Contract ID: | 120039 | Estimate Number: | 0011 | Contract No: | 710855 | |||
Residency: | MUSKOGEE (01100) | Estimate Type: | Progressive | Account No: | 404100 | |||
Project Number(s): | SSR-014N(085)SR, SSR-156N(174)SR, SSR-156N(181)SR | ||||||||||||
Primary Job Piece No: | 27592(04) | ||||||||||||
Contract Description: | RESURFACE (ASPHALT) US-75: BEGIN JUST NORTH OF US-62E, EXTEND NORTH. PROJECT LENGTH = 9.26 MILES | ||||||||||||
Primary County: | OKMULGEE | ||||||||||||
Name of Road: | US-75 | ||||||||||||
Prime Contractor: | GLOVER & ASSOCIATES, INC. | ||||||||||||
2832 N. COUNTRY CLUB | |||||||||||||
MUSKOGEE , OK 74403 | |||||||||||||
Surety Company: | WESTFIELD INSURANCE COMPANY | ||||||||||||
Date Let: | 01/19/2012 | NTP Effective Date: | 07/02/2012 | Pay Period: | 01/16/2013 TO 01/31/2013 |
Date Awarded: | 02/06/2012 | Date Work Began: | 08/29/2012 | Original Contract Time: | 150 |
Date Contract Executed: | 02/21/2012 | Date Time Stopped: | Current Time Charged: | 144.00 | |
Date NTP Issued: | 02/28/2012 | Completion Date: | Current Time Allowed: | 150.00 | |
General Liability Expires: | 02/01/2013 | Workman's Comp Expires: | 02/01/2013 | Percent Time Used: | 96.00 % |
Specification Year: | 2009 | Date Approved: | |||
Current Contract Amount: | $2,800,836.17 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $2,800,836.17 | Participating: | $0.00 | $0.00 | $0.00 | ||
Percent Complete: | 92.59 % | Non Participating: | $2,642,828.60 | $2,641,180.18 | $1,648.42 | ||
Funds Available: | $207,448.99 | Total Earnings: | $2,642,828.60 | $2,641,180.18 | $1,648.42 | ||
Unearned Balance: | $207,448.99 | Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||
Gross Earnings: | $2,642,828.60 | $2,641,180.18 | $1,648.42 | ||||
Other Adjustments: | $-49,441.42 | $-49,441.42 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $2,593,387.18 | $2,591,738.76 | $1,648.42 |
Contract ID: | 120039 | Estimate Number: | 0011 | Primary JP: | 27592(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
27592(04) | 0008 | SUPERPAVE, TYPE S4(PG 76-28 OK) | * HMA Deduction as per Sec. 411 | 0005 | -30.00 | $78.00 | $-2,340.00 |
27592(04) | 0009 | SUPERPAVE, TYPE S4(PG 64-22 OK) | * HMA Deduction as per Sec. 411 | 0005 | -70.00 | $66.77 | $-4,673.90 |
27592(04) | 0009 | SUPERPAVE, TYPE S4(PG 64-22 OK) | * HMA Deduction as per Sec. 411 | 0006 | -90.00 | $66.77 | $-6,009.30 |
27592(05) | 0025 | SUPERPAVE, TYPE S4(PG 76-28 OK) | * HMA Deduction as per Sec. 411 | 0003 | -61.45 | $78.00 | $-4,793.10 |
27592(05) | 0025 | SUPERPAVE, TYPE S4(PG 76-28 OK) | * HMA Deduction as per Sec. 411 | 0004 | -200.00 | $78.00 | $-15,600.00 |
27592(05) | 0025 | SUPERPAVE, TYPE S4(PG 76-28 OK) | * HMA Deduction as per Sec. 411 | 0008 | -19.04 | $78.00 | $-1,485.12 |
27592(05) | 0026 | SUPERPAVE, TYPE S4(PG 64-22 OK) | * HMA Deduction as per Sec. 411 | 0004 | -70.00 | $74.00 | $-5,180.00 |
29013(04) | 0041 | SUPERPAVE, TYPE S4(PG 76-28 OK) | * HMA Deduction as per Sec. 411 | 0006 | -60.00 | $78.00 | $-4,680.00 |
29013(04) | 0041 | SUPERPAVE, TYPE S4(PG 76-28 OK) | * HMA Deduction as per Sec. 411 | 0007 | -60.00 | $78.00 | $-4,680.00 | Subtotals For Line Item Adjustments | $-49,441.42 | * = User applied Line Item Adjustments |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 120039 | Estimate Number: | 0011 | Primary JP: | 27592(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: SSR-014N(085)SR | Project: 27592(04) | Category: 0200/ROADWAY - SSR-014N(085)SR | ||||||||
0001 | EARTHWORK | 202(H) 0185 | LSUM | 1.000 | 1.000 | 1.000 | $38,000.00 | $0.00 | $38,000.00 | |
0002 | TEMPORARY SILT FENCE | 221(C) 2801 | LF | 800.000 | 800.000 | 190.000 | $6.98 | $0.00 | $1,326.20 | |
