STOCKPILE PAYMENT HISTORY |
Project |
Line Nbr |
Stockpile Description |
Adjustment Type |
Estimate Nbr |
Adjusted Amount |
26604(04) |
0016 |
15 oz separator fabric |
Stockpiled Material Adjustment |
0032 |
$-4,717.35 |
26604(04) |
0016 |
15 oz separator fabric |
Stockpiled Material Initial Payment |
0004 |
$29,147.67 |
26604(04) |
0016 |
15 oz separator fabric |
Stockpiled Material Adjustment |
0031 |
$-24,430.33 |
26604(04) |
0017 |
6 oz separator fabric |
Stockpiled Material Adjustment |
0013 |
$-2,897.84 |
26604(04) |
0017 |
6 oz separator fabric |
Stockpiled Material Adjustment |
0030 |
$-3,228.14 |
26604(04) |
0017 |
6 oz separator fabric |
Stockpiled Material Initial Payment |
0004 |
$17,189.09 |
26604(04) |
0017 |
6 oz separator fabric |
Stockpiled Material Adjustment |
0010 |
$-5,396.39 |
26604(04) |
0017 |
6 oz separator fabric |
Stockpiled Material Adjustment |
0031 |
$-1,426.37 |
26604(04) |
0017 |
6 oz separator fabric |
Stockpiled Material Adjustment |
0032 |
$-4,240.35 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Initial Payment |
0020 |
$29,459.75 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Initial Payment |
0003 |
$1,363.08 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Adjustment |
0028 |
$-343.32 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Closure |
0031 |
$-240,826.71 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Closure |
0031 |
$-21,035.85 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Closure |
0031 |
$-52,326.60 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Closure |
0031 |
$-17,892.67 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Closure |
0031 |
$-29,459.75 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Closure |
0031 |
$-790.88 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Initial Payment |
0030 |
$240,826.71 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Adjustment |
0030 |
$-57.22 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Adjustment |
0029 |
$-57.22 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Initial Payment |
0027 |
$21,035.85 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Adjustment |
0027 |
$-57.22 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Adjustment |
0026 |
$-57.22 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Initial Payment |
0022 |
$52,326.60 |
26604(04) |
0033 |
6"Drain |
Stockpiled Material Initial Payment |
0021 |
$17,892.67 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Closure |
0031 |
$-535.63 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Initial Payment |
0020 |
$161,662.53 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Adjustment |
0030 |
$-37.78 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Initial Payment |
0030 |
$22,124.99 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Closure |
0031 |
$-161,662.53 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Closure |
0031 |
$-80,557.20 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Initial Payment |
0021 |
$80,557.20 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Closure |
0031 |
$-32,930.21 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Adjustment |
0022 |
$-229.51 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Initial Payment |
0022 |
$32,930.21 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Initial Payment |
0003 |
$1,820.16 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Adjustment |
0019 |
$-246.92 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Adjustment |
0026 |
$-223.24 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Closure |
0031 |
$-22,124.99 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Adjustment |
0025 |
$-517.53 |
26604(04) |
0035 |
6"Pipe |
Stockpiled Material Adjustment |
0023 |
$-29.55 |
26604(04) |
0052 |
6"pipe |
Stockpiled Material Closure |
0031 |
$-2,463.17 |
26604(04) |
0052 |
6"pipe |
Stockpiled Material Adjustment |
0013 |
$-380.22 |
26604(04) |
0052 |
6"pipe |
Stockpiled Material Initial Payment |
0003 |
$3,640.47 |
26604(04) |
0052 |
6"pipe |
Stockpiled Material Adjustment |
0030 |
$-797.08 |
26604(04) |
0053 |
6"pipe |
Stockpiled Material Closure |
0031 |
$-142.70 |
26604(04) |
0053 |
6"pipe |
Stockpiled Material Initial Payment |
0003 |
$142.70 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0022 |
$-92.31 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0017 |
$-47.26 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0016 |
$-196.23 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0015 |
$-256.74 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0014 |
$-39.47 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Initial Payment |
0007 |
$39,826.59 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Initial Payment |
0003 |
$2,479.16 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0025 |
$-11.10 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0025 |
$-470.66 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0024 |
$-461.73 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0021 |
$-95.71 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0020 |
$-50.34 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0019 |
$-388.97 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0018 |
$-379.70 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Closure |
0031 |
$-35,959.20 |
26604(04) |
0121 |
21"24"27"CMPx4'long(10"pile encasement) |
Stockpiled Material Adjustment |
0029 |
$-3,856.29 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-197,110.83 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-295,664.36 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-39,422.17 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0028 |
