Contract ID: | 110526 | Estimate Number: | 0001 | Contract No: | ||||
Residency: | TULSA (08100) | Estimate Type: | Progressive | Account No: | ||||
Project Number(s): | SBR-172A(515)SB, SBR-272A(005)SB | ||||||||||||
Primary Job Piece No: | 27633(04) | ||||||||||||
Contract Description: | BRIDGE REHABILITATION SH-51: OVER PITTSBURG AVE 0.5 MI E OF HARVARD AVE, AND OVER MK&T RAILROAD 0.7 MI E OF YALE AVE IN THE CITY OF TULSA. PROJECT LENGTH = 0.051 MILES | ||||||||||||
Primary County: | TULSA | ||||||||||||
Name of Road: | SH-51 | ||||||||||||
Prime Contractor: | BECCO CONTRACTORS, INC. | ||||||||||||
P.O. BOX 9159 | |||||||||||||
TULSA , OK 74157 | |||||||||||||
Surety Company: | MID-CONTINENT CASUALTY COMPANY | ||||||||||||
Date Let: | 01/19/2012 | NTP Effective Date: | 04/23/2012 | Pay Period: | 03/22/2012 TO 04/30/2012 |
Date Awarded: | 02/06/2012 | Date Work Began: | Original Contract Time: | 240 | |
Date Contract Executed: | 02/21/2012 | Date Time Stopped: | Current Time Charged: | 8.00 | |
Date NTP Issued: | 03/22/2012 | Completion Date: | Current Time Allowed: | 240.00 | |
General Liability Expires: | 03/01/2013 | Workman's Comp Expires: | 02/01/2013 | Percent Time Used: | 3.33 % |
Specification Year: | 2009 | Date Approved: | |||
Current Contract Amount: | $2,680,788.96 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $2,680,788.96 | Participating: | $0.00 | $0.00 | $0.00 | ||
Percent Complete: | 4.98 % | Non Participating: | $133,433.58 | $0.00 | $133,433.58 | ||
Funds Available: | $2,547,355.38 | Total Earnings: | $133,433.58 | $0.00 | $133,433.58 | ||
Unearned Balance: | $2,547,355.38 | Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||
Gross Earnings: | $133,433.58 | $0.00 | $133,433.58 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $133,433.58 | $0.00 | $133,433.58 |
Contract ID: | 110526 | Estimate Number: | 0001 | Primary JP: | 27633(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
01 | Incentive/Disincentive Substantial Completion | NOT ENTERED | NOT ENTERED | 200.00 DYS | $4,200.00 | N | |||
02 | Incentive/Disincentive Bridge A | NOT ENTERED | NOT ENTERED | 80.00 DYS | $4,000.00 | N |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 110526 | Estimate Number: | 0001 | Primary JP: | 27633(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0100/ROADWAY - SBR-172A(515)SB | ||||||||
0001 | CLEARING AND GRUBBING | 201(A) 0102 | LSUM | 1.000 | 1.000 | 0.000 | $10,000.00 | $0.00 | $0.00 | |
0002 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 411(C) 5950 | TON | 409.000 | 409.000 | 0.000 | $115.00 | $0.00 | $0.00 | |
0003 | COLD MILLING PAVEMENT | 412 5267 | SY | 1,015.000 | 1,015.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0004 | 42" F-SHAPED PARAPET | 504(E) 6190 | LF | 542.000 | 542.000 | 0.000 | $185.00 | $0.00 | $0.00 | |
0005 | CLASS C CONCRETE | 509(D) 0325 | CY | 10.600 | 10.600 | 0.000 | $500.00 | $0.00 | $0.00 | |
0006 | REMOVAL OF CONCRETE MEDIAN BARRIER | 619(B) 4915 | LF | 542.000 | 542.000 | 135.350 | 135.350 | $25.00 | $3,383.75 | $3,383.75 |
0007 | REMOVAL OF CONCRETE DITCH LINER | 619(B) 5881 | LF | 44.000 | 44.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0008 | REMOVAL OF 4" CONCRETE DIVIDING STRIP | 619(B) 6130 | SY | 53.000 | 53.000 | 52.640 | 52.640 | $10.00 | $526.40 | $526.40 |
Subtotals For Category 0100/ROADWAY - SBR-172A(515)SB | $3,910.15 | $3,910.15 | ||||||||
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0200/BRIDGE 'A' - SBR-172A(515)SB | ||||||||
0009 | CLSM BACKFILL | 501(G) 6309 | CY | 16.000 | 16.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
0010 | APPROACH SLAB | 504(A) 1304 | SY | 228.200 | 228.200 | 0.000 | $215.00 | $0.00 | $0.00 | |