0003 | SOLID SLAB SODDING | 230(A) 2806 | SY | 200.000 | 200.000 | 0.000 | $7.00 | $0.00 | $0.00 | |
0004 | AGGREGATE BASE TYPE A | 303(A) 2100 | CY | 389.000 | 389.000 | 235.400 | $38.48 | $0.00 | $9,058.19 | |
0005 | TRAFFIC BOUND SURFACE COURSE TYPE E | 402(E) 0225 | TON | 10.000 | 10.000 | 0.000 | $208.83 | $0.00 | $0.00 | |
0006 | TACK COAT | 407(B) 0250 | GAL | 5,951.000 | 5,951.000 | 6,309.500 | $2.33 | $0.00 | $14,701.14 | |
0007 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 411(B) 5945 | TON | 242.000 | 242.000 | 242.820 | $85.00 | $0.00 | $20,639.70 | |
0008 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 411(C) 5950 | TON | 7,500.000 | 7,500.000 | 7,572.980 | $78.00 | $0.00 | $590,692.44 | |
0009 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 411(C) 5960 | TON | 3,100.000 | 3,100.000 | 3,565.730 | $66.77 | $0.00 | $238,083.79 | |
0010 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 411(I) 6310 | TON | 30.000 | 30.000 | 0.000 | $200.16 | $0.00 | $0.00 | |
0011 | COLD MILLING PAVEMENT | 412 5267 | SY | 30,342.000 | 30,342.000 | 27,152.340 | $0.68 | $0.00 | $18,463.59 | |
0012 | RUMBLE STRIP-METHOD HMA-CYC | 413(B) 4863 | LF | 48,370.000 | 48,370.000 | 18,899.000 | $0.22 | $0.00 | $4,157.78 | |
0013 | RAPID CURE JOINT SEALANT | 504(G) 6390 | LF | 240.000 | 240.000 | 112.000 | $22.24 | $0.00 | $2,490.88 | |
0014 | ELASTOMERIC MORTAR | 504(H) 6389 | CF | 20.000 | 20.000 | 20.700 | $222.40 | $0.00 | $4,603.68 | |
0015 | REMOVAL OF CONCRETE PAVEMENT W/ASPHALT OVERLAY | 619(B) 4763 | SY | 200.000 | 200.000 | 105.800 | $13.49 | $0.00 | $1,427.24 | |
0016 | LOOP DETECTOR WIRE | 828(B) 8136 | LF | 550.000 | 550.000 | 564.000 | $5.56 | $0.00 | $3,135.84 | |
0017 | TRAFFIC STRIPE (PLASTIC)(SYMBOLS, WORDS, ETC.) | 855(B) 3300 | EA | 36.000 | 36.000 | 48.000 | $133.44 | $0.00 | $6,405.12 | |
0018 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 856(A) 8530 | LF | 53,207.000 | 53,207.000 | 44,362.000 | $0.37 | $0.00 | $16,413.94 | |
0019 | TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 856(A) 8535 | LF | 12,093.000 | 12,093.000 | 5,976.000 | $0.56 | $0.00 | $3,346.56 | |
0020 | TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 856(A) 8548 | LF | 224.000 | 224.000 | 0.000 | $6.67 | $0.00 | $0.00 | |
0021 | ARROW DISPLAY(TYPE A) | 880(A) 8800 | SD | 180.000 | 180.000 | 90.000 | $5.56 | $0.00 | $500.40 | |
0022 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.950 | $9,763.55 | $0.00 | $9,275.38 | |
Subtotals For Category 0200/ROADWAY - SSR-014N(085)SR | $0.00 | $982,721.87 | ||||||||
Subtotals For Project SSR-014N(085)SR /27592(04) | $0.00 | $982,721.87 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: SSR-156N(174)SR | Project: 27592(05) | Category: 0200/ROADWAY - SSR-156N(174)SR | ||||||||
0023 | TRAFFIC BOUND SURFACE COURSE TYPE E | 402(E) 0225 | TON | 943.000 | 943.000 | 0.000 | $26.40 | $0.00 | $0.00 | |
0024 | TACK COAT | 407(B) 0250 | GAL | 7,955.000 | 7,955.000 | 77.500 | 7,543.000 | $2.33 | $180.58 | $17,575.20 |
0025 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 411(C) 5950 | TON | 11,043.000 | 11,043.000 | 10,959.340 | $78.00 | $0.00 | $854,828.52 | |
0026 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 411(C) 5960 | TON | 2,707.000 | 2,707.000 | 2,603.030 | $74.00 | $0.00 | $192,624.22 | |
0027 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 411(I) 6310 | TON | 30.000 | 30.000 | 0.000 | $180.89 | $0.00 | $0.00 | |
0028 | COLD MILLING PAVEMENT | 412 5267 | SY | 46,790.000 | 46,790.000 | 47,114.700 | $0.65 | $0.00 | $30,624.56 | |
0029 | RUMBLE STRIP-METHOD HMA-CYC | 413(B) 4863 | LF | 39,500.000 | 39,500.000 | 52,130.000 | $0.23 | $0.00 | $11,989.90 | |
0030 | TRAFFIC STRIPE (PLASTIC)(SYMBOLS, WORDS, ETC.) | 855(B) 3300 | EA | 20.000 | 20.000 | 15.000 | $133.44 | $0.00 | $2,001.60 | |