$-94,772.59 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0006 |
$197,110.83 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0029 |
$-37,626.13 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0007 |
$246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0009 |
$246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0030 |
$-13,082.88 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0010 |
$246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0017 |
$39,422.17 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0022 |
$-10,530.29 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0023 |
$-61,691.76 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0010 |
$147,833.12 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0030 |
$-41,807.99 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-147,833.12 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0025 |
$-10,530.29 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Adjustment |
0026 |
$-61,691.76 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0016 |
$295,664.36 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-194,726.94 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0004 |
$289,925.68 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0005 |
$236,534.93 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Initial Payment |
0005 |
$246,388.54 |
26604(04) |
0123 |
Prestressed PC Beams type III |
Stockpiled Material Closure |
0031 |
$-246,388.54 |
26604(04) |
0126 |
Sealed Exp Joint |
Stockpiled Material Initial Payment |
0016 |
$59,711.48 |
26604(04) |
0126 |
Sealed Exp Joint |
Stockpiled Material Closure |
0031 |
$-35,150.81 |
26604(04) |
0126 |
Sealed Exp Joint |
Stockpiled Material Adjustment |
0027 |
$-11,174.69 |
26604(04) |
0126 |
Sealed Exp Joint |
Stockpiled Material Adjustment |
0029 |
$-7,609.43 |
26604(04) |
0126 |
Sealed Exp Joint |
Stockpiled Material Adjustment |
0030 |
$-5,776.55 |
26604(04) |
0127 |
F- shaped parapet reinforcing steel |
Stockpiled Material Initial Payment |
0027 |
$11,055.78 |
26604(04) |
0127 |
F- shaped parapet reinforcing steel |
Stockpiled Material Closure |
0031 |
$-11,055.78 |
26604(04) |
0127 |
F- shaped parapet reinforcing steel |
Stockpiled Material Initial Payment |
0028 |
$23,087.22 |
26604(04) |
0127 |
F- shaped parapet reinforcing steel |
Stockpiled Material Closure |
0031 |
$-23,087.22 |
26604(04) |
0128 |
Handrails and anchors |
Stockpiled Material Adjustment |
0033 |
$-20,321.16 |
26604(04) |
0128 |
Handrails and anchors |
Stockpiled Material Initial Payment |
0014 |
$30,296.05 |
26604(04) |
0128 |
Handrails and anchors |
Stockpiled Material Adjustment |
0033 |
$-10,150.19 |
26604(04) |
0128 |
Handrails and anchors |
Stockpiled Material Initial Payment |
0009 |
$43,373.20 |
26604(04) |
0128 |
Handrails and anchors |
Stockpiled Material Initial Payment |
0011 |
$48,004.65 |
26604(04) |
0128 |
Handrails and anchors |
Stockpiled Material Adjustment |
0031 |
$-23,052.04 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0028 |
$-191,689.11 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0017 |
$-105,079.35 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0030 |
$-273,057.61 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-106,753.40 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-777,426.67 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-282,741.38 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-14,520.00 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-1,479,312.75 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-188,494.25 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-201,844.59 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-401,829.12 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-201,844.59 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-100,922.29 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Closure |
0031 |
$-408,333.77 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0018 |
$-53,166.92 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0022 |
$-23,468.36 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0023 |
$-172,204.58 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0024 |
$-270,005.27 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0025 |
$-108,368.72 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0026 |
$-186,392.93 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0026 |
$408,333.77 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0027 |
$-41,805.33 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0004 |
$2,203,269.42 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0008 |
$777,426.67 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0008 |
$282,741.38 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0008 |
$14,520.00 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0008 |
$1,479,312.75 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0009 |
$188,494.25 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0011 |
$201,844.59 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0011 |
$401,829.12 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0013 |
$201,844.59 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Initial Payment |
0014 |
$100,922.29 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0015 |
$-144,212.21 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0016 |
$-150,673.00 |
26604(04) |
0130 |
Structural steel - raw material |