0011 | SAW-CUT GROOVING | 504(B) 1305 | SY | 483.400 | 483.400 | 0.000 | $5.00 | $0.00 | $0.00 | |
0012 | SEALED EXPANSION JOINT | 504(C) 6250 | LF | 50.600 | 50.600 | 0.000 | $270.00 | $0.00 | $0.00 | |
0013 | 42" F-SHAPED PARAPET | 504(E) 6190 | LF | 180.000 | 180.000 | 0.000 | $125.00 | $0.00 | $0.00 | |
0014 | STRUCTURAL STEEL | 506(A) 1322 | LB | 750.000 | 750.000 | 0.000 | $18.00 | $0.00 | $0.00 | |
0015 | SPECIAL CONCRETE FINISH | 509 6152 | SY | 270.000 | 270.000 | 0.000 | $40.00 | $0.00 | $0.00 | |
0016 | CLASS AA CONCRETE | 509(A) 1326 | CY | 68.700 | 68.700 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0017 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 12,340.000 | 12,340.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
0018 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $25,000.00 | $0.00 | $0.00 | |
0019 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $5,000.00 | $0.00 | $0.00 | |
0020 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 160.000 | 160.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0021 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 100.000 | 100.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0022 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 2.000 | 2.000 | 0.000 | $55.00 | $0.00 | $0.00 | |
0023 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 100.000 | 100.000 | 0.000 | $600.00 | $0.00 | $0.00 | |
0024 | SEALER CRACK PREPARATION | 523(A) 6550 | LF | 90.000 | 90.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0025 | SEALER RESIN | 523(B) 6560 | GAL | 2.000 | 2.000 | 0.000 | $165.00 | $0.00 | $0.00 | |
0026 | (PL)REPAIR BRIDGE ITEMS | 540 4500 | LSUM | 1.000 | 1.000 | 0.000 | $15,000.00 | $0.00 | $0.00 | |
0027 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4510 | LSUM | 1.000 | 1.000 | 0.000 | $15,000.00 | $0.00 | $0.00 | |
0028 | REMOVAL OF BRIDGE ITEMS | 619(B) 2500 | LSUM | 1.000 | 1.000 | 0.250 | 0.250 | $13,000.00 | $3,250.00 | $3,250.00 |
0029 | REMOVAL OF BRIDGE ITEM (TYPE A) | 619(B) 2510 | LSUM | 1.000 | 1.000 | 0.250 | 0.250 | $70,000.00 | $17,500.00 | $17,500.00 |
Subtotals For Category 0200/BRIDGE 'A' - SBR-172A(515)SB | $20,750.00 | $20,750.00 | ||||||||
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0201/BRIDGE 'B' - SBR-172A(515)SB | ||||||||
0030 | CLSM BACKFILL | 501(G) 6309 | CY | 16.000 | 16.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
0031 | APPROACH SLAB | 504(A) 1304 | SY | 228.200 | 228.200 | 0.000 | $215.00 | $0.00 | $0.00 | |
0032 | SAW-CUT GROOVING | 504(B) 1305 | SY | 483.400 | 483.400 | 0.000 | $5.00 | $0.00 | $0.00 | |
0033 | SEALED EXPANSION JOINT | 504(C) 6250 | LF | 50.600 | 50.600 | 0.000 | $270.00 | $0.00 | $0.00 | |
0034 | 42" F-SHAPED PARAPET | 504(E) 6190 | LF | 180.000 | 180.000 | 0.000 | $125.00 | $0.00 | $0.00 | |
0035 | STRUCTURAL STEEL | 506(A) 1322 | LB | 750.000 | 750.000 | 0.000 | $18.00 | $0.00 | $0.00 | |
0036 | SPECIAL CONCRETE FINISH | 509 6152 | SY | 274.000 | 274.000 | 0.000 | $40.00 | $0.00 | $0.00 | |
0037 | CLASS AA CONCRETE | 509(A) 1326 | CY | 68.700 | 68.700 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0038 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 12,360.000 | 12,360.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
0039 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $25,000.00 | $0.00 | $0.00 | |
0040 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $5,000.00 | $0.00 | $0.00 | |
0041 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 160.000 | 160.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0042 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 100.000 | 100.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0043 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 2.000 | 2.000 | 0.000 | $55.00 | $0.00 | $0.00 | |
