Oklahoma Department of Transportation
Final Estimate Affidavit

Contract ID: 120066   Estimate Number: 0010 , Final     Spec Year: 2009
Primary JP: 28128(47)   Residency: HEAVENER (02200)     Contract No: 710891
Date Created: 01/22/2014   Contractor FEI: 431710461     Account No: 404200

Project Number(s): BTOP-239B(001)
Contract Description: SAFETY IMPROVEMENTS (FIBER OPTIC CABLE) US-270/US-271: FROM THE CITY OF WILBURTON TO THE CITY OF POTEAU. PROJECT LENGTH = 41.790 MILES.
Primary County: LATIMER              
Name of Road: US-270 / US-271              
Prime Contractor: AMERICAN DIRECTIONAL BORING,INC. DBA ADB UTILITY CONTRACTORS           Time Charged: 122.00
    1425 N. ASHBY ROAD           Time Allowed: 125.00
    ST. LOUIS , MO   63132           Percent Time: 97.60 %

  Paid To Date: $1,752,559.61 Payable This Statement: $-4,541.55

CONTRACTOR AFFIDAVIT
STATE OF ___________________ )  
  )     §  
COUNTY OF __________________ )  
The undersigned contractor or duly authorized agent, of lawful age, being first duly sworn, on oath say that this claim is true and correct.
Affiant further states that the work, services or materials as shown by this claim have been completed or supplied in accordance with the plans, specifications, orders, requests and all other terms of the contract. Affiant further states that (s)he is duly authorized agent of the contractor for the purpose of certifying the facts pertaining to the giving of things of value to government personnel in order to procure the contract or obtain payment; that (s)he is fully aware of the facts and circumstances surrounding the making of the contract and has been personally and directly involved in the proceedings leading to the procurement of the contract and the filing of this claim; and, neither the contractor nor anyone subject to the contractor's direction or control has been paid, given or donated or agreed to pay, give or donate to any officer or employee of the State of Oklahoma any money or other thing of value, either directly or
indirectly, in procuring the contract or obtaining payment. The affiant further certifies that all laborers, mechanics, apprentices and trainees employed by him/her or by any subcontractor performing work under the contract on the project have been paid wages at rates not less than those required by the contract provisions, and that the work performed by each such laborer, mechanic, apprentice or trainee conformed to the classifications set forth in the contract or training program provisions applicable to the wage rate paid.
Affiant hereby agrees that Contractor will accept this estimate as full compensation for all money due Contractor by the Department of Transportation, and hereby relinquish all claims, either in contract or in tort, which have arisen or which might arise out of the construction of said project. That to the best of my knowledge and belief, all indebtedness for labor, materials, fuel, equipment, equipment rental, parts, supplies, insurance premiums, and claims for items not specifically mentioned, which are attributable to performance of the work on this project or which were incorporated therein in any manner, have been paid in full, and that there are not now any presently outstanding, unpaid claims for such indebtedness; that my position with the company is such, that if there were any such outstanding claims of the nature specified herein, I would ordinarily be aware of them.
Further affiant sayeth not.                                
AMERICAN DIRECTIONAL BORING,INC. DBA ADB UTILITY CONTRACTORS                               
 
_________________________________________________
Affiant Signature
 
_________________________________________________
Affiant Printed Name
                          PE Seal
_________________________________________________
Affiant Company Position
Subscribed and sworn to before me this ______ day of ____________, 20____
My Commission Number: ____________ My Commission Expires: ______________
   
_________________________________________________              
_________________________________________________
                    Professional Engineer Signature
              Oklahoma Department of Transportation
Corporate Seal
Notary Seal                  

Oklahoma Department of Transportation
Final Estimate Summary
Created:    01/22/2014
Contract ID: 120066   Estimate Number: 0010     Contract No: 710891
Residency: HEAVENER (02200)   Estimate Type: Final     Account No: 404200

Project Number(s): BTOP-239B(001)
Primary Job Piece No: 28128(47)
Contract Description: SAFETY IMPROVEMENTS (FIBER OPTIC CABLE) US-270/US-271: FROM THE CITY OF WILBURTON TO THE CITY OF POTEAU. PROJECT LENGTH = 41.790 MILES.
Primary County: LATIMER              
Name of Road: US-270 / US-271              
Prime Contractor: AMERICAN DIRECTIONAL BORING,INC. DBA ADB UTILITY CONTRACTORS              
    1425 N. ASHBY ROAD              
    ST. LOUIS , MO   63132              
Surety Company: TRAVELERS INDEMNITY COMPANY              

