Contract ID: | 110204 | Estimate Number: | 0014 | Contract No: | 611334 | |||
Residency: | TETRA TECH (08002) | Estimate Type: | Progressive | Account No: | 400800 | |||
Project Number(s): | IMY-NBIP(436) | ||||||||||||
Primary Job Piece No: | 21901(04) | ||||||||||||
Contract Description: | BRIDGE PAINTING AND REHABILITATION I-244: AT MULTIPLE LOCATIONS IN THE CITY OF TULSA. | ||||||||||||
Primary County: | TULSA | ||||||||||||
Name of Road: | I-244 | ||||||||||||
Prime Contractor: | V. H. P. ENTERPRISES, INC. | ||||||||||||
728 WESLEY AVE. | |||||||||||||
TARPON SPRINGS , FL 34689 | |||||||||||||
Surety Company: | INTERNATIONAL FIDELITY INSURANCE COMPANY | ||||||||||||
Date Let: | 03/17/2011 | NTP Effective Date: | 08/01/2011 | Pay Period: | 03/01/2012 TO 03/15/2012 |
Date Awarded: | 04/04/2011 | Date Work Began: | 08/01/2011 | Original Contract Time: | 240 |
Date Contract Executed: | 05/12/2011 | Date Time Stopped: | Current Time Charged: | 212.00 | |
Date NTP Issued: | 06/10/2011 | Completion Date: | Current Time Allowed: | 254.00 | |
General Liability Expires: | 03/13/2013 | Workman's Comp Expires: | 10/24/2012 | Percent Time Used: | 83.46 % |
Specification Year: | 2009 | Date Approved: | 03/26/2012 | ||
Current Contract Amount: | $9,560,431.85 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $8,940,379.50 | Participating: | $5,806,324.75 | $4,932,531.67 | $873,793.08 | ||
Percent Complete: | 61.34 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $3,696,376.30 | Total Earnings: | $5,806,324.75 | $4,932,531.67 | $873,793.08 | ||
Unearned Balance: | $3,076,323.95 | Stockpiled Materials: | $76,480.80 | $83,582.40 | $-7,101.60 | ||
Gross Earnings: | $5,882,805.55 | $5,016,114.07 | $866,691.48 | ||||
Other Adjustments: | $-18,750.00 | $-18,750.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $5,864,055.55 | $4,997,364.07 | $866,691.48 |
Contract ID: | 110204 | Estimate Number: | 0014 | Primary JP: | 21901(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | New rehabilitation items | Approved | 02/07/2012 | 14.0 | $620,052.35 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0013 | $-4,646.40 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $48,364.80 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0004 | $-1,293.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0014 | $-7,101.60 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0011 | $-3,828.00 |
21901(04) | 0101 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0003 | $-897.60 |
21901(04) | 0130 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $19,324.80 |
21901(04) | 0171 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $5,280.00 |
21901(04) | 0180 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $6,494.40 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0011 | $-4,646.40 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0008 | $-4,276.80 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Initial Payment | 0001 | $26,980.80 |
21901(04) | 0256 | ANODES - Maxwell Supply | Stockpiled Material Adjustment | 0003 | $-3,273.60 | Subtotals For Stockpile Payments | $76,480.80 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
Lane Rental | 0012 | $-18,750.00 | Subtotals For Contract Adjustments | $-18,750.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 110204 | Estimate Number: | 0014 | Primary JP: | 21901(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0200/NBI 18357, BRIDGE NO. 3 | ||||||||
0001 | CLSM BACKFILL | 501(G) 6315 | CY | 24.000 | 24.000 | 0.000 | $315.00 | $0.00 | $0.00 | |
0002 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0003 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 90.000 | 90.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0004 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 3.400 | 3.400 | 0.000 | $92.00 | $0.00 | $0.00 | |
0005 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 10.000 | 50.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0006 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 10.000 | 50.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0200/NBI 18357, BRIDGE NO. 3 | $0.00 | $0.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0201/NBI 17608, BRIDGE NO. 53 | ||||||||
0007 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0008 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $140,750.00 | $0.00 | $0.00 | |
0009 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $500.00 | $0.00 | $0.00 | |
0010 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 14.000 | 70.000 | 8.310 | $410.00 | $0.00 | $3,407.10 | |
0011 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 3,658.000 | 3,658.000 | 0.000 | $82.00 | $0.00 | $0.00 | |
0012 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 421.000 | 477.000 | 8.310 | $10.00 | $0.00 | $83.10 | |
8110 | CONSTRUCTION MISCELLANEOUS | 104 0400 | SF | 0.000 | 100.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
8111 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 68.000 | 0.000 | $27.00 | $0.00 | $0.00 | |
Subtotals For Category 0201/NBI 17608, BRIDGE NO. 53 | $0.00 | $3,490.20 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0202/NBI 18277, BRIDGE NO. 51 | ||||||||
0013 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 15.000 | 75.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0014 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 15.000 | 75.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0202/NBI 18277, BRIDGE NO. 51 | $0.00 | $0.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0203/NBI 18042, BRIDGE NO. 49W | ||||||||