0044 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 100.000 | 100.000 | 0.000 | $600.00 | $0.00 | $0.00 | |
0045 | SEALER CRACK PREPARATION | 523(A) 6550 | LF | 90.000 | 90.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0046 | SEALER RESIN | 523(B) 6560 | GAL | 2.000 | 2.000 | 0.000 | $165.00 | $0.00 | $0.00 | |
0047 | (PL)REPAIR BRIDGE ITEMS | 540 4500 | LSUM | 1.000 | 1.000 | 0.000 | $5,000.00 | $0.00 | $0.00 | |
0048 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4510 | LSUM | 1.000 | 1.000 | 0.000 | $15,000.00 | $0.00 | $0.00 | |
0049 | REMOVAL OF BRIDGE ITEMS | 619(B) 2500 | LSUM | 1.000 | 1.000 | 0.000 | $13,000.00 | $0.00 | $0.00 | |
0050 | REMOVAL OF BRIDGE ITEM (TYPE A) | 619(B) 2510 | LSUM | 1.000 | 1.000 | 0.000 | $70,000.00 | $0.00 | $0.00 | |
Subtotals For Category 0201/BRIDGE 'B' - SBR-172A(515)SB | $0.00 | $0.00 | ||||||||
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0300/TRAFFIC OPERATIONS - SBR-172A(515)SB | ||||||||
0051 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 857(A) 8839 | LF | 11,099.000 | 11,099.000 | 20,377.000 | 20,377.000 | $0.15 | $3,056.55 | $3,056.55 |
0052 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 857(E) 8887 | EA | 1,150.000 | 1,150.000 | 0.000 | $1.10 | $0.00 | $0.00 | |
0053 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 857(F) 8006 | LF | 12,961.000 | 12,961.000 | 3,576.000 | 3,576.000 | $0.11 | $393.36 | $393.36 |
0054 | SAND FILLED IMPACT ATTENUATION MODULE | 870(A) 8485 | SD | 7,200.000 | 7,200.000 | 304.000 | 304.000 | $0.30 | $91.20 | $91.20 |
0055 | DELIVER PORTABLE LONGITUDINAL BARRIER | 877(B) 8484 | LF | 1,488.000 | 1,488.000 | 1,107.000 | 1,107.000 | $20.00 | $22,140.00 | $22,140.00 |
0056 | RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 877(C) 8486 | LF | 1,385.000 | 1,385.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0057 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 480.000 | 480.000 | 16.000 | 16.000 | $5.50 | $88.00 | $88.00 |
0058 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 5,760.000 | 5,760.000 | 128.000 | 128.000 | $0.30 | $38.40 | $38.40 |
0059 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 7,080.000 | 7,080.000 | 456.000 | 456.000 | $1.40 | $638.40 | $638.40 |
0060 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 11,880.000 | 11,880.000 | 368.000 | 368.000 | $0.55 | $202.40 | $202.40 |
0061 | CONSTRUCTION BARRICADES(TYPE III) | 880(C) 8842 | SD | 5,880.000 | 5,880.000 | 176.000 | 176.000 | $0.55 | $96.80 | $96.80 |
0062 | WING BARRICADES | 880(C) 8848 | SD | 960.000 | 960.000 | 0.000 | $1.10 | $0.00 | $0.00 | |
0063 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 23,640.000 | 23,640.000 | 712.000 | 712.000 | $0.06 | $42.72 | $42.72 |
0064 | DRUMS | 880(F) 8878 | SD | 15,600.000 | 15,600.000 | 1,920.000 | 1,920.000 | $0.28 | $537.60 | $537.60 |
0065 | PORT.CHANGEABLE MESSAGE SIGN | 882(A) 8306 | SD | 480.000 | 480.000 | 28.000 | 28.000 | $16.00 | $448.00 | $448.00 |
Subtotals For Category 0300/TRAFFIC OPERATIONS - SBR-172A(515)SB | $27,773.43 | $27,773.43 | ||||||||
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0301/TRAFFIC SIGNING AND STRIPING - SBR-172A(515)SB | ||||||||
0066 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 4,751.000 | 4,751.000 | 0.000 | $1.10 | $0.00 | $0.00 | |
Subtotals For Category 0301/TRAFFIC SIGNING AND STRIPING - SBR-172A(515)SB | $0.00 | $0.00 | ||||||||
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0600/STAKING - SBR-172A(515)SB | ||||||||
0067 | CONSTRUCTION STAKING LEVEL II | 642(B) 0096 | LSUM | 1.000 | 1.000 | 0.250 | 0.250 | $4,000.00 | $1,000.00 | $1,000.00 |
Subtotals For Category 0600/STAKING - SBR-172A(515)SB | $1,000.00 | $1,000.00 | ||||||||