Date Let: 01/19/2012 NTP Effective Date: 04/02/2012 Pay Period: 11/01/2012  TO  01/21/2014
Date Awarded: 02/06/2012 Date Work Began: 04/02/2012 Original Contract Time: 125
Date Contract Executed: 02/23/2012 Date Time Stopped: 02/28/2013 Current Time Charged: 122.00
Date NTP Issued: 03/06/2012 Completion Date: 02/28/2013 Current Time Allowed: 125.00
General Liability Expires: 04/07/2013 Workman's Comp Expires: 04/07/2013 Percent Time Used: 97.60 %
Specification Year: 2009        

Bid Amount: $1,906,450.18 Total to Date Prev to Date This Estimate
Funds Available (Bid + Positive C/O): $1,941,615.68 Participating: $1,745,394.11 $1,749,101.16 $-3,707.05
Percent Complete: 90.26 % Non Participating: $7,165.50 $0.00 $7,165.50
Unearned Balance: $189,056.07 Total Earnings: $1,752,559.61 $1,749,101.16 $3,458.45
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $1,752,559.61 $1,749,101.16 $3,458.45
Other Adjustments: $16,000.00 $24,000.00 $-8,000.00
Liq Dam/Disincentive: $-16,000.00 $-16,000.00 $0.00
TOTAL: $1,752,559.61 $1,757,101.16 $-4,541.55

Estimate Adjustment Detail

Contract ID: 120066   Estimate Number: 0010     Primary JP: 28128(47)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Matl taken into warehouse stock Approved 02/27/2013 0.0 $7,165.50
002 Final Quantity Change Order Approved 06/07/2013 0.0 $-189,056.06
003 Credit back days to contract Approved 01/21/2014 10.0 $28,000.00


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Milestone Adjust. (Prog. Est. Only) 0007 $24,000.00
Milestone Adjust. (Prog. Est. Only) 0010 $-24,000.00
Milstone Adjust. (C/O) 0010 $16,000.00
Subtotals For Contract Adjustments $16,000.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 Incentive/Disincentive Conduit & Ground Boxes 04/02/2012 06/13/2012 85.00 DYS $2,000.00 Y
02 Incentive/Disincentive Fiber Optic Cable Installation 06/14/2012 07/31/2012 50.00 DYS $2,000.00 Y


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
01 User ent Milestone Inc/Dis 0006 $24,000.00
01 User ent Milestone Inc/Dis 0007 $-24,000.00
02 System Application of Disincentive Adj 0007 $-16,000.00
Subtotals For Milestones $-16,000.00

