Fed/State Project Number: ACIMY-XTWN(067) |
Project: 17428(77) |
Category: 0100/ROADWAY |
0001 |
SOLID SLAB SODDING |
230(A) 2806 |
SY |
14,340.000 |
55,894.000 |
4,253.380 |
121,455.610 |
$2.91 |
$12,377.34 |
$353,435.83 |
0002 |
MOWING |
241 2832 |
AC |
11.840 |
11.840 |
5.020 |
18.020 |
$72.71 |
$365.00 |
$1,310.23 |
0003 |
TRAFFIC BOUND SURFACE COURSE TYPE E |
402(E) 0225 |
TON |
810.000 |
810.000 |
|
365.190 |
$32.30 |
$0.00 |
$11,795.64 |
0004 |
SUPERPAVE, TYPE S3(PATCH)(PG64-22OK) |
411(H) 6210 |
TON |
1,538.000 |
1,538.000 |
|
0.000 |
$145.43 |
$0.00 |
$0.00 |
0005 |
FULL DEPTH P.C. CONCRETE PATCHING(PLACEMENT ONLY) |
414(E) 0225 |
SY |
885.000 |
885.000 |
|
87.500 |
$215.60 |
$0.00 |
$18,865.00 |
0006 |
P.C. CONCRETE FOR PAVEMENT |
414(G) 5275 |
CY |
184.000 |
184.000 |
|
19.540 |
$181.78 |
$0.00 |
$3,551.98 |
0007 |
CONCRETE CURB (6" BARRIER-INTEGRAL) |
609(A) 0300 |
LF |
125.000 |
125.000 |
|
200.000 |
$24.72 |
$0.00 |
$4,944.00 |
0008 |
COMBINED CURB & GUTTER (6" BARRIER) |
609(B) 0383 |
LF |
75.000 |
75.000 |
-25.000 |
189.000 |
$20.36 |
$-509.00 |
$3,848.04 |
0009 |
6" CONCRETE SIDEWALK |
610(A) 0605 |
SY |
35.000 |
721.000 |
16.670 |
930.750 |
$72.71 |
$1,212.08 |
$67,674.84 |
0010 |
CONTRACTOR HEALTH SAFETY PLAN |
620(C) 5910 |
LSUM |
1.000 |
1.000 |
|
1.000 |
$7,271.28 |
$0.00 |
$7,271.28 |
0011 |
CONTAMINATED MATERIALS MANAGEMENT PLAN |
620(C) 5920 |
LSUM |
1.000 |
1.000 |
|
1.000 |
$7,271.28 |
$0.00 |
$7,271.31 |
0012 |
FENCE-STYLE CLF (4'HIGH, CLASS A) |
624(E) 4288 |
LF |
1,600.000 |
1,600.000 |
|
690.000 |
$50.90 |
$0.00 |
$35,121.00 |
8012 |
(SP)TIME (B) BID |
644 7211 |
DAY |
0.000 |
50.000 |
50.000 |
50.000 |
$12,500.00 |
$625,000.00 |
$625,000.00 |
Subtotals For Category 0100/ROADWAY |
$638,445.42 |
$1,140,089.15 |
|
Fed/State Project Number: ACIMY-XTWN(067) |
Project: 17428(77) |
Category: 0200/BRIDGE |
0013 |
REMOVAL OF EXISTING BRIDGE STRUCTURE |
619(D) 1397 |
LSUM |
1.000 |
1.000 |
|
1.000 |
$7,550,431.73 |
$0.00 |
$7,550,431.72 |
0014 |
(SP) DELIVERY OF USED STEEL BEAM, UP TO 60' |
660(A) 0100 |
MILE |
86,994.000 |
104,024.000 |
3,878.000 |
107,902.000 |
$4.42 |
$17,140.76 |
$476,926.84 |
0015 |
(SP) DELIVERY OF USED STEEL BEAM, > 60' |
660(A) 0110 |
MILE |
132,663.000 |
135,725.000 |
-2,946.000 |
132,779.000 |
$4.42 |
$-13,021.32 |
$586,883.18 |
8000 |
CONSTRUCTION MISCELLANEOUS |
104 0700 |
LSUM |
0.000 |
1.000 |
|
1.000 |
$88,794.87 |
$0.00 |
$88,794.87 |
8002 |
(SP)DELIVERY OF USED STL BEAM, UP TO 60' |
660(A) 0100 |
MILE |
0.000 |
17,030.000 |
-3,299.000 |
13,731.000 |
$0.53 |
$-1,748.47 |
$7,277.43 |
8003 |
(SP) DELIVERY OF USED STEEL BEAM, > 60' |
660(A) 0110 |
MILE |
0.000 |
3,062.000 |
4,912.000 |
7,974.000 |
$0.53 |
$2,603.36 |
$4,226.22 |
8004 |
REMOVAL OF EXISTING BRIDGE STRUCTURE |
619(D) 1397 |
LSUM |
0.000 |
1.000 |
|
1.000 |
$-2,500.00 |
$0.00 |
$-2,500.00 |
8007 |
REMOVAL OF CONCRETE PAVEMENT |
619(B) 4727 |
SY |
0.000 |
11,469.000 |
11,469.000 |
11,469.000 |
$5.06 |
$58,033.14 |
$58,033.14 |
8008 |
REMOVAL OF CURB AND GUTTER |
619(B) 4726 |
LF |
0.000 |
7,199.000 |
7,199.000 |
7,199.000 |
$2.81 |
$20,229.19 |
$20,229.19 |
8009 |
REMOVAL OF EXISTING RETAINING WALL |
619(B) 6068 |
LF |
0.000 |
1,928.000 |
1,928.000 |
1,928.000 |
$38.45 |
$74,131.60 |
$74,131.60 |
8010 |
REMOVAL OF EXISTING PARAPET |
619(B) 6252 |
LF |
0.000 |
3,663.000 |
3,663.000 |
3,663.000 |
$15.14 |
$55,457.82 |
$55,457.82 |
8011 |
SAWING PAVEMENT |
619(C) 0924 |
LF |