Stockpiled Material Adjustment |
0029 |
$-376,392.63 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-18,621.09 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-38,958.42 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-41,736.93 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-21,831.62 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-93,051.00 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0028 |
$-33,744.21 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0029 |
$-2,505.78 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0029 |
$-15,070.24 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0030 |
$-6,075.79 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-13,527.72 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-132,222.10 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-237,718.07 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0031 |
$-32,830.19 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0017 |
$93,051.00 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0019 |
$-3,916.74 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0020 |
$-6,628.33 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0021 |
$-16,872.11 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0022 |
$-1,807.73 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0023 |
$-28,923.61 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0026 |
$-4,218.03 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0027 |
$-5,423.18 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0004 |
$20,126.35 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0005 |
$113,017.50 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0008 |
$34,673.75 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0008 |
$132,222.10 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0011 |
$237,718.07 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0012 |
$32,830.19 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0013 |
$18,621.09 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0014 |
$38,958.42 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0015 |
$-20,126.35 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0015 |
$-1,749.27 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0015 |
$41,736.93 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0015 |
$21,831.62 |
26604(04) |
0131 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0017 |
$-7,230.90 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0028 |
$-10,821.36 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0015 |
$8,347.39 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0029 |
$-16,455.49 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-152,705.21 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-92,463.34 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-282,613.37 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-247,755.29 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-70,993.16 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-17,336.88 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-73,632.17 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-32,747.44 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-8,347.39 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Closure |
0030 |
$-81,966.25 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0017 |
$-732.83 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0017 |
$81,966.25 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0019 |
$-2,290.11 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0020 |
$-1,007.65 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0021 |
$-3,022.94 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0022 |
$-1,786.28 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0023 |
$-4,946.63 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0024 |
$-183.21 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0027 |
$-320.61 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0004 |
$26,761.90 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0005 |
$169,402.50 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0008 |
$92,463.34 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0008 |
$282,613.37 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0011 |
$247,755.29 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0012 |
$70,993.16 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0013 |
$17,336.88 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0014 |
$73,632.17 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0015 |
$-1,648.88 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0015 |
$32,747.44 |
26604(04) |
0132 |
Anchor bolts, nuts, and washers |
Stockpiled Material Adjustment |
0028 |
$-241.80 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Closure |
0031 |
$-183,966.99 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Closure |
0031 |
$-80,826.96 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Closure |
0031 |
$-107,769.29 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Closure |
0031 |
$-21,774.46 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Adjustment |
0028 |
$-22,186.75 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Initial Payment |
0012 |
$231,124.69 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Adjustment |
0030 |
$-6,509.00 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Initial Payment |
0018 |
$80,826.96 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Initial Payment |
0022 |