Line Item Detail

Contract ID: 120066   Estimate Number: 0010     Primary JP: 28128(47)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BTOP-239B(001) Project:    28128(47) Category:    0300/TRAFFIC
0001 CLEARING AND GRUBBING 201(A) 0102 LSUM 1.000 1.000   1.000 $1,000.00 $0.00 $1,000.00
0002 TEMPORARY SILT FENCE 221(C) 2801 LF 2,000.000 1,446.000   1,446.000 $8.70 $0.00 $12,580.20
0003 SOLID SLAB SODDING 230(A) 2806 SY 2,000.000 990.000   990.000 $7.08 $0.00 $7,009.20
0004 CLASS A CONCRETE 509(B) 0321 CY 15.360 10.020   10.020 $1,041.57 $0.00 $10,436.53
0005 3" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8316 LF 1,350.000 584.000   584.000 $61.00 $0.00 $35,624.00
0006 3" GALV. STEEL ELECTRICAL CONDUIT PUSHED OR BORED 802(A) 8318 LF 100.000 0.000   0.000 $46.90 $0.00 $0.00
0007 1 1/2" HIGH DENSITY PE PIPE - BORED 802(C) 8551 LF 14,840.000 16,371.000 -1,119.000 16,371.000 $14.68 $-16,426.92 $240,326.28
0008 1 1/2" HIGH DENSITY PE PIPE - TRENCHED 802(C) 8556 LF 67,285.000 58,862.000 -811.000 58,862.000 $8.68 $-7,039.48 $510,922.16
0009 1 1/2" HIGH DENSITY PE PIPE - PLOWED 802(C) 8565 LF 144,828.000 146,954.000 -2,525.000 146,954.000 $3.13 $-7,903.25 $459,966.02
0010 GROUND BOX (R3248) 803(B) 8135 EA 54.000 54.000   54.000 $1,166.93 $0.00 $63,014.22
0011 GROUND BOX (B2-48) 803(B) 8150 EA 24.000 23.000   23.000 $1,670.70 $0.00 $38,426.10
0012 REINFORCING STEEL 804(B) 2916 LB 288.000 227.450   227.450 $14.00 $0.00 $3,184.30
0013 (SP)FIBER OPTIC CABLE, 96 SMF 818(A) 8730 LF 238,862.000 231,748.000 -1,644.000 231,748.000 $0.85 $-1,397.40 $196,985.80
0014 (SP) FIBER OPTIC CABLE, 48 INDOOR/OUTDOOR PLENUM 818(A) 8739 LF 1,200.000 1,800.000   1,800.000 $1.00 $0.00 $1,800.00
0015 (SP)FIBER OPTIC PATCH PANEL, 96 PORT 818(B) 8755 EA 4.000 4.000   4.000 $1,282.00 $0.00 $5,128.00
0016 (SP)FIBER OPTIC CABLE TERMINATION 818(D) 8740 EA 192.000 192.000   192.000 $42.90 $0.00 $8,236.80
0017 (SP) SHIELD ISOLATION PEDESTAL 818(F) 8370 EA 5.000 5.000   5.000 $672.50 $0.00 $3,362.50
0018 (SP) SHIELD ISOLATION PEDESTAL (MINI) 818(F) 8375 EA 13.000 8.000   8.000 $429.00 $0.00 $3,432.00
0019 (SP)FIBER OPTIC ROUTE SIGN & INSTALLATION 818(G) 5570 EA 250.000 240.000 -10.000 240.000 $204.00 $-2,040.00 $48,960.00
Subtotals For Category     0300/TRAFFIC    $-34,807.05 $1,650,394.11
Fed/State Project Number:    BTOP-239B(001) Project:    28128(47) Category:    0301/TEMPORARY TRAFFIC
0020 (PL)TRUCK MOUNTED ATTENUATOR 876(A) 8482 SD 170.000 0.000   0.000 $200.00 $0.00 $0.00
0021 FLAGGER 880(I) 8902 SD 45.000 0.000   0.000 $175.00 $0.00 $0.00
0022 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.050 1.000 $17,000.00 $850.00 $17,000.00
0023 PORT.CHANGEABLE MESSAGE SIGN 882(A) 8306 SD 170.000 0.000   0.000 $130.00 $0.00 $0.00
Subtotals For Category     0301/TEMPORARY TRAFFIC    $850.00 $17,000.00
Fed/State Project Number:    BTOP-239B(001) Project:    28128(47) Category:    0640/CONSTRUCTION
0024 SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000 0.150 1.000 $15,000.00 $2,250.00 $15,000.00
0025 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $35,000.00 $0.00 $35,000.00
8001 INCENTIVE FOR EARLY COMPLETION 108 0174 LSUM 0.000 1.000 1.000 1.000 $24,000.00 $24,000.00 $24,000.00
8002 INCENTIVE FOR EARLY COMPLETION 108 0174 LSUM 0.000 1.000 1.000 1.000 $4,000.00 $4,000.00 $4,000.00
Subtotals For Category     0640/CONSTRUCTION    $30,250.00 $78,000.00
Fed/State Project Number:    BTOP-239B(001) Project:    28128(47) Category:    0900/FEDERAL NON PARTICIPATING
8000 HANGERS 504 6224 EA 0.000 50.000 50.000 50.000 $143.31 $7,165.50 $7,165.50
Subtotals For Category     0900/FEDERAL NON PARTICIPATING    $7,165.50 $7,165.50
Subtotals For Project BTOP-239B(001) /28128(47) $3,458.45 $1,752,559.61