0015 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0016 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $110,000.00 | $0.00 | $104,500.00 | |
0017 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0018 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 527.000 | 527.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0019 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 59.000 | 59.000 | 9.050 | 18.480 | $10.00 | $90.50 | $184.80 |
Subtotals For Category 0203/NBI 18042, BRIDGE NO. 49W | $90.50 | $106,684.80 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0204/NBI 18082, BRIDGE NO. 48 | ||||||||
0020 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0021 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $255,000.00 | $0.00 | $242,250.00 | |
0022 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.100 | $4,000.00 | $0.00 | $400.00 | |
0023 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 7.000 | 35.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0024 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 7.000 | 35.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0204/NBI 18082, BRIDGE NO. 48 | $0.00 | $242,650.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0205/NBI 18079, BRIDGE NO. 47 | ||||||||
0025 | CLSM BACKFILL | 501(G) 6309 | CY | 9.000 | 9.000 | 0.000 | $165.00 | $0.00 | $0.00 | |
0026 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0027 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $120,000.00 | $0.00 | $114,000.00 | |
0028 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $2,000.00 | $0.00 | $100.00 | |
0029 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 30.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0030 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 6.000 | 30.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
8112 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 57.000 | 0.000 | $27.00 | $0.00 | $0.00 | |
Subtotals For Category 0205/NBI 18079, BRIDGE NO. 47 | $0.00 | $114,100.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0206/NBI 18062, BRIDGE NO. 44 | ||||||||
0031 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0032 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.450 | 0.850 | $250,000.00 | $112,500.00 | $212,500.00 |
0033 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $4,000.00 | $0.00 | $200.00 | |
Subtotals For Category 0206/NBI 18062, BRIDGE NO. 44 | $112,500.00 | $212,700.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0207/NBI 18060, BRIDGE NO. 39 | ||||||||
0034 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0035 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $69,700.00 | $0.00 | $66,215.00 | |
0036 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0037 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 1.000 | 5.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0038 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 1.000 | 5.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0207/NBI 18060, BRIDGE NO. 39 | $0.00 | $68,215.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0208/NBI 18059, BRIDGE NO. 37 | ||||||||
0039 | CLSM BACKFILL | 501(G) 6309 | CY | 2.000 | 2.000 | 0.000 | $165.00 | $0.00 | $0.00 | |
0040 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0041 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $140,000.00 | $0.00 | $133,000.00 | |
0042 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0043 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 21.000 | 105.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0044 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 509.000 | 509.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0045 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 75.000 | 159.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0208/NBI 18059, BRIDGE NO. 37 | $0.00 | $135,000.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0209/NBI 18020, BRIDGE NO. 36W | ||||||||
0046 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0047 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $102,000.00 | $0.00 | $96,900.00 | |
0048 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0049 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 10.000 | 50.000 | 47.530 | $410.00 | $0.00 | $19,487.30 | |
0050 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 10.000 | 50.000 | 47.530 | $10.00 | $0.00 | $475.30 | |
Subtotals For Category 0209/NBI 18020, BRIDGE NO. 36W | $0.00 | $118,862.60 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0210/NBI 18021, BRIDGE NO. 35W | ||||||||
0051 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0052 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $90,100.00 | $0.00 | $85,595.00 | |
0053 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0054 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 4.000 | 28.000 | 0.000 | 63.780 | $410.00 | $0.00 | $26,149.80 |
0055 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 4.000 | 28.000 | 63.780 | $10.00 | $0.00 | $637.80 | |
Subtotals For Category 0210/NBI 18021, BRIDGE NO. 35W | $0.00 | $114,382.60 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0211/NBI 18022, BRIDGE NO. 34W | ||||||||
0056 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0057 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $62,000.00 | $0.00 | $58,900.00 | |
