Contract ID: | 100617 | Estimate Number: | 0034 | Contract No: | 610850 | |||
Residency: | TULSA (08100) | Estimate Type: | Progressive | Account No: | 400800 | |||
Project Number(s): | IMY-0044-2(396)225 | ||||||||||||
Primary Job Piece No: | 06374(44) | ||||||||||||
Contract Description: | GRADE, DRAIN, SURFACE, AND BRIDGE I-44: FROM RIVERSIDE DRIVE TO EAST OF PEORIA AVENUE IN THE CITY OF TULSA. PROJECT LENGTH = 1.215 MILES. | ||||||||||||
Primary County: | TULSA | ||||||||||||
Name of Road: | I-44 | ||||||||||||
Prime Contractor: | BECCO CONTRACTORS, INC. | ||||||||||||
P.O. BOX 9159 | |||||||||||||
TULSA , OK 74157 | |||||||||||||
Surety Company: | MID-CONTINENT CASUALTY COMPANY | ||||||||||||
Date Let: | 11/18/2010 | NTP Effective Date: | 03/01/2011 | Pay Period: | 08/01/2012 TO 05/31/2013 |
Date Awarded: | 12/06/2010 | Date Work Began: | 03/01/2011 | Original Contract Time: | 720 |
Date Contract Executed: | 12/22/2010 | Date Time Stopped: | 03/04/2013 | Current Time Charged: | 736.00 |
Date NTP Issued: | 01/05/2011 | Completion Date: | 03/04/2013 | Current Time Allowed: | 772.00 |
General Liability Expires: | 03/01/2014 | Workman's Comp Expires: | 02/01/2014 | Percent Time Used: | 95.34 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $33,045,743.73 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $32,439,488.87 | Participating: | $32,932,623.55 | $32,822,831.80 | $109,791.75 | ||
Percent Complete: | 99.62 % | Non Participating: | $130,603.09 | $130,603.09 | $0.00 | ||
Funds Available: | $