Fed/State Project Number: SBR-172A(515)SB | Project: 27633(04) | Category: 0640/CONSTRUCTION - SBR-172A(515)SB | ||||||||
0068 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $160,000.00 | $80,000.00 | $80,000.00 |
Subtotals For Category 0640/CONSTRUCTION - SBR-172A(515)SB | $80,000.00 | $80,000.00 | ||||||||
Subtotals For Project SBR-172A(515)SB /27633(04) | $133,433.58 | $133,433.58 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: SBR-272A(005)SB | Project: 29053(04) | Category: 0100/ROADWAY - SBR-272A(005)SB | ||||||||
0069 | CLEARING AND GRUBBING | 201(A) 0102 | LSUM | 1.000 | 1.000 | 0.000 | $10,000.00 | $0.00 | $0.00 | |
0070 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 411(C) 5950 | TON | 126.000 | 126.000 | 0.000 | $145.00 | $0.00 | $0.00 | |
0071 | COLD MILLING PAVEMENT | 412 5267 | SY | 1,112.000 | 1,112.000 | 0.000 | $6.00 | $0.00 | $0.00 | |
0072 | REMOVAL OF GUARDRAIL | 619(B) 4780 | LF | 100.000 | 100.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0073 | BEAM GUARDRAIL W-BEAM SINGLE | 623(A) 0932 | LF | 81.250 | 81.250 | 0.000 | $24.00 | $0.00 | $0.00 | |
0074 | GUARDRAIL BRIDGE CONNECTION-TYPE A | 623(I) 8675 | EA | 1.000 | 1.000 | 0.000 | $3,300.00 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY - SBR-272A(005)SB | $0.00 | $0.00 | ||||||||
Fed/State Project Number: SBR-272A(005)SB | Project: 29053(04) | Category: 0200/BRIDGE 'A' - SBR-272A(005)SB | ||||||||
0075 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 697.000 | 697.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0076 | CLSM BACKFILL | 501(G) 6309 | CY | 539.900 | 539.900 | 0.000 | $80.00 | $0.00 | $0.00 | |
0077 | (PL)FALSEWORK JACKING | 502(C) 6116 | LSUM | 1.000 | 1.000 | 0.000 | $6,500.00 | $0.00 | $0.00 | |
0078 | APPROACH SLAB | 504(A) 1304 | SY | 587.000 | 587.000 | 0.000 | $215.00 | $0.00 | $0.00 | |
0079 | SAW-CUT GROOVING | 504(B) 1305 | SY | 1,456.900 | 1,456.900 | 0.000 | $5.00 | $0.00 | $0.00 | |
0080 | SEALED EXPANSION JOINT | 504(C) 6250 | LF | 134.400 | 134.400 | 0.000 | $270.00 | $0.00 | $0.00 | |
0081 | 42" F-SHAPED PARAPET | 504(E) 6190 | LF | 612.600 | 612.600 | 0.000 | $125.00 | $0.00 | $0.00 | |
0082 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0083 | STAINLESS STEEL FIXED BEARING ASSEMBLY | 507(A) 6170 | EA | 14.000 | 14.000 | 0.000 | $2,000.00 | $0.00 | $0.00 | |
0084 | CLASS AA CONCRETE | 509(A) 1326 | CY | 226.100 | 226.100 | 0.000 | $1,150.00 | $0.00 | $0.00 | |
0085 | CLASS C CONCRETE | 509(D) 1331 | CY | 100.700 | 100.700 | 0.000 | $290.00 | $0.00 | $0.00 | |
0086 | MECHANICAL SPLICES | 511 6306 | EA | 790.000 | 790.000 | 0.000 | $12.00 | $0.00 | $0.00 | |
0087 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 76,568.000 | 76,568.000 | 0.000 | $1.55 | $0.00 | $0.00 | |
0088 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $220,000.00 | $0.00 | $0.00 | |
0089 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $35,000.00 | $0.00 | $0.00 | |
0090 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 1,118.000 | 1,118.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0091 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 192.000 | 192.000 | 0.000 | $12.00 | $0.00 | $0.00 | |
0092 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 6.400 | 6.400 | 0.000 | $200.00 | $0.00 | $0.00 | |
0093 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 61.200 | 61.200 | 0.000 | $680.00 | $0.00 | $0.00 | |
0094 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4510 | LSUM | 1.000 | 1.000 | 0.000 | $2,000.00 | $0.00 | $0.00 | |
0095 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 7.000 | 7.000 | 0.000 | $1,500.00 | $0.00 | $0.00 | |