$107,769.29 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Initial Payment |
0026 |
$21,774.46 |
26604(04) |
0134 |
Deck Pans |
Stockpiled Material Adjustment |
0029 |
$-18,461.95 |
26604(04) |
0135 |
|
Stockpiled Material Closure |
0031 |
$-10,256.71 |
26604(04) |
0135 |
|
Stockpiled Material Initial Payment |
0027 |
$6,503.21 |
26604(04) |
0135 |
|
Stockpiled Material Closure |
0031 |
$-649.98 |
26604(04) |
0135 |
|
Stockpiled Material Closure |
0031 |
$-6,503.21 |
26604(04) |
0135 |
|
Stockpiled Material Closure |
0031 |
$-10,863.65 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0028 |
$-1,041.99 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0029 |
$-331.00 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0030 |
$-71.40 |
26604(04) |
0135 |
|
Stockpiled Material Initial Payment |
0030 |
$10,863.65 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0020 |
$-2,408.82 |
26604(04) |
0135 |
|
Stockpiled Material Initial Payment |
0020 |
$26,906.15 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0021 |
$-3,243.57 |
26604(04) |
0135 |
|
Stockpiled Material Initial Payment |
0021 |
$1,299.96 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0022 |
$-1,994.70 |
26604(04) |
0135 |
|
Stockpiled Material Initial Payment |
0022 |
$649.98 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0023 |
$-1,736.20 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0024 |
$-1,349.66 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0025 |
$-1,939.36 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0026 |
$-1,620.49 |
26604(04) |
0135 |
|
Stockpiled Material Adjustment |
0027 |
$-912.25 |
26604(04) |
0135 |
|
Stockpiled Material Closure |
0031 |
$-1,299.96 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Closure |
0031 |
$-15,458.06 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0016 |
$-1,023.12 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0017 |
$-255.82 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0018 |
$-2,999.37 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0019 |
$-255.66 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0020 |
$-255.82 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0022 |
$-1,834.42 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0023 |
$-1,928.25 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0024 |
$-1,745.76 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0025 |
$-4,573.30 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0026 |
$-247.62 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0026 |
$-1,196.02 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Initial Payment |
0005 |
$16,654.08 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Initial Payment |
0013 |
$16,654.08 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0014 |
$-255.82 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Adjustment |
0015 |
$-1,279.11 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Initial Payment |
0015 |
$19,917.71 |
26604(04) |
0137 |
Bridge A Crashwall |
Stockpiled Material Closure |
0031 |
$-19,917.71 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0005 |
$12,486.42 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0005 |
$10,326.90 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0007 |
$76,288.85 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0007 |
$5,969.71 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0007 |
$40,218.76 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0007 |
$77,522.45 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0008 |
$71,211.44 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0008 |
$27,134.62 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0010 |
$-52.34 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0010 |
$66,302.12 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0010 |
$38,460.95 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0010 |
$97,602.48 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0011 |
$-341.10 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0011 |
$28,691.41 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0012 |
$-356.44 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0012 |
$27,708.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0012 |
$1,356.23 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0012 |
$19,423.61 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0013 |
$-211.87 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0013 |
$40,793.96 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0013 |
$38,978.07 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0014 |
$-167.42 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0014 |
$23,385.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0014 |
$27,708.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0014 |
$26,356.67 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0014 |
$12,851.23 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0014 |
$27,708.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0014 |
$30,706.41 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0015 |
$-396.29 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0015 |
$60,661.31 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0015 |
$11,863.63 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0015 |
$31,280.99 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0016 |
$-386.78 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0016 |
$39,558.33 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0016 |
$55,417.86 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0016 |
