Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    03/02/2012
Contract ID: 110325   Estimate Number: 0003     Contract No: 710332
Residency: PURCELL (03200)   Estimate Type: Progressive     Account No: 400350

Project Number(s): STP-114B(276)AG
Primary Job Piece No: 27785(04)
Contract Description: PEDESTRIAN IMPROVEMENT CITY STREET (12TH STREET): FROM SANTA FE AVE, EXTEND EAST TO JANEWAY AVE IN THE CITY OF MOORE. PROJECT LENGTH = 0.52 MILES
Primary County: CLEVELAND              
Name of Road: CITY STREET (12TH ST              
Prime Contractor: RUDY CONSTRUCTION CO.              
    3101 NE 63RD STREET              
    OKLAHOMA CITY , OK   73121              
Surety Company: TRAVELERS INDEMNITY COMPANY              

Date Let: 08/18/2011 NTP Effective Date: 12/05/2011 Pay Period: 02/01/2012  TO  02/29/2012
Date Awarded: 09/12/2011 Date Work Began: 12/05/2011 Original Contract Time: 60
Date Contract Executed: 09/26/2011 Date Time Stopped: Current Time Charged: 87.00
Date NTP Issued: 09/29/2011 Completion Date: Current Time Allowed: 60.00
General Liability Expires: 08/01/2012 Workman's Comp Expires: 08/01/2012 Percent Time Used: 145.00 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $158,341.50 Total to Date Prev to Date This Estimate
Bid Amount: $158,341.50 Participating: $166,149.20 $154,534.86 $11,614.34
Percent Complete: 100 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $0.00 Total Earnings: $166,149.20 $154,534.86 $11,614.34
Unearned Balance: $0.00 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $166,149.20 $154,534.86 $11,614.34
Other Adjustments: $5,692.30 $0.00 $5,692.30
Liq Dam/Disincentive: $-13,500.00 $0.00 $-13,500.00
TOTAL: $158,341.50 $154,534.86 $3,806.64

Estimate Adjustment Detail

Contract ID: 110325   Estimate Number: 0003     Primary JP: 27785(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0003 -27.0 $500.00 $-13,500.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
LD Adjustment (Prog. Est. Only) 0003 $13,500.00
Withhold to Funds Avail(Prog. Est. Only) 0003 $-7,807.70
Subtotals For Contract Adjustments $5,692.30


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 110325   Estimate Number: 0003     Primary JP: 27785(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-114B(276)AG Project:    27785(04) Category:    0100/ROADWAY
0001 SELECTIVE CLEARING 201 0181 LSUM 1.000 1.000   1.000 $4,000.00 $0.00 $4,000.00
0002 TEMPORARY SILT FENCE 221(C) 2801 LF 2,800.000 2,800.000   0.000 $1.50 $0.00 $0.00
0003 (PL)TEMPORARY INLET SEDIMENT FILTER 221(H) 0450 EA 2.000 2.000   0.000 $75.00 $0.00 $0.00
0004 SOLID SLAB SODDING 230(A) 2806 SY 1,571.000 1,571.000 2,792.860 2,792.860 $2.50 $6,982.15 $6,982.15
0005 TRAFFIC BOUND SURFACE COURSE TYPE A 402(A) 0217 TON 41.000 41.000   0.000 $27.00 $0.00 $0.00
0006 2'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1525 LF 156.000 156.000 0.000 264.100 $20.00 $0.00 $5,282.00
0007 4" CONCRETE SIDEWALK 610(A) 0602 SY 1,642.000 1,642.000 14.440 1,707.990 $40.00 $577.60 $68,319.60
0008 6" CONCRETE DRIVEWAY 610(B) 0604 SY 625.000 625.000 5.350 779.200 $60.00 $321.00 $46,752.00
0009 TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 269.000 269.000   200.000 $40.00 $0.00 $8,000.00
0010 VALVE BOXES ADJUST TO GRADE 612(E) 0647 EA 8.000 8.000 1.000 7.000 $150.00 $150.00 $1,050.00
0011 METER BOXES ADJUST TO GRADE 612(F) 0648 EA 2.000 2.000   2.000 $150.00 $0.00 $300.00
0012 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 316.000 316.000   264.000 $7.00 $0.00 $1,848.00
0013 REMOVAL OF CONCRETE DRIVEWAY 619(B) 4766 SY 627.000 627.000 5.350 797.330 $7.00 $37.45 $5,581.31
0014 REMOVAL OF SIDEWALK 619(B) 4792 SY 233.000 233.000   284.000 $7.00 $0.00 $1,988.00
0015 SAWING PAVEMENT 619(C) 0924 LF 855.000 855.000 765.380 765.380 $3.00 $2,296.14 $2,296.14
Subtotals For Category     0100/ROADWAY    $10,364.34 $152,399.20
Fed/State Project Number:    STP-114B(276)AG Project:    27785(04) Category:    0300/TRAFFIC
0016 (PL)REMOVE & RESET GROUND MOUNTED SIGN 805(D) 8760 EA 3.000 3.000   0.000 $200.00 $0.00 $0.00
0017 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 1.000 $5,000.00 $1,250.00 $5,000.00
Subtotals For Category     0300/TRAFFIC    $1,250.00 $5,000.00
Fed/State Project Number:    STP-114B(276)AG Project:    27785(04) Category:    0600/STAKING
0018 CONSTRUCTION STAKING LEVEL II 642(B) 0096 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
Subtotals For Category     0600/STAKING    $0.00 $5,000.00
Fed/State Project Number:    STP-114B(276)AG Project:    27785(04) Category:    0640/CONSTRUCTION
0019 MOBILIZATION 641 1552 LSUM 1.000 1.000   0.750 $5,000.00 $0.00 $3,750.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $3,750.00
Subtotals For Project STP-114B(276)AG /27785(04) $11,614.34 $166,149.20