Contract ID: | 110204 | Estimate Number: | 0027 | Contract No: | 611334 | |||
Residency: | TETRA TECH (08002) | Estimate Type: | Progressive | Account No: | 400800 | |||
Project Number(s): | IMY-NBIP(436) | ||||||||||||
Primary Job Piece No: | 21901(04) | ||||||||||||
Contract Description: | BRIDGE PAINTING AND REHABILITATION I-244: AT MULTIPLE LOCATIONS IN THE CITY OF TULSA. | ||||||||||||
Primary County: | TULSA | ||||||||||||
Name of Road: | I-244 | ||||||||||||
Prime Contractor: | V. H. P. ENTERPRISES, INC. | ||||||||||||
728 WESLEY AVE. | |||||||||||||
TARPON SPRINGS , FL 34689 | |||||||||||||
Surety Company: | INTERNATIONAL FIDELITY INSURANCE COMPANY | ||||||||||||
Date Let: | 03/17/2011 | NTP Effective Date: | 08/01/2011 | Pay Period: | 09/16/2012 TO 09/30/2012 |
Date Awarded: | 04/04/2011 | Date Work Began: | 08/01/2011 | Original Contract Time: | 240 |
Date Contract Executed: | 05/12/2011 | Date Time Stopped: | Current Time Charged: | 401.00 | |
Date NTP Issued: | 06/10/2011 | Completion Date: | Current Time Allowed: | 374.00 | |
General Liability Expires: | 03/13/2013 | Workman's Comp Expires: | 03/13/2013 | Percent Time Used: | 107.22 % |
Specification Year: | 2009 | Date Approved: | |||
Current Contract Amount: | $9,526,426.36 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $8,940,379.50 | Participating: | $9,126,894.29 | $9,043,717.70 | $83,176.59 | ||
Percent Complete: | 95.04 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $472,282.07 | Total Earnings: | $9,126,894.29 | $9,043,717.70 | $83,176.59 | ||
Unearned Balance: | $-113,764.79 | Stockpiled Materials: | $0.00 | $24,763.20 | $-24,763.20 | ||
Gross Earnings: | $9,126,894.29 | $9,068,480.90 | $58,413.39 | ||||
Other Adjustments: | $-18,750.00 | $11,250.00 | $-30,000.00 | ||||
Liq Dam/Disincentive: | $-54,000.00 | $-36,000.00 | $-18,000.00 | ||||
TOTAL: | $9,054,144.29 | $9,043,730.90 | $10,413.39 |
Contract ID: | 110204 | Estimate Number: | 0027 | Primary JP: | 21901(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | New rehabilitation items | Approved | 02/07/2012 | 14.0 | $620,052.35 |
002 | Bearing Assembly | Approved | 09/11/2012 | 120.0 | $-34,005.49 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $48,364.80 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0025 | $-475.20 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0023 | $-5,121.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0019 | $-6,520.80 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0018 | $-6,045.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0003 | $-897.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0014 | $-7,101.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0004 | $-1,293.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0016 | $-6,652.80 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0011 | $-3,828.00 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0015 | $-4,514.40 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0013 | $-4,646.40 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0017 | $-1,267.20 |
21901(04) | 0130 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $19,324.80 |
21901(04) | 0130 | ANODES - Maxwell Supply | Stockpiled Material Closure | 0027 | $-19,324.80 |
21901(04) | 0171 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $5,280.00 |
21901(04) | 0171 | ANODES - Maxwell Supply | Stockpiled Material Closure | 0027 | $-1,953.60 |
21901(04) | 0171 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0020 | $-3,326.40 |
21901(04) | 0180 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0021 | $-4,224.00 |
21901(04) | 0180 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $6,494.40 |
21901(04) | 0180 | ANODES - Maxwell Supply | Stockpiled Material Closure | 0027 | $-2,270.40 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Closure | 0027 | $-1,214.40 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0003 | $-3,273.60 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0026 | $-2,112.00 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $26,980.80 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0011 | $-4,646.40 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0022 | $-9,345.60 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0008 | $-4,276.80 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0025 | $-2,112.00 | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | ||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount |
System Application of Liquidated Damages | 0017 | --2.0 | $2,000.00 | $-4,000.00 |
System Application of Liquidated Damages | 0018 | --15 | $2,000.00 | $-30,000.00 |
System Application of Liquidated Damages | 0019 | --10 | $2,000.00 | $-20,000.00 |
System Application of Liquidated Damages | 0023 | --67 | $2,000.00 | $-134,000.00 |
System Application of Liquidated Damages | 0024 | --15 | $2,000.00 | $-30,000.00 |
System Application of Liquidated Damages | 0025 | --14 | $2,000.00 | $-28,000.00 |
System Application of Liquidated Damages | 0026 | -105 | $2,000.00 | $210,000.00 |
System Application of Liquidated Damages | 0027 | --9.0 | $2,000.00 | $-18,000.00 | Subtotals For Liquidated Damages | $-54,000.00 |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
Lane Rental | 0012 | $-18,750.00 |
LD Adjustment (Prog. Est. Only) | 0023 | $188,000.00 |
LD Adjustment (Prog. Est. Only) | 0024 | $30,000.00 |
LD Adjustment (Prog. Est. Only) | 0025 | $22,000.00 |
LD Adjustment (Prog. Est. Only) | 0026 | $-210,000.00 |
LD Adjustment (Prog. Est. Only) | 0027 | $-30,000.00 | Subtotals For Contract Adjustments | $-18,750.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 110204 | Estimate Number: | 0027 | Primary JP: | 21901(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0200/NBI 18357, BRIDGE NO. 3 | ||||||||
0001 | CLSM BACKFILL | 501(G) 6315 | CY | 24.000 | 24.000 | 9.000 | 9.000 | $315.00 | $2,835.00 | $2,835.00 |
0002 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 10.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0003 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 90.000 | 90.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0004 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 3.400 | 3.400 | 0.000 | $92.00 | $0.00 | $0.00 | |
0005 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 10.000 | 50.000 | 24.790 | $410.00 | $0.00 | $10,163.90 | |
