Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    10/16/2012
Contract ID: 110396   Estimate Number: 0015     Contract No: 710120
Residency: ALTUS (05200)   Estimate Type: Progressive     Account No: 400500

Project Number(s): BRFY-105B(169)
Primary Job Piece No: 25822(04)
Contract Description: BRIDGE AND APPROACHES US-283: OVER TIMBER CREEK, 0.50 MILES SOUTH OF THE ROGER MILLS COUNTY LINE. PROJECT LENGTH = 0.309 MILES.
Primary County: BECKHAM              
Name of Road: US-283              
Prime Contractor: MANHATTAN ROAD & BRIDGE COMPANY              
    5601 S. 122ND E. AVE.              
    TULSA , OK   74146              
Surety Company:              

Date Let: 06/30/2011 NTP Effective Date: 09/01/2011 Pay Period: 10/01/2012  TO  10/15/2012
Date Awarded: 07/11/2011 Date Work Began: 11/01/2011 Original Contract Time: 180
Date Contract Executed: 07/22/2011 Date Time Stopped: Current Time Charged: 244.00
Date NTP Issued: 07/29/2011 Completion Date: Current Time Allowed: 224.00
General Liability Expires: 10/01/2013 Workman's Comp Expires: 10/01/2013 Percent Time Used: 108.93 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $1,371,350.99 Total to Date Prev to Date This Estimate
Bid Amount: $1,367,072.99 Participating: $1,225,499.56 $1,190,432.18 $35,067.38
Percent Complete: 87.69 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $168,824.48 Total Earnings: $1,225,499.56 $1,190,432.18 $35,067.38
Unearned Balance: $164,546.48 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $1,225,499.56 $1,190,432.18 $35,067.38
Other Adjustments: $-7,973.05 $-7,973.05 $0.00
Liq Dam/Disincentive: $-15,000.00 $-15,000.00 $0.00
TOTAL: $1,202,526.51 $1,167,459.13 $35,067.38

Estimate Adjustment Detail

Contract ID: 110396   Estimate Number: 0015     Primary JP: 25822(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Time Adjustment Approved 10/20/2011 44.0 $0.00
002 Temporary Structure Approved 06/20/2012 0.0 $4,278.00
003 Changing unit of measure on the Unclassified Exavation Pending 0 0.0 $51,757.88


