Contract ID: | 110420 | Estimate Number: | 0022 | Contract No: | 710553 | |||
Residency: | CLAREMORE (08300) | Estimate Type: | Progressive | Account No: | 400800 | |||
Project Number(s): | STPY-118C(096)SS | ||||||||||||
Primary Job Piece No: | 24183(04) | ||||||||||||
Contract Description: | WIDEN AND RESURFACE SH-66: FROM 1.25 MILES EAST OF THE ROGERS COUNTY LINE, EXTEND NORTHEAST. PROJECT LENGTH = 5.621 MILES. | ||||||||||||
Primary County: | CRAIG | ||||||||||||
Name of Road: | SH-66 | ||||||||||||
Prime Contractor: | BECCO CONTRACTORS, INC. | ||||||||||||
P.O. BOX 9159 | |||||||||||||
TULSA , OK 74157 | |||||||||||||
Surety Company: | MID-CONTINENT CASUALTY CO. | ||||||||||||
Date Let: | 10/20/2011 | NTP Effective Date: | 03/05/2012 | Pay Period: | 01/16/2013 TO 01/31/2013 |
Date Awarded: | 11/07/2011 | Date Work Began: | 03/05/2012 | Original Contract Time: | 270 |
Date Contract Executed: | 11/17/2011 | Date Time Stopped: | Current Time Charged: | 259.00 | |
Date NTP Issued: | 02/03/2012 | Completion Date: | Current Time Allowed: | 287.00 | |
General Liability Expires: | 03/01/2014 | Workman's Comp Expires: | 02/01/2014 | Percent Time Used: | 90.24 % |
Specification Year: | 2009 | Date Approved: | |||
Current Contract Amount: | $7,498,806.49 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $7,425,911.85 | Participating: | $4,660,823.43 | $4,491,391.37 | $169,432.06 | ||
Percent Complete: | 61.71 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $2,870,959.23 | Total Earnings: | $4,660,823.43 | $4,491,391.37 | $169,432.06 | ||
Unearned Balance: | $2,798,064.59 | Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||
Gross Earnings: | $4,660,823.43 | $4,491,391.37 | $169,432.06 | ||||
Other Adjustments: | $-32,976.17 | $-32,976.17 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $4,627,847.26 | $4,458,415.20 | $169,432.06 |
Contract ID: | 110420 | Estimate Number: | 0022 | Primary JP: | 24183(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Add curb and gutter pay item | Approved | 12/04/2012 | 10.0 | $51,254.64 |
002 | Add asphalt removal | Approved | 01/08/2013 | 7.0 | $21,640.00 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0002 | 152.80 | $0.04 | $7.40 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0003 | 737.00 | $0.08 | $62.24 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0004 | 50.69 | $0.08 | $4.28 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0005 | 50.69 | $0.05 | $2.76 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0006 | 3,320.00 | $0.05 | $180.77 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0009 | 4,003.10 | $-0.03 | $-145.91 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0010 | 357.87 | $-0.03 | $-13.04 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0013 | 8,238.00 | $0.08 | $720.41 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0014 | 3,441.96 | $0.08 | $301.00 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0015 | 3,351.00 | $0.06 | $222.67 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0016 | 1,389.00 | $0.06 | $92.30 |
24183(04) | 0001 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0018 | 16,814.32 | $0.06 | $1,117.31 |