0006 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 10.000 | 50.000 | 24.790 | $10.00 | $0.00 | $247.90 | |
Subtotals For Category 0200/NBI 18357, BRIDGE NO. 3 | $2,835.00 | $13,246.80 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0201/NBI 17608, BRIDGE NO. 53 | ||||||||
0007 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 50.000 | 0.000 | 3.600 | $10.50 | $0.00 | $37.80 |
0008 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $140,750.00 | $0.00 | $140,750.00 | |
0009 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0010 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 14.000 | 70.000 | 51.800 | $410.00 | $0.00 | $21,238.00 | |
0011 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 3,658.000 | 2,898.000 | 2,886.130 | $82.00 | $0.00 | $236,662.66 | |
0012 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 421.000 | 477.000 | -52.960 | 51.800 | $10.00 | $-529.60 | $518.00 |
8012 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 15.000 | 0.000 | 15.000 | $1,550.00 | $0.00 | $23,250.00 |
8013 | REINFORCING STEEL | 511(A) 1332 | LB | 0.000 | 2,763.000 | 2,763.000 | $1.75 | $0.00 | $4,835.25 | |
8016 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 0.000 | 160.000 | 52.960 | 52.960 | $10.00 | $529.60 | $529.60 |
8110 | CONSTRUCTION MISCELLANEOUS | 104 0400 | SF | 0.000 | 100.000 | 99.990 | $30.00 | $0.00 | $2,999.70 | |
8111 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 68.000 | 63.420 | $27.00 | $0.00 | $1,712.34 | |
8320 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 3.000 | 3.000 | $1,865.41 | $0.00 | $5,596.23 | |
8321 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 9.000 | 9.000 | $886.70 | $0.00 | $7,980.30 | |
8322 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 11.000 | 4.000 | $513.72 | $0.00 | $2,054.88 | |
Subtotals For Category 0201/NBI 17608, BRIDGE NO. 53 | $0.00 | $448,664.76 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0202/NBI 18277, BRIDGE NO. 51 | ||||||||
0013 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 15.000 | 75.000 | 17.460 | $410.00 | $0.00 | $7,158.60 | |
0014 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 15.000 | 75.000 | 17.460 | $10.00 | $0.00 | $174.60 | |
Subtotals For Category 0202/NBI 18277, BRIDGE NO. 51 | $0.00 | $7,333.20 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0203/NBI 18042, BRIDGE NO. 49W | ||||||||
0015 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 200.000 | 0.000 | 98.300 | $10.50 | $0.00 | $1,032.15 |
0016 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $110,000.00 | $0.00 | $110,000.00 | |
0017 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0018 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 527.000 | 167.000 | 164.000 | $92.00 | $0.00 | $15,088.00 | |
0019 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 59.000 | 20.000 | 18.480 | $10.00 | $0.00 | $184.80 | |
8015 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 0.000 | 18.480 | 0.000 | $410.00 | $0.00 | $0.00 | |
8355 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 10.000 | 12.000 | $1,865.41 | $0.00 | $22,384.92 | |
8356 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 9.000 | 0.000 | $886.70 | $0.00 | $0.00 | |
Subtotals For Category 0203/NBI 18042, BRIDGE NO. 49W | $0.00 | $150,689.87 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0204/NBI 18082, BRIDGE NO. 48 | ||||||||
0020 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 120.000 | 0.000 | 16.800 | $10.50 | $0.00 | $176.40 |
0021 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $255,000.00 | $0.00 | $255,000.00 | |
0022 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $4,000.00 | $0.00 | $4,000.00 | |
0023 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 7.000 | 20.000 | 19.780 | $410.00 | $0.00 | $8,109.80 | |
0024 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 7.000 | 20.000 | 19.780 | $10.00 | $0.00 | $197.80 | |
8312 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 4.000 | 5.000 | $1,865.41 | $0.00 | $9,327.05 | |
8313 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 8.000 | 6.000 | $886.70 | $0.00 | $5,320.20 | |
Subtotals For Category 0204/NBI 18082, BRIDGE NO. 48 | $0.00 | $282,131.25 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0205/NBI 18079, BRIDGE NO. 47 | ||||||||
0025 | CLSM BACKFILL | 501(G) 6309 | CY | 9.000 | 9.000 | 9.000 | 9.000 | $165.00 | $1,485.00 | $1,485.00 |
0026 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 80.000 | 0.000 | 9.600 | $10.50 | $0.00 | $100.80 |
0027 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $120,000.00 | $0.00 | $120,000.00 | |
0028 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0029 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 30.000 | 32.790 | $410.00 | $0.00 | $13,443.90 | |
0030 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 6.000 | 30.000 | 32.790 | $10.00 | $0.00 | $327.90 | |
8112 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 57.000 | 8.330 | $27.00 | $0.00 | $224.91 | |
8310 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 4.000 | 4.000 | $1,865.41 | $0.00 | $7,461.64 | |
Subtotals For Category 0205/NBI 18079, BRIDGE NO. 47 | $1,485.00 | $145,044.15 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0206/NBI 18062, BRIDGE NO. 44 | ||||||||
0031 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 150.000 | 0.000 | 2.400 | $10.50 | $0.00 | $25.20 |
0032 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $250,000.00 | $0.00 | $250,000.00 | |
0033 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $4,000.00 | $0.00 | $4,000.00 | |
8300 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 21.000 | 20.000 | $1,865.41 | $0.00 | $37,308.20 | |
8301 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 5.000 | 0.000 | $886.70 | $0.00 | $0.00 | |
Subtotals For Category 0206/NBI 18062, BRIDGE NO. 44 | $0.00 | $291,333.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0207/NBI 18060, BRIDGE NO. 39 | ||||||||
0034 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 25.000 | 0.000 | 6.000 | $10.50 | $0.00 | $63.00 |
0035 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $69,700.00 | $0.00 | $69,700.00 | |
0036 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0037 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 1.000 | 5.000 | 0.000 | 18.120 | $410.00 | $0.00 | $7,429.20 |