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
25822(04) 0018 Type B6 SCE5 Stockpiled Material Initial Payment 0001 $1,477.68
25822(04) 0018 Type B6 SCE5 Stockpiled Material Closure 0014 $-1,477.68
25822(04) 0027 Reinforcing Steel Stockpiled Material Adjustment 0008 $-2,883.83
25822(04) 0027 Reinforcing Steel Stockpiled Material Initial Payment 0001 $20,596.65
25822(04) 0027 Reinforcing Steel Stockpiled Material Adjustment 0003 $-17,712.82
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0011 --10 $750.00 $-7,500.00
System Application of Liquidated Damages 0012 --10 $750.00 $-7,500.00
Subtotals For Liquidated Damages $-15,000.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
25822(04) 0004 TYPE A-SALVAGED TOPSOIL * Missing Material Certification 0013 -0.50 $5,000.00 $-2,500.00
25822(04) 0004 TYPE A-SALVAGED TOPSOIL * Missing Material Certification 0014 0.50 $5,000.00 $2,500.00
25822(04) 0023 FENCE-STYLE SWF (5 BARBED WIRE) * Missing Material Certification 0007 -1,460.00 $3.48 $-5,080.80
25822(04) 0023 FENCE-STYLE SWF (5 BARBED WIRE) * Missing Material Certification 0009 1,460.00 $3.48 $5,080.80
25822(04) 0030 TRAFFIC STRIPE(PLASTIC)(4" WIDE) * Missing Material Certification 0013 -6,053.00 $0.85 $-5,145.05
25822(04) 0031 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) * Missing Material Certification 0007 -9,623.00 $0.30 $-2,886.90
25822(04) 0031 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) * Missing Material Certification 0010 9,623.00 $0.30 $2,886.90
25822(04) 0035 SAND FILLED IMPACT ATTENUATION MODULE * Missing Material Certification 0007 -44.00 $0.70 $-30.80
25822(04) 0035 SAND FILLED IMPACT ATTENUATION MODULE * Missing Material Certification 0009 44.00 $0.70 $30.80
25822(04) 0036 DELIVER PORTABLE LONGITUDINAL BARRIER * Missing Material Certification 0007 -900.00 $14.75 $-13,275.00
25822(04) 0036 DELIVER PORTABLE LONGITUDINAL BARRIER * Missing Material Certification 0009 900.00 $14.75 $13,275.00
25822(04) 8001 18" CORR. GALV. STEEL PIPE * Missing Material Certification 0014 -80.00 $35.35 $-2,828.00
Subtotals For Line Item Adjustments $-7,973.05
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 110396   Estimate Number: 0015     Primary JP: 25822(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BRFY-105B(169) Project:    25822(04) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201(A) 0102 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 22,214.000 22,214.000   22,214.000 $3.25 $0.00 $72,195.50
0003 UNCLASSIFIED BORROW 202(D) 0184 CY 30,556.000 30,556.000   14,630.500 $4.00 $0.00 $58,522.00
0004 TYPE A-SALVAGED TOPSOIL 205(A) 4229 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0005 TEMPORARY SILT FENCE 221(C) 2801 LF 2,000.000 2,000.000   1,694.000 $1.25 $0.00 $2,117.50
0006 TEMPORARY SILT DIKE 221(F) 0100 LF 120.000 120.000   0.000 $8.00 $0.00 $0.00
0007 SOLID SLAB SODDING 230(A) 2806 SY 27,104.000 27,104.000 32,067.380 32,067.380 $1.00 $32,067.38 $32,067.38
0008 VEGETATIVE MULCHING 233(A) 2817 AC 5.600 5.600   0.000 $300.00 $0.00 $0.00
0009 FLY ASH 307(A) 4200 TON 406.000 406.000   404.290 $66.50 $0.00 $26,885.29
0010 CEMENTITIOUS STABILIZED SUBGRADE 307(E) 4240 SY 7,467.000 7,467.000   7,467.000 $2.00 $0.00 $14,934.00
0011 TRAFFIC BOUND SURFACE COURSE TYPE E 402(E) 0225 TON 500.000 500.000   0.000 $26.00 $0.00 $0.00
0012 SUPERPAVE, TYPE S3(PG 70-28 OK) 411(B) 5940 TON 910.000 910.000   842.560 $75.68 $0.00 $63,764.94
0013 SUPERPAVE, TYPE S3(PG 64-22 OK) 411(B) 5945 TON 5,312.000 5,312.000   4,360.710 $68.59 $0.00 $299,101.10
0014 SUPERPAVE, TYPE S4(PG 70-28 OK) 411(C) 5955 TON 580.000 580.000   627.050 $86.50 $0.00 $54,239.83
0015 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 953.000 953.000   927.000 $85.62 $0.00 $79,369.74
0016 CLASS C CONCRETE 509(D) 0325 CY 25.000 25.000   0.000 $250.00 $0.00 $0.00
0017 24" R.C.PIPE CLASS III 613(A) 0492 LF 116.000 116.000   116.000 $92.00 $0.00 $10,672.00
