Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    10/24/2013
Contract ID: 110213   Estimate Number: 0006     Contract No: 611171
Residency: DUNCAN (07100)   Estimate Type: Progressive     Account No: 400700

Project Number(s): NHY-021N(053)3P, NHY-011N(091)3P
Primary Job Piece No: 28155(04)
Contract Description: RESURFACE (ASPHALT) SH-7: FROM THE COMANCHE COUNTY LINE, EXTEND EAST. US-81: FROM THE SH-7W JUNCTION, EXTEND NORTH. PROJECT LENGTH = 6.9 MILES.
Primary County: STEPHENS              
Name of Road: SH-7 / US-81              
Prime Contractor: T & G CONSTRUCTION, INC.              
    800 S. E. 1ST STREET              
    LAWTON , OK   73501              
Surety Company: WESTFIELD INSURANCE COMPANY              

Date Let: 02/17/2011 NTP Effective Date: 07/05/2011 Pay Period: 11/01/2011  TO  10/15/2013
Date Awarded: 03/07/2011 Date Work Began: 06/20/2011 Original Contract Time: 75
Date Contract Executed: 03/22/2011 Date Time Stopped: 11/07/2011 Current Time Charged: 67.00
Date NTP Issued: 03/31/2011 Completion Date: 11/07/2011 Current Time Allowed: 75.00
General Liability Expires: 10/01/2014 Workman's Comp Expires: 10/01/2014 Percent Time Used: 89.33 %
Specification Year: 2009     Date Approved:

Current Contract Amount: $3,460,151.44 Total to Date Prev to Date This Estimate
Bid Amount: $3,199,135.24 Participating: $3,390,920.57 $3,133,562.37 $257,358.20
Percent Complete: 98.27 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $59,883.73 Total Earnings: $3,390,920.57 $3,133,562.37 $257,358.20
Unearned Balance: $-201,132.47 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $3,390,920.57 $3,133,562.37 $257,358.20
Other Adjustments: $9,347.14 $193,908.17 $-184,561.03
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $3,400,267.71 $3,327,470.54 $72,797.17

Estimate Adjustment Detail

Contract ID: 110213   Estimate Number: 0006     Primary JP: 28155(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Additional Funding Approved 10/03/2011 0.0 $261,016.20


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Withhold to Funds Avail(Prog. Est. Only) 0004 $-95,296.39
Withhold to Funds Avail(Prog. Est. Only) 0005 $95,296.39
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
28155(04) 0005 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0001 10,522.57 $5.00 $52,680.19
28155(04) 0005 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0002 10,897.46 $5.00 $54,557.04
28155(04) 0005 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0003 46.62 $5.00 $233.40
28155(04) 0005 SUPERPAVE, TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0004 0.00 $0.00 $-3,636.08
28155(04) 0005 SUPERPAVE, TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $-107,470.63
28155(04) 0005 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0006 -1.08 $3.80 $-4.11
28155(04) 0006 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0001 3,191.32 $5.00 $15,977.02
28155(04) 0006 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0003 3,524.58 $5.00 $17,645.46
28155(04) 0006 SUPERPAVE, TYPE S4(PG 64-22 OK) * HMA Deduction as per Sec. 411 0004 0.00 $0.00 $-873.05
28155(04) 0006 SUPERPAVE, TYPE S4(PG 64-22 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $-33,622.48
28155(04) 0006 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0006 -0.08 $3.80 $-0.31
28156(04) 0020 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0002 162.46 $4.38 $711.67
28156(04) 0020 SUPERPAVE, TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0003 22.95 $4.38 $100.54
28156(04) 0020 SUPERPAVE, TYPE S3(PG 70-28 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $-812.21
28156(04) 0021 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0003 6,897.59 $5.00 $34,532.10
28156(04) 0021 SUPERPAVE, TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0004 0.00 $0.00 $-676.48
28156(04) 0021 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0004 4,972.11 $5.00 $24,892.37
28156(04) 0021 SUPERPAVE, TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0006 1.10 $3.80 $4.19
28156(04) 0021 SUPERPAVE, TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $-59,424.47
28156(04) 0022 SUPERPAVE, TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0003 3,349.51 $5.00 $16,768.99
28156(04) 0022 SUPERPAVE, TYPE S4(PG 64-22 OK) * HMA Deduction as per Sec. 411 0004 0.00 $0.00 $-19,005.00
28156(04) 0022 SUPERPAVE, TYPE S4(PG 64-22 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $16,768.99
Subtotals For Line Item Adjustments $9,347.14
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 110213   Estimate Number: 0006     Primary JP: 28155(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    NHY-021N(053)3P Project:    28155(04) Category:    0100/ROADWAY - NHY-021N(053)3P
0001 TEMPORARY SILT FENCE 221(C) 2801 LF 1,600.000 1,600.000   0.000 $2.20 $0.00 $0.00
0002 TEMPORARY SILT DIKE 221(F) 0100 LF 160.000 160.000   0.000 $7.00 $0.00 $0.00
0003 FABRIC REINFORCEMENT 409(A) 4242 SY 137,984.000 137,984.000   138,992.000 $0.65 $0.00 $90,344.80
0004 BITUMINOUS BINDER 409(B) 4268 GAL 34,496.000 34,496.000 273.300 18,288.900 $2.75 $751.58 $50,294.49
0005 SUPERPAVE, TYPE S4(PG 70-28 OK) 411(C) 5955 TON 21,466.000 21,466.000 -1.080 21,465.570 $60.40 $-65.23 $1,296,520.43
0006 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 6,710.000 6,710.000 -0.080 6,715.820 $54.55 $-4.36 $366,347.99
0007 COLD MILLING PAVEMENT 412 5267 SY 146,432.000 146,432.000   151,110.220 $1.00 $0.00 $151,110.22
0008 RUMBLE STRIP-METHOD HMA-CON 413(A) 4861 LF 101,376.000 101,376.000   93,398.000 $0.15 $0.00 $14,009.70
0009 MAILBOX INSTALLATION-SINGLE 629(A) 4958 EA 7.000 7.000   6.000 $65.00 $0.00 $390.00
0010 MAILBOX 629(C) 4960 EA 7.000 7.000   6.000 $25.00 $0.00 $150.00
0011 REMOVAL OF MAILBOX INSTALLATION 629(D) 4961 EA 7.000 7.000   6.000 $10.00 $0.00 $60.00
0012 TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) 855(A) 8840 LF 114,894.000 114,894.000   122,135.000 $0.36 $0.00 $43,968.60
0013 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 38.000 38.000   38.000 $75.00 $0.00 $2,850.00
0014 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $4,000.00 $0.00 $4,000.00
8000 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000 1.000 1.000 $141,093.11 $141,093.11 $141,093.11
8020 PAVEMENT/BRIDGE SMOOTHNESS ADJUSTMENT 430 5010 LSUM 0.000 1.000 1.000 1.000 $29,392.56 $29,392.56 $29,392.56
Subtotals For Category     0100/ROADWAY - NHY-021N(053)3P    $171,167.66 $2,190,531.90
Subtotals For Project NHY-021N(053)3P /28155(04) $171,167.66 $2,190,531.90