0038 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 1.000 | 5.000 | 18.120 | $10.00 | $0.00 | $181.20 | |
8290 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 7.000 | 6.000 | $886.70 | $0.00 | $5,320.20 | |
Subtotals For Category 0207/NBI 18060, BRIDGE NO. 39 | $0.00 | $84,693.60 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0208/NBI 18059, BRIDGE NO. 37 | ||||||||
0039 | CLSM BACKFILL | 501(G) 6309 | CY | 2.000 | 2.000 | 2.000 | 2.000 | $165.00 | $330.00 | $330.00 |
0040 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 100.000 | 0.000 | 28.800 | $10.50 | $0.00 | $302.40 |
0041 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $140,000.00 | $0.00 | $140,000.00 | |
0042 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0043 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 21.000 | 105.000 | 57.410 | $410.00 | $0.00 | $23,538.10 | |
0044 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 509.000 | 509.000 | 286.340 | $92.00 | $0.00 | $26,343.28 | |
0045 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 75.000 | 159.000 | 57.410 | $10.00 | $0.00 | $574.10 | |
8280 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 2.000 | 1.000 | $1,865.41 | $0.00 | $1,865.41 | |
8281 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 10.000 | 10.000 | $886.70 | $0.00 | $8,867.00 | |
Subtotals For Category 0208/NBI 18059, BRIDGE NO. 37 | $330.00 | $203,820.29 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0209/NBI 18020, BRIDGE NO. 36W | ||||||||
0046 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 75.000 | 0.000 | 21.100 | $10.50 | $0.00 | $221.55 |
0047 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $102,000.00 | $0.00 | $102,000.00 | |
0048 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0049 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 10.000 | 48.000 | 47.530 | $410.00 | $0.00 | $19,487.30 | |
0050 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 10.000 | 50.000 | 47.530 | $10.00 | $0.00 | $475.30 | |
8344 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 1.000 | 1.000 | $866.70 | $0.00 | $866.70 | |
8345 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 9.000 | 9.000 | $513.72 | $0.00 | $4,623.48 | |
Subtotals For Category 0209/NBI 18020, BRIDGE NO. 36W | $0.00 | $129,674.33 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0210/NBI 18021, BRIDGE NO. 35W | ||||||||
0051 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0052 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $90,100.00 | $0.00 | $90,100.00 | |
0053 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0054 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 4.000 | 28.000 | 0.000 | 63.780 | $410.00 | $0.00 | $26,149.80 |
0055 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 4.000 | 28.000 | 63.780 | $10.00 | $0.00 | $637.80 | |
8340 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 9.000 | 9.000 | $866.70 | $0.00 | $7,800.30 | |
Subtotals For Category 0210/NBI 18021, BRIDGE NO. 35W | $0.00 | $126,687.90 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0211/NBI 18022, BRIDGE NO. 34W | ||||||||
0056 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 200.000 | 0.000 | 17.600 | $10.50 | $0.00 | $184.80 |
0057 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $62,000.00 | $0.00 | $62,000.00 | |
0058 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0059 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 7.000 | 51.000 | 50.750 | $410.00 | $0.00 | $20,807.50 | |
0060 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 7.000 | 51.000 | 50.750 | $10.00 | $0.00 | $507.50 | |
8330 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 9.000 | 9.000 | $866.70 | $0.00 | $7,800.30 | |
Subtotals For Category 0211/NBI 18022, BRIDGE NO. 34W | $0.00 | $93,300.10 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0212/NBI 18023, BRIDGE NO. 31 | ||||||||
0061 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0062 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $18,870.00 | $0.00 | $18,870.00 | |
0063 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0064 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 8.000 | 33.000 | 32.740 | $410.00 | $0.00 | $13,423.40 | |
0065 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 8.000 | 33.000 | 32.740 | $10.00 | $0.00 | $327.40 | |
8265 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 20.000 | 19.000 | $866.70 | $0.00 | $16,467.30 | |
Subtotals For Category 0212/NBI 18023, BRIDGE NO. 31 | $0.00 | $49,588.10 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0213/NBI 18024, BRIDGE NO. 29 | ||||||||
0066 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 75.000 | 0.000 | 27.100 | $10.50 | $0.00 | $284.55 |
0067 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $18,955.00 | $0.00 | $18,955.00 | |
0068 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $500.00 | $0.00 | $25.00 | |
0069 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 2.000 | 10.000 | 0.000 | 20.390 | $410.00 | $0.00 | $8,359.90 |
0070 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 2.000 | 10.000 | 20.390 | $10.00 | $0.00 | $203.90 | |
8255 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 1.000 | $1,865.41 | $0.00 | $1,865.41 | |
8256 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 6.000 | 6.000 | $866.70 | $0.00 | $5,200.20 | |
Subtotals For Category 0213/NBI 18024, BRIDGE NO. 29 | $0.00 | $34,893.96 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0214/NBI 18028, BRIDGE NO. 27 | ||||||||
0071 | (PL)FALSEWORK JACKING | 502 6116 | LSUM | 1.000 | 1.000 | 1.000 | 1.000 | $5,000.00 | $5,000.00 | $5,000.00 |
0072 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0073 | CLASS A CONCRETE | 509(B) 1328 | CY | 16.600 | 16.600 | 16.600 | $72.50 | $0.00 | $1,203.50 | |
0074 | REINFORCING STEEL | 511(A) 1332 | LB | 965.000 | 965.000 | 0.000 | 965.000 | $5.00 | $0.00 | $4,825.00 |
0075 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $20,145.00 | $0.00 | $20,145.00 | |
0076 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0077 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 4.000 | 20.000 | 20.500 | $10.00 | $0.00 | $205.00 | |
0078 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 4.000 | 20.000 | 52.860 | $10.00 | $0.00 | $528.60 | |