0018 TYPE B6 SLOPED CONCRETE END SECTION 613(N) 7521 EA 2.000 2.000 2.000 2.000 $1,500.00 $3,000.00 $3,000.00
0019 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $1,000.00 $0.00 $1,000.00
0020 REMOVAL OF FENCE 619(B) 4725 LF 5,996.000 5,996.000   3,933.000 $0.50 $0.00 $1,966.50
0021 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 4,867.000 4,867.000   4,622.220 $5.00 $0.00 $23,111.10
0022 REMOVAL OF GUARDRAIL 619(B) 4780 LF 300.000 300.000   1,052.000 $1.00 $0.00 $1,052.00
0023 FENCE-STYLE SWF (5 BARBED WIRE) 624(C) 4459 LF 2,550.000 2,550.000   4,218.000 $3.48 $0.00 $14,678.64
8001 18" CORR. GALV. STEEL PIPE 613(B) 0689 LF 0.000 80.000 0.000 80.000 $35.35 $0.00 $2,828.00
8002 INLET (SMD-TYPE 2) 611(G) 6002 EA 0.000 1.000   0.000 $1,450.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY    $35,067.38 $771,505.52
Fed/State Project Number:    BRFY-105B(169) Project:    25822(04) Category:    0200/BRIDGE 'A'
0024 UNCLASSIFIED EXCAVATION 202(A) 1301 CY 1,456.000 1,456.000   1,456.000 $3.00 $0.00 $4,368.00
0025 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 1306 CY 278.000 278.000   278.000 $6.00 $0.00 $1,668.00
0026 CLASS AA CONCRETE 509(A) 1326 CY 759.000 759.000   759.000 $355.00 $0.00 $269,445.00
0027 REINFORCING STEEL 511(A) 1332 LB 107,621.000 107,621.000   107,621.000 $0.75 $0.00 $80,715.75
0028 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $2,000.00 $0.00 $2,000.00
Subtotals For Category     0200/BRIDGE 'A'    $0.00 $358,196.75
Fed/State Project Number:    BRFY-105B(169) Project:    25822(04) Category:    0300/TRAFFIC
0029 (PL)REMOVE & RESET EXISTING SIGNS 805(D) 8756 EA 3.000 3.000   0.000 $150.00 $0.00 $0.00
0030 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 6,400.000 6,400.000   6,053.000 $0.85 $0.00 $5,145.05
0031 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 857(A) 8839 LF 3,200.000 3,200.000   9,623.000 $0.30 $0.00 $2,886.90
0032 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) 857(C) 8851 LF 1,600.000 1,600.000   0.000 $0.65 $0.00 $0.00
0033 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 857(E) 8887 EA 1,600.000 1,600.000   0.000 $0.40 $0.00 $0.00
0034 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 857(F) 8006 LF 3,200.000 3,200.000   845.000 $0.06 $0.00 $50.70
0035 SAND FILLED IMPACT ATTENUATION MODULE 870(A) 8485 SD 1,800.000 1,800.000   476.000 $0.70 $0.00 $333.20
0036 DELIVER PORTABLE LONGITUDINAL BARRIER 877(B) 8484 LF 1,800.000 1,800.000   1,020.000 $14.75 $0.00 $15,045.00
0037 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 2,660.000 2,660.000   2,722.000 $0.02 $0.00 $54.44
0038 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 1,080.000 1,080.000   1,956.000 $0.75 $0.00 $1,467.00
0039 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 720.000 720.000   3,775.000 $2.75 $0.00 $10,381.25
0040 CONSTRUCTION BARRICADES(TYPE III) 880(C) 8842 SD 240.000 240.000   596.000 $2.75 $0.00 $1,639.00
0041 WING BARRICADES 880(C) 8848 SD 840.000 840.000   1,080.000 $0.02 $0.00 $21.60
0042 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 1,320.000 1,320.000   2,651.000 $0.45 $0.00 $1,192.95
0043 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 2,520.000 2,520.000   4,050.000 $0.45 $0.00 $1,822.50
0044 DRUMS 880(F) 8878 SD 2,520.000 2,520.000   9,014.000 $0.55 $0.00 $4,957.70
Subtotals For Category     0300/TRAFFIC    $0.00 $44,997.29
Fed/State Project Number:    BRFY-105B(169) Project:    25822(04) Category:    0600/STAKING
0045 CONSTRUCTION STAKING LEVEL II 642(B) 0096 LSUM 1.000 1.000   1.000 $5,700.00 $0.00 $5,700.00
Subtotals For Category     0600/STAKING    $0.00 $5,700.00
Fed/State Project Number:    BRFY-105B(169) Project:    25822(04) Category:    0640/CONSTRUCTION
0046 SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.100 $1,000.00 $0.00 $100.00
0047 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $45,000.00 $0.00 $45,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $45,100.00
Subtotals For Project BRFY-105B(169) /25822(04) $35,067.38 $1,225,499.56