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    NHY-011N(091)3P Project:    28156(04) Category:    0100/ROADWAY - NHY-011N(091)3P
0015 EARTHWORK 202(H) 0185 LSUM 1.000 1.000   1.000 $30,000.00 $0.00 $30,000.00
0016 TEMPORARY SILT FENCE 221(C) 2801 LF 800.000 800.000   0.000 $2.20 $0.00 $0.00
0017 TEMPORARY SILT DIKE 221(F) 0100 LF 160.000 160.000   0.000 $7.00 $0.00 $0.00
0018 FABRIC REINFORCEMENT 409(A) 4242 SY 60,368.000 60,368.000 0.000 58,838.670 $1.00 $0.00 $58,838.67
0019 BITUMINOUS BINDER 409(B) 4268 GAL 15,092.000 15,092.000 -1,603.000 6,365.700 $2.75 $-4,408.25 $17,505.68
0020 SUPERPAVE, TYPE S3(PG 70-28 OK) 411(B) 5940 TON 1,120.000 1,120.000 0.000 185.410 $63.70 $0.00 $11,810.62
0021 SUPERPAVE, TYPE S4(PG 70-28 OK) 411(C) 5955 TON 10,910.000 10,910.000 1.100 11,870.800 $62.05 $68.26 $736,583.15
0022 SUPERPAVE, TYPE S4(PG 64-22 OK) 411(C) 5960 TON 3,355.000 3,355.000 0.000 3,349.510 $59.20 $0.00 $198,290.99
0023 COLD MILLING PAVEMENT 412 5267 SY 3,800.000 3,800.000   4,338.010 $3.00 $0.00 $13,014.03
0024 MAILBOX INSTALLATION-SINGLE 629(A) 4958 EA 16.000 16.000   6.000 $65.00 $0.00 $390.00
0025 MAILBOX INSTALLATION-MULTIPLE 629(B) 4959 EA 2.000 2.000   0.000 $95.00 $0.00 $0.00
0026 MAILBOX 629(C) 4960 EA 20.000 20.000   6.000 $25.00 $0.00 $150.00
0027 REMOVAL OF MAILBOX INSTALLATION 629(D) 4961 EA 20.000 20.000   6.000 $5.00 $0.00 $30.00
0028 REMOVE AND RESET MAILBOX 629(E) 5048 EA 6.000 6.000   6.000 $100.00 $0.00 $600.00
0029 TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) 855(A) 8840 LF 50,270.000 50,270.000   53,050.000 $0.40 $0.00 $21,220.00
0030 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 36.000 36.000   39.000 $75.00 $0.00 $2,925.00
0031 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $18,500.00 $0.00 $18,500.00
8010 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000 1.000 1.000 $77,005.67 $77,005.67 $77,005.67
8030 PAVEMENT/BRIDGE SMOOTHNESS ADJUSTMENT 430 5010 LSUM 0.000 1.000 1.000 1.000 $13,524.86 $13,524.86 $13,524.86
Subtotals For Category     0100/ROADWAY - NHY-011N(091)3P    $86,190.54 $1,200,388.67
Subtotals For Project NHY-011N(091)3P /28156(04) $86,190.54 $1,200,388.67