$60,567.44 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0016 |
$144,013.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0017 |
$-375.07 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0018 |
$-499.60 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0019 |
$-333.19 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0020 |
$-479.18 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0021 |
$-614.05 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0022 |
$-431.84 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0023 |
$-315.24 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0024 |
$-248.36 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0025 |
$-330.63 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0026 |
$-377.57 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0027 |
$-414.49 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Initial Payment |
0027 |
$38,835.85 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0028 |
$-935.66 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0029 |
$-293.10 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Adjustment |
0030 |
$-571.27 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-4,354.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-10,326.90 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-76,288.85 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-5,969.71 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-40,218.76 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-77,522.45 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-71,211.44 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-27,134.62 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-66,302.12 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-38,460.95 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-97,602.48 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-28,691.41 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-27,708.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-1,356.23 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-19,423.61 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-40,793.96 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-38,978.07 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-23,385.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-27,708.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-26,356.67 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-12,851.23 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-27,708.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-30,706.41 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-60,661.31 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-11,863.63 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-31,280.99 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-39,558.33 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-55,417.86 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-60,567.44 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-144,013.93 |
26604(04) |
0138 |
Bridge A - Substructure |
Stockpiled Material Closure |
0031 |
$-38,835.85 |
26604(04) |
0141 |
Piles, 10X42 |
Stockpiled Material Initial Payment |
0003 |
$4,850.00 |
26604(04) |
0141 |
Piles, 10X42 |
Stockpiled Material Adjustment |
0012 |
$-4,850.00 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Closure |
0014 |
$-20,810.40 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Closure |
0014 |
$-52,121.69 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Adjustment |
0012 |
$-32,719.80 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Adjustment |
0012 |
$-10,607.61 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Initial Payment |
0004 |
$20,810.40 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Initial Payment |
0004 |
$62,729.30 |
26604(04) |
0142 |
Piles,12X53 |
Stockpiled Material Initial Payment |
0003 |
$32,719.80 |
26604(04) |
0143 |
piles, 14X89 |
Stockpiled Material Adjustment |
0012 |
$-20,311.90 |
26604(04) |
0143 |
piles, 14X89 |
Stockpiled Material Initial Payment |
0003 |
$20,311.90 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Adjustment |
0029 |
$-972.22 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Adjustment |
0023 |
$-941.48 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Adjustment |
0029 |
$-628.49 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Closure |
0031 |
$-522.01 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Initial Payment |
0014 |
$1,150.50 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Adjustment |
0028 |
$-1,624.81 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Adjustment |
0021 |
$-971.85 |
26604(04) |
0148 |
16GaugeCSP18"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$4,510.08 |
26604(04) |
0149 |
16GaugeCSP36"DrillShaft |
Stockpiled Material Adjustment |
0028 |
$-3,293.34 |
26604(04) |
0149 |
16GaugeCSP36"DrillShaft |
Stockpiled Material Adjustment |
0023 |
$-1,515.98 |
26604(04) |
0149 |
16GaugeCSP36"DrillShaft |
Stockpiled Material Adjustment |
0029 |
$-2,765.31 |
26604(04) |
0149 |
16GaugeCSP36"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$7,574.60 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Adjustment |
0027 |
$-2,146.01 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Adjustment |
0027 |
$-942.74 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Initial Payment |
0003 |
$2,785.41 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Adjustment |
0025 |
$-359.33 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Initial Payment |