0058 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0059 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 7.000 | 56.000 | 50.750 | $410.00 | $0.00 | $20,807.50 | |
0060 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 7.000 | 56.000 | 50.750 | $10.00 | $0.00 | $507.50 | |
Subtotals For Category 0211/NBI 18022, BRIDGE NO. 34W | $0.00 | $82,215.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0212/NBI 18023, BRIDGE NO. 31 | ||||||||
0061 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0062 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.250 | $18,870.00 | $0.00 | $4,717.50 | |
0063 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.250 | $500.00 | $0.00 | $125.00 | |
0064 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 8.000 | 40.000 | 32.740 | $410.00 | $0.00 | $13,423.40 | |
0065 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 8.000 | 40.000 | 32.740 | $10.00 | $0.00 | $327.40 | |
Subtotals For Category 0212/NBI 18023, BRIDGE NO. 31 | $0.00 | $18,593.30 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0213/NBI 18024, BRIDGE NO. 29 | ||||||||
0066 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0067 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $18,955.00 | $0.00 | $0.00 | |
0068 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $500.00 | $0.00 | $0.00 | |
0069 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 2.000 | 10.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0070 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 2.000 | 10.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0213/NBI 18024, BRIDGE NO. 29 | $0.00 | $0.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0214/NBI 18028, BRIDGE NO. 27 | ||||||||
0071 | (PL)FALSEWORK JACKING | 502 6116 | LSUM | 1.000 | 1.000 | 0.000 | $5,000.00 | $0.00 | $0.00 | |
0072 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0073 | CLASS A CONCRETE | 509(B) 1328 | CY | 16.600 | 16.600 | 0.000 | $72.50 | $0.00 | $0.00 | |
0074 | REINFORCING STEEL | 511(A) 1332 | LB | 965.000 | 965.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0075 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $20,145.00 | $0.00 | $0.00 | |
0076 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $500.00 | $0.00 | $0.00 | |
0077 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 4.000 | 20.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0078 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 4.000 | 20.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0079 | (PL)REPAIR BRIDGE ITEM (TYPE B) | 540 4525 | EA | 6.000 | 6.000 | 0.000 | $5,000.00 | $0.00 | $0.00 | |
8101 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 16.600 | 0.000 | $7.22 | $0.00 | $0.00 | |
Subtotals For Category 0214/NBI 18028, BRIDGE NO. 27 | $0.00 | $0.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0215/NBI 18031, BRIDGE NO. 25 | ||||||||
0080 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0081 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $25,245.00 | $0.00 | $0.00 | |
0082 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $500.00 | $0.00 | $0.00 | |
0083 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 14.255 | $410.00 | $0.00 | $5,844.55 | |
0084 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 3.000 | 15.000 | 14.255 | $10.00 | $0.00 | $142.55 | |
Subtotals For Category 0215/NBI 18031, BRIDGE NO. 25 | $0.00 | $5,987.10 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0216/NBI 18075, BRIDGE NO. 23 | ||||||||
0085 | CLSM BACKFILL | 501(G) 6309 | CY | 3.000 | 3.000 | 0.000 | $315.00 | $0.00 | $0.00 | |
0086 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0087 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $120,000.00 | $0.00 | $114,000.00 | |
0088 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $2,000.00 | $0.00 | $100.00 | |
0089 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 13.160 | 19.700 | $410.00 | $5,395.60 | $8,077.00 |
0090 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 3.000 | 15.000 | 13.160 | 19.700 | $10.00 | $131.60 | $197.00 |
Subtotals For Category 0216/NBI 18075, BRIDGE NO. 23 | $5,527.20 | $122,374.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0217/NBI 18146, BRIDGE NO. 20 | ||||||||
0091 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0092 | CLASS A CONCRETE | 509(B) 1328 | CY | 170.700 | 180.700 | 30.000 | 80.000 | $400.00 | $12,000.00 | $32,000.00 |
0093 | REINFORCING STEEL | 511(A) 1332 | LB | 39,497.000 | 41,050.000 | 6,941.400 | 18,510.400 | $1.75 | $12,147.45 | $32,393.20 |
0094 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.350 | 0.760 | $910,000.00 | $318,500.00 | $691,600.00 |
0095 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $10,000.00 | $0.00 | $500.00 | |
0096 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 145.000 | 145.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0097 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 5.600 | 5.600 | 0.000 | $92.00 | $0.00 | $0.00 | |
0098 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 126.000 | 82.030 | $410.00 | $0.00 | $33,632.30 | |
0099 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 203.000 | 203.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0100 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 925.000 | 925.000 | 113.190 | 364.300 | $10.00 | $1,131.90 | $3,643.00 |
0101 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 1,832.000 | 1,832.000 | 269.000 | 673.000 | $52.00 | $13,988.00 | $34,996.00 |