0079 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 6.000 | 6.000 | 6.000 | 6.000 | $5,000.00 | $30,000.00 | $30,000.00 |
8101 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 16.600 | 0.000 | 16.600 | $7.22 | $0.00 | $119.85 |
8245 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 0.000 | $1,865.41 | $0.00 | $0.00 | |
8246 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 5.000 | 0.000 | $886.70 | $0.00 | $0.00 | |
Subtotals For Category 0214/NBI 18028, BRIDGE NO. 27 | $35,000.00 | $62,526.95 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0215/NBI 18031, BRIDGE NO. 25 | ||||||||
0080 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 50.000 | 0.000 | 2.400 | $10.50 | $0.00 | $25.20 |
0081 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $25,245.00 | $0.00 | $25,245.00 | |
0082 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0083 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 14.255 | $410.00 | $0.00 | $5,844.55 | |
0084 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 3.000 | 15.000 | 14.255 | $10.00 | $0.00 | $142.55 | |
8233 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 6.000 | 6.000 | $886.70 | $0.00 | $5,320.20 | |
8235 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 1.000 | 1.000 | $513.72 | $0.00 | $513.72 | |
Subtotals For Category 0215/NBI 18031, BRIDGE NO. 25 | $0.00 | $37,591.22 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0216/NBI 18075, BRIDGE NO. 23 | ||||||||
0085 | CLSM BACKFILL | 501(G) 6309 | CY | 3.000 | 3.000 | 1.500 | $315.00 | $0.00 | $472.50 | |
0086 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 75.000 | 0.000 | 16.400 | $10.50 | $0.00 | $172.20 |
0087 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $120,000.00 | $0.00 | $120,000.00 | |
0088 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0089 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 0.000 | 19.700 | $410.00 | $0.00 | $8,077.00 |
0090 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 3.000 | 15.000 | 19.700 | $10.00 | $0.00 | $197.00 | |
8224 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 1.000 | $1,865.41 | $0.00 | $1,865.41 | |
8225 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 8.000 | 7.000 | $886.70 | $0.00 | $6,206.90 | |
8226 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 2.000 | 2.000 | $513.72 | $0.00 | $1,027.44 | |
Subtotals For Category 0216/NBI 18075, BRIDGE NO. 23 | $0.00 | $140,018.45 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0217/NBI 18146, BRIDGE NO. 20 | ||||||||
0091 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 200.000 | 0.000 | 134.600 | $10.50 | $0.00 | $1,413.30 |
0092 | CLASS A CONCRETE | 509(B) 1328 | CY | 170.700 | 180.700 | 2.000 | 170.700 | $400.00 | $800.00 | $68,280.00 |
0093 | REINFORCING STEEL | 511(A) 1332 | LB | 39,497.000 | 41,050.000 | 463.200 | 39,497.000 | $1.75 | $810.60 | $69,119.76 |
0094 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $910,000.00 | $0.00 | $910,000.00 | |
0095 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $10,000.00 | $0.00 | $10,000.00 | |
0096 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 145.000 | 145.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0097 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 5.600 | 5.600 | 0.000 | $92.00 | $0.00 | $0.00 | |
0098 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 126.000 | 25.140 | 135.940 | $410.00 | $10,307.40 | $55,735.40 |
0099 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 203.000 | 203.000 | 124.540 | $92.00 | $0.00 | $11,457.68 | |
0100 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 925.000 | 925.000 | 25.140 | 868.230 | $10.00 | $251.40 | $8,682.30 |
0101 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 1,832.000 | 1,832.000 | 2,016.000 | $52.00 | $0.00 | $104,832.00 | |
8102 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 180.000 | 2.000 | 170.700 | $7.22 | $14.44 | $1,232.45 |
8113 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 259.500 | 130.330 | $27.00 | $0.00 | $3,518.91 | |
8211 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 24.000 | 23.000 | $1,865.41 | $0.00 | $42,904.43 | |
8212 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 3.000 | 3.000 | $886.70 | $0.00 | $2,660.10 | |
8213 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 7.000 | 7.000 | $513.72 | $0.00 | $3,596.04 | |
Subtotals For Category 0217/NBI 18146, BRIDGE NO. 20 | $12,183.84 | $1,293,432.37 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0218/NBI 18058, BRIDGE NO. 18 | ||||||||
0102 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0103 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $51,000.00 | $0.00 | $51,000.00 | |
0104 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $5,000.00 | $0.00 | $5,000.00 | |
0105 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 5.000 | 25.000 | 3.040 | $410.00 | $0.00 | $1,246.40 | |
0106 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 5.000 | 25.000 | 3.040 | $10.00 | $0.00 | $30.40 | |
8204 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 1.000 | 1.000 | $886.70 | $0.00 | $886.70 | |
8205 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 2.000 | 2.000 | $1,865.41 | $0.00 | $3,730.82 | |
Subtotals For Category 0218/NBI 18058, BRIDGE NO. 18 | $0.00 | $61,894.32 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0219/NBI 18064, BRIDGE NO. 17 | ||||||||
0107 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0108 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $65,000.00 | $0.00 | $65,000.00 | |
0109 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0110 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 4.000 | 20.000 | 2.700 | $410.00 | $0.00 | $1,107.00 | |
0111 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 4.000 | 20.000 | 2.700 | $10.00 | $0.00 | $27.00 | |
Subtotals For Category 0219/NBI 18064, BRIDGE NO. 17 | $0.00 | $66,634.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0220/NBI 18351, BRIDGE NO. 4 | ||||||||
0112 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 10.000 | 0.000 | 1.200 | $10.50 | $0.00 | $12.60 |
0113 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $185,000.00 | $0.00 | $185,000.00 | |
0114 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $1,000.00 | $0.00 | $1,000.00 | |