0031 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 856(A) 8530 | LF | 83,800.000 | 83,800.000 | 80,903.000 | $0.37 | $0.00 | $29,934.11 | |
0032 | TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 856(A) 8535 | LF | 18,300.000 | 18,300.000 | 10,192.000 | $0.56 | $0.00 | $5,707.52 | |
0033 | TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 856(A) 8548 | LF | 175.000 | 175.000 | 144.000 | $6.67 | $0.00 | $960.48 | |
0034 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 857(F) 8006 | LF | 35,400.000 | 35,400.000 | 5,567.000 | $0.07 | $0.00 | $389.69 | |
0035 | ARROW DISPLAY(TYPE A) | 880(A) 8800 | SD | 180.000 | 180.000 | 43.000 | $5.56 | $0.00 | $239.08 | |
0036 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.950 | $15,000.00 | $0.00 | $14,250.00 | |
Subtotals For Category 0200/ROADWAY - SSR-156N(174)SR | $180.58 | $1,161,124.88 | ||||||||
Subtotals For Project SSR-156N(174)SR /27592(05) | $180.58 | $1,161,124.88 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: SSR-156N(181)SR | Project: 29013(04) | Category: 0200/ROADWAY - SSR-156N(181)SR | ||||||||
0037 | TEMPORARY SILT FENCE | 221(C) 2801 | LF | 50.000 | 50.000 | 0.000 | $10.83 | $0.00 | $0.00 | |
0038 | SOLID SLAB SODDING | 230(A) 2806 | SY | 50.000 | 50.000 | 0.000 | $16.68 | $0.00 | $0.00 | |
0039 | FABRIC REINFORCEMENT | 409(A) 4242 | SY | 42,580.000 | 42,580.000 | 0.000 | 39,668.130 | $0.62 | $0.00 | $24,594.24 |
0040 | BITUMINOUS BINDER | 409(B) 4268 | GAL | 10,675.000 | 10,675.000 | 9,917.720 | $2.50 | $0.00 | $24,794.30 | |
0041 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 411(C) 5950 | TON | 4,770.000 | 4,770.000 | 4,359.460 | $78.00 | $0.00 | $340,037.88 | |
0042 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 411(I) 6310 | TON | 30.000 | 30.000 | 0.000 | $150.00 | $0.00 | $0.00 | |
0043 | COLD MILLING PAVEMENT | 412 5267 | SY | 42,580.000 | 42,580.000 | 30,465.180 | $0.69 | $0.00 | $21,020.97 | |
0044 | HANDRAILING | 504(F) 6006 | LF | 50.000 | 50.000 | 33.000 | 33.000 | $44.48 | $1,467.84 | $1,467.84 |
0045 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 688.000 | 688.000 | 0.000 | 227.310 | $78.95 | $0.00 | $17,946.13 |
0046 | TACTILE WARNING DEVICE-NEW | 610(I) 4610 | SF | 350.000 | 350.000 | 238.000 | $27.80 | $0.00 | $6,616.40 | |
0047 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 520.000 | 520.000 | 170.000 | $10.50 | $0.00 | $1,785.00 | |
0048 | LOOP DETECTOR WIRE | 828(B) 8136 | LF | 3,950.000 | 3,950.000 | 3,633.000 | $5.56 | $0.00 | $20,199.48 | |
0049 | TRAFFIC STRIPE (PLASTIC)(SYMBOLS, WORDS, ETC.) | 855(B) 3300 | EA | 69.000 | 69.000 | 55.000 | $133.44 | $0.00 | $7,339.20 | |
0050 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 856(A) 8530 | LF | 33,550.000 | 33,550.000 | 19,671.000 | $0.37 | $0.00 | $7,278.27 | |
0051 | TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 856(A) 8535 | LF | 1,450.000 | 1,450.000 | 2,694.000 | $0.56 | $0.00 | $1,508.64 | |
0052 | TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 856(A) 8548 | LF | 568.000 | 568.000 | 638.000 | $6.67 | $0.00 | $4,255.46 | |
0053 | TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 856(A) 8555 | LF | 520.000 | 520.000 | 514.000 | $11.12 | $0.00 | $5,715.68 | |
0054 | ARROW DISPLAY(TYPE A) | 880(A) 8800 | SD | 180.000 | 180.000 | 31.000 | $5.56 | $0.00 | $172.36 | |
0055 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 60.000 | 60.000 | 0.000 | $5.56 | $0.00 | $0.00 | |
0056 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.950 | $15,000.00 | $0.00 | $14,250.00 | |
Subtotals For Category 0200/ROADWAY - SSR-156N(181)SR | $1,467.84 | $498,981.85 | ||||||||
Subtotals For Project SSR-156N(181)SR /29013(04) | $1,467.84 | $498,981.85 |