8102 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 180.000 | 0.000 | $7.22 | $0.00 | $0.00 | |
8113 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 259.500 | 0.000 | $27.00 | $0.00 | $0.00 | |
Subtotals For Category 0217/NBI 18146, BRIDGE NO. 20 | $357,767.35 | $828,764.50 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0218/NBI 18058, BRIDGE NO. 18 | ||||||||
0102 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0103 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.100 | 0.850 | $51,000.00 | $5,100.00 | $43,350.00 |
0104 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $5,000.00 | $0.00 | $250.00 | |
0105 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 5.000 | 25.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0106 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 5.000 | 25.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0218/NBI 18058, BRIDGE NO. 18 | $5,100.00 | $43,600.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0219/NBI 18064, BRIDGE NO. 17 | ||||||||
0107 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0108 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.200 | 0.800 | $65,000.00 | $13,000.00 | $52,000.00 |
0109 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $500.00 | $0.00 | $25.00 | |
0110 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 4.000 | 20.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0111 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 4.000 | 20.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0219/NBI 18064, BRIDGE NO. 17 | $13,000.00 | $52,025.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0220/NBI 18351, BRIDGE NO. 4 | ||||||||
0112 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0113 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.000 | $185,000.00 | $0.00 | $0.00 | |
0114 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.000 | $1,000.00 | $0.00 | $0.00 | |
0115 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 15.000 | 15.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0116 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 0.600 | 0.600 | 0.000 | $92.00 | $0.00 | $0.00 | |
0117 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0118 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 1,518.000 | 1,518.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0119 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 172.000 | 184.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0220/NBI 18351, BRIDGE NO. 4 | $0.00 | $0.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0221/NBI 17607, BRIDGE NO. 52 | ||||||||
0120 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0121 | CLASS A CONCRETE | 509(B) 1328 | CY | 46.800 | 46.800 | 0.000 | $1,550.00 | $0.00 | $0.00 | |
0122 | REINFORCING STEEL | 511(A) 1332 | LB | 6,711.000 | 6,711.000 | 0.000 | $1.75 | $0.00 | $0.00 | |
0123 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.210 | 0.900 | $645,000.00 | $135,450.00 | $580,500.00 |
0124 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | $5,000.00 | $0.00 | $250.00 | |
0125 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 105.000 | 105.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0126 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 4.000 | 4.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0127 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 21.000 | 105.000 | 21.740 | $10.00 | $0.00 | $217.40 | |
0128 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 2,369.000 | 2,369.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0129 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 434.000 | 518.000 | 21.740 | $10.00 | $0.00 | $217.40 | |
0130 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 732.000 | 732.000 | 0.000 | $52.00 | $0.00 | $0.00 | |
8103 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 46.800 | 0.000 | $7.22 | $0.00 | $0.00 | |
Subtotals For Category 0221/NBI 17607, BRIDGE NO. 52 | $135,450.00 | $581,184.80 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0222/NBI 18276, BRIDGE NO. 50 | ||||||||
0131 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 18.000 | 90.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0132 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 18.000 | 90.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0222/NBI 18276, BRIDGE NO. 50 | $0.00 | $0.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0223/NBI 18042, BRIDGE NO. 49E | ||||||||
0133 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0134 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $114,036.00 | $0.00 | $108,334.20 | |
0135 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0136 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 2.000 | 10.000 | 16.660 | 33.700 | $410.00 | $6,830.60 | $13,817.00 |
0137 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 527.000 | 527.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0138 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 61.000 | 69.000 | 7.610 | 15.220 | $10.00 | $76.10 | $152.20 |
Subtotals For Category 0223/NBI 18042, BRIDGE NO. 49E | $6,906.70 | $122,803.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0224/NBI 18067, BRIDGE NO. 46 | ||||||||
0139 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0140 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $113,118.00 | $0.00 | $107,462.10 | |
0141 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.150 | $500.00 | $0.00 | $75.00 | |