0115 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 15.000 | 15.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0116 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 0.600 | 0.600 | 0.000 | $92.00 | $0.00 | $0.00 | |
0117 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 4.220 | $410.00 | $0.00 | $1,730.20 | |
0118 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 1,518.000 | 1,048.000 | 1,041.380 | $92.00 | $0.00 | $95,806.96 | |
0119 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 172.000 | 184.000 | 4.220 | $10.00 | $0.00 | $42.20 | |
8200 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 4.000 | 4.000 | $866.70 | $0.00 | $3,466.80 | |
8202 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 1.000 | $1,865.41 | $0.00 | $1,865.41 | |
Subtotals For Category 0220/NBI 18351, BRIDGE NO. 4 | $0.00 | $288,924.17 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0221/NBI 17607, BRIDGE NO. 52 | ||||||||
0120 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 50.000 | 0.000 | 51.400 | $10.50 | $0.00 | $539.70 |
0121 | CLASS A CONCRETE | 509(B) 1328 | CY | 46.800 | 0.000 | 0.000 | $1,550.00 | $0.00 | $0.00 | |
0122 | REINFORCING STEEL | 511(A) 1332 | LB | 6,711.000 | 0.000 | 0.000 | $1.75 | $0.00 | $0.00 | |
0123 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $645,000.00 | $0.00 | $645,000.00 | |
0124 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $5,000.00 | $0.00 | $5,000.00 | |
0125 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 105.000 | 105.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0126 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 4.000 | 4.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0127 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 21.000 | 105.000 | 130.710 | $10.00 | $0.00 | $1,307.10 | |
0128 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 2,369.000 | 2,369.000 | 2,073.080 | $25.00 | $0.00 | $51,827.00 | |
0129 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 434.000 | 518.000 | 130.710 | $10.00 | $0.00 | $1,307.10 | |
0130 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 732.000 | 732.000 | 0.000 | 0.000 | $52.00 | $0.00 | $0.00 |
8103 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 46.800 | 0.000 | $7.22 | $0.00 | $0.00 | |
8315 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 18.000 | 18.000 | $1,865.41 | $0.00 | $33,577.38 | |
8316 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 4.000 | 3.000 | $886.70 | $0.00 | $2,660.10 | |
Subtotals For Category 0221/NBI 17607, BRIDGE NO. 52 | $0.00 | $741,218.38 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0222/NBI 18276, BRIDGE NO. 50 | ||||||||
0131 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 18.000 | 90.000 | 14.520 | $410.00 | $0.00 | $5,953.20 | |
0132 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 18.000 | 90.000 | 14.520 | $10.00 | $0.00 | $145.20 | |
Subtotals For Category 0222/NBI 18276, BRIDGE NO. 50 | $0.00 | $6,098.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0223/NBI 18042, BRIDGE NO. 49E | ||||||||
0133 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 175.000 | 0.000 | 87.700 | $10.50 | $0.00 | $920.85 |
0134 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $114,036.00 | $0.00 | $114,036.00 | |
0135 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0136 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 2.000 | 10.000 | 0.000 | 33.700 | $410.00 | $0.00 | $13,817.00 |
0137 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 527.000 | 527.000 | 152.000 | $25.00 | $0.00 | $3,800.00 | |
0138 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 61.000 | 69.000 | 15.220 | $10.00 | $0.00 | $152.20 | |
8350 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 7.000 | 10.000 | $1,865.41 | $0.00 | $18,654.10 | |
8351 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 6.000 | 0.000 | $886.70 | $0.00 | $0.00 | |
Subtotals For Category 0223/NBI 18042, BRIDGE NO. 49E | $0.00 | $151,880.15 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0224/NBI 18067, BRIDGE NO. 46 | ||||||||
0139 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 25.000 | 0.000 | 2.400 | $10.50 | $0.00 | $25.20 |
0140 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $113,118.00 | $0.00 | $113,118.00 | |
0141 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0142 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 70.000 | 940.000 | 938.220 | $25.00 | $0.00 | $23,455.50 | |
0143 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 8.000 | 8.000 | 2.860 | $10.00 | $0.00 | $28.60 | |
8014 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 0.000 | 7.000 | 2.860 | 2.860 | $410.00 | $1,172.60 | $1,172.60 |
8114 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 27.500 | 8.330 | $27.00 | $0.00 | $224.91 | |
8308 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 11.000 | 9.000 | $1,865.41 | $0.00 | $16,788.69 | |
Subtotals For Category 0224/NBI 18067, BRIDGE NO. 46 | $1,172.60 | $155,313.50 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0225/NBI 18089, BRIDGE NO. 45 | ||||||||
0144 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 75.000 | 0.000 | 4.800 | $10.50 | $0.00 | $50.40 |
0145 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $119,331.00 | $0.00 | $119,331.00 | |
0146 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0147 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 28.000 | 33.000 | -2.860 | 32.640 | $410.00 | $-1,172.60 | $13,382.40 |
0148 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 1,337.000 | 1,100.000 | 1,096.400 | $25.00 | $0.00 | $27,410.00 | |
0149 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 177.000 | 33.000 | 32.640 | $10.00 | $0.00 | $326.40 | |
8115 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 51.000 | 8.330 | $27.00 | $0.00 | $224.91 | |
8305 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 11.000 | 11.000 | $1,865.41 | $0.00 | $20,519.51 | |
Subtotals For Category 0225/NBI 18089, BRIDGE NO. 45 | $-1,172.60 | $181,744.62 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0226/NBI 18054, BRIDGE NO. 43 | ||||||||
0150 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 200.000 | 0.000 | 18.000 | $10.50 | $0.00 | $189.00 |
0151 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $112,540.00 | $0.00 | $112,540.00 | |
0152 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0153 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 9.000 | 45.000 | 29.970 | $410.00 | $0.00 | $12,287.70 | |
