Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    01/02/2018
Contract ID: 100617   Estimate Number: 0036     Contract No: 610850
Residency: TULSA (08100)   Estimate Type: Progressive     Account No: 400800

Project Number(s): IMY-0044-2(396)225
Primary Job Piece No: 06374(44)
Contract Description: GRADE, DRAIN, SURFACE, AND BRIDGE I-44: FROM RIVERSIDE DRIVE TO EAST OF PEORIA AVENUE IN THE CITY OF TULSA. PROJECT LENGTH = 1.215 MILES.
Primary County: TULSA              
Name of Road: I-44              
Prime Contractor: BECCO CONTRACTORS, INC.              
    P.O. BOX 9159              
    TULSA , OK   74157              
Surety Company: MID-CONTINENT CASUALTY COMPANY              

Date Let: 11/18/2010 NTP Effective Date: 03/01/2011 Pay Period: 08/16/2013  TO  12/15/2017
Date Awarded: 12/06/2010 Date Work Began: 03/01/2011 Original Contract Time: 720
Date Contract Executed: 12/22/2010 Date Time Stopped: 03/04/2013 Current Time Charged: 736.00
Date NTP Issued: 01/05/2011 Completion Date: 03/04/2013 Current Time Allowed: 772.00
General Liability Expires: 03/01/2018 Workman's Comp Expires: 02/01/2018 Percent Time Used: 95.34 %
Specification Year: 1999     Date Approved: 01/02/2018

Bid Amount: $32,439,488.87 Total to Date Prev to Date This Estimate
Funds Available (Bid + Positive C/O): $33,209,755.06 Participating: $32,995,221.10 $32,965,109.20 $30,111.90
Percent Complete: 99.71 % Non Participating: $153,885.62 $153,885.62 $0.00
Unearned Balance: $96,208.93 Total Earnings: $33,149,106.72 $33,118,994.82 $30,111.90
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $33,149,106.72 $33,118,994.82 $30,111.90
Other Adjustments: $1,899,439.41 $1,813,514.10 $85,925.31
Liq Dam/Disincentive: $-1,935,000.00 $-1,935,000.00 $0.00
TOTAL: $33,113,546.13 $32,997,508.92 $116,037.21

Estimate Adjustment Detail

Contract ID: 100617   Estimate Number: 0036     Primary JP: 06374(44)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Addendum to (SP) CA000002 Approved 07/12/2011 0.0 $0.00
002 Powder Coating Hwy. Lighting Approved 09/14/2011 0.0 $57,911.70
003 Class B bridge deck repair Approved 05/08/2012 0.0 $63,980.79
004 Structural steel Approved 12/06/2011 0.0 $3,184.00
005 Material for Joint repair Approved 12/06/2011 0.0 $109,115.89
006 Temporary Roadway Lighting Approved 12/06/2011 0.0 $262,500.00
007 Labor & Equipment River Joint Approved 03/05/2012 0.0 $21,487.20
008 Median Barrier Light Pole Footing Approved 05/08/2012 0.0 $35,737.80
009 Waffle house demolition Approved 06/04/2012 0.0 $6,660.00
010 SS Manhole Approved 09/11/2012 0.0 $7,989.36
011 Water Vault Royal Arms Approved 04/01/2013 0.0 $37,688.12
012 Addition of B-Time and C-Time for Disincentive Only Approved 06/10/2013 129.0 $0.00
013 Non-participating precast concrete median barrier, Type I Approved 03/19/2013 0.0 $0.00
014 Pavement Smoothness Bonus Approved 08/13/2013 0.0 $31,549.06
017 Asphalt Binder Price Adjustment Approved 12/05/2017 0.0 $132,462.27


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0003 $-3,555.16
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0028 $-46,651.19
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0005 $-1,127.28
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0006 $-7,594.13
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0007 $-4,309.60
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0008 $-10,352.40
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0009 $-32,073.76
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0012 $-9,080.08
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0013 $-28,115.42
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0014 $-10,892.06
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0015 $-16,506.13
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0016 $-2,198.27
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0017 $-5,269.53
06374(44) 0019 Separator Fabric Stockpiled Material Closure 0017 $-224,223.57
06374(44) 0019 Separator Fabric Stockpiled Material Initial Payment 0017 $224,223.57
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0018 $-6,815.65
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0019 $-12,482.98
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0020 $-27,734.47
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0021 $-28,881.01
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0022 $-33,188.29
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0023 $-6,067.15
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0024 $-29,033.69
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0025 $-12,370.42
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0026 $-7,515.85
06374(44) 0019 Separator Fabric Stockpiled Material Adjustment 0027 $-8,213.34
06374(44) 0019 Separator Fabric Stockpiled Material Initial Payment 0003 $350,027.86
06374(44) 0028 Stockpiled Material Closure 0034 $0.01
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0007 $-8,844.51
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0008 $-6,310.70
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0009 $-18,850.52
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0010 $-10,478.25
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0013 $-2,348.49
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0014 $-4,624.78
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0015 $-2,636.14
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0016 $-83.04
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0017 $-4,650.86
06374(44) 0028 Dowel (Baskets) Stockpiled Material Closure 0017 $-102,813.30
06374(44) 0028 Dowel (Baskets) Stockpiled Material Closure 0017 $-41,906.51
06374(44) 0028 Dowel (Baskets) Stockpiled Material Initial Payment 0017 $144,719.81
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0018 $-7,177.08
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0019 $-3,052.37
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0020 $-9,938.00
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0021 $-571.72
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0022 $-1,750.61
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0024 $-6,062.27
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0025 $-10,068.52
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0026 $-10,972.85
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0027 $-9,384.28
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0028 $-5,240.41
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0031 $-66,362.64
06374(44) 0028 Dowel (Baskets) Stockpiled Material Adjustment 0032 $-9,488.21
06374(44) 0028 Dowel (Baskets) Stockpiled Material Initial Payment 0003 $156,989.73
06374(44) 0028 Dowel (Baskets) Stockpiled Material Initial Payment 0006 $41,906.51
06374(44) 0030 Stockpiled Material Closure 0034 $-0.04
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0015 $-64,739.09
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0016 $-11,900.30
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0017 $-54,468.71
06374(44) 0030 Reinforcing steel Stockpiled Material Closure 0017 $-333,538.63
06374(44) 0030 Reinforcing steel Stockpiled Material Initial Payment 0017 $333,538.63
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0018 $-49,382.67
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0019 $-6,854.63
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0020 $-11,624.03
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0023 $-127,634.09
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0024 $-32,020.66
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0025 $-23,495.41
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0027 $-2,735.11
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0028 $-25,323.28
06374(44) 0030 Reinforcing steel Stockpiled Material Initial Payment 0007 $483,443.45
06374(44) 0030 Reinforcing steel Stockpiled Material Adjustment 0014 $-73,265.43
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-2,234.21
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-2,079.49
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-500.00
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0003 $1,774.78
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0028 $-5,376.94
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0003 $0.00
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0027 $-2,150.78
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0005 $-386.87
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0002 $5,920.59
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0006 $-193.43
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0006 $1,095.00
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0006 $5,427.02
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0006 $500.00
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0025 $-2,150.78
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0007 $2,403.87
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0024 $-1,075.39
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0008 $2,234.21
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0008 $2,079.49
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0034 $-3,123.37
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0009 $-677.02
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0023 $-3,763.86
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0018 $-3,226.16
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0010 $5,560.00
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0012 $-290.15
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0032 $-2,150.78
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0015 $-1,354.04
06374(44) 0057 Manhole (4') Stockpiled Material Initial Payment 0017 $24,093.45
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-5,560.00
06374(44) 0057 Manhole (4') Stockpiled Material Adjustment 0017 $-1,075.39
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-3,019.08
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-1,774.78
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-1,095.00
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-5,427.02
06374(44) 0057 Manhole (4') Stockpiled Material Closure 0017 $-2,403.87
06374(44) 0058 MH 5' Stockpiled Material Adjustment 0012 $-868.74
06374(44) 0058 MH 5' Stockpiled Material Adjustment 0009 $-1,737.47
06374(44) 0058 MH 5' Stockpiled Material Initial Payment 0006 $2,266.62
06374(44) 0058 MH 5' Stockpiled Material Initial Payment 0002 $4,691.20
06374(44) 0058 MH 5' Stockpiled Material Closure 0034 $-486.52
06374(44) 0058 MH 5' Stockpiled Material Adjustment 0028 $-2,576.73
06374(44) 0058 MH 5' Stockpiled Material Adjustment 0027 $-1,288.36
06374(44) 0058 MH 5' Stockpiled Material Initial Payment 0017 $4,351.61
06374(44) 0058 MH 5' Stockpiled Material Closure 0017 $-2,266.62
06374(44) 0058 MH 5' Stockpiled Material Closure 0017 $-2,084.99
06374(44) 0059 Stockpiled Material Closure 0034 $-1.45
06374(44) 0059 MH 6' Stockpiled Material Adjustment 0016 $-922.94
06374(44) 0059 MH 6' Stockpiled Material Closure 0017 $-4,263.56
06374(44) 0059 MH 6' Stockpiled Material Initial Payment 0009 $4,263.56
06374(44) 0059 MH 6' Stockpiled Material Adjustment 0009 $-720.05
06374(44) 0059 MH 6' Stockpiled Material Initial Payment 0007 $2,118.08
06374(44) 0059 MH 6' Stockpiled Material Initial Payment 0006 $304.00
06374(44) 0059 MH 6' Stockpiled Material Adjustment 0004 $-1,440.10
06374(44) 0059 MH 6' Stockpiled Material Initial Payment 0017 $11,806.70
06374(44) 0059 MH 6' Stockpiled Material Closure 0017 $-5,121.06
06374(44) 0059 MH 6' Stockpiled Material Initial Payment 0002 $2,268.00
06374(44) 0059 MH 6' Stockpiled Material Closure 0034 $-11,806.70
06374(44) 0059 MH 6' Stockpiled Material Initial Payment 0003 $6,044.00
06374(44) 0059 MH 6' Stockpiled Material Adjustment 0016 $-106.40
06374(44) 0059 MH 6' Stockpiled Material Closure 0017 $-304.00
06374(44) 0059 MH 6' Stockpiled Material Closure 0017 $-2,118.08
06374(44) 0062 Stockpiled Material Closure 0034 $-1.80
06374(44) 0062 Spe. inlet drain Stockpiled Material Initial Payment 0002 $1,253.16
06374(44) 0062 Spe. inlet drain Stockpiled Material Initial Payment 0003 $1,093.07
06374(44) 0062 Spe. inlet drain Stockpiled Material Initial Payment 0006 $2,630.45
06374(44) 0062 Spe. inlet drain Stockpiled Material Closure 0017 $-1,253.16
06374(44) 0062 Spe. inlet drain Stockpiled Material Closure 0017 $-1,093.07