0096 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4530 | LSUM | 1.000 | 1.000 | 0.000 | $25,000.00 | $0.00 | $0.00 | |
0097 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(H) 6204 | LF | 143.000 | 143.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0098 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(I) 6207 | LF | 40.000 | 40.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0099 | REMOVAL OF BRIDGE ITEMS | 619(B) 2500 | LSUM | 1.000 | 1.000 | 0.000 | $190,000.00 | $0.00 | $0.00 | |
Subtotals For Category 0200/BRIDGE 'A' - SBR-272A(005)SB | $0.00 | $0.00 | ||||||||
Fed/State Project Number: SBR-272A(005)SB | Project: 29053(04) | Category: 0300/TRAFFIC CONTROL - SBR-272A(005)SB | ||||||||
0100 | REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 857(C) 8851 | LF | 9,929.000 | 9,929.000 | 0.000 | $1.30 | $0.00 | $0.00 | |
0101 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 857(F) 8006 | LF | 13,645.000 | 13,645.000 | 0.000 | $0.11 | $0.00 | $0.00 | |
0102 | (SP)CONST.ZONE IMPACT ATTEN. | 871(B) 8705 | SD | 240.000 | 240.000 | 0.000 | $3.30 | $0.00 | $0.00 | |
0103 | DELIVER PORTABLE LONGITUDINAL BARRIER | 877(B) 8484 | LF | 1,275.000 | 1,275.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0104 | RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 877(C) 8486 | LF | 1,000.000 | 1,000.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0105 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 360.000 | 360.000 | 0.000 | $5.50 | $0.00 | $0.00 | |
0106 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 2,160.000 | 2,160.000 | 0.000 | $0.55 | $0.00 | $0.00 | |
0107 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 6,720.000 | 6,720.000 | 0.000 | $0.55 | $0.00 | $0.00 | |
0108 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 8,640.000 | 8,640.000 | 0.000 | $0.55 | $0.00 | $0.00 | |
0109 | CONSTRUCTION BARRICADES(TYPE III) | 880(C) 8842 | SD | 1,080.000 | 1,080.000 | 0.000 | $1.65 | $0.00 | $0.00 | |
0110 | WING BARRICADES | 880(C) 8848 | SD | 480.000 | 480.000 | 0.000 | $1.10 | $0.00 | $0.00 | |
0111 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 3,000.000 | 3,000.000 | 0.000 | $0.40 | $0.00 | $0.00 | |
0112 | DRUMS | 880(F) 8878 | SD | 16,440.000 | 16,440.000 | 0.000 | $0.30 | $0.00 | $0.00 | |
0113 | TRAFFIC SURVEILLANCE, POLICE | 880(L) 8911 | HOUR | 240.000 | 240.000 | 0.000 | $65.00 | $0.00 | $0.00 | |
0114 | PORT.CHANGEABLE MESSAGE SIGN | 882(A) 8306 | SD | 240.000 | 240.000 | 0.000 | $16.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC CONTROL - SBR-272A(005)SB | $0.00 | $0.00 | ||||||||
Fed/State Project Number: SBR-272A(005)SB | Project: 29053(04) | Category: 0301/TRAFFIC SIGNING AND STRIPING - SBR-272A(005)SB | ||||||||
0115 | GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 853 9069 | EA | 3.000 | 3.000 | 0.000 | $55.00 | $0.00 | $0.00 | |
0116 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 9,841.000 | 9,841.000 | 0.000 | $0.55 | $0.00 | $0.00 | |
0117 | TRAFFIC STRIPE(PLASTIC)(6" WIDE) | 855(A) 8813 | LF | 2,569.000 | 2,569.000 | 0.000 | $1.10 | $0.00 | $0.00 | |
0118 | TRAFFIC STRIPE(PLASTIC)(8" WIDE) | 855(A) 8814 | LF | 520.000 | 520.000 | 0.000 | $2.20 | $0.00 | $0.00 | |
0119 | TRAFFIC STRIPE(PLASTIC)(12" WIDE) | 855(A) 8818 | LF | 224.000 | 224.000 | 0.000 | $3.30 | $0.00 | $0.00 | |
0120 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 856(A) 8530 | LF | 1,176.000 | 1,176.000 | 0.000 | $2.20 | $0.00 | $0.00 | |
0121 | TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 856(A) 8535 | LF | 635.000 | 635.000 | 0.000 | $3.30 | $0.00 | $0.00 | |
Subtotals For Category 0301/TRAFFIC SIGNING AND STRIPING - SBR-272A(005)SB | $0.00 | $0.00 | ||||||||
Subtotals For Project SBR-272A(005)SB /29053(04) | $0.00 | $0.00 |