24183(04) | 0002 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0009 | 696.00 | $-0.03 | $-25.37 |
24183(04) | 0002 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0013 | 552.00 | $0.08 | $48.27 |
24183(04) | 0002 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0015 | 45.00 | $0.06 | $2.99 |
24183(04) | 0002 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0016 | 1,488.00 | $0.06 | $98.88 |
24183(04) | 0002 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0017 | 192.00 | $0.06 | $12.76 |
24183(04) | 0002 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0018 | 11,169.00 | $0.06 | $742.18 |
24183(04) | 0004 | TEMPORARY SILT FENCE | * Missing Material Certification | 0001 | -2,255.00 | $2.00 | $-4,510.00 |
24183(04) | 0004 | TEMPORARY SILT FENCE | * Missing Material Certification | 0002 | 2,255.00 | $2.00 | $4,510.00 |
24183(04) | 0005 | TEMPORARY SILT DIKE | * Missing Material Certification | 0001 | -273.00 | $10.00 | $-2,730.00 |
24183(04) | 0005 | TEMPORARY SILT DIKE | * Missing Material Certification | 0002 | 273.00 | $10.00 | $2,730.00 |
24183(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | * HMA Deduction as per Sec. 411 | 0007 | -727.60 | $54.00 | $-39,290.40 |
24183(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0007 | 1,162.00 | $0.77 | $899.21 |
24183(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | * Asphalt Binder Adjustment | 0007 | -727.60 | $0.77 | $-560.25 |
24183(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0008 | 3,234.30 | $0.77 | $2,502.86 |
24183(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | * Asphalt Binder Adjustment | 0013 | 727.60 | $0.77 | $560.25 |
24183(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | * HMA Deduction as per Sec. 411 | 0016 | 0.54 | $54.00 | $29.16 |
24183(04) | 0023 | SUPERPAVE, TYPE S4(PG 64-22 OK) | Asphalt Binder Adjustment | 0007 | 213.00 | $0.88 | $188.38 |
24183(04) | 0028 | CLASS AA CONCRETE | * COMPRESSIVE STRENGTH | 0011 | 0.00 | $0.00 | $-211.75 |
24183(04) | 0028 | CLASS AA CONCRETE | * COMPRESSIVE STRENGTH | 0013 | 3.50 | $-150.15 | $-525.53 |
24183(04) | 0055 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | * Missing Material Certification | 0014 | -221.00 | $0.54 | $-119.34 |
24183(04) | 0055 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | * Missing Material Certification | 0016 | -779.00 | $0.54 | $-420.66 |
24183(04) | 0055 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | * Missing Material Certification | 0019 | 1,000.00 | $0.54 | $540.00 | Subtotals For Line Item Adjustments | $-32,976.17 | * = User applied Line Item Adjustments |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 110420 | Estimate Number: | 0022 | Primary JP: | 24183(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STPY-118C(096)SS | Project: 24183(04) | Category: 0100/ROADWAY | ||||||||
0001 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 43,245.000 | 43,245.000 | 43,245.000 | $8.00 | $0.00 | $345,960.00 | |
0002 | UNCLASSIFIED BORROW | 202(D) 0184 | CY | 19,838.000 | 19,838.000 | 19,838.000 | $8.00 | $0.00 | $158,704.00 | |
0003 | TYPE A-SALVAGED TOPSOIL | 205(A) 4229 | LSUM | 1.000 | 1.000 | 0.500 | $100,000.00 | $0.00 | $50,000.00 | |