06374(44) 0062 Spe. inlet drain Stockpiled Material Closure 0017 $-2,630.45
06374(44) 0062 Spe. inlet drain Stockpiled Material Initial Payment 0017 $4,976.68
06374(44) 0062 Spe. inlet drain Stockpiled Material Adjustment 0020 $-1,841.97
06374(44) 0062 Spe. inlet drain Stockpiled Material Adjustment 0032 $-3,132.91
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0032 $-4,336.12
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0009 $-1,995.88
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0008 $2,873.53
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0007 $6,505.59
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0006 $8,917.47
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0006 $2,865.16
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0006 $-1,774.11
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0006 $2,420.72
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0005 $-887.06
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0004 $-665.29
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0003 $4,883.72
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0002 $9,779.52
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-2,873.53
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-6,505.59
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-8,917.47
06374(44) 0063 CICI 2(std) Stockpiled Material Initial Payment 0017 $31,814.55
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-2,865.16
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-2,420.72
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-4,883.72
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0017 $-3,348.36
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0017 $-867.22
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0015 $-1,108.82
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0028 $-3,468.90
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0027 $-2,601.67
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0025 $-1,734.45
06374(44) 0063 CICI 2(std) Stockpiled Material Adjustment 0018 $-3,468.90
06374(44) 0063 CICI 2(std) Stockpiled Material Closure 0034 $-15,337.29
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0006 $7,751.82
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0028 $-6,792.32
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-5,400.51
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-3,591.18
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0006 $5,400.51
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0007 $4,691.54
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-6,407.83
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0005 $-538.21
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0004 $-1,076.42
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0008 $3,591.18
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0003 $-807.32
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0003 $5,775.00
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0006 $-269.11
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0015 $-1,076.42
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0002 $12,597.26
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0012 $-538.21
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0006 $5,604.16
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0027 $-2,910.99
06374(44) 0064 CICI 2(B) Stockpiled Material Initial Payment 0017 $39,222.04
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0025 $-2,910.99
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-4,691.54
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0024 $-1,940.66
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0023 $-3,881.32
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0022 $-1,940.66
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0019 $-3,881.32
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-5,604.16
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0034 $-11,082.46
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-7,751.82
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0032 $-3,881.32
06374(44) 0064 CICI 2(B) Stockpiled Material Adjustment 0009 $-1,883.74
06374(44) 0064 CICI 2(B) Stockpiled Material Closure 0017 $-5,775.00
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0028 $-2,374.78
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0032 $-1,187.39
06374(44) 0065 CICI 2(D) Stockpiled Material Closure 0034 $-4,649.36
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0018 $-1,187.39
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0024 $-1,187.39
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0025 $-1,187.39
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0027 $-2,374.78
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0009 $-369.03
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0012 $-369.03
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0015 $-1,476.11
06374(44) 0065 CICI 2(D) Stockpiled Material Closure 0017 $-2,363.92
06374(44) 0065 CICI 2(D) Stockpiled Material Initial Payment 0017 $14,148.48
06374(44) 0065 CICI 2(D) Stockpiled Material Closure 0017 $-4,416.07
06374(44) 0065 CICI 2(D) Stockpiled Material Closure 0017 $-962.00
06374(44) 0065 CICI 2(D) Stockpiled Material Closure 0017 $-1,924.00
06374(44) 0065 CICI 2(D) Stockpiled Material Closure 0017 $-4,482.49
06374(44) 0065 CICI 2(D) Stockpiled Material Initial Payment 0002 $5,316.15
06374(44) 0065 CICI 2(D) Stockpiled Material Initial Payment 0003 $4,416.07
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0003 $-369.03
06374(44) 0065 CICI 2(D) Stockpiled Material Adjustment 0004 $-369.03
06374(44) 0065 CICI 2(D) Stockpiled Material Initial Payment 0006 $962.00
06374(44) 0065 CICI 2(D) Stockpiled Material Initial Payment 0006 $1,924.00
06374(44) 0065 CICI 2(D) Stockpiled Material Initial Payment 0007 $4,482.49
06374(44) 0066 INLET CICI DES. 2(2B) Stockpiled Material Closure 0017 $-825.00
06374(44) 0066 INLET CICI DES. 2(2B) Stockpiled Material Adjustment 0028 $-2,880.00
06374(44) 0066 INLET CICI DES. 2(2B) Stockpiled Material Initial Payment 0009 $2,055.00
06374(44) 0066 INLET CICI DES. 2(2B) Stockpiled Material Initial Payment 0006 $825.00
06374(44) 0066 INLET CICI DES. 2(2B) Stockpiled Material Initial Payment 0017 $2,880.00
06374(44) 0066 INLET CICI DES. 2(2B) Stockpiled Material Closure 0017 $-2,055.00
06374(44) 0067 Stockpiled Material Closure 0034 $-2.44
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Adjustment 0032 $-2,461.59
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Closure 0017 $-1,276.00
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Initial Payment 0006 $2,634.50
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Initial Payment 0006 $1,276.00
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Initial Payment 0017 $3,910.50
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Closure 0017 $-2,634.50
06374(44) 0067 CICI DES. 3 (2B) Stockpiled Material Adjustment 0017 $-1,446.47
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Closure 0034 $-14.58
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Adjustment 0023 $-1,528.68
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Initial Payment 0010 $5,870.60
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Adjustment 0015 $-445.87
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Adjustment 0028 $-1,528.68
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Initial Payment 0017 $9,186.66
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Closure 0017 $-5,870.60
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Closure 0017 $-951.53
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Closure 0017 $-2,364.53
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Adjustment 0022 $-4,586.04
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Initial Payment 0009 $951.53
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Initial Payment 0006 $2,810.40
06374(44) 0068 GPI TYPE 2(DES. 8) Stockpiled Material Adjustment 0017 $-1,528.68
06374(44) 0069 Stockpiled Material Closure 0034 $-0.45
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Initial Payment 0002 $2,405.00
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Initial Payment 0006 $1,609.94
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Closure 0034 $-1,166.45
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Adjustment 0009 $-1,069.34
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Initial Payment 0017 $1,166.45
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Adjustment 0009 $-443.49
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Adjustment 0003 $-1,335.21
06374(44) 0069 GPI type 2 (des.10) Stockpiled Material Closure 0017 $-1,166.45
06374(44) 0070 GPI Type 2(Des.14) Stockpiled Material Initial Payment 0006 $2,234.79
06374(44) 0070 GPI Type 2(Des.14) Stockpiled Material Adjustment 0009 $-2,234.79
06374(44) 0071 Stockpiled Material Closure 0034 $1.02
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Initial Payment 0002 $1,158.00
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Adjustment 0016 $-142.80
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Adjustment 0015 $-142.80
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Adjustment 0024 $-157.92
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Adjustment 0012 $-142.80
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Initial Payment 0017 $2,424.60
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Closure 0017 $-565.00
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Closure 0017 $-565.00
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Closure 0017 $-565.00
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Closure 0017 $-729.60
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Adjustment 0017 $-2,267.70
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Initial Payment 0007 $565.00
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Initial Payment 0006 $565.00
06374(44) 0071 inlet Median Barr.Des 2 Stockpiled Material Initial Payment 0006 $565.00
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Adjustment 0012 $-1,214.40
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Closure 0017 $-644.43
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Adjustment 0014 $-173.49
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Closure 0017 $-3,032.80
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Initial Payment 0002 $2,032.32
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Closure 0034 $-8,060.01
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Closure 0017 $-4,185.60
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Closure 0017 $-1,103.83
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Closure 0017 $-6,140.24
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Adjustment 0019 $-1,409.39
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Adjustment 0017 $-5,637.54
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Initial Payment 0008 $6,140.24
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Initial Payment 0007 $1,103.83
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Initial Payment 0017 $15,106.94
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Initial Payment 0006 $4,185.60
06374(44) 0072 inlet median barr des 2-2 Stockpiled Material Initial Payment 0006 $3,032.80
06374(44) 0073 Inlet W/Lrg.JCT.Box Stockpiled Material Closure 0017 $-2,969.85
06374(44) 0073 Inlet W/Lrg.JCT.Box Stockpiled Material Initial Payment 0017 $2,969.85
06374(44) 0073 Inlet W/Lrg.JCT.Box Stockpiled Material Initial Payment 0006 $2,969.85
06374(44) 0073 Inlet W/Lrg.JCT.Box Stockpiled Material Adjustment 0032 $-2,969.85
06374(44) 0074 Stockpiled Material Closure 0034 $2.56
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Initial Payment 0010 $1,987.84
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Initial Payment 0006 $3,182.02
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Adjustment 0028 $-1,435.49
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Initial Payment 0017 $5,115.86
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Closure 0017 $-3,182.02
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Closure 0017 $-1,987.84
06374(44) 0074 Inlet W/small Juc.Box Stockpiled Material Adjustment 0032 $-3,682.93
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0009 $-1,348.16
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0027 $-1,079.57