0.000 |
832.000 |
832.000 |
832.000 |
$5.69 |
$4,734.08 |
$4,734.08 |
8013 |
TEMPORARY SILT FENCE |
221(C) 2801 |
LF |
0.000 |
3,700.000 |
3,700.000 |
3,700.000 |
$2.94 |
$10,878.00 |
$10,878.00 |
Subtotals For Category 0200/BRIDGE |
$228,438.16 |
$8,935,504.09 |
|
Fed/State Project Number: ACIMY-XTWN(067) |
Project: 17428(77) |
Category: 0330/TRAFFIC CONTROL |
0016 |
RAILROAD FLAGGING |
104 0950 |
DAY |
28.000 |
54.500 |
|
54.500 |
$1,454.26 |
$0.00 |
$79,257.17 |
0017 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(ARROWS) |
857(B) 8842 |
EA |
15.000 |
15.000 |
|
0.000 |
$36.36 |
$0.00 |
$0.00 |
0018 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(WORDS) |
857(B) 8845 |
EA |
15.000 |
15.000 |
|
0.000 |
$79.98 |
$0.00 |
$0.00 |
0019 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) |
857(C) 8851 |
LF |
15,000.000 |
15,000.000 |
|
0.000 |
$0.36 |
$0.00 |
$0.00 |
0020 |
NONREMOVABLE PAVEMENT MARKING TAPE(4" WIDE) |
857(D) 8869 |
LF |
5,000.000 |
5,000.000 |
|
0.000 |
$1.45 |
$0.00 |
$0.00 |
0021 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 |
857(E) 8887 |
EA |
4,000.000 |
4,000.000 |
|
0.000 |
$0.51 |
$0.00 |
$0.00 |
0022 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) |
857(F) 8006 |
LF |
20,000.000 |
20,000.000 |
|
0.000 |
$0.22 |
$0.00 |
$0.00 |
0023 |
DELIVER PORTABLE LONGITUDINAL BARRIER |
877(B) 8484 |
LF |
500.000 |
500.000 |
|
290.000 |
$14.54 |
$0.00 |
$4,216.60 |
0024 |
ARROW DISPLAY(TYPE C) |
880(A) 8812 |
SD |
1,000.000 |
1,000.000 |
|
0.000 |
$1.45 |
$0.00 |
$0.00 |
0025 |
CONSTRUCTION SIGNS 0 TO 6.25 SF |
880(B) 8818 |
SD |
17,000.000 |
17,000.000 |
-89.000 |
5,661.000 |
$0.07 |
$-6.23 |
$396.27 |
0026 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF |
880(B) 8821 |
SD |
4,000.000 |
4,000.000 |
-554.000 |
5,553.000 |
$0.15 |
$-83.10 |
$832.95 |
0027 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF |
880(B) 8822 |
EA |
14.000 |
14.000 |
|
0.000 |
$65.44 |
$0.00 |
$0.00 |
0028 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF |
880(B) 8824 |
SD |
800.000 |
800.000 |
-27.000 |
2,243.000 |
$10.18 |
$-274.86 |
$22,833.74 |
0029 |
CONSTRUCTION BARRICADES(TYPE II) |
880(C) 8836 |
SD |
800.000 |
800.000 |
-27.000 |
1,074.000 |
$0.73 |
$-19.71 |
$784.02 |
0030 |
CONSTRUCTION BARRICADES(TYPE III) |
880(C) 8842 |
SD |
10,000.000 |
10,000.000 |
-624.000 |
6,203.000 |
$0.87 |
$-542.88 |
$5,396.61 |
0031 |
BARRICADES(TYPE III) |
880(C) 8845 |
EA |
30.000 |
30.000 |
|
0.000 |
$218.14 |
$0.00 |
$0.00 |
0032 |
WING BARRICADES |
880(C) 8848 |
SD |
200.000 |
200.000 |
|
0.000 |
$2.91 |
$0.00 |
$0.00 |
0033 |
WARNING LIGHTS(TYPE A) |
880(E) 8860 |
SD |
21,000.000 |
21,000.000 |
-1,270.000 |
14,029.000 |
$0.07 |
$-88.90 |
$982.03 |
0034 |
WARNING LIGHTS(TYPE A) |
880(E) 8863 |
EA |
60.000 |
60.000 |
|
0.000 |
$34.90 |
$0.00 |
$0.00 |
0035 |
DRUMS |
880(F) 8878 |
SD |
8,000.000 |
8,000.000 |
-2,343.000 |
9,474.000 |
$0.15 |
$-351.45 |
$1,421.10 |
0036 |
TUBE CHANNELIZERS |
880(G) 8884 |
SD |
1,000.000 |
1,000.000 |
|
2,422.000 |
$0.58 |
$0.00 |
$1,404.76 |
0037 |
CHANNELIZER CONES |
880(G) 8890 |
SD |
1,000.000 |
1,000.000 |
|
0.000 |
$0.58 |
$0.00 |
$0.00 |
0038 |
FLAGGER |
880(I) 8902 |
SD |
112.000 |
112.000 |
|
0.000 |
$239.95 |
$0.00 |
$0.00 |
0039 |
PORT.CHANGEABLE MESSAGE SIGN |
882(A) 8306 |
SD |
2,000.000 |
2,000.000 |
10.000 |
400.000 |
$4.36 |
$43.60 |
$1,744.00 |
Subtotals For Category 0330/TRAFFIC CONTROL |
$-1,323.53 |
$119,269.25 |
|