0142 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 70.000 | 70.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0143 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 8.000 | 8.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
8114 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 27.500 | 0.000 | $27.00 | $0.00 | $0.00 | |
Subtotals For Category 0224/NBI 18067, BRIDGE NO. 46 | $0.00 | $107,537.10 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0225/NBI 18089, BRIDGE NO. 45 | ||||||||
0144 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0145 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $119,331.00 | $0.00 | $113,364.45 | |
0146 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.100 | $500.00 | $0.00 | $50.00 | |
0147 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 28.000 | 140.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0148 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 1,337.000 | 1,337.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0149 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 177.000 | 289.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
8115 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 51.000 | 0.000 | $27.00 | $0.00 | $0.00 | |
Subtotals For Category 0225/NBI 18089, BRIDGE NO. 45 | $0.00 | $113,414.45 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0226/NBI 18054, BRIDGE NO. 43 | ||||||||
0150 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0151 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $112,540.00 | $56,270.00 | $56,270.00 |
0152 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | 0.050 | $500.00 | $25.00 | $25.00 |
0153 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 9.000 | 45.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0154 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 665.000 | 665.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0155 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 74.000 | 110.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
Subtotals For Category 0226/NBI 18054, BRIDGE NO. 43 | $56,295.00 | $56,295.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0227/NBI 18127, BRIDGE NO. 41 | ||||||||
0156 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0157 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.200 | 0.200 | $207,842.00 | $41,568.40 | $41,568.40 |
0158 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 0.050 | 0.050 | $1,000.00 | $50.00 | $50.00 |
0159 | PREPARATION OF CRACKS, ABOVE WATER | 520(A) 6058 | LF | 10.000 | 10.000 | 0.000 | $28.00 | $0.00 | $0.00 | |
0160 | EPOXY RESIN, ABOVE WATER | 520(C) 6060 | GAL | 0.500 | 0.500 | 0.000 | $92.00 | $0.00 | $0.00 | |
0161 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 5.000 | 25.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0162 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 5.000 | 25.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
8116 | SILICONE CONSTRUCTION JOINT | 509 6386 | LF | 0.000 | 30.000 | 0.000 | $27.00 | $0.00 | $0.00 | |
Subtotals For Category 0227/NBI 18127, BRIDGE NO. 41 | $41,618.40 | $41,618.40 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0228/NBI 18062, BRIDGE NO. 40 | ||||||||
0163 | CLSM BACKFILL | 501(G) 6309 | CY | 3.000 | 3.000 | 0.000 | $315.00 | $0.00 | $0.00 | |
0164 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0165 | CLASS A CONCRETE | 509(B) 1328 | CY | 9.200 | 9.200 | 0.000 | $1,800.00 | $0.00 | $0.00 | |
0166 | REINFORCING STEEL | 511(A) 1332 | LB | 2,274.000 | 2,274.000 | 0.000 | $1.75 | $0.00 | $0.00 | |
0167 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $103,700.00 | $0.00 | $98,515.00 | |
0168 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0169 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 6.000 | 30.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0170 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 35.000 | 59.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0171 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 200.000 | 200.000 | 0.000 | $55.00 | $0.00 | $0.00 | |
8104 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 9.200 | 0.000 | $7.22 | $0.00 | $0.00 | |
Subtotals For Category 0228/NBI 18062, BRIDGE NO. 40 | $0.00 | $99,015.00 | ||||||||
Fed/State Project Number: IMY-NBIP(436) | Project: 21901(04) | Category: 0229/NBI 18068, BRIDGE NO. 38 | ||||||||
0172 | STRUCTURAL STEEL | 506(A) 1322 | LB | 500.000 | 500.000 | 0.000 | $10.50 | $0.00 | $0.00 | |
0173 | CLASS A CONCRETE | 509(B) 1328 | CY | 11.200 | 11.200 | 0.000 | $1,800.00 | $0.00 | $0.00 | |
0174 | REINFORCING STEEL | 511(A) 1332 | LB | 3,071.000 | 3,071.000 | 0.000 | $1.75 | $0.00 | $0.00 | |
0175 | PAINTING EXISTING STRUCTURES | 512(A) 1323 | LSUM | 1.000 | 1.000 | 0.950 | $139,281.00 | $0.00 | $132,316.95 | |
0176 | COLLECTION AND HANDLING OF WASTE | 512(B) 6303 | LSUM | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0177 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 3.000 | 15.000 | 0.000 | $410.00 | $0.00 | $0.00 | |
0178 | (SP)CARBON FIBER-REINFORCED POLYMER | 524(A) 6610 | SF | 785.000 | 785.000 | 0.000 | $92.00 | $0.00 | $0.00 | |
0179 | (SP)CORROSION INHIBITOR(SURFACE APPLIED) | 535 6130 | SY | 126.000 | 138.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0180 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 540 4515 | EA | 246.000 | 246.000 | 0.000 | $55.00 | $0.00 | $0.00 | |
8105 | CLASS A CONCRETE | 509(B) 1328 | CY | 0.000 | 11.200 | 0.000 | $7.22 |