0004 | TEMPORARY SILT FENCE | 221(C) 2801 | LF | 18,500.000 | 18,500.000 | 11,189.000 | $2.00 | $0.00 | $22,378.00 | |
0005 | TEMPORARY SILT DIKE | 221(F) 0100 | LF | 1,218.000 | 1,218.000 | 571.000 | $10.00 | $0.00 | $5,710.00 | |
0006 | DITCH LINER PROTECTION | 229 4318 | LF | 12,300.000 | 12,300.000 | 6,125.000 | $1.25 | $0.00 | $7,656.25 | |
0007 | SOLID SLAB SODDING | 230(A) 2806 | SY | 115,898.000 | 115,898.000 | 74,721.220 | $1.50 | $0.00 | $112,081.83 | |
0008 | SEEDING METHOD A | 232(A) 2813 | AC | 24.000 | 24.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
0009 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 24.000 | 24.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
0010 | MOWING | 241 2832 | AC | 48.000 | 48.000 | 44.290 | $50.00 | $0.00 | $2,214.50 | |
0011 | FLY ASH | 307(A) 4200 | TON | 4,567.000 | 4,567.000 | 3,504.560 | $55.00 | $0.00 | $192,750.80 | |
0012 | LIME | 307(D) 4230 | TON | 488.000 | 488.000 | 25.480 | $90.00 | $0.00 | $2,293.20 | |
0013 | CEMENTITIOUS STABILIZED SUBGRADE | 307(E) 4240 | SY | 84,553.000 | 84,553.000 | 65,790.420 | $2.00 | $0.00 | $131,580.84 | |
0014 | LIME PRETREATMENT | 307(G) 4260 | SY | 34,826.000 | 34,826.000 | 1,721.780 | $0.50 | $0.00 | $860.89 | |
0015 | TRAFFIC BOUND SURFACE COURSE TYPE E | 402(E) 0225 | TON | 1,362.000 | 1,362.000 | 817.350 | $18.00 | $0.00 | $14,712.30 | |
0016 | TACK COAT | 407(B) 0250 | GAL | 31,104.000 | 31,104.000 | 2,576.000 | 8,426.000 | $2.00 | $5,152.00 | $16,852.00 |
0017 | PRIME COAT | 408 5774 | GAL | 20,651.000 | 20,651.000 | 8,289.130 | $2.00 | $0.00 | $16,578.26 | |
0018 | FABRIC REINFORCEMENT | 409(A) 4242 | SY | 93,495.000 | 93,495.000 | 20,216.440 | $1.00 | $0.00 | $20,216.44 | |
0019 | BITUMINOUS BINDER | 409(B) 4268 | GAL | 18,700.000 | 18,700.000 | 4,004.440 | $3.50 | $0.00 | $14,015.54 | |
0020 | SUPERPAVE, TYPE S3(PG 70-28 OK) | 411(B) 5940 | TON | 15,915.000 | 15,915.000 | 7,906.020 | $61.00 | $0.00 | $482,267.22 | |
0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 411(B) 5945 | TON | 32,463.000 | 32,463.000 | 1,319.160 | 25,834.570 | $54.00 | $71,234.64 | $1,395,066.78 |
0022 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 411(C) 5955 | TON | 9,861.000 | 9,861.000 | 2,135.580 | $82.00 | $0.00 | $175,117.56 | |
0023 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 411(C) 5960 | TON | 7,934.000 | 7,934.000 | 1,108.270 | $73.00 | $0.00 | $80,903.71 | |
0024 | COLD MILLING PAVEMENT | 412 5267 | SY | 79,426.000 | 79,426.000 | 47,013.980 | $1.50 | $0.00 | $70,520.98 | |
0025 | P.C.CONCRETE PAVEMENT(PLACEMENT) | 414(A) 0210 | SY | 1,362.000 | 1,362.000 | 768.970 | $35.00 | $0.00 | $26,913.95 | |
0026 | P.C. CONCRETE FOR PAVEMENT | 414(G) 5275 | CY | 227.000 | 227.000 | 141.630 | $110.00 | $0.00 | $15,579.30 | |
0027 | STRUCTURAL EXCAVATION UNCLASSIFIED | 501(A) 0313 | CY | 160.000 | 160.000 | 77.680 | $15.00 | $0.00 | $1,165.20 | |
0028 | CLASS AA CONCRETE | 509(A) 0319 | CY | 262.000 | 262.000 | 262.000 | $550.00 | $0.00 | $144,100.00 | |
0029 | CLASS C CONCRETE | 509(D) 0325 | CY | 960.000 | 960.000 | 232.340 | 632.110 | $360.00 | $83,642.40 | $227,559.60 |
0030 | REINFORCING STEEL | 511(A) 0332 | LB | 32,166.000 | 32,166.000 | 32,166.000 | $1.30 | $0.00 | $41,815.82 | |