06374(44) 0075 inlet smd-type1 Stockpiled Material Initial Payment 0002 $3,641.24
06374(44) 0075 inlet smd-type1 Stockpiled Material Initial Payment 0003 $2,044.33
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0005 $-337.04
06374(44) 0075 inlet smd-type1 Stockpiled Material Initial Payment 0006 $3,257.40
06374(44) 0075 inlet smd-type1 Stockpiled Material Initial Payment 0008 $2,716.89
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0028 $-2,159.15
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0032 $-1,079.57
06374(44) 0075 inlet smd-type1 Stockpiled Material Closure 0034 $-3,160.19
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0017 $-1,079.57
06374(44) 0075 inlet smd-type1 Stockpiled Material Closure 0017 $-2,716.89
06374(44) 0075 inlet smd-type1 Stockpiled Material Closure 0017 $-1,619.00
06374(44) 0075 inlet smd-type1 Stockpiled Material Closure 0017 $-2,044.33
06374(44) 0075 inlet smd-type1 Stockpiled Material Closure 0017 $-3,257.40
06374(44) 0075 inlet smd-type1 Stockpiled Material Initial Payment 0017 $9,637.62
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0023 $-1,079.57
06374(44) 0075 inlet smd-type1 Stockpiled Material Adjustment 0015 $-337.04
06374(44) 0076 Stockpiled Material Closure 0034 $-1.84
06374(44) 0076 inlet smd-type2 Stockpiled Material Adjustment 0015 $-6.22
06374(44) 0076 inlet smd-type2 Stockpiled Material Initial Payment 0002 $560.00
06374(44) 0076 inlet smd-type2 Stockpiled Material Adjustment 0004 $-186.68
06374(44) 0076 inlet smd-type2 Stockpiled Material Adjustment 0005 $-186.68
06374(44) 0076 inlet smd-type2 Stockpiled Material Initial Payment 0017 $1,113.78
06374(44) 0076 inlet smd-type2 Stockpiled Material Initial Payment 0007 $560.00
06374(44) 0076 inlet smd-type2 Stockpiled Material Closure 0034 $-1,113.78
06374(44) 0076 inlet smd-type2 Stockpiled Material Closure 0017 $-553.78
06374(44) 0076 inlet smd-type2 Stockpiled Material Closure 0017 $-560.00
06374(44) 0076 inlet smd-type2 Stockpiled Material Adjustment 0015 $-184.80
06374(44) 0076 inlet smd-type2 Stockpiled Material Initial Payment 0006 $560.00
06374(44) 0077 Stockpiled Material Closure 0034 $-0.34
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0027 $-633.33
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0014 $-70.37
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0015 $-985.18
06374(44) 0077 Fram Grate CICI Stockpiled Material Initial Payment 0007 $10,070.38
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0028 $-844.44
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0032 $-1,308.98
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0017 $-1,337.03
06374(44) 0077 Fram Grate CICI Stockpiled Material Closure 0017 $-6,622.26
06374(44) 0077 Fram Grate CICI Stockpiled Material Initial Payment 0017 $6,622.26
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0018 $-140.74
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0019 $-703.70
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0020 $-879.63
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0025 $-774.07
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0010 $-2,251.83
06374(44) 0077 Fram Grate CICI Stockpiled Material Adjustment 0013 $-140.74
06374(44) 0078 Stockpiled Material Closure 0034 $0.15
06374(44) 0078 CICI Stockpiled Material Adjustment 0027 $-697.09
06374(44) 0078 CICI Stockpiled Material Adjustment 0014 $-87.14
06374(44) 0078 CICI Stockpiled Material Adjustment 0015 $-1,045.65
06374(44) 0078 CICI Stockpiled Material Initial Payment 0007 $9,096.98
06374(44) 0078 CICI Stockpiled Material Adjustment 0028 $-784.23
06374(44) 0078 CICI Stockpiled Material Adjustment 0032 $-2,169.74
06374(44) 0078 CICI Stockpiled Material Adjustment 0017 $-479.25
06374(44) 0078 CICI Stockpiled Material Closure 0017 $-5,742.19
06374(44) 0078 CICI Stockpiled Material Initial Payment 0017 $5,742.19
06374(44) 0078 CICI Stockpiled Material Adjustment 0018 $-87.14
06374(44) 0078 CICI Stockpiled Material Adjustment 0019 $-304.98
06374(44) 0078 CICI Stockpiled Material Adjustment 0020 $-304.98
06374(44) 0078 CICI Stockpiled Material Adjustment 0025 $-914.93
06374(44) 0078 CICI Stockpiled Material Adjustment 0010 $-2,004.16
06374(44) 0078 CICI Stockpiled Material Adjustment 0013 $-217.84
06374(44) 0106 Impact att. Stockpiled Material Initial Payment 0008 $98,970.24
06374(44) 0106 Impact att. Stockpiled Material Adjustment 0031 $-18,325.99
06374(44) 0106 Impact att. Stockpiled Material Closure 0017 $-98,970.24
06374(44) 0106 Impact att. Stockpiled Material Initial Payment 0017 $98,970.24
06374(44) 0106 Impact att. Stockpiled Material Closure 0034 $-7,340.27
06374(44) 0106 Impact att. Stockpiled Material Adjustment 0020 $-36,651.99
06374(44) 0106 Impact att. Stockpiled Material Adjustment 0029 $-36,651.99
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0007 $-17,414.19
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0006 $-14,177.03
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0005 $-12,608.76
06374(44) 0116 18" ductileiron pipe Stockpiled Material Initial Payment 0004 $164,950.23
06374(44) 0116 18" ductileiron pipe Stockpiled Material Initial Payment 0004 $82,097.58
06374(44) 0116 18" ductileiron pipe Stockpiled Material Closure 0034 $-175,921.98
06374(44) 0116 18" ductileiron pipe Stockpiled Material Initial Payment 0017 $175,921.98
06374(44) 0116 18" ductileiron pipe Stockpiled Material Closure 0017 $-164,950.23
06374(44) 0116 18" ductileiron pipe Stockpiled Material Closure 0017 $-10,971.75
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0015 $-1,482.45
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0014 $-3,033.05
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0009 $-5,689.30
06374(44) 0116 18" ductileiron pipe Stockpiled Material Adjustment 0008 $-16,721.05
06374(44) 0119 6" DIP Stockpiled Material Initial Payment 0004 $23,665.37
06374(44) 0119 6" DIP Stockpiled Material Adjustment 0012 $-22,562.27
06374(44) 0119 6" DIP Stockpiled Material Adjustment 0006 $-1,026.14
06374(44) 0119 6" DIP Stockpiled Material Adjustment 0007 $-76.96
06374(44) 0121 12" DIP Stockpiled Material Adjustment 0006 $-9,829.46
06374(44) 0121 12" DIP Stockpiled Material Initial Payment 0004 $43,503.44
06374(44) 0121 12" DIP Stockpiled Material Adjustment 0012 $-13,876.89
06374(44) 0121 12" DIP Stockpiled Material Closure 0017 $-19,797.09
06374(44) 0122 16" DIP Stockpiled Material Initial Payment 0004 $53,273.95
06374(44) 0122 16" DIP Stockpiled Material Adjustment 0012 $-10,615.79
06374(44) 0122 16" DIP Stockpiled Material Closure 0017 $-42,658.16
06374(44) 0122 16" DIP Stockpiled Material Initial Payment 0017 $42,658.16
06374(44) 0122 16" DIP Stockpiled Material Adjustment 0033 $-42,658.16
06374(44) 0124 6" PVC Stockpiled Material Adjustment 0004 $-11,191.36
06374(44) 0124 6" PVC Stockpiled Material Initial Payment 0017 $5,115.29
06374(44) 0124 6" PVC Stockpiled Material Adjustment 0033 $-5,115.29
06374(44) 0124 6" PVC Stockpiled Material Closure 0017 $-5,115.29
06374(44) 0124 6" PVC Stockpiled Material Adjustment 0007 $-1,119.14
06374(44) 0124 6" PVC Stockpiled Material Initial Payment 0004 $17,425.79
06374(44) 0126 6" Gate Valve Stockpiled Material Closure 0034 $-1,792.12
06374(44) 0126 6" Gate Valve Stockpiled Material Adjustment 0033 $796.34
06374(44) 0126 6" Gate Valve Stockpiled Material Initial Payment 0017 $995.78
06374(44) 0126 6" Gate Valve Stockpiled Material Closure 0017 $-995.78
06374(44) 0126 6" Gate Valve Stockpiled Material Adjustment 0012 $-7,566.86
06374(44) 0126 6" Gate Valve Stockpiled Material Adjustment 0007 $-398.26
06374(44) 0126 6" Gate Valve Stockpiled Material Initial Payment 0004 $8,960.90
06374(44) 0139 P.C. Beams Br. A Stockpiled Material Adjustment 0017 $-238,751.22
06374(44) 0139 P.C. Beams Br. A Stockpiled Material Initial Payment 0003 $376,455.15
06374(44) 0139 P.C. Beams Br. A Stockpiled Material Adjustment 0013 $-137,703.93
06374(44) 0139 P.C. Beams Br. A Stockpiled Material Initial Payment 0017 $238,751.22
06374(44) 0139 P.C. Beams Br. A Stockpiled Material Closure 0017 $-238,751.22
06374(44) 0168 Stockpiled Material Closure 0034 $0.06
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Adjustment 0026 $-232,119.30
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Initial Payment 0017 $396,373.17
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Initial Payment 0004 $237,537.27
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Adjustment 0020 $-164,253.93
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Initial Payment 0003 $158,835.90
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Closure 0017 $-237,537.27
06374(44) 0168 P.C.Beams Br. B Stockpiled Material Closure 0017 $-158,835.90
06374(44) 0171 Reinf. steel for F-shape par. Stockpiled Material Initial Payment 0023 $10,860.92
06374(44) 0171 Reinf. steel for F-shape par. Stockpiled Material Adjustment 0029 $-10,860.92
06374(44) 0176 Br. Stockpiled Material Closure 0020 $-94,069.50
06374(44) 0176 Br. Stockpiled Material Closure 0017 $-94,069.50
06374(44) 0176 Br. Stockpiled Material Initial Payment 0017 $94,069.50
06374(44) 0176 Br. Stockpiled Material Initial Payment 0012 $94,069.50
06374(44) 0180 Epox. Reinf. Br. B Stockpiled Material Adjustment 0028 $-27,118.45
06374(44) 0180 Epox. Reinf. Br. B Stockpiled Material Adjustment 0031 $-3,665.44
06374(44) 0180 Epox. Reinf. Br. B Stockpiled Material Adjustment 0025 $-9,500.88
06374(44) 0180 Epox. Reinf. Br. B Stockpiled Material Closure 0034 $-4,045.18
06374(44) 0180 Epox. Reinf. Br. B Stockpiled Material Initial Payment 0023 $61,667.98
06374(44) 0180 Epox. Reinf. Br. B Stockpiled Material Adjustment 0023 $-17,338.03
06374(44) 0200 Stru. steel Stockpiled Material Initial Payment 0017 $335,527.10
06374(44) 0200 Stru. steel Stockpiled Material Initial Payment 0006 $830,070.00
06374(44) 0200 Stru. steel Stockpiled Material Closure 0017 $-335,527.10
06374(44) 0200 Stru. steel Stockpiled Material Adjustment 0024 $-335,527.10
06374(44) 0200 Stru. steel Stockpiled Material Adjustment 0012 $-494,542.90
06374(44) 0212 Abut. bearing assembly Stockpiled Material Initial Payment 0017 $3,676.12
06374(44) 0212 Abut. bearing assembly Stockpiled Material Closure 0034 $-2,225.03
06374(44) 0212 Abut. bearing assembly Stockpiled Material Adjustment 0024 $-1,451.09
06374(44) 0212 Abut. bearing assembly Stockpiled Material Initial Payment 0013 $2,829.69
06374(44) 0212 Abut. bearing assembly Stockpiled Material Closure 0017 $-3,676.12
06374(44) 0212 Abut. bearing assembly Stockpiled Material Adjustment 0013 $846.43
06374(44) 0213 expansion bearing assembly Stockpiled Material Closure 0017 $-20,506.81
06374(44) 0213 expansion bearing assembly Stockpiled Material Initial Payment 0017 $20,506.81
06374(44) 0213 expansion bearing assembly Stockpiled Material Closure 0034 $-7,372.34
06374(44) 0213 expansion bearing assembly Stockpiled Material Adjustment 0024 $-13,134.47
06374(44) 0213 expansion bearing assembly Stockpiled Material Initial Payment 0013 $25,613.70
06374(44) 0213 expansion bearing assembly Stockpiled Material Adjustment 0013 $-5,106.89
06374(44) 0245 Extruded Panel groundmount Stockpiled Material Adjustment 0030 $-2,580.48
06374(44) 0245 Extruded Panel groundmount Stockpiled Material Initial Payment 0020 $2,580.48
06374(44) 0246 Extruded Panel overhead Stockpiled Material Adjustment 0030 $-21,046.00
06374(44) 0246 Extruded Panel overhead Stockpiled Material Initial Payment 0020 $21,046.00
06374(44) 0267 Ped. heads Stockpiled Material Initial Payment 0013 $54,358.00
06374(44) 0267 Ped. heads Stockpiled Material Initial Payment 0015 $12,727.86
06374(44) 0267 Ped. heads Stockpiled Material Initial Payment 0008 $42,497.00
06374(44) 0267 Ped. heads Stockpiled Material Initial Payment 0008 $15,080.00
06374(44) 0267 Ped. heads Stockpiled Material Initial Payment 0012 $56,989.29
06374(44) 0267 Ped. heads Stockpiled Material Closure 0017 $-14,577.33
06374(44) 0267 Ped. heads Stockpiled Material Closure 0017 $-42,497.00
06374(44) 0267 Ped. heads Stockpiled Material Closure 0017 $-56,989.29
06374(44) 0267 Ped. heads Stockpiled Material Closure 0017 $-54,358.00
06374(44) 0267 Ped. heads Stockpiled Material Closure 0017 $-12,727.86
06374(44) 0267 Ped. heads Stockpiled Material Initial Payment 0017 $181,149.48
06374(44) 0267 Ped. heads Stockpiled Material Closure 0034 $-13,910.50
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0026 $-20,150.08