0154 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 665.000 | 665.000 | 557.600 | $92.00 | $0.00 | $51,299.20 | |
0155 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 74.000 | 110.000 | 29.970 | $10.00 | $0.00 | $299.70 | |
8298 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 13.000 | 12.000 | $1,865.41 | $0.00 | $22,384.92 | |
8299 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 4.000 | 3.000 | $886.70 | $0.00 | $2,660.10 | |
Subtotals For Category 0226/NBI 18054, BRIDGE NO. 43 | $0.00 | $202,160.62 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0227/NBI 18127, BRIDGE NO. 41 | ||||||||
0156 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 50.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0157 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $207,842.00 | $0.00 | $207,842.00 | |
0158 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $1,000.00 | $0.00 | $1,000.00 | |
0159 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 10.000 | 10.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0160 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 0.500 | 0.500 | 0.000 | $92.00 | $0.00 | $0.00 | |
0161 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 5.000 | 25.000 | 22.750 | $410.00 | $0.00 | $9,327.50 | |
0162 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 5.000 | 25.000 | 22.750 | $10.00 | $0.00 | $227.50 | |
8116 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 30.000 | 0.000 | $27.00 | $0.00 | $0.00 | |
8295 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 8.000 | 8.000 | $1,865.41 | $0.00 | $14,923.28 | |
Subtotals For Category 0227/NBI 18127, BRIDGE NO. 41 | $0.00 | $233,320.28 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0228/NBI 18062, BRIDGE NO. 40 | ||||||||
0163 | CLSM BACKFILL | 501(G) 6309 | CY | 3.000 | 3.000 | 3.000 | 3.000 | $315.00 | $945.00 | $945.00 |
0164 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 25.000 | 0.000 | 3.600 | $10.50 | $0.00 | $37.80 |
0165 | CLASS A CONCRETE | 509(B) 1328 | CY | 9.200 | 9.200 | 9.200 | $1,800.00 | $0.00 | $16,560.00 | |
0166 | REINFORCING STEEL | 511(A) 1332 | LB | 2,274.000 | 2,274.000 | 2,274.000 | $1.75 | $0.00 | $3,979.50 | |
0167 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $103,700.00 | $0.00 | $103,700.00 | |
0168 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0169 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 30.000 | 7.280 | $410.00 | $0.00 | $2,984.80 | |
0170 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 35.000 | 59.000 | 45.800 | $10.00 | $0.00 | $458.00 | |
0171 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 200.000 | 200.000 | 0.000 | 126.000 | $55.00 | $0.00 | $6,930.00 |
8104 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 9.200 | 9.200 | $7.22 | $0.00 | $66.42 | |
8292 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 10.000 | 10.000 | $886.70 | $0.00 | $8,867.00 | |
Subtotals For Category 0228/NBI 18062, BRIDGE NO. 40 | $945.00 | $145,028.52 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0229/NBI 18068, BRIDGE NO. 38 | ||||||||
0172 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0173 | CLASS A CONCRETE | 509(B) 1328 | CY | 11.200 | 11.200 | 11.200 | $1,800.00 | $0.00 | $20,160.00 | |
0174 | REINFORCING STEEL | 511(A) 1332 | LB | 3,071.000 | 3,071.000 | 3,071.000 | $1.75 | $0.00 | $5,374.25 | |
0175 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $139,281.00 | $0.00 | $139,281.00 | |
0176 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0177 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 8.060 | $410.00 | $0.00 | $3,304.60 | |
0178 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 785.000 | 300.000 | 294.510 | $92.00 | $0.00 | $27,094.92 | |
0179 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 126.000 | 138.000 | 67.630 | $10.00 | $0.00 | $676.30 | |
0180 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 246.000 | 246.000 | 0.000 | 160.000 | $55.00 | $0.00 | $8,800.00 |
8105 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 11.200 | 11.200 | $7.22 | $0.00 | $80.86 | |
8285 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 0.000 | $1,865.41 | $0.00 | $0.00 | |
8286 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 2.000 | 1.000 | $886.70 | $0.00 | $886.70 | |
Subtotals For Category 0229/NBI 18068, BRIDGE NO. 38 | $0.00 | $206,158.63 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0230/NBI 18020, BRIDGE NO. 36E | ||||||||
0181 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 20.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0182 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $87,975.00 | $0.00 | $87,975.00 | |
0183 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0184 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 10.000 | 47.000 | 46.620 | $410.00 | $0.00 | $19,114.20 | |
0185 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 10.000 | 47.000 | 46.620 | $10.00 | $0.00 | $466.20 | |
8342 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 4.000 | 4.000 | $886.70 | $0.00 | $3,546.80 | |
Subtotals For Category 0230/NBI 18020, BRIDGE NO. 36E | $0.00 | $111,602.20 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0231/NBI 18021, BRIDGE NO. 35E | ||||||||
0186 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 20.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0187 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $90,100.00 | $0.00 | $90,100.00 | |
0188 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0189 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 34.000 | 38.270 | $410.00 | $0.00 | $15,690.70 | |
0190 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 6.000 | 34.000 | 38.270 | $10.00 | $0.00 | $382.70 | |
8335 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 1.000 | 0.000 | $886.70 | $0.00 | $0.00 | |
Subtotals For Category 0231/NBI 18021, BRIDGE NO. 35E | $0.00 | $106,673.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0232/NBI 18022, BRIDGE NO. 34E | ||||||||
0191 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 25.000 | 0.000 | 12.000 | $10.50 | $0.00 | $126.00 |
0192 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $92,650.00 | $0.00 | $92,650.00 | |