0031 | TYPE I PLAIN RIPRAP | 601(A) 0297 | TON | 348.000 | 348.000 | 38.130 | 72.380 | $40.00 | $1,525.20 | $2,895.20 |
0032 | CONCRETE CURB (6" MNTBLE-INTEGRAL) | 609(A) 0288 | LF | 3,501.000 | 0.000 | 0.000 | $6.00 | $0.00 | $0.00 | |
0033 | 6" CONCRETE DRIVEWAY | 610(B) 0604 | SY | 144.000 | 144.000 | 130.690 | $75.00 | $0.00 | $9,801.75 | |
0034 | INLET CI DES. 1 (STD) | 611(G) 5100 | EA | 2.000 | 2.000 | 2.000 | $3,500.00 | $0.00 | $7,000.00 | |
0035 | INLET CI DES. 1 (2C) | 611(G) 5111 | EA | 1.000 | 1.000 | 1.000 | $8,500.00 | $0.00 | $8,500.00 | |
0036 | 24" R.C.PIPE CLASS III | 613(A) 0492 | LF | 58.000 | 58.000 | 64.000 | $60.00 | $0.00 | $3,840.00 | |
0037 | 36" R.C.PIPE CLASS III | 613(A) 0494 | LF | 60.000 | 60.000 | 60.000 | $100.00 | $0.00 | $6,000.00 | |
0038 | 28 1/2" X 18" R.C.PIPE ARCH CLASS A-III | 613(A) 4410 | LF | 868.000 | 868.000 | 793.260 | $70.00 | $0.00 | $55,528.20 | |
0039 | 18" CORR. GALV. STEEL PIPE | 613(B) 0689 | LF | 136.000 | 136.000 | 136.000 | $38.00 | $0.00 | $5,168.00 | |
0040 | 28 1/2" X 18" PREFAB. CULVERT END SECTION, ARCH | 613(L) 4584 | EA | 50.000 | 50.000 | 44.000 | $1,000.00 | $0.00 | $44,000.00 | |
0041 | 24" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5730 | EA | 2.000 | 2.000 | 2.000 | $700.00 | $0.00 | $1,400.00 | |
0042 | 36" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5734 | EA | 2.000 | 2.000 | 2.000 | $1,300.00 | $0.00 | $2,600.00 | |
0043 | STANDARD BEDDING MATERIAL, CLASS C | 613(T) 1187 | CY | 98.000 | 98.000 | 97.150 | $50.00 | $0.00 | $4,857.50 | |
0044 | TRENCH EXCAVATION | 613(V) 1180 | CY | 138.000 | 138.000 | 137.400 | $25.00 | $0.00 | $3,435.00 | |
0045 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 619(A) 0920 | LSUM | 1.000 | 1.000 | 1.000 | $20,000.00 | $0.00 | $20,000.00 | |
0046 | REMOVAL OF HEADWALL | 619(B) 0291 | EA | 32.000 | 32.000 | 18.000 | $1,500.00 | $0.00 | $27,000.00 | |
0047 | SAWING PAVEMENT | 619(C) 0924 | LF | 68,877.000 | 68,877.000 | 59,978.500 | $1.00 | $0.00 | $59,978.50 | |
0048 | FENCE-STYLE WWF | 624(A) 4281 | LF | 405.000 | 405.000 | 0.000 | $4.00 | $0.00 | $0.00 | |
0049 | FENCE-STYLE SWF (5 BARBED WIRE) | 624(C) 4459 | LF | 16,880.000 | 16,880.000 | 9,695.000 | $4.00 | $0.00 | $38,780.00 | |
0050 | MAILBOX INSTALLATION-SINGLE | 629(A) 4958 | EA | 9.000 | 9.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
0051 | MAILBOX INSTALLATION-MULTIPLE | 629(B) 4959 | EA | 3.000 | 3.000 | 0.000 | $250.00 | $0.00 | $0.00 | |
0052 | MAILBOX | 629(C) 4960 | EA | 15.000 | 15.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0053 | REMOVAL OF MAILBOX INSTALLATION | 629(D) 4961 | EA | 15.000 | 15.000 | 9.000 | $5.00 | $0.00 | $45.00 | |
8000 | 2'-8" COMB.CRB.& GUT.(6" MNTBLE-NOTCH) | 609(B) 0394 | LF | 0.000 | 3,501.000 | 2,096.000 | $20.64 | $0.00 | $43,261.44 | |
8001 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 0.000 | 4,000.000 | 4,000.000 | $5.41 | $0.00 | $21,640.00 | |
Subtotals For Category 0100/ROADWAY | $161,554.24 | $4,141,305.56 | ||||||||
Fed/State Project Number: STPY-118C(096)SS | Project: 24183(04) | Category: 0300/TRAFFIC CONTROL | ||||||||