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0022 $-16,118.95
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0031 $-20,150.08
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0030 $-20,150.08
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0028 $-30,225.13
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0024 $-60,444.66
06374(44) 0267 Ped. heads Stockpiled Material Adjustment 0014 $-502.67
06374(44) 0276 Stockpiled Material Closure 0034 $1.90
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0028 $-4,814.79
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0030 $-19,259.16
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0031 $-28,888.74
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0033 $-21,958.67
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Initial Payment 0015 $131,734.00
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Closure 0017 $-131,734.00
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Initial Payment 0017 $131,734.00
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0020 $-6,740.71
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0022 $-33,703.54
06374(44) 0276 40' MTG.Ht.Hl.PTP. Stockpiled Material Adjustment 0026 $-16,370.29
06374(44) 0277 Stockpiled Material Closure 0034 $-0.01
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0016 $-6,194.09
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0030 $-5,946.65
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0028 $-1,238.88
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0022 $-1,734.44
06374(44) 0277 Breakaway base Stockpiled Material Initial Payment 0015 $25,422.00
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0020 $-2,477.77
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0031 $-644.64
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0026 $-3,716.65
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0018 $-1,238.88
06374(44) 0277 Breakaway base Stockpiled Material Adjustment 0024 $-2,229.99
06374(44) 0277 Breakaway base Stockpiled Material Initial Payment 0017 $19,227.91
06374(44) 0277 Breakaway base Stockpiled Material Closure 0017 $-19,227.91
06374(44) 0278 Stockpiled Material Closure 0034 $-0.50
06374(44) 0278 Roadway Luminaire Stockpiled Material Adjustment 0033 $-5,766.88
06374(44) 0278 Roadway Luminaire Stockpiled Material Adjustment 0031 $-14,973.24
06374(44) 0278 Roadway Luminaire Stockpiled Material Adjustment 0030 $-16,082.37
06374(44) 0278 Roadway Luminaire Stockpiled Material Adjustment 0028 $-3,327.39
06374(44) 0278 Roadway Luminaire Stockpiled Material Adjustment 0026 $-52,683.62
06374(44) 0278 Roadway Luminaire Stockpiled Material Initial Payment 0017 $92,834.00
06374(44) 0278 Roadway Luminaire Stockpiled Material Closure 0017 $-92,834.00
06374(44) 0278 Roadway Luminaire Stockpiled Material Initial Payment 0012 $92,834.00
06374(44) 0279 Stockpiled Material Closure 0034 $-0.17
06374(44) 0279 Underpass Luminaire Stockpiled Material Initial Payment 0012 $6,560.00
06374(44) 0279 Underpass Luminaire Stockpiled Material Closure 0017 $-6,560.00
06374(44) 0279 Underpass Luminaire Stockpiled Material Adjustment 0033 $-183.27
06374(44) 0279 Underpass Luminaire Stockpiled Material Adjustment 0030 $-6,376.56
06374(44) 0279 Underpass Luminaire Stockpiled Material Initial Payment 0017 $6,560.00
06374(44) 0281 Stockpiled Material Closure 0034 $0.01
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0031 $-3,644.59
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0030 $-6,128.64
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0020 $-7,186.88
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0022 $-2,671.00
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0024 $-2,958.85
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0018 $-282.20
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Initial Payment 0017 $33,339.95
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Closure 0017 $-33,339.95
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0026 $-3,964.88
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0028 $-1,949.28
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Initial Payment 0008 $37,601.14
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0016 $-4,261.19
06374(44) 0281 1/C no.4 ele.conduit Stockpiled Material Adjustment 0033 $-4,553.64
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Milstone Adjust. (C/O) 0034 $1,935,000.00
Subtotals For Contract Adjustments $1,935,000.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0005 -796.00 $1.50 $-1,194.00
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0014 -150.00 $1.50 $-225.00
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0017 -96.00 $1.50 $-144.00
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0019 -425.00 $1.50 $-637.50
06374(44) 0005 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0020 246.00 $1.50 $369.00
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0023 -100.00 $1.50 $-150.00
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0027 -210.00 $1.50 $-315.00
06374(44) 0005 TEMPORARY SILT FENCE * Missing Material Certification 0032 1,815.00 $1.50 $2,722.50
06374(44) 0005 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0035 284.00 $1.50 $426.00
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0004 1,001.02 $0.42 $426.06
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0007 663.89 $2.80 $1,859.31
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0008 1,318.72 $2.80 $3,693.25
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0009 1,625.11 $2.80 $4,551.33
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0010 303.59 $2.80 $850.24
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0013 4,056.04 $2.80 $11,359.47
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0014 1,804.27 $2.80 $5,053.09
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0015 514.01 $2.67 $1,375.30
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0016 406.32 $2.67 $1,087.16
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0017 3,168.40 $2.23 $7,091.29
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0018 1,103.97 $2.23 $2,470.83
06374(44) 0018 OPEN GRADED BITUMINOUS BASE * Material Discrepancy Adjustments 0019 -43.94 $38.00 $-1,669.72
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0019 43.94 $2.23 $98.34
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0020 685.39 $2.23 $1,533.99
06374(44) 0018 OPEN GRADED BITUMINOUS BASE * Material Discrepancy Adjustments 0020 43.94 $38.00 $1,669.72
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0021 237.08 $2.23 $530.62
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0022 4,197.08 $2.23 $9,393.61
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0023 977.57 $2.30 $2,249.03
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0024 2,520.07 $2.30 $5,797.75
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0025 32.61 $2.30 $75.02
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0026 214.92 $2.30 $494.45
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0027 2,705.94 $2.92 $7,916.58
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0028 1,259.33 $2.92 $3,684.33
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0029 1,028.75 $3.42 $3,524.12
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0030 1,560.30 $3.42 $5,345.01
06374(44) 0018 OPEN GRADED BITUMINOUS BASE Asphalt Binder Adjustment 0031 739.68 $3.55 $2,626.33
06374(44) 0018 OPEN GRADED BITUMINOUS BASE * HMA Deduction as per Sec. 411 0031 0.00 $0.00 $-46,280.00
06374(44) 0023 (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) Asphalt Binder Adjustment 0016 1,089.45 $3.95 $4,314.15
06374(44) 0023 (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) Asphalt Binder Adjustment 0021 132.58 $3.31 $439.16
06374(44) 0023 (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) Asphalt Binder Adjustment 0025 567.98 $3.40 $1,933.93
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0012 246.89 $4.70 $1,161.63
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0015 44.65 $4.49 $200.70
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0016 1,005.06 $4.49 $4,517.80
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0021 117.47 $3.76 $441.69
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0023 13.41 $3.86 $51.83
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0025 388.03 $3.86 $1,499.76
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0026 30.77 $3.86 $118.93
06374(44) 0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0029 114.18 $5.75 $657.11
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $-37.97
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0006 30.14 $1.97 $59.53
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0007 43.77 $4.70 $205.94
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0008 103.52 $4.70 $487.07
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0009 187.16 $4.70 $880.60
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0010 375.96 $4.70 $1,768.91
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0012 147.47 $4.70 $693.85
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0014 210.35 $4.70 $989.71
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0015 113.90 $4.49 $511.99
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0016 1,377.01 $4.49 $6,189.73
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0018 29.50 $3.76 $110.92
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0020 106.40 $3.76 $400.07
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0021 371.60 $3.76 $1,397.24
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0022 125.85 $3.76 $473.20
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0023 104.71 $3.86 $404.71
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0025 425.15 $3.86 $1,643.23
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0027 226.90 $4.91 $1,115.23
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * Missing Material Certification 0030 -127.38 $48.00 $-6,114.24
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0030 127.38 $5.75 $733.08
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * Missing Material Certification 0032 -57.64 $48.00 $-2,766.72
06374(44) 0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0032 57.64 $5.96 $343.83
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0006 0.00 $0.00 $-6,152.78
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0006 2,774.83 $2.25 $6,263.35
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0008 56.20 $5.37 $302.20
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0009 177.24 $5.37 $953.06
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0010 363.63 $5.37 $1,955.31
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0011 160.99 $5.37 $865.68
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0012 183.28 $5.37 $985.53
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0014 14.06 $5.37 $75.60
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0015 126.96 $5.13 $652.22
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0016 883.08 $5.13 $4,536.56
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0018 15.31 $4.29 $65.79
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0020 108.34 $4.29 $465.56
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Material Discrepancy Adjustments 0021 -230.92 $66.00 $-15,240.72
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0021 528.44 $4.29 $2,270.81
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0022 67.08 $4.29 $288.26
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0023 56.58 $4.41 $249.93
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0025 281.19 $4.41 $1,242.07
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0027 4.10 $5.61 $23.03
06374(44) 0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0029 95.18 $6.57 $626.02
06374(44) 0042 SOUND BARRIER WALL * Missing Material Certification 0019 -1,337.22 $155.00 $-207,269.10
06374(44) 0042 SOUND BARRIER WALL * Material Discrepancy Adjustments 0020 1,337.22 $155.00 $207,269.10
06374(44) 0048 1'-8" COMB. CURB & GUTTER (6" BARRIER) * Missing Material Certification 0032 -730.00 $17.00 $-12,410.00
06374(44) 0054 6" CONCRETE DIVIDING STRIP * Missing Material Certification 0026 -268.36 $38.00 $-10,197.68
06374(44) 0054 6" CONCRETE DIVIDING STRIP * Missing Material Certification 0030 268.36 $38.00 $10,197.68
06374(44) 0056 (PL)TACTILE WARNING DEVICE-NEW * Missing Material Certification 0025 -173.00 $35.00 $-6,055.00