0193 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0194 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 10.000 | 30.000 | 0.000 | 44.820 | $410.00 | $0.00 | $18,376.20 |
0195 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 10.000 | 30.000 | 44.820 | $10.00 | $0.00 | $448.20 | |
8325 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 1.000 | 1.000 | $886.70 | $0.00 | $886.70 | |
8326 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 2.000 | 2.000 | $513.72 | $0.00 | $1,027.44 | |
Subtotals For Category 0232/NBI 18022, BRIDGE NO. 34E | $0.00 | $114,014.54 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0233/NBI 18026, BRIDGE NO. 33 | ||||||||
0196 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 30.000 | 0.000 | 11.800 | $10.50 | $0.00 | $123.90 |
0197 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $17,000.00 | $0.00 | $17,000.00 | |
0198 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $200.00 | $0.00 | $200.00 | |
0199 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 23.000 | 22.020 | $410.00 | $0.00 | $9,028.20 | |
0200 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 3.000 | 23.000 | 22.020 | $10.00 | $0.00 | $220.20 | |
8275 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 3.000 | 3.000 | $866.70 | $0.00 | $2,600.10 | |
Subtotals For Category 0233/NBI 18026, BRIDGE NO. 33 | $0.00 | $29,172.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0234/NBI 18025, BRIDGE NO. 32 | ||||||||
0201 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 100.000 | 0.000 | 19.600 | $10.50 | $0.00 | $205.80 |
0202 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $19,465.00 | $0.00 | $19,465.00 | |
0203 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $200.00 | $0.00 | $200.00 | |
0204 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 2.000 | 8.000 | 7.070 | $410.00 | $0.00 | $2,898.70 | |
0205 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 2.000 | 8.000 | 7.070 | $10.00 | $0.00 | $70.70 | |
8270 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 2.000 | 2.000 | $1,865.41 | $0.00 | $3,730.82 | |
8271 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 6.000 | 5.000 | $886.70 | $0.00 | $4,433.50 | |
Subtotals For Category 0234/NBI 18025, BRIDGE NO. 32 | $0.00 | $31,004.52 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0235/NBI 18027, BRIDGE NO. 30 | ||||||||
0206 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 50.000 | 0.000 | 4.800 | $10.50 | $0.00 | $50.40 |
0207 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $19,720.00 | $0.00 | $19,720.00 | |
0208 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $200.00 | $0.00 | $10.00 | |
0209 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 2.000 | 10.000 | 10.040 | $410.00 | $0.00 | $4,116.40 | |
0210 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 2.000 | 10.000 | 10.040 | $10.00 | $0.00 | $100.40 | |
8260 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 7.000 | 7.000 | $866.70 | $0.00 | $6,066.90 | |
Subtotals For Category 0235/NBI 18027, BRIDGE NO. 30 | $0.00 | $30,064.10 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0236/NBI 18029, BRIDGE NO. 28 | ||||||||
0211 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 75.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0212 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $19,720.00 | $0.00 | $19,720.00 | |
0213 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $200.00 | $0.00 | $200.00 | |
0214 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 5.000 | 25.000 | 28.840 | $410.00 | $0.00 | $11,824.40 | |
0215 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 5.000 | 25.000 | 28.840 | $10.00 | $0.00 | $288.40 | |
8250 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 1.000 | $1,865.41 | $0.00 | $1,865.41 | |
8251 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 5.000 | 4.000 | $886.70 | $0.00 | $3,546.80 | |
Subtotals For Category 0236/NBI 18029, BRIDGE NO. 28 | $0.00 | $37,445.01 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0237/NBI 18032, BRIDGE NO. 26 | ||||||||
0216 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 20.000 | 0.000 | 10.800 | $10.50 | $0.00 | $113.40 |
0217 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $23,205.00 | $0.00 | $23,205.00 | |
0218 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $200.00 | $0.00 | $200.00 | |
0219 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 5.000 | 38.000 | 37.070 | $410.00 | $0.00 | $15,198.70 | |
0220 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 5.000 | 38.000 | 37.070 | $10.00 | $0.00 | $370.70 | |
8240 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 7.000 | 7.000 | $886.70 | $0.00 | $6,206.90 | |
Subtotals For Category 0237/NBI 18032, BRIDGE NO. 26 | $0.00 | $45,294.70 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0238/NBI 18102, BRIDGE NO. 24 | ||||||||
0221 | CLSM BACKFILL | 501(G) 6309 | CY | 1.500 | 1.500 | 1.500 | $315.00 | $0.00 | $472.50 | |
0222 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 75.000 | 0.000 | 16.300 | $10.50 | $0.00 | $171.15 |
0223 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $205,450.00 | $0.00 | $205,450.00 | |
0224 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $1,000.00 | $0.00 | $1,000.00 | |
0225 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 0.000 | 53.970 | $410.00 | $0.00 | $22,127.70 |
0226 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 531.000 | 531.000 | 501.860 | $92.00 | $0.00 | $46,171.12 | |
0227 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 62.000 | 74.000 | 53.970 | $10.00 | $0.00 | $539.70 | |
8230 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 3.000 | 3.000 | $886.70 | $0.00 | $2,660.10 | |
8231 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 9.000 | 9.000 | $513.72 | $0.00 | $4,623.48 | |
Subtotals For Category 0238/NBI 18102, BRIDGE NO. 24 | $0.00 | $283,215.75 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0239/NBI 18356, BRIDGE NO. 22 | ||||||||
0228 | CLSM BACKFILL | 501(G) 6309 | CY | 42.700 | 42.700 | 13.000 | 13.000 | $315.00 | $4,095.00 | $4,095.00 |
0229 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 80.000 | 0.000 | 55.800 | $10.50 | $0.00 | $585.90 |
0230 | CLASS A CONCRETE | 509(B) 1328 | CY | 4.900 | 4.900 | 0.000 | $1,800.00 | $0.00 | $0.00 | |
0231 | REINFORCING STEEL | 511(A) 1332 | LB | 570.000 | 570.000 | 0.000 | $1.75 | $0.00 | $0.00 | |
