.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Milestone Adjust. (Prog. Est. Only) 0013 $148,000.00
Subtotals For Contract Adjustments $148,000.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 Conduit & Ground Boxes 06/04/2012 12/04/2012 171.00 DYS $2,000.00 Y
02 Fiber Optic Cable Installation 10/31/2012 12/18/2012 45.00 DYS $2,000.00 Y


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
01 System Application of Disincentive Adj 0006 $-16,000.00
01 System Application of Disincentive Adj 0007 $-30,000.00
01 System Application of Disincentive Adj 0008 $-62,000.00
01 System Application of Disincentive Adj 0009 $-30,000.00
01 System Application of Disincentive Adj 0010 $-30,000.00
01 System Application of Disincentive Adj 0011 $-8,000.00
02 System Application of Disincentive Adj 0012 $-6,000.00
Subtotals For Milestones $-182,000.00

Line Item Detail

Contract ID: 120078   Estimate Number: 0013     Primary JP: 28128(34)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BTOP-267N(003) Project:    28128(34) Category:    0300/TRAFFIC
0001 RAILROAD FLAGGING 104 0900 HOUR 24.000 24.000   7.000 $98.75 $0.00 $691.25
0002 CLEARING AND GRUBBING 201(A) 0102 LSUM 1.000 1.000   1.000 $14,275.00 $0.00 $14,275.00
0003 TEMPORARY SILT FENCE 221(C) 2801 LF 2,000.000 2,000.000 0.000 1,380.000 $6.05 $0.00 $8,349.00
0004 SOLID SLAB SODDING 230(A) 2806 SY 2,000.000 2,000.000   0.000 $5.95 $0.00 $0.00
0005 CLASS A CONCRETE 509(B) 0321 CY 20.000 20.000   0.000 $250.00 $0.00 $0.00
0006 3" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8316 LF 4,125.000 4,125.000   3,792.000 $60.95 $0.00 $231,122.40
0007 1 1/2" HIGH DENSITY PE PIPE - BORED 802(C) 8551 LF 6,121.000 19,000.000   21,056.000 $9.95 $0.00 $209,507.20
0008 1 1/2" HIGH DENSITY PE PIPE - TRENCHED 802(C) 8556 LF 10,000.000 15,000.000   13,757.000 $7.75 $0.00 $106,616.75
0009 1 1/2" HIGH DENSITY PE PIPE - PLOWED 802(C) 8565 LF 217,630.000 193,630.000 -5,324.000 186,629.000 $2.25 $-11,979.00 $419,915.25
0010 GROUND BOX (R3248) 803(B) 8135 EA 90.000 90.000 7.000 69.000 $885.90 $6,201.30 $61,127.10
0011 GROUND BOX (B2-48) 803(B) 8150 EA 15.000 15.000 -2.000 1.000 $1,275.00 $-2,550.00 $1,275.00
0012 REINFORCING STEEL 804(B) 2916 LB 240.000 240.000   0.000 $3.60 $0.00 $0.00
0013 (SP)FIBER OPTIC CABLE, 144 SMF 818(A) 8733 LF 229,331.000 229,331.000 -4,518.000 226,066.000 $0.71 $-3,207.78 $160,506.86
0014 (SP)FIBER OPTIC PATCH PANEL, 144 PORT 818(B) 8760 EA 2.000 2.000   2.000 $3,450.00 $0.00 $6,900.00
0015 (SP)FIBER OPTIC CABLE TERMINATION 818(D) 8740 EA 288.000 288.000 288.000 288.000 $38.75 $11,160.00 $11,160.00
0016 (SP) SHIELD ISOLATION PEDESTAL 818(F) 8370 EA 5.000 5.000   0.000 $145.00 $0.00 $0.00
0017 (SP) SHIELD ISOLATION PEDESTAL (MINI) 818(F) 8375 EA 27.000 27.000 1.000 15.000 $182.50 $182.50 $2,737.50
0018 (SP)FIBER OPTIC ROUTE SIGN & INSTALLATION 818(G) 5570 EA 176.000 176.000 81.000 208.000 $72.75 $5,892.75 $15,132.00
Subtotals For Category     0300/TRAFFIC    $5,699.77 $1,249,315.31
Fed/State Project Number:    BTOP-267N(003) Project:    28128(34) Category:    0301/TEMPORARY TRAFFIC
0019 (PL)TRUCK MOUNTED ATTENUATOR 876(A) 8482 SD 190.000 190.000   6.000 $25.00 $0.00 $150.00
0020 FLAGGER 880(I) 8902 SD 45.000 45.000   4.000 $63.25 $0.00 $253.00
0021 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   0.950 $20,125.00 $0.00 $19,118.75
0022 PORT.CHANGEABLE MESSAGE SIGN 882(A) 8306 SD 190.000 190.000   5.000 $25.00 $0.00 $125.00
Subtotals For Category     0301/TEMPORARY TRAFFIC    $0.00 $19,646.75
Fed/State Project Number:    BTOP-267N(003) Project:    28128(34) Category:    0640/CONSTRUCTION
0023 SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.800 $12,375.00 $0.00 $9,900.00
0024 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $17,240.00 $0.00 $17,240.00
8000 1 1/2" HIGH DENSITY PE PIPE - TRENCHED 802(C) 8556 LF 0.000 2,500.000 1,257.000 1,257.000 $-0.85 $-1,068.45 $-1,068.45
8001 1 1/2" HIGH DENSITY PE PIPE - BORED 802(C) 8551 LF 0.000 11,349.000 13,405.000 13,405.000 $-1.00 $-13,405.00 $-13,405.00
Subtotals For Category     0640/CONSTRUCTION    $-14,473.45 $12,666.55
Fed/State Project Number:    BTOP-267N(003) Project:    28128(34) Category:    0900/FEDERAL NON PARTICIPATING
Subtotals For Category     0900/FEDERAL NON PARTICIPATING    $0.00 $0.00
Subtotals For Project BTOP-267N(003) /28128(34) $-8,773.68 $1,281,628.61