06374(44) 0056 (PL)TACTILE WARNING DEVICE-NEW * Missing Material Certification 0028 -16.00 $35.00 $-560.00
06374(44) 0056 (PL)TACTILE WARNING DEVICE-NEW * Missing Material Certification 0030 -40.00 $35.00 $-1,400.00
06374(44) 0056 (PL)TACTILE WARNING DEVICE-NEW * Missing Material Certification 0031 189.00 $35.00 $6,615.00
06374(44) 0056 (PL)TACTILE WARNING DEVICE-NEW * Missing Material Certification 0032 -139.00 $35.00 $-4,865.00
06374(44) 0061 MANHOLE FRAME & COVER * Missing Material Certification 0017 -2.00 $350.00 $-700.00
06374(44) 0061 MANHOLE FRAME & COVER * Missing Material Certification 0018 -4.00 $350.00 $-1,400.00
06374(44) 0061 MANHOLE FRAME & COVER * Missing Material Certification 0019 -3.00 $350.00 $-1,050.00
06374(44) 0061 MANHOLE FRAME & COVER * Material Discrepancy Adjustments 0020 -14.00 $350.00 $-4,900.00
06374(44) 0061 MANHOLE FRAME & COVER * Material Discrepancy Adjustments 0027 23.00 $350.00 $8,050.00
06374(44) 0062 (PL)SPECIAL INLET DRAIN * Material Discrepancy Adjustments 0020 -1.00 $5,000.00 $-5,000.00
06374(44) 0062 (PL)SPECIAL INLET DRAIN * Missing Material Certification 0032 -2.00 $5,000.00 $-10,000.00
06374(44) 0063 INLET CICI DES. 2 (STD) * Missing Material Certification 0032 -2.00 $2,300.00 $-4,600.00
06374(44) 0064 INLET CICI DES. 2 (B) * Missing Material Certification 0028 -7.00 $2,800.00 $-19,600.00
06374(44) 0064 INLET CICI DES. 2 (B) * Missing Material Certification 0032 -4.00 $2,800.00 $-11,200.00
06374(44) 0071 INLET MEDIAN BARRIER DES. 2 * Missing Material Certification 0024 -1.00 $3,100.00 $-3,100.00
06374(44) 0071 INLET MEDIAN BARRIER DES. 2 * Missing Material Certification 0027 -2.00 $3,100.00 $-6,200.00
06374(44) 0071 INLET MEDIAN BARRIER DES. 2 * Missing Material Certification 0032 -1.00 $1,500.00 $-1,500.00
06374(44) 0072 INLET MEDIAN BARRIER DES. 2-2 * Missing Material Certification 0019 -1.00 $5,100.00 $-5,100.00
06374(44) 0082 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0012 -1,227.00 $50.00 $-61,350.00
06374(44) 0082 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0013 1,227.00 $50.00 $61,350.00
06374(44) 0082 18" R.C.PIPE CLASS III * Missing Material Certification 0015 -347.00 $50.00 $-17,350.00
06374(44) 0082 18" R.C.PIPE CLASS III * Missing Material Certification 0016 -55.00 $50.00 $-2,750.00
06374(44) 0082 18" R.C.PIPE CLASS III * Missing Material Certification 0017 -797.00 $50.00 $-39,850.00
06374(44) 0082 18" R.C.PIPE CLASS III * Missing Material Certification 0018 -350.00 $50.00 $-17,500.00
06374(44) 0082 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0022 1,549.00 $50.00 $77,450.00
06374(44) 0083 24" R.C.PIPE CLASS III * Missing Material Certification 0018 -274.00 $55.00 $-15,070.00
06374(44) 0083 24" R.C.PIPE CLASS III * Missing Material Certification 0023 274.00 $55.00 $15,070.00
06374(44) 0103 EDGE DRAIN CONDUIT-PERFORATED * Missing Material Certification 0015 -788.00 $5.00 $-3,940.00
06374(44) 0103 EDGE DRAIN CONDUIT-PERFORATED * Missing Material Certification 0016 -1,709.00 $5.00 $-8,545.00
06374(44) 0103 EDGE DRAIN CONDUIT-PERFORATED * Missing Material Certification 0017 -225.00 $5.00 $-1,125.00
06374(44) 0103 EDGE DRAIN CONDUIT-PERFORATED * Missing Material Certification 0019 -450.00 $5.00 $-2,250.00
06374(44) 0103 EDGE DRAIN CONDUIT-PERFORATED * Missing Material Certification 0023 15,860.00 $5.00 $79,300.00
06374(44) 0103 EDGE DRAIN CONDUIT-PERFORATED * Material Discrepancy Adjustments 0024 -12,688.00 $5.00 $-63,440.00
06374(44) 0109 MANHOLE (4' DIAMETER) * Missing Material Certification 0031 -4.00 $2,500.00 $-10,000.00
06374(44) 0109 MANHOLE (4' DIAMETER) * Material Discrepancy Adjustments 0032 1.00 $2,500.00 $2,500.00
06374(44) 0109 MANHOLE (4' DIAMETER) * Material Discrepancy Adjustments 0033 3.00 $2,500.00 $7,500.00
06374(44) 0140 APPROACH SLAB * Missing Material Certification 0019 -248.00 $130.00 $-32,240.00
06374(44) 0140 APPROACH SLAB * Material Discrepancy Adjustments 0025 124.00 $130.00 $16,120.00
06374(44) 0140 APPROACH SLAB * Material Discrepancy Adjustments 0027 124.00 $130.00 $16,120.00
06374(44) 0141 SEALED EXPANSION JOINT * Missing Material Certification 0019 -84.30 $215.00 $-18,124.50
06374(44) 0141 SEALED EXPANSION JOINT * Material Discrepancy Adjustments 0025 84.30 $215.00 $18,124.50
06374(44) 0142 42" F-SHAPED PARAPET * Missing Material Certification 0019 -981.60 $47.00 $-46,135.20
06374(44) 0142 42" F-SHAPED PARAPET * Material Discrepancy Adjustments 0025 490.80 $47.00 $23,067.60
06374(44) 0142 42" F-SHAPED PARAPET * Material Discrepancy Adjustments 0027 490.80 $47.00 $23,067.60
06374(44) 0143 STRUCTURAL STEEL * Missing Material Certification 0017 -2,710.00 $1.50 $-4,065.00
06374(44) 0143 STRUCTURAL STEEL * Missing Material Certification 0023 2,710.00 $1.50 $4,065.00
06374(44) 0147 SLOPE WALL (5") * Material Discrepancy Adjustments 0025 -387.00 $70.00 $-27,090.00
06374(44) 0147 SLOPE WALL (5") * Material Discrepancy Adjustments 0026 387.00 $70.00 $27,090.00
06374(44) 0154 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0029 -2,474.00 $3.00 $-7,422.00
06374(44) 0154 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0031 24,740.00 $3.00 $74,220.00
06374(44) 0154 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0032 -22,266.00 $3.00 $-66,798.00
06374(44) 0158 (SP) SEALER RESIN * Material Discrepancy Adjustments 0020 -17.50 $80.00 $-1,400.00
06374(44) 0158 (SP) SEALER RESIN * Material Discrepancy Adjustments 0031 17.50 $80.00 $1,400.00
06374(44) 0162 6" NON-PERF.PIPE UNDERDRAIN RND. * Missing Material Certification 0017 -25.00 $15.00 $-375.00
06374(44) 0162 6" NON-PERF.PIPE UNDERDRAIN RND. * Material Discrepancy Adjustments 0019 25.00 $15.00 $375.00
06374(44) 0167 CLSM BACKFILL * Missing Material Certification 0026 -278.00 $75.00 $-20,850.00
06374(44) 0167 CLSM BACKFILL * Material Discrepancy Adjustments 0027 178.00 $75.00 $13,350.00
06374(44) 0167 CLSM BACKFILL * Material Discrepancy Adjustments 0032 100.00 $75.00 $7,500.00
06374(44) 0171 42" F-SHAPED PARAPET * Material Discrepancy Adjustments 0029 -1,082.00 $47.00 $-50,854.00
06374(44) 0171 42" F-SHAPED PARAPET * Material Discrepancy Adjustments 0030 1,082.00 $47.00 $50,854.00
06374(44) 0174 STRUCTURAL STEEL * Missing Material Certification 0026 -3,000.00 $1.50 $-4,500.00
06374(44) 0174 STRUCTURAL STEEL * Material Discrepancy Adjustments 0028 2,807.00 $1.50 $4,210.50
06374(44) 0180 EPOXY COATED REINFORCING STEEL * Missing Material Certification 0028 -109,348.60 $0.80 $-87,478.88
06374(44) 0180 EPOXY COATED REINFORCING STEEL * Missing Material Certification 0031 109,348.60 $0.80 $87,478.88
06374(44) 0185 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0029 -2,971.00 $3.00 $-8,913.00
06374(44) 0185 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0031 2,971.00 $3.00 $8,913.00
06374(44) 0189 (SP) SEALER RESIN * Material Discrepancy Adjustments 0029 -19.50 $80.00 $-1,560.00
06374(44) 0189 (SP) SEALER RESIN * Material Discrepancy Adjustments 0031 2.50 $80.00 $200.00
06374(44) 0199 42" F-SHAPED PARAPET * Missing Material Certification 0017 -337.00 $47.00 $-15,839.00
06374(44) 0199 42" F-SHAPED PARAPET * Material Discrepancy Adjustments 0025 337.00 $47.00 $15,839.00
06374(44) 0208 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0029 -2,121.00 $3.00 $-6,363.00
06374(44) 0208 WATER REPELLENT (VISUALLY INSPECTED) * Material Discrepancy Adjustments 0031 2,121.00 $3.00 $6,363.00
06374(44) 0211 (SP) SEALER RESIN * Material Discrepancy Adjustments 0029 -23.00 $80.00 $-1,840.00
06374(44) 0222 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) * Missing Material Certification 0027 -5,552.00 $0.45 $-2,498.40
06374(44) 0222 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) * Material Discrepancy Adjustments 0029 -80.00 $0.45 $-36.00
06374(44) 0222 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) * Missing Material Certification 0031 -5,602.00 $0.45 $-2,520.90
06374(44) 0222 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) * Missing Material Certification 0036 11,234.00 $0.45 $5,055.30
06374(44) 0243 REINFORCING STEEL * Missing Material Certification 0031 -7,952.00 $1.20 $-9,542.40
06374(44) 0243 REINFORCING STEEL * Missing Material Certification 0033 -468.00 $1.20 $-561.60
06374(44) 0243 REINFORCING STEEL * Missing Material Certification 0036 8,420.00 $1.20 $10,104.00
06374(44) 0244 SHEET ALUMINUM SIGNS * Missing Material Certification 0030 -210.25 $12.00 $-2,523.00
06374(44) 0244 SHEET ALUMINUM SIGNS * Missing Material Certification 0031 -294.91 $12.00 $-3,538.92
06374(44) 0244 SHEET ALUMINUM SIGNS * Missing Material Certification 0032 -173.73 $12.00 $-2,084.76
06374(44) 0244 SHEET ALUMINUM SIGNS * Missing Material Certification 0036 678.89 $12.00 $8,146.68
06374(44) 0245 EXTRUDED ALUMINUM PANEL SIGNS * Missing Material Certification 0030 -401.50 $20.00 $-8,030.00
06374(44) 0245 EXTRUDED ALUMINUM PANEL SIGNS * Missing Material Certification 0036 401.50 $20.00 $8,030.00
06374(44) 0246 EXTRUDED ALUMINUM PANEL SIGNS(OVERHEAD SIGNS) * Missing Material Certification 0030 -1,916.55 $20.00 $-38,331.00
06374(44) 0246 EXTRUDED ALUMINUM PANEL SIGNS(OVERHEAD SIGNS) * Missing Material Certification 0036 1,916.55 $20.00 $38,331.00
06374(44) 0248 3"@7.58 GALV.STEEL PIPE POST * Missing Material Certification 0031 -175.50 $25.00 $-4,387.50
06374(44) 0248 3"@7.58 GALV.STEEL PIPE POST * Missing Material Certification 0032 -58.50 $25.00 $-1,462.50
06374(44) 0248 3"@7.58 GALV.STEEL PIPE POST * Missing Material Certification 0036 234.00 $25.00 $5,850.00
06374(44) 0250 1 3/4" SQUARE TUBE POST * Missing Material Certification 0031 -45.50 $7.00 $-318.50
06374(44) 0250 1 3/4" SQUARE TUBE POST * Missing Material Certification 0032 -25.66 $7.00 $-179.62
06374(44) 0250 1 3/4" SQUARE TUBE POST * Missing Material Certification 0036 71.16 $7.00 $498.12
06374(44) 0251 2" SQUARE TUBE POST * Missing Material Certification 0031 -116.92 $11.00 $-1,286.12
06374(44) 0251 2" SQUARE TUBE POST * Material Discrepancy Adjustments 0032 116.92 $11.00 $1,286.12
06374(44) 0252 2 1/4" SQUARE TUBE POST * Missing Material Certification 0031 -326.96 $11.00 $-3,596.56
06374(44) 0252 2 1/4" SQUARE TUBE POST * Material Discrepancy Adjustments 0032 326.96 $11.00 $3,596.56
06374(44) 0257 TRAFFIC STRIPE(PAINT)(4" WIDE) * Material Discrepancy Adjustments 0029 -13,283.00 $0.30 $-3,984.90
06374(44) 0257 TRAFFIC STRIPE(PAINT)(4" WIDE) * Material Discrepancy Adjustments 0030 13,283.00 $0.30 $3,984.90
06374(44) 0259 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) * Missing Material Certification 0027 -4.00 $160.00 $-640.00
06374(44) 0259 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) * Material Discrepancy Adjustments 0028 4.00 $160.00 $640.00
06374(44) 0259 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) * Missing Material Certification 0033 -29.00 $160.00 $-4,640.00
06374(44) 0259 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) * Missing Material Certification 0036 29.00 $160.00 $4,640.00
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0026 -3,000.00 $0.65 $-1,950.00
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Material Discrepancy Adjustments 0028 3,000.00 $0.65 $1,950.00
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Material Discrepancy Adjustments 0029 -14,993.00 $0.65 $-9,745.45
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0030 9,745.45 $0.65 $6,334.54
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0031 -22,648.75 $0.65 $-14,721.69
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Material Discrepancy Adjustments 0032 27,896.30 $0.65 $18,132.60
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0033 -3,615.70 $0.65 $-2,350.21
06374(44) 0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) * Missing Material Certification 0036 3,615.70 $0.65 $2,350.21
06374(44) 0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) * Missing Material Certification 0026 -1,848.00 $0.88 $-1,626.24
06374(44) 0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) * Material Discrepancy Adjustments 0028 1,280.00 $0.88 $1,126.40
06374(44) 0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) * Material Discrepancy Adjustments 0029 -8,784.00 $0.88 $-7,729.92
06374(44) 0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) * Missing Material Certification 0030 7,729.92 $0.88 $6,802.33
06374(44) 0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) * Missing Material Certification 0031 -7,224.00 $0.88 $-6,357.12