0014 |
$21,205.09 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Closure |
0031 |
$-14,401.75 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Closure |
0031 |
$-21,205.09 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Initial Payment |
0003 |
$16,547.76 |
26604(04) |
0150 |
Rebar 48" Drilled Shafts |
Stockpiled Material Adjustment |
0017 |
$-1,483.67 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0025 |
$-13,727.30 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0015 |
$-1,211.23 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0015 |
$-2,684.97 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0014 |
$-8,052.74 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0013 |
$-3,701.97 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0012 |
$-4,427.10 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0011 |
$-6,411.66 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0008 |
$-7,060.46 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0009 |
$-5,381.21 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0010 |
$-8,468.35 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Adjustment |
0007 |
$-1,793.74 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Initial Payment |
0005 |
$24,680.63 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Initial Payment |
0005 |
$5,847.19 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Initial Payment |
0003 |
$48,798.09 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Initial Payment |
0003 |
$82,771.73 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Initial Payment |
0003 |
$47,982.55 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Closure |
0031 |
$-67,833.20 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Closure |
0031 |
$-48,798.09 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Closure |
0031 |
$-5,847.19 |
26604(04) |
0151 |
EpoxyReb.Dril.Shafts 60" |
Stockpiled Material Closure |
0031 |
$-24,680.63 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Closure |
0031 |
$-10,522.19 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$10,522.19 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$21,796.13 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$11,582.73 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Closure |
0031 |
$-18,089.36 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Adjustment |
0012 |
$-11,582.73 |
26604(04) |
0152 |
EpoxReb 72"DrillShaft |
Stockpiled Material Adjustment |
0012 |
$-3,706.77 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0008 |
$-542.77 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0009 |
$-549.19 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0010 |
$-264.96 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0011 |
$-320.36 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-45,209.63 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-196,206.46 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-36,194.75 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-39,670.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-47,000.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-16,450.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-67,316.29 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Closure |
0031 |
$-468,966.19 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0012 |
$-313.73 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0013 |
$-508.31 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0014 |
$-345.25 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0015 |
$-479.21 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0016 |
$-69.05 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0018 |
$-24.36 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0019 |
$-38.85 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0019 |
$-468.78 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0020 |
$-1,463.70 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0022 |
$-2,927.40 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0023 |
$-3,769.02 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0024 |
$-2,561.47 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$4,408.33 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$56,400.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$196,206.46 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0003 |
$36,194.75 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0004 |
$39,670.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0004 |
$47,000.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0004 |
$16,450.00 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0005 |
$-134.89 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0005 |
$67,316.29 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Initial Payment |
0005 |
$468,966.19 |
26604(04) |
0153 |
EpoxReb 84"DrillShaft |
Stockpiled Material Adjustment |
0006 |
$-817.37 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Closure |
0031 |
$-149,238.43 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0012 |
$-412.53 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0013 |
$-318.03 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0014 |
$-392.57 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0015 |
$-348.46 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0016 |
$-45.90 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0017 |
$-155.00 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0019 |
$-39.64 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0020 |