0054 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 857(A) 8839 | LF | 20,000.000 | 20,000.000 | 15,100.000 | $0.11 | $0.00 | $1,661.00 | |
0055 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 857(E) 8887 | EA | 5,000.000 | 5,000.000 | 1,000.000 | $0.54 | $0.00 | $540.00 | |
0056 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 857(F) 8006 | LF | 20,000.000 | 20,000.000 | 940.000 | $0.16 | $0.00 | $150.40 | |
0057 | (PL)TRUCK MOUNTED ATTENUATOR | 876(A) 8482 | SD | 540.000 | 540.000 | 4.000 | $5.40 | $0.00 | $21.60 | |
0058 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 3,240.000 | 3,240.000 | 924.000 | 10,178.000 | $0.85 | $785.40 | $8,651.30 |
0059 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 1,620.000 | 1,620.000 | 490.000 | 8,227.000 | $1.08 | $529.20 | $8,885.16 |
0060 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 5,400.000 | 5,400.000 | 1,700.000 | 14,723.000 | $2.16 | $3,672.00 | $31,801.68 |
0061 | CONSTRUCTION BARRICADES(TYPE III) | 880(C) 8842 | SD | 1,620.000 | 1,620.000 | 21.000 | 1,670.000 | $0.27 | $5.67 | $450.90 |
0062 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 6,750.000 | 6,750.000 | 1,155.000 | 14,298.000 | $0.11 | $127.05 | $1,572.78 |
0063 | DRUMS | 880(F) 8878 | SD | 13,770.000 | 13,770.000 | 0.000 | $0.11 | $0.00 | $0.00 | |
0064 | CHANNELIZER CONES | 880(G) 8890 | SD | 36,990.000 | 36,990.000 | 23,170.000 | 146,661.000 | $0.05 | $1,158.50 | $7,333.05 |
0065 | FLAGGER | 880(I) 8902 | SD | 540.000 | 540.000 | 16.000 | 466.000 | $100.00 | $1,600.00 | $46,600.00 |
0066 | PORT.CHANGEABLE MESSAGE SIGN | 882(A) 8306 | SD | 540.000 | 540.000 | 0.000 | $8.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC CONTROL | $7,877.82 | $107,667.87 | ||||||||
Fed/State Project Number: STPY-118C(096)SS | Project: 24183(04) | Category: 0301/SIGNING & STRIPIING | ||||||||
0067 | (PL)REMOVE & RESET GROUND MOUNTED SIGN | 805(D) 8760 | EA | 6.000 | 6.000 | 0.000 | $216.00 | $0.00 | $0.00 | |
0068 | SHEET ALUMINUM SIGNS | 850(A) 8110 | SF | 205.300 | 205.300 | 0.000 | $12.00 | $0.00 | $0.00 | |
0069 | 2" SQUARE TUBE POST | 851(C) 8324 | LF | 442.500 | 442.500 | 0.000 | $8.00 | $0.00 | $0.00 | |
0070 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 89,805.000 | 89,805.000 | 0.000 | $0.35 | $0.00 | $0.00 | |
Subtotals For Category 0301/SIGNING & STRIPIING | $0.00 | $0.00 | ||||||||
Fed/State Project Number: STPY-118C(096)SS | Project: 24183(04) | Category: 0600/STAKING | ||||||||
0071 | CONSTRUCTION STAKING LEVEL II | 642(B) 0096 | LSUM | 1.000 | 1.000 | 0.750 | $50,000.00 | $0.00 | $37,500.00 | |
Subtotals For Category 0600/STAKING | $0.00 | $37,500.00 | ||||||||
Fed/State Project Number: STPY-118C(096)SS | Project: 24183(04) | Category: 0640/CONSTRUCTION | ||||||||
0072 | SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.750 | $4,000.00 | $0.00 | $3,000.00 | |
0073 | FIELD OFFICE | 640(A) 1426 | EA | 1.000 | 1.000 | 1.000 | $10,000.00 | $0.00 | $10,000.00 | |
0074 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 0.990 | $365,000.00 | $0.00 | $361,350.00 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $374,350.00 | ||||||||
Subtotals For Project STPY-118C(096)SS /24183(04) | $169,432.06 | $4,660,823.43 |