06374(44) 0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) * Material Discrepancy Adjustments 0032 8,846.08 $0.88 $7,784.55
06374(44) 0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) * Missing Material Certification 0026 -1,347.00 $2.15 $-2,896.05
06374(44) 0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) * Material Discrepancy Adjustments 0029 -2,912.00 $2.15 $-6,260.80
06374(44) 0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) * Missing Material Certification 0030 9,156.85 $2.15 $19,687.23
06374(44) 0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) * Missing Material Certification 0031 -6,399.75 $2.15 $-13,759.46
06374(44) 0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) * Material Discrepancy Adjustments 0032 1,501.90 $2.15 $3,229.09
06374(44) 0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) * Rounding Error Correction 0035 0.00 $0.00 $-0.01
06374(44) 0263 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) * Missing Material Certification 0031 -292.75 $16.00 $-4,684.00
06374(44) 0263 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) * Missing Material Certification 0033 -182.50 $16.00 $-2,920.00
06374(44) 0263 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) * Material Discrepancy Adjustments 0033 292.75 $16.00 $4,684.00
06374(44) 0263 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) * Missing Material Certification 0036 182.50 $16.00 $2,920.00
06374(44) 0272 JUNCTION BOX(6" X 6" X 4") * Material Discrepancy Adjustments 0020 -1.00 $450.00 $-450.00
06374(44) 0272 JUNCTION BOX(6" X 6" X 4") * Missing Material Certification 0033 -3.00 $450.00 $-1,350.00
06374(44) 0273 PULL BOX(SIZE I) * Missing Material Certification 0030 -9.00 $515.00 $-4,635.00
06374(44) 0273 PULL BOX(SIZE I) * Missing Material Certification 0033 -4.00 $515.00 $-2,060.00
06374(44) 0275 REINFORCING STEEL * Missing Material Certification 0016 -400.80 $1.40 $-561.12
06374(44) 0275 REINFORCING STEEL * Material Discrepancy Adjustments 0020 -467.60 $1.40 $-654.64
06374(44) 0275 REINFORCING STEEL * Material Discrepancy Adjustments 0022 868.40 $1.40 $1,215.76
06374(44) 0275 REINFORCING STEEL * Missing Material Certification 0030 -647.00 $1.40 $-905.80
06374(44) 0275 REINFORCING STEEL * Missing Material Certification 0031 -100.20 $1.40 $-140.28
06374(44) 0275 REINFORCING STEEL * Missing Material Certification 0033 -334.00 $1.40 $-467.60
06374(44) 0281 1/C NO.4 ELECTRICAL CONDUCTOR * Missing Material Certification 0016 -6,040.00 $1.75 $-10,570.00
06374(44) 0281 1/C NO.4 ELECTRICAL CONDUCTOR * Missing Material Certification 0018 -400.00 $1.75 $-700.00
06374(44) 0281 1/C NO.4 ELECTRICAL CONDUCTOR * Material Discrepancy Adjustments 0019 6,440.00 $1.75 $11,270.00
06374(44) 0283 1/C NO.12 ELECTRICAL CONDUCTOR * Material Discrepancy Adjustments 0020 -1,000.00 $0.65 $-650.00
06374(44) 0283 1/C NO.12 ELECTRICAL CONDUCTOR * Material Discrepancy Adjustments 0022 -4,750.00 $0.65 $-3,087.50
06374(44) 0283 1/C NO.12 ELECTRICAL CONDUCTOR * Material Discrepancy Adjustments 0025 5,750.00 $0.65 $3,737.50
06374(44) 8001 RAPID CURE JOINT SEALANT * Missing Material Certification 0031 -318.92 $10.00 $-3,189.20
06374(44) 8001 RAPID CURE JOINT SEALANT * Material Discrepancy Adjustments 0035 318.92 $10.00 $3,189.20
06374(44) 8003 ELASTOMERIC MORTAR * Missing Material Certification 0031 -91.49 $200.00 $-18,298.00
06374(44) 8003 ELASTOMERIC MORTAR * Material Discrepancy Adjustments 0035 91.49 $200.00 $18,298.00
Subtotals For Line Item Adjustments $-35,560.59
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 TIME 'B' BID 03/01/2011 07/12/2012 499.00 DYS $15,000.00 Y
02 TIME 'C' BID 08/17/2011 07/12/2012 330.00 DYS $15,000.00 Y


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
01 System Application of Disincentive Adj 0029 $-165,000.00
01 System Application of Disincentive Adj 0030 $-240,000.00
01 System Application of Disincentive Adj 0031 $-450,000.00
01 System Application of Disincentive Adj 0032 $-180,000.00
02 System Application of Disincentive Adj 0029 $-30,000.00
02 System Application of Disincentive Adj 0030 $-240,000.00
02 System Application of Disincentive Adj 0031 $-450,000.00
02 System Application of Disincentive Adj 0032 $-180,000.00
Subtotals For Milestones $-1,935,000.00

Line Item Detail

Contract ID: 100617   Estimate Number: 0036     Primary JP: 06374(44)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $100,000.00 $0.00 $100,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 132,993.000 132,993.000   132,993.000 $4.00 $0.00 $531,972.00
0003 UNCLASSIFIED BORROW 202(C) 0184 CY 73,890.000 73,890.000   59,041.920 $4.00 $0.00 $236,167.68
0004 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   1.000 $200,000.00 $0.00 $200,000.00
0005 TEMPORARY SILT FENCE 223 2801 LF 5,685.000 5,685.000   9,007.000 $1.50 $0.00 $13,510.50
0006 TEMPORARY SEDIMENT FILTER 224 2803 EA 50.000 50.000   11.000 $50.00 $0.00 $550.00
0007 TEMPORARY SEDIMENT BASIN 225 2804 EA 5.000 5.000   0.000 $300.00 $0.00 $0.00
0008 SOLID SLAB SODDING 230(A) 2806 SY 159,003.000 159,003.000 20,998.000 178,411.000 $1.10 $23,097.80 $196,252.11
0009 WATERING 230(F) 2812 MGAL 6,360.000 6,360.000 84.860 4,180.000 $3.00 $254.58 $12,540.00
0010 SEEDING METHOD A 232(A) 2813 AC 32.840 32.840   0.000 $200.00 $0.00 $0.00
0011 VEGETATIVE MULCHING 233(A) 2817 AC 68.000 68.000   0.000 $100.00 $0.00 $0.00
0012 FERTILIZING (10-20-10) 234(A) 2824 TON 20.850 20.850 0.320 19.130 $600.00 $192.00 $11,478.00
0013 FERTILIZING (0-46-0) 234(A) 4406 TON 2.470 2.470   0.000 $600.00 $0.00 $0.00
0014 MOWING 241 2832 AC 68.000 68.000   71.010 $50.00 $0.00 $3,550.50
0015 (PL)STABILIZED CONSTRUCTION EXIT 242 0400 EA 4.000 4.000   4.000 $1,500.00 $0.00 $6,000.00
0016 (PL)TEMPORARY INLET SEDIMENT FILTER 243 0450 EA 137.000 137.000   0.000 $50.00 $0.00 $0.00
0017 AGGREGATE BASE 303 0192 CY 65,184.000 65,184.000   65,184.000 $27.00 $0.00 $1,759,968.00
0018 OPEN GRADED BITUMINOUS BASE 319 5190 TON 32,168.000 32,168.000   32,168.000 $38.00 $0.00 $1,222,384.00
0019 SEPARATOR FABRIC 325 5271 SY 547,681.000 547,681.000   547,681.000 $0.85 $0.00 $465,528.88
0020 (SP)MODIFIED SUBGRADE 327(J) 4290 SY 191,576.000 191,576.000   191,576.000 $2.80 $0.00 $536,412.80
0021 (SP)GEOSYNTHETIC SUBGRADE REINFORCEMENT 328 2600 SY 1,000.000 1,000.000   0.000 $5.00 $0.00 $0.00
0022 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 500.000 500.000   0.000 $15.00 $0.00 $0.00
0023 (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) 411(S2) 5930 TON 1,722.000 1,722.000   1,790.010 $47.00 $0.00 $84,130.47
0024 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) 411(S3) 5940 TON 1,672.000 1,672.000   1,960.460 $62.00 $0.00 $121,548.52
0025 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 2,477.000 2,477.000   4,164.410 $48.00 $0.00 $199,891.68
0026 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 6,811.000 6,811.000   8,682.340 $66.00 $0.00 $573,034.44
0027 (SP)P.C.CONCRETE PAVEMENT(PLACEMENT) 414(A) 0210 SY 31,341.000 31,341.000   31,341.000 $9.00 $0.00 $282,069.00
0028 (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) 414(A1) 5725 SY 84,191.000 84,191.000   84,191.000 $15.00 $0.00 $1,262,865.00
0029 9" H.E.S. CONCRETE (PATCHING) 414(B) 5072 SY 1,000.000 1,000.000   390.360 $65.00 $0.00 $25,373.40
0030 (SP)CONT. REINF. P.C.C. PAVEMENT(PLACEMENT) 414(D) 4425 SY 49,230.000 49,230.000   49,230.000 $23.00 $0.00 $1,132,290.00
0031 TERMINAL JOINT 414(F) 5262 EA 14.000 14.000   14.000 $5,000.00 $0.00 $70,000.00
0032 TERMINAL JOINT SLEEPER SLAB 414(G) 5263 SY 733.320 733.320   733.320 $55.00 $0.00 $40,332.61
0033 (SP)P.C. CONCRETE FOR PAVEMENT 414(P) 6000 CY 47,923.000 47,923.000   45,631.560 $82.00 $0.00 $3,741,787.92
0034 COLD MILLING PAVEMENT 417 5267 SY 38,878.000 38,878.000   49,064.000 $1.00 $0.00 $49,064.00
0035 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 477.000 477.000   474.000 $40.00 $0.00 $18,960.00
0036 42" F-SHAPED PARAPET 504(F) 6190 LF 515.000 515.000   515.000 $55.00 $0.00 $28,325.00
0037 CLASS A CONCRETE 509(B) 0321 CY 1,486.730 1,486.730   1,484.170 $325.00 $0.00 $482,355.25
0038 CLASS A CONCRETE (MEDIAN BARRIER, DES.1-A) 509(B) 4153 CY 288.940 288.940   368.890 $200.00 $0.00 $73,778.00
0039 CLASS A CONCRETE FOR SMALL STRUCTURES 509(C) 0322 CY 16.420 16.420   16.420 $285.00 $0.00 $4,679.70
0040 CLASS C CONCRETE 509(D) 0325 CY 128.710 128.710   126.720 $250.00 $0.00 $31,680.00
0041 RETAINING WALL 510(A) 6333 SY 2,623.200 2,623.200   2,623.100 $340.00 $0.00 $891,854.00
0042 SOUND BARRIER WALL 510(B) 6334 SY 10,768.700 10,768.700   10,941.690 $155.00 $0.00 $1,695,961.95
0043 REINFORCING STEEL 511(A) 0332 LB 239,269.000 239,269.000   232,738.660 $0.40 $0.00 $93,095.46
0044 DRILLED SHAFTS 30" DIAMETER 516(A) 6091 LF 5,735.000 5,735.000   5,820.000 $95.00 $0.00 $552,900.00
0045 CONCRETE CURB (4" MNTBLE-INTEGRAL) 609(A) 0287 LF 3,508.000 3,508.000   2,649.200 $3.00 $0.00 $7,947.60
0046 CONCRETE CURB (6" BARRIER-INTEGRAL) 609(A) 0300 LF 20,140.000 20,140.000   20,440.350 $4.00 $0.00 $81,761.40
0047 CONCRETE CURB (8" BARRIER-INTEGRAL) 609(A) 0380 LF 14,015.000 14,015.000   11,289.000 $5.00 $0.00 $56,445.00
0048 1'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1513 LF 1,197.000 1,197.000   1,512.000 $17.00 $0.00 $25,704.00
0049 4" CONCRETE SIDEWALK 610(A) 0602 SY 4,131.000 4,131.000   1,554.200 $28.00 $0.00 $43,517.60
0050 (PL)4" DECORATIVE CONCRETE SIDEWALK 610(A) 0650 SY 16.000 16.000   0.000 $75.00 $0.00 $0.00
0051 (PL)6" DECORATIVE CONCRETE SIDEWALK 610(A) 0654 SY 187.000 187.000   604.790 $80.00 $0.00 $48,383.20
0052 6" CONCRETE DRIVEWAY (H.E.S.) 610(B) 0399 SY 3,499.000 3,499.000   3,916.840 $40.00 $0.00 $156,673.60
0053 4" CONCRETE DIVIDING STRIP 610(C) 0608 SY 241.000 241.000   254.620 $25.00 $0.00 $6,365.50
0054 6" CONCRETE DIVIDING STRIP 610(C) 0609 SY 394.000 394.000   417.080 $38.00 $0.00 $15,849.04
0055 DECORATIVE MEDIAN CONCRETE 610(C) 5824 SY 877.000 877.000   4,144.910 $80.00 $0.00 $331,592.80
0056 (PL)TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 208.000 208.000   432.000 $35.00 $0.00 $15,120.00
0057 MANHOLE (4' DIAMETER) 611(A) 2657 EA 68.000 68.000   69.000 $2,000.00 $0.00 $138,000.00
0058 MANHOLE (5' DIAMETER) 611(A) 2658 EA 6.000 6.000   6.000 $3,200.00 $0.00 $19,200.00
0059 MANHOLE (6' DIAMETER) 611(A) 2659 EA 7.000 7.000   7.000 $5,600.00 $0.00 $39,200.00
0060 SPECIAL MANHOLE 611(C) 0484 CF 6,805.000 6,805.000   4,073.440 $17.00 $0.00 $69,248.48
0061 MANHOLE FRAME & COVER 611(D) 4215 EA 112.000 112.000   112.000 $350.00 $0.00 $39,200.00
0062 (PL)SPECIAL INLET DRAIN 611(E) 4012 EA 3.000 3.000   3.000 $5,000.00 $0.00 $15,000.00
0063 INLET CICI DES. 2 (STD) 611(E) 5112 EA 49.000 49.000   48.000 $2,300.00 $0.00 $110,400.00
0064 INLET CICI DES. 2 (B) 611(E) 5113 EA 52.000 52.000   52.000 $2,800.00 $0.00 $145,600.00
0065 INLET CICI DES. 2 (D) 611(E) 5115 EA 16.000 16.000   16.000 $3,200.00 $0.00 $51,200.00
0066 INLET CICI DES. 2 (2B) 611(E) 5117 EA 1.000 1.000   1.000 $3,200.00 $0.00 $3,200.00
0067 INLET CICI DES. 3 (2B) 611(E) 5123 EA 3.000 3.000   3.000 $5,200.00 $0.00 $15,600.00
0068 INLET GPI TYPE 2 (DES. 8) 611(E) 5334 EA 7.000 7.000   7.000 $3,800.00 $0.00 $26,600.00
0069 INLET GPI TYPE 2 (DES. 10) 611(E) 5336 EA 2.000 2.000   2.000 $4,100.00 $0.00 $8,200.00
0070 INLET GPI TYPE 2 (DES. 14) 611(E) 5340 EA 1.000 1.000   1.000 $4,300.00 $0.00 $4,300.00
0071 INLET MEDIAN BARRIER DES. 2 611(E) 5692 EA 9.000 9.000   9.000 $3,100.00 $0.00 $27,900.00
0072 INLET MEDIAN BARRIER DES. 2-2 611(E) 5693 EA 13.000 13.000   13.000 $5,100.00 $0.00 $66,300.00
0073 INLET W/LRG.JCT.BOX,CICI-JB-1,DES.2 611(E) 5870 EA 1.000 1.000   1.000 $7,600.00 $0.00 $7,600.00
0074 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(B) 611(E) 5972 EA 4.000 4.000   4.000 $6,100.00 $0.00 $24,400.00
0075 INLET (SMD-TYPE 1) 611(E) 6000 EA 12.000 12.000   12.000 $3,100.00 $0.00 $37,200.00
0076 INLET (SMD-TYPE 2) 611(E) 6002 EA 3.000 3.000   3.000 $2,800.00 $0.00 $8,400.00
0077 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 318.000 318.000   316.000 $350.00 $0.00 $110,600.00
0078 CAST IRON CURB INLETS 611(K) 4488 EA 464.000 464.000   462.000 $255.00 $0.00 $117,810.00
0079 DROP INLET GRATE (24" SPDI) 611(L) 4479 EA 1.000 1.000   1.000 $1,500.00 $0.00 $1,500.00
0080 MANHOLES ADJUST TO GRADE 612(A) 0641 EA 8.000 8.000   8.000 $800.00 $0.00 $6,400.00
0081 INLETS ADJUST TO GRADE 612(E) 0645 EA 1.000 1.000   1.000 $1,100.00 $0.00 $1,100.00