$-42.77 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0022 |
$-85.55 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0023 |
$-137.41 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0024 |
$-75.12 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0027 |
$-92.63 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0027 |
$-1,370.16 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0028 |
$-2,067.53 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0029 |
$-2,162.95 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Initial Payment |
0004 |
$4,478.99 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0005 |
$-89.72 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Initial Payment |
0005 |
$154,839.07 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0006 |
$-543.55 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0007 |
$-35.77 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0008 |
$-501.82 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0009 |
$-472.46 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0010 |
$-345.39 |
26604(04) |
0155 |
2" SCH40 #150 Threaded pipe caps/couplers |
Stockpiled Material Adjustment |
0011 |
$-344.65 |
26604(04) |
0158 |
FRP covers |
Stockpiled Material Initial Payment |
0031 |
$131,083.01 |
26604(04) |
0158 |
FRP covers |
Stockpiled Material Adjustment |
0033 |
$-60,999.02 |
26604(04) |
0158 |
FRP covers |
Stockpiled Material Adjustment |
0031 |
$-69,785.48 |
26604(04) |
0159 |
Canopy system hardware |
Stockpiled Material Initial Payment |
0007 |
$71,295.46 |
26604(04) |
0159 |
Canopy system hardware |
Stockpiled Material Initial Payment |
0034 |
$349,120.00 |
26604(04) |
0159 |
Canopy system hardware |
Stockpiled Material Initial Payment |
0030 |
$241,112.27 |
26604(04) |
0160 |
Anchor bolts, nuts, washers |
Stockpiled Material Initial Payment |
0008 |
$3,024.00 |
26604(04) |
0160 |
Anchor bolts, nuts, washers |
Stockpiled Material Initial Payment |
0007 |
$29,322.50 |
26604(04) |
0160 |
Anchor bolts, nuts, washers |
Stockpiled Material Adjustment |
0031 |
$-517.04 |
26604(04) |
0163 |
6"pipe |
Stockpiled Material Initial Payment |
0003 |
$587.29 |
26604(04) |
0163 |
6"pipe |
Stockpiled Material Closure |
0031 |
$-445.36 |
26604(04) |
0163 |
6"pipe |
Stockpiled Material Adjustment |
0029 |
$-141.93 |
26604(04) |
0164 |
6'pipe |
Stockpiled Material Initial Payment |
0003 |
$155.18 |
26604(04) |
0173 |
16GaugeCSP36"DrillShafts |
Stockpiled Material Initial Payment |
0003 |
$2,286.67 |
26604(04) |
0173 |
16GaugeCSP36"DrillShafts |
Stockpiled Material Closure |
0033 |
$-2,286.67 |
26604(04) |
0175 |
anchor bolts, nuts, and washers |
Stockpiled Material Initial Payment |
0007 |
$804.81 |
26604(04) |
0179 |
Sealed expansion joint w/ seal and anchors |
Stockpiled Material Initial Payment |
0007 |
$12,134.92 |
26604(04) |
0179 |
Sealed expansion joint w/ seal and anchors |
Stockpiled Material Adjustment |
0011 |
$-12,134.92 |
26604(04) |
0181 |
Studs |
Stockpiled Material Adjustment |
0007 |
$-10,264.21 |
26604(04) |
0181 |
Studs |
Stockpiled Material Initial Payment |
0004 |
$10,264.21 |
26604(04) |
0182 |
Deck Forms |
Stockpiled Material Adjustment |
0011 |
$-21,268.20 |
26604(04) |
0182 |
Deck Forms |
Stockpiled Material Initial Payment |
0007 |
$21,268.20 |
26604(04) |
0184 |
Deck rebar |
Stockpiled Material Initial Payment |
0007 |
$65,558.54 |
26604(04) |
0184 |
Deck rebar |
Stockpiled Material Initial Payment |
0007 |
$27,044.60 |
26604(04) |
0184 |
Deck rebar |
Stockpiled Material Adjustment |
0011 |
$-13,938.65 |
26604(04) |
0184 |
Deck rebar |
Stockpiled Material Closure |
0012 |
$-13,105.95 |
26604(04) |
0184 |
Deck rebar |
Stockpiled Material Adjustment |
0011 |
$-65,558.54 |
26604(04) |
0200 |
Extruded Aluminum Signs |
Stockpiled Material Initial Payment |
0028 |
$907.70 |
26604(04) |
0200 |
Extruded Aluminum Signs |
Stockpiled Material Adjustment |
0037 |
$-580.67 |
26604(04) |
0200 |
Extruded Aluminum Signs |
Stockpiled Material Adjustment |
0038 |
$-327.03 |
26604(04) |
0201 |
Extreded Aluminum Panel Signs (Overhead) |
Stockpiled Material Initial Payment |
0028 |
$12,181.93 |
26604(04) |
0201 |
Extreded Aluminum Panel Signs (Overhead) |
Stockpiled Material Adjustment |
0033 |
$-12,181.93 |
26604(04) |
0217 |
12.5' PortableLong.Barr. |
Stockpiled Material Adjustment |
0004 |
$-3,780.01 |
26604(04) |
0217 |
12.5' PortableLong.Barr. |
Stockpiled Material Adjustment |
0003 |
$-72,860.62 |
26604(04) |
0217 |
12.5' PortableLong.Barr. |
Stockpiled Material Initial Payment |
0003 |
$76,640.63 |
26604(04) |
0248 |
cast in place med. barrier box |
Stockpiled Material Adjustment |
0031 |
$-3,772.41 |
26604(04) |
0248 |
cast in place med. barrier box |
Stockpiled Material Adjustment |
0033 |
$-5,740.62 |
26604(04) |
0248 |
cast in place med. barrier box |
Stockpiled Material Initial Payment |
0011 |
$12,696.49 |
26604(04) |
0258 |
1/C no. 4 Elect. Cond. |
Stockpiled Material Adjustment |
0005 |
$-410.35 |
26604(04) |
0258 |
1/C no. 4 Elect. Cond. |
Stockpiled Material Initial Payment |
0003 |
$78,479.49 |
26604(04) |
0258 |
1/C no. 4 Elect. Cond. |
Stockpiled Material Adjustment |
0033 |
$-23,387.44 |
26604(04) |
0270 |
Holophane LEDG |
Stockpiled Material Adjustment |
0033 |
$-90,102.00 |
26604(04) |
0270 |
Holophane LEDG |
Stockpiled Material Initial Payment |
0031 |
$90,102.00 |
26604(04) |
0271 |
IO LTG |
Stockpiled Material Initial Payment |
0031 |
$129,596.00 |
26604(04) |
0272 |
Post top Luuminaire |
Stockpiled Material Initial Payment |
0034 |
$27,996.00 |
Subtotals For Stockpile Payments |
$978,222.15 |