0232 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $250,750.00 | $0.00 | $250,750.00 | |
0233 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0234 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 80.000 | 80.000 | 51.300 | $28.00 | $0.00 | $1,436.40 | |
0235 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 3.100 | 3.100 | 0.500 | $92.00 | $0.00 | $46.00 | |
0236 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 8.000 | 37.000 | 36.670 | $410.00 | $0.00 | $15,034.70 | |
0237 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 2,577.000 | 1,900.000 | 1,868.540 | $92.00 | $0.00 | $171,905.68 | |
0238 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 321.000 | 37.000 | 36.670 | $10.00 | $0.00 | $366.70 | |
8106 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 4.900 | 0.000 | $7.22 | $0.00 | $0.00 | |
8117 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 52.500 | 0.000 | $27.00 | $0.00 | $0.00 | |
8220 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 8.000 | 7.000 | $1,865.41 | $0.00 | $13,057.87 | |
8221 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 3.000 | 2.000 | $513.72 | $0.00 | $1,027.44 | |
Subtotals For Category 0239/NBI 18356, BRIDGE NO. 22 | $4,095.00 | $460,305.69 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0240/NBI 18353, BRIDGE NO. 21 | ||||||||
0239 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 10.000 | 0.000 | 4.000 | $10.50 | $0.00 | $42.00 |
0240 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $249,347.00 | $0.00 | $249,347.00 | |
0241 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $1,000.00 | $0.00 | $1,000.00 | |
0242 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 45.000 | 45.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0243 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 1.700 | 1.700 | 0.000 | $92.00 | $0.00 | $0.00 | |
0244 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 15.000 | 14.420 | $410.00 | $0.00 | $5,912.20 | |
0245 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 6.000 | 15.000 | 14.420 | $10.00 | $0.00 | $144.20 | |
8118 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 127.000 | 0.000 | $27.00 | $0.00 | $0.00 | |
8215 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 4.000 | 4.000 | $1,865.41 | $0.00 | $7,461.64 | |
8216 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 2.000 | 2.000 | $886.70 | $0.00 | $1,773.40 | |
8217 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 6.000 | 6.000 | $513.72 | $0.00 | $3,082.32 | |
Subtotals For Category 0240/NBI 18353, BRIDGE NO. 21 | $0.00 | $268,762.76 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0241/NBI 18145, BRIDGE NO. 19 | ||||||||
0246 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0247 | CLASS A CONCRETE | 509(B) 1328 | CY | 110.400 | 110.400 | 110.400 | $1,800.00 | $0.00 | $198,720.00 | |
0248 | REINFORCING STEEL | 511(A) 1332 | LB | 30,138.000 | 30,138.000 | 30,138.000 | $1.75 | $0.00 | $52,741.51 | |
0249 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $598,237.65 | $0.00 | $598,237.65 | |
0250 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $5,000.00 | $0.00 | $5,000.00 | |
0251 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 75.000 | 75.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0252 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 2.900 | 2.900 | 0.000 | $92.00 | $0.00 | $0.00 | |
0253 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 38.000 | 98.000 | 37.700 | 144.040 | $410.00 | $15,457.00 | $59,056.40 |
0254 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 1,188.000 | 713.000 | 705.470 | $92.00 | $0.00 | $64,903.24 | |
0255 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 728.000 | 728.000 | 37.700 | 510.510 | $10.00 | $377.00 | $5,105.10 |
0256 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 1,022.000 | 1,022.000 | 0.000 | 976.000 | $55.00 | $0.00 | $53,680.00 |
8107 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 110.400 | 110.400 | $7.22 | $0.00 | $797.09 | |
8119 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 150.000 | 170.830 | $27.00 | $0.00 | $4,612.41 | |
8207 | (PL)REPLACE BRIDGE ITEM (TYPE B) | 545 4825 | EA | 0.000 | 1.000 | 1.000 | $1,865.41 | $0.00 | $1,865.41 | |
8208 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 2.000 | 2.000 | $886.70 | $0.00 | $1,773.40 | |
8209 | (PL)REPAIR BRIDGE ITEM (TYPE C) | 540 4535 | EA | 0.000 | 6.000 | 6.000 | $513.72 | $0.00 | $3,082.32 | |
Subtotals For Category 0241/NBI 18145, BRIDGE NO. 19 | $15,834.00 | $1,049,574.53 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0242/NBI 18113, BRIDGE NO. 16 | ||||||||
0257 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 0.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0258 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 1.000 | $137,283.00 | $0.00 | $137,283.00 | |
0259 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0260 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 46.000 | 230.000 | 2.330 | $410.00 | $0.00 | $955.30 | |
0261 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 46.000 | 230.000 | 2.330 | $10.00 | $0.00 | $23.30 | |
8203 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 0.000 | 4.000 | 4.000 | $886.70 | $0.00 | $3,546.80 | |
Subtotals For Category 0242/NBI 18113, BRIDGE NO. 16 | $0.00 | $142,308.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0300/TRAFFIC | ||||||||
0262 | (PL)TRUCK MOUNTED ATTENUATOR | 876(A) 8482 | SD | 500.000 | 500.000 | 155.000 | $10.00 | $0.00 | $1,550.00 | |
0263 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 1.000 | $75,000.00 | $0.00 | $75,000.00 | |
0264 | PORT.CHANGEABLE MESSAGE SIGN | 882(A) 8306 | SD | 1,000.000 | 1,000.000 | 797.000 | $5.00 | $0.00 | $3,985.00 | |
8020 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 0.000 | 1.000 | 0.250 | 1.000 | $41,875.00 | $10,468.75 | $41,875.00 |
Subtotals For Category 0300/TRAFFIC | $10,468.75 | $122,410.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0640/CONSTRUCTION | ||||||||
0265 | FIELD OFFICE | 640(A) 1426 | EA | 1.000 | 1.000 | 1.000 | $10,000.00 | $0.00 | $10,000.00 | |
0266 | MOBILIZATION | 641 1399 | LSUM | 1.000 | 1.000 | 1.000 | $250,000.00 | $0.00 | $250,000.00 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $260,000.00 | ||||||||
Subtotals For Project IMY-NBIP(436) /21901(04) | $83,176.59 | $9,126,894.29 |