0082 18" R.C.PIPE CLASS III 613(B) 0491 LF 8,731.000 8,731.000   8,533.000 $50.00 $0.00 $426,650.00
0083 24" R.C.PIPE CLASS III 613(B) 0492 LF 2,778.000 2,778.000   2,985.000 $55.00 $0.00 $164,175.00
0084 30" R.C.PIPE CLASS III 613(B) 0493 LF 149.000 149.000   149.000 $63.00 $0.00 $9,387.00
0085 36" R.C.PIPE CLASS III 613(B) 0494 LF 1,351.000 1,351.000   1,351.000 $75.00 $0.00 $101,325.00
0086 48" R.C.PIPE CLASS III 613(B) 0496 LF 226.000 226.000   226.000 $98.00 $0.00 $22,148.00
0087 24" X 38" R.C.PIPE ELLIPTICAL CLASS HE-III 613(B) 4505 LF 198.000 198.000   198.000 $86.00 $0.00 $17,028.00
0088 18" CORR. GALV. STEEL PIPE 613(D) 0689 LF 6.000 6.000   0.000 $24.00 $0.00 $0.00
0089 24" CORR. GALV. STEEL PIPE 613(D) 0690 LF 4.000 4.000   0.000 $30.00 $0.00 $0.00
0090 18" PREFAB. CULVERT END SECTION, ROUND 613(M) 5726 EA 1.000 1.000   1.000 $900.00 $0.00 $900.00
0091 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $300,000.00 $0.00 $300,000.00
0092 REMOVAL OF CONCRETE PAVEMENT 619(B) 4727 SY 33,795.000 33,795.000   33,795.000 $3.00 $0.00 $101,385.00
0093 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 99,350.000 99,350.000   99,350.000 $2.50 $0.00 $248,375.01
0094 REMOVAL OF DRAINAGE INLETS 619(B) 4741 EA 40.000 40.000   40.000 $300.00 $0.00 $12,000.00
0095 REMOVAL OF MANHOLES 619(B) 4742 EA 27.000 27.000   27.000 $300.00 $0.00 $8,100.00
0096 REMOVAL OF CONCRETE DRIVEWAY 619(B) 4766 SY 1,297.000 1,297.000   1,297.000 $7.00 $0.00 $9,079.00
0097 REMOVAL OF GUARD RAIL 619(B) 4780 LF 321.000 321.000   321.000 $3.00 $0.00 $963.00
0098 REMOVAL OF SIDEWALK 619(B) 4792 SY 1,569.000 1,569.000   1,569.000 $5.00 $0.00 $7,845.00
0099 REMOVAL OF CONCRETE MEDIAN BARRIER 619(B) 4915 LF 7,196.000 7,196.000   7,196.000 $4.00 $0.00 $28,784.00
0100 REMOVAL OF 6" CONCRETE DIVIDING STRIP 619(B) 6132 SY 990.000 990.000   990.000 $7.00 $0.00 $6,930.00
0101 PRECAST CONCRETE MEDIAN BARRIER, TYPE I 627(A) 4310 LF 3,721.000 0.000 0.000 3,103.000 $25.00 $0.00 $77,575.00
0102 CONCRETE MEDIAN BARRIER, DESIGN 1 627(I) 4317 LF 5,473.000 5,473.000   4,922.780 $40.00 $0.00 $196,911.20
0103 EDGE DRAIN CONDUIT-PERFORATED 653(A) 5915 LF 36,547.000 36,547.000   37,103.000 $5.00 $0.00 $185,515.00
0104 EDGE DRAIN OUTLET LATERAL-NONPERFORATED 653(B) 5916 LF 285.000 285.000   135.000 $5.00 $0.00 $675.00
0105 OUTLET LATERAL HEADWALL 653(C) 5946 EA 13.000 13.000   4.000 $400.00 $0.00 $1,600.00
0106 (PL)IMPACT ATTENUATOR 871 8325 EA 6.000 6.000   5.000 $20,000.00 $0.00 $100,000.00
0107 (PL)REMOVAL OF HIGH MAST TOWER 890(A) 8708 EA 2.000 2.000   2.000 $3,000.00 $0.00 $6,000.00
8016 PAVEMENT/BRIDGE SMOOTHNESS ADJUSTMENT 430 5010 LSUM 0.000 1.000   0.000 $31,549.06 $0.00 $0.00
8018 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000   0.000 $83,086.51 $0.00 $0.00
8019 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000   0.000 $6,687.24 $0.00 $0.00
8020 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000   0.000 $8,649.45 $0.00 $0.00
8021 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000   0.000 $18,370.87 $0.00 $0.00
8022 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000   0.000 $15,668.20 $0.00 $0.00
Subtotals For Category     0100/ROADWAY    $23,544.38 $20,669,159.30
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0101/SANITARY SEWER
0108 FILTER FABRIC 602(C) 4205 SY 19,059.000 19,059.000   0.000 $3.00 $0.00 $0.00
0109 MANHOLE (4' DIAMETER) 611(A) 2657 EA 7.000 7.000   7.000 $2,500.00 $0.00 $17,500.00
0110 MANHOLE (5' DIAMETER) 611(A) 2658 EA 21.000 21.000   21.000 $5,500.00 $0.00 $115,500.00
0111 ADD'L.DEPTH IN MANHOLE (4' DIAMETER) 611(B) 2680 VF 14.000 14.000   14.140 $200.00 $0.00 $2,828.00
0112 ADD'L.DEPTH IN MANHOLE (5' DIAMETER) 611(B) 2681 VF 213.000 213.000   213.140 $550.00 $0.00 $117,227.00
0113 MANHOLE FRAME & COVER 611(D) 4215 EA 28.000 28.000   28.000 $400.00 $0.00 $11,200.00
0114 8" POLYVINYL CHLORIDE (PVC) PIPE 615(C) 6120 LF 284.000 284.000   299.000 $60.00 $0.00 $17,940.00
0115 SANITARY SEWER SERVICE CONNECTION 615(D) 0300 EA 4.000 4.000   7.000 $3,000.00 $0.00 $21,000.00
0116 18" DUCTILE IRON PIPE 616(A) 5125 LF 5,113.000 5,113.000   5,113.000 $170.00 $0.00 $869,210.00
0117 (PL)36" STEEL CASING 616(I) 5273 LF 295.000 295.000   473.000 $55.00 $0.00 $26,015.00
0118 BORE AND JACK 36" CASING 616(U) 6230 LF 220.000 220.000 -2.000 398.000 $400.00 $-800.00 $159,200.00
8008 MANHOLES ADJUST TO GRADE 612(A) 0641 EA 0.000 2.000   2.000 $3,994.68 $0.00 $7,989.36
Subtotals For Category     0101/SANITARY SEWER    $-800.00 $1,365,609.36
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0102/WATERLINE
0119 6" DUCTILE IRON PIPE 616(A) 5121 LF 2,050.000 2,050.000   823.210 $60.00 $0.00 $49,392.60
0120 8" DUCTILE IRON PIPE 616(A) 5122 LF 89.000 89.000   49.000 $90.00 $0.00 $4,410.00
0121 12" DUCTILE IRON PIPE 616(A) 5124 LF 1,672.000 1,672.000   1,695.000 $110.00 $0.00 $186,450.00
0122 16" DUCTILE IRON PIPE 616(A) 5894 LF 1,394.000 1,394.000   1,394.000 $130.00 $0.00 $181,220.00
0123 2" POLYVINYL CHLORIDE (PVC) PIPE 616(B) 5218 LF 68.000 68.000   34.000 $75.00 $0.00 $2,550.00
0124 6" POLYVINYL CHLORIDE (PVC) PIPE 616(B) 5223 LF 3,564.000 3,564.000   4,997.000 $70.00 $0.00 $349,790.00
0125 8" POLYVINYL CHLORIDE (PVC) PIPE 616(B) 5225 LF 153.000 153.000   193.000 $100.00 $0.00 $19,300.00
0126 6" GATE VALVE 616(D) 1070 EA 25.000 25.000   20.000 $1,000.00 $0.00 $20,000.00
0127 8" GATE VALVE 616(D) 1080 EA 4.000 4.000   3.000 $1,500.00 $0.00 $4,500.00
0128 12" GATE VALVE 616(D) 1100 EA 5.000 5.000   4.000 $2,500.00 $0.00 $10,000.00
0129 16" GATE VALVE 616(D) 1125 EA 2.000 2.000   2.000 $6,500.00 $0.00 $13,000.00
0130 FIRE HYDRANTS 616(G) 1192 EA 8.000 8.000   8.000 $2,500.00 $0.00 $20,000.00
0131 (PL)18" STEEL CASING 616(I) 5264 LF 181.000 181.000   181.000 $20.00 $0.00 $3,620.00
0132 (PL)30" STEEL CASING 616(I) 5272 LF 64.000 64.000   64.000 $30.00 $0.00 $1,920.00
0133 SERVICE CONNECTION (SHORT) 616(N) 0090 EA 11.000 11.000   21.000 $1,200.00 $0.00 $25,200.00
0134 SHORT WATER SERVICE & RESET METER 616(N) 0094 EA 13.000 13.000   15.000 $1,000.00 $0.00 $15,000.00
0135 BORE AND JACK 18" CASING 616(U) 6205 LF 181.000 181.000   181.000 $240.00 $0.00 $43,440.00
0136 BORE AND JACK 30" CASING 616(U) 6220 LF 64.000 64.000   64.000 $340.00 $0.00 $21,760.00
8013 24" CONCRETE TO DUCTILE IRON ADAPTER 616(L) 0300 EA 0.000 2.000   2.000 $6,521.00 $0.00 $13,042.00
Subtotals For Category     0102/WATERLINE    $0.00 $984,594.60
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0200/BRIDGE 'A'
0137 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 120.000 120.000   120.000 $15.00 $0.00 $1,800.00
0138 CLSM BACKFILL 501(G) 6309 CY 227.000 227.000   227.000 $75.00 $0.00 $17,025.00
0139 PRESTRESSED CONCRETE BEAMS (TYPE IV) 503(A) 1313 LF 2,692.800 2,692.800   2,692.800 $160.00 $0.00 $430,848.00
0140 APPROACH SLAB 504(A) 1304 SY 248.000 248.000   248.000 $130.00 $0.00 $32,240.00
0141 SEALED EXPANSION JOINT 504(C) 6250 LF 84.300 84.300   84.300 $215.00 $0.00 $18,124.50
0142 42" F-SHAPED PARAPET 504(F) 6190 LF 981.600 981.600   981.600 $47.00 $0.00 $46,135.20
0143 STRUCTURAL STEEL 506(A) 1322 LB 2,710.000 2,710.000   2,710.000 $1.50 $0.00 $4,065.00
0144 (PL)SPECIAL CONCRETE FINISH 509 6152 SY 307.000 307.000   307.000 $32.00 $0.00 $9,824.00
0145 CLASS AA CONCRETE 509(A) 1326 CY 640.200 640.200   640.200 $360.00 $0.00 $230,472.00
0146 CLASS A CONCRETE 509(B) 1328 CY 447.200 447.200   447.200 $360.00 $0.00 $160,992.00
0147 SLOPE WALL (5") 510(C) 6138 SY 387.000 387.000   487.720 $70.00 $0.00 $34,140.40
0148 REINFORCING STEEL 511(A) 1332 LB 3,420.000 3,420.000   3,420.000 $0.70 $0.00 $2,394.00
0149 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 224,550.000 224,550.000   224,550.000 $0.80 $0.00 $179,640.00
0150 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 50.000 50.000   50.000 $21.00 $0.00 $1,050.00
0151 PILES, FURNISHED (HP 12X53) 514(A) 6011 LF 618.000 618.000   618.000 $28.00 $0.00 $17,304.00
0152 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 50.000 50.000   49.500 $10.00 $0.00 $495.00
0153 PILES, DRIVEN (HP 12X53) 514(B) 6294 LF 618.000 618.000   615.940 $10.00 $0.00 $6,159.40
0154 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 2,474.000 2,474.000   2,474.000 $3.00 $0.00 $7,422.00
0155 DRILLED SHAFTS 60" DIAMETER 516(A) 6096 LF 88.000 88.000   88.000 $450.00 $0.00 $39,600.00
0156 DRILLED SHAFTS 72" DIAMETER 516(A) 6098 LF 202.000 202.000   202.000 $650.00 $0.00 $131,300.00
0157 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 783.000 783.000   783.000 $3.00 $0.00 $2,349.00
0158 (SP) SEALER RESIN 523(B) 6560 GAL 17.500 17.500   17.500 $80.00 $0.00 $1,400.00
0159 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 32.000 32.000   32.000 $550.00 $0.00 $17,600.00
0160 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 22.000 22.000   22.000 $700.00 $0.00 $15,400.00
0161 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 75.000 75.000   75.000 $30.00 $0.00 $2,250.00
0162 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 25.000 25.000   25.000 $15.00 $0.00 $375.00
0163 (PL)REMOVAL OF BRIDGE ITEMS 619(B) 2500 LSUM 1.000 1.000   1.000 $70,000.00 $0.00 $70,000.00
0164 (PL)REMOVAL OF BRIDGE ITEM (TYPE A) 619(B) 2510 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
8014 CONSTRUCTION MISCELLANEOUS 104 0700 LSUM 0.000 1.000   1.000 $14,405.59 $0.00 $14,405.59
Subtotals For Category     0200/BRIDGE 'A'    $0.00 $1,499,810.09
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0201/BRIDGE 'B'
0165 SELECT BORROW 202(D) 1303 CY 95.000 95.000   95.000 $25.00 $0.00 $2,375.00
0166 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 315.000 315.000   315.000 $15.00 $0.00 $4,725.00
0167 CLSM BACKFILL 501(G) 6309 CY 278.000 278.000   278.000 $75.00 $0.00 $20,850.00
0168 PRESTRESSED CONCRETE BEAMS (TYPE IV) 503(A) 1313 LF 2,892.100 2,892.100   2,892.100 $160.00 $0.00 $462,736.00
0169 APPROACH SLAB 504(A) 1304 SY 248.000 248.000   248.000 $130.00 $0.00 $32,240.00
0170 SEALED EXPANSION JOINT 504(C) 6250 LF 70.000 70.000   70.000 $215.00 $0.00 $15,050.00
0171 42" F-SHAPED PARAPET 504(F) 6190 LF 1,082.100 1,082.100   1,082.100 $47.00 $0.00 $50,858.70
0172 RAPID CURE JOINT SEALANT 504(H) 6390 LF 70.500 70.500   70.500 $30.00 $0.00 $2,115.00
0173 ELASTOMERIC MORTAR 504(I) 6389 CF 18.700 18.700   18.700 $400.00 $0.00 $7,480.00
0174 STRUCTURAL STEEL 506(A) 1322 LB 3,000.000 3,000.000   3,000.000 $1.50 $0.00 $4,500.00
0175 (PL)SPECIAL CONCRETE FINISH 509 6152 SY 546.000 546.000   546.000 $32.00 $0.00 $17,472.00
0176 CLASS AA CONCRETE 509(A) 1326 CY 867.100 867.100   867.100 $360.00 $0.00 $312,156.00
0177 CLASS A CONCRETE 509(B) 1328 CY 501.200 501.200   501.200 $360.00 $0.00 $180,432.00
0178 SLOPE WALL (5") 510(C) 6138 SY 386.000 386.000   486.720 $70.00 $0.00 $34,070.40
0179 REINFORCING STEEL 511(A) 1332 LB 4,130.000 4,130.000   4,130.000 $0.70 $0.00 $2,891.00
0180 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 276,850.000 276,850.000   276,850.000 $0.80 $0.00 $221,480.00
0181 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 50.000 50.000   50.000 $21.00 $0.00 $1,050.00
0182 PILES, FURNISHED (HP 12X53) 514(A) 6011 LF 618.000 618.000   618.000 $28.00 $0.00 $17,304.00
0183 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 50.000 50.000   51.500 $10.00 $0.00 $515.00
0184 PILES, DRIVEN (HP 12X53) 514(B) 6294 LF 618.000 618.000   614.040 $10.00 $0.00 $6,140.40
0185 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 2,971.000 2,971.000   2,971.000 $3.00 $0.00 $8,913.00
0186 DRILLED SHAFTS 60" DIAMETER 516(A) 6096 LF 80.000 80.000   80.000 $450.00 $0.00 $36,000.00
0187 DRILLED SHAFTS 72" DIAMETER 516(A) 6098 LF 238.000 238.000   238.000 $650.00 $0.00 $154,700.00
0188 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 915.000 915.000   915.000 $3.00 $0.00 $2,745.00
0189 (SP) SEALER RESIN 523(B) 6560 GAL 19.500 19.500   19.500 $80.00 $0.00 $1,560.00
0190 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 36.000 36.000   36.000 $550.00 $0.00 $19,800.00
0191 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 22.000 22.000   22.000 $700.00 $0.00 $15,400.00
0192 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 75.000 75.000   75.000 $30.00 $0.00 $2,250.00
0193 (PL)REMOVAL OF BRIDGE ITEMS 619(B) 2500 LSUM 1.000 1.000   1.000 $70,000.00 $0.00 $70,000.00
0194 (PL)REMOVAL OF BRIDGE ITEM (TYPE A) 619(B) 2510 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
Subtotals For Category     0201/BRIDGE 'B'    $0.00 $1,712,808.50
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0202/BRIDGE 'C'
0195 SELECT BORROW 202(D) 1303 CY 80.000 80.000   80.000 $25.00 $0.00 $2,000.00
0196 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 400.000 400.000   400.000 $15.00 $0.00 $6,000.00
0197 CLSM BACKFILL 501(G) 6309 CY 583.000 583.000   583.000 $75.00 $0.00 $43,725.00
0198 APPROACH SLAB 504(A) 1304 SY 765.000 765.000   765.000 $130.00 $0.00 $99,450.00
0199 42" F-SHAPED PARAPET 504(F) 6190 LF 674.000 674.000   674.000 $47.00 $0.00 $31,678.00
0200 STRUCTURAL STEEL 506(A) 1322 LB 716,890.000 716,890.000   716,890.000 $1.30 $0.00 $931,957.00
0201 (PL)SPECIAL CONCRETE FINISH 509 6152 SY 2,871.000 2,871.000   2,871.000 $32.00 $0.00 $91,872.00
0202 CLASS AA CONCRETE 509(A) 1326 CY 1,220.700 1,220.700   1,220.700 $360.00 $0.00 $439,452.00
0203 CLASS A CONCRETE 509(B) 1328 CY 847.600 847.600   847.600 $360.00 $0.00 $305,136.00
0204 SLOPE WALL (5") 510(C) 6138 SY 1,314.000 1,314.000   1,314.000 $70.00 $0.00 $91,980.00
0205 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 394,100.000 394,100.000   394,100.000 $0.80 $0.00 $315,280.00
0206 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 1,530.000 1,530.000   1,530.000 $21.00 $0.00 $32,130.00
0207 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 1,530.000 1,530.000   1,471.700 $10.00 $0.00 $14,717.00
0208 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 2,121.000 2,121.000   2,121.000 $3.00 $0.00 $6,363.00
0209 DRILLED SHAFTS 60" DIAMETER 516(A) 6096 LF 452.000 452.000   452.000 $450.00 $0.00 $203,400.00
0210 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 1,096.000 1,096.000   1,096.000 $3.00 $0.00 $3,288.00
0211 (SP) SEALER RESIN 523(B) 6560 GAL 23.000 23.000   23.000 $80.00 $0.00 $1,840.00
0212 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 26.000 26.000   26.000 $300.00 $0.00 $7,800.00
0213 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 39.000 39.000   39.000 $1,500.00 $0.00 $58,500.00
0214 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 272.000 272.000   272.000 $25.00 $0.00 $6,800.00
0215 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 36.000 36.000   36.000 $15.00 $0.00 $540.00
0216 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $50,000.00 $0.00 $50,000.00
0217 CONCRETE MEDIAN BARRIER, DESIGN 1 627(I) 4317 LF 337.000 337.000   337.000 $40.00 $0.00 $13,480.00
8010 CONSTRUCTION MISCELLANEOUS 104 0700 LSUM 0.000 1.000   1.000 $3,184.00 $0.00 $3,184.00
Subtotals For Category     0202/BRIDGE 'C'    $0.00 $2,760,572.00
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0300/TRAFFIC CONTROL
0218 RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN 627(O) 4410 LF 6,809.000 6,809.000   17,755.500 $3.00 $0.00 $53,266.50
0219 RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER 627(P) 4425 LF 25,595.000 25,595.000   11,676.500 $10.00 $0.00 $116,765.00
0220 (PL)SPECIAL SIGNS 850(D) 8120 SF 166.000 166.000   0.000 $11.00 $0.00 $0.00
0221 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 14,108.000 14,108.000 -1,275.500 107,590.950 $0.30 $-382.65 $32,277.29
0222 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) 856(C) 8851 LF 52,430.000 52,430.000 -779.000 28,339.000 $0.45 $-350.55 $12,752.55
0223 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS 856(G) 8881 EA 2,665.000 2,665.000   2,924.000 $1.60 $0.00 $4,678.40
0224 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 39,205.000 39,205.000 -8,676.000 56,982.500 $0.16 $-1,388.16 $9,117.20
0225 SAND FILLED IMPACT ATTENUATION MODULE 870(A) 8485 SD 12,150.000 12,150.000   6,570.000 $0.30 $0.00 $1,971.00
0226 (PL)TRUCK MOUNTED ATTENUATOR 876(C) 8482 SD 180.000 180.000 2.000 139.000 $38.00 $76.00 $5,282.00
0227 MODULAR GLARE SCREEN 878(C) 8487 SD 81,420.000 81,420.000   55,238.000 $0.11 $0.00 $6,076.18
0228 ARROW DISPLAY(TYPE C) 880(A) 8812 SD 1,560.000 1,560.000   90.000 $16.00 $0.00 $1,440.00
0229 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 29,790.000 29,790.000 272.000 46,677.000 $0.55 $149.60 $25,672.35
0230 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 24,990.000 24,990.000 32.000 40,479.000 $0.30 $9.60 $12,143.70
0231 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 27,090.000 27,090.000 560.000 55,548.000 $1.60 $896.00 $88,876.80
0232 BARRICADES(TYPE III) 880(C) 8842 SD 22,710.000 22,710.000   35,821.000 $0.55 $0.00 $19,701.55
0233 WING BARRICADES 880(C) 8848 SD 5,760.000 5,760.000 96.000 5,623.000 $0.11 $10.56 $618.53
0234 VERTICAL PANELS 880(D) 8854 SD 2,760.000 2,760.000   4,104.000 $0.30 $0.00 $1,231.20
0235 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 39,900.000 39,900.000 432.000 87,536.000 $0.30 $129.60 $26,260.80
0236 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 204,360.000 204,360.000   106,760.000 $0.01 $0.00 $1,067.60
0237 DRUMS 880(F) 8878 SD 201,420.000 201,420.000 -165.000 237,105.000 $0.11 $-18.15 $26,081.55
0238 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 500.000 500.000   1,449.500 $50.00 $0.00 $72,475.00
0239 PORT.CHANGEABLE MESSAGE SIGN 882(B) 8306 SD 1,680.000 1,680.000   671.000 $16.00 $0.00 $10,736.00
Subtotals For Category     0300/TRAFFIC CONTROL    $-868.15 $528,491.20
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0301/TRAFFIC SIGNING AND STRIPING
0240 CLASS A CONCRETE 509(B) 0321 CY 216.000 216.000   168.000 $520.00 $0.00 $87,360.00
0241 DRILLED SHAFTS 60" DIAMETER 516(A) 6096 LF 140.000 140.000   140.000 $600.00 $0.00 $84,000.00
0242 STRUCTURAL CONCRETE 804(A) 2915 CY 17.810 17.810   17.810 $400.00 $0.00 $7,124.00
0243 REINFORCING STEEL 804(B) 2916 LB 8,548.000 8,548.000 0.000 8,548.000 $1.20 $0.00 $10,257.60
0244 SHEET ALUMINUM SIGNS 850(A) 8110 SF 1,145.000 1,145.000 160.160 1,121.390 $12.00 $1,921.92 $13,456.68
0245 EXTRUDED ALUMINUM PANEL SIGNS 850(B) 8112 SF 364.000 364.000 -3.000 398.500 $20.00 $-60.00 $7,970.00
0246 EXTRUDED ALUMINUM PANEL SIGNS(OVERHEAD SIGNS) 850(B) 8114 SF 1,875.000 1,875.000 -5.010 1,911.540 $20.00 $-100.20 $38,230.80
0247 4"@13 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3206 LF 226.000 226.000 37.670 235.340 $28.00 $1,054.76 $6,589.52
0248 3"@7.58 GALV.STEEL PIPE POST 851(B) 3218 LF 32.000 32.000 0.080 264.830 $25.00 $2.00 $6,620.75
0249 3 1/2"@9.11 GALV.STEEL PIPE POST 851(B) 3219 LF 114.000 114.000   116.500 $28.00 $0.00 $3,262.00
0250 1 3/4" SQUARE TUBE POST 851(C) 8321 LF 73.000 73.000 10.080 77.740 $7.00 $70.56 $544.18
0251 2" SQUARE TUBE POST 851(C) 8324 LF 315.000 315.000 109.570 346.250 $11.00 $1,205.27 $3,808.75
0252 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 1,128.000 1,128.000 80.250 880.380 $11.00 $882.75 $9,684.18
0253 OVHD.SN.STR., MONOTUBE TYPE A 80' 852(B) 0110 EA 1.000 1.000   1.000 $50,000.00 $0.00 $50,000.00
0254 OVHD.SN.STR., MONOTUBE TYPE A 85' 852(B) 0115 EA 1.000 1.000   1.000 $53,000.00 $0.00 $53,000.00
0255 OVHD.SN.STR., MONOTUBE TYPE A 100' 852(B) 0130 EA 1.000 1.000   1.000 $58,000.00 $0.00 $58,000.00
0256 OVHD.SN.STR., MONOTUBE TYPE C 852(B) 0500 EA 1.000 1.000   1.000 $36,500.00 $0.00 $36,500.00
0257 TRAFFIC STRIPE(PAINT)(4" WIDE) 854(A) 8800 LF 18,245.000 18,245.000 -30.000 25,328.500 $0.30 $-9.00 $7,598.55
0258 TRAFFIC STRIPE(PAINT)(ARROW) 854(B) 8803 EA 10.000 10.000   13.000 $87.00 $0.00 $1,131.00
0259 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) 854(C) 8525 EA 69.000 69.000 0.000 73.000 $160.00 $0.00 $11,680.00
0260 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 854(C) 8530 LF 41,481.000 41,481.000 1,206.500 45,466.130 $0.65 $784.23 $29,553.00
0261 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) 854(C) 8535 LF 18,118.000 18,118.000   17,856.000 $0.88 $0.00 $15,713.28
0262 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) 854(C) 8540 LF 10,918.000 10,918.000 22.500 10,681.250 $2.15 $48.38 $22,964.69
0263 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) 854(C) 8555 LF 512.000 512.000 0.000 475.250 $16.00 $0.00 $7,604.00
0264 (PL)REMOVAL OF OVERHEAD SIGN STRUCTURE & SIGNS 890(A) 8718 LSUM 1.000 1.000   1.000 $2,200.00 $0.00 $2,200.00
0265 (PL)REMOVAL OF GROUND MOUNTED SIGNS 890(A) 8720 LSUM 1.000 1.000   1.000 $1,100.00 $0.00 $1,100.00
0266 (PL)REMOVE & RESET OVERHEAD SIGN STRUCTURE 890A/B 8758 EA 1.000 1.000 -0.500 0.000 $2,200.00 $-1,100.00 $0.00
Subtotals For Category     0301/TRAFFIC SIGNING AND STRIPING    $4,700.67 $575,952.98
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0302/TRAFFIC SIGNAL
0267 (PL)TRAFFIC ITEMS(SIGNALS) 890 7706 LSUM 1.000 1.000   1.000 $560,000.00 $0.00 $560,000.00
Subtotals For Category     0302/TRAFFIC SIGNAL    $0.00 $560,000.00
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0303/TRAFFIC LIGHTING
0268 3/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8300 LF 515.000 515.000   515.000 $10.00 $0.00 $5,150.00
0269 1 1/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8306 LF 1,560.000 1,560.000 4.000 1,560.000 $10.00 $40.00 $15,600.00
0270 2" PVC SCH.40 PLASTIC CONDUIT BORED 802(B) 8340 LF 2,155.000 2,155.000   2,155.000 $13.00 $0.00 $28,015.00
0271 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8342 LF 24,485.000 24,485.000   24,485.000 $4.50 $0.00 $110,182.50
0272 JUNCTION BOX(6" X 6" X 4") 802(D) 8370 EA 4.000 4.000   4.000 $450.00 $0.00 $1,800.00
0273 PULL BOX(SIZE I) 803 8065 EA 76.000 76.000 1.000 76.000 $515.00 $515.00 $39,140.00
0274 STRUCTURAL CONCRETE 804(A) 2915 CY 68.440 68.440   68.440 $540.00 $0.00 $36,957.60
0275 REINFORCING STEEL 804(B) 2916 LB 3,941.200 3,941.200   3,941.200 $1.40 $0.00 $5,517.68
0276 40' MTG.HT.HL.PTP.(G.STL.) 806(D) 8989 EA 152.000 152.000 1.000 153.000 $1,200.00 $1,200.00 $183,600.00
0277 BREAKAWAY BASE (DES. B) 807 8092 EA 114.000 114.000 2.000 116.000 $510.00 $1,020.00 $59,160.00
0278 (PL)ROADWAY LUMINAIRE 809(A) 8090 EA 186.000 186.000 1.000 187.000 $760.00 $760.00 $142,120.00
0279 UNDERPASS LUMINIARE 809(B) 8098 EA 32.000 32.000   32.000 $470.00 $0.00 $15,040.00
0280 SERVICE POLE 810(A) 3118 EA 3.000 3.000   3.000 $3,400.00 $0.00 $10,200.00
0281 1/C NO.4 ELECTRICAL CONDUCTOR 811 8038 LF 59,220.000 59,220.000   59,220.000 $1.75 $0.00 $103,635.00
0282 1/C NO.10 ELECTRICAL CONDUCTOR 811 8044 LF 1,520.000 1,520.000   1,520.000 $0.90 $0.00 $1,368.00
0283 1/C NO.12 ELECTRICAL CONDUCTOR 811 8046 LF 23,250.000 23,250.000   23,250.000 $0.65 $0.00 $15,112.50
8002 (PL)TRAFFIC ITEMS(LIGHTING) 890 7708 LSUM 0.000 1.000   1.000 $57,911.70 $0.00 $57,911.70
8005 CLASS A CONCRETE 509(B) 0321 CY 0.000 45.360   45.360 $577.50 $0.00 $26,195.40
8006 REINFORCING STEEL 804(B) 2916 LB 0.000 6,720.000   6,720.000 $1.42 $0.00 $9,542.40
8012 (SP)TEMPORARY ROADWAY LIGHTING ASSEMBLY 880(M) 8340 LMDY 0.000 50,000.000   46,786.000 $5.25 $0.00 $245,626.50
Subtotals For Category     0303/TRAFFIC LIGHTING    $3,535.00 $1,111,874.28
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0600/STAKING
0284 STAKING 642 0098 LSUM 1.000 1.000   1.000 $150,000.00 $0.00 $150,000.00
Subtotals For Category     0600/STAKING    $0.00 $150,000.00
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0640/CONSTRUCTION
0285 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.750 $10,000.00 $0.00 $7,500.00
0286 FIELD OFFICE 640 1426 EA 1.000 1.000   1.000 $15,000.00 $0.00 $15,000.00
0287 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $980,000.00 $0.00 $980,000.00
0288 (SP)CONTRACTORS QUALITY CONTROL 643 0087 LSUM 1.000 1.000   0.250 $65,000.00 $0.00 $16,250.00
8004 CLASS B BRIDGE DECK REPAIR 505(B) 6019 SY 0.000 433.780   433.780 $117.43 $0.00 $50,938.79
8007 (PL)RIGHT-OF-WAY CLEARANCE 643 0094 LSUM 0.000 1.000   1.000 $6,660.00 $0.00 $6,660.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $1,076,348.79
Fed/State Project Number:    IMY-0044-2(396)225 Project:    06374(44) Category:    0900/FEDERAL NON PARTICIPATING
8001 RAPID CURE JOINT SEALANT 504(H) 6390 LF 0.000 318.920   318.920 $10.00 $0.00 $3,189.20
8003 ELASTOMERIC MORTAR 504(I) 6389 CF 0.000 91.490   91.490 $200.00 $0.00 $18,298.00
8009 CONSTRUCTION MISCELLANEOUS 104 0600 EA 0.000 1.000   1.000 $23,282.53 $0.00 $23,282.53
8011 CONSTRUCTION MISCELLANEOUS 104 0700 LSUM 0.000 1.000   1.000 $109,115.89 $0.00 $109,115.89
8015 PRECAST CONCRETE MEDIAN BARRIER, TYPE I 627(A) 4310 LF 0.000 3,721.000   0.000 $25.00 $0.00 $0.00
Subtotals For Category     0900/FEDERAL NON PARTICIPATING    $0.00 $153,885.62
Subtotals For Project IMY-0044-2(396)225 /06374(44) $30,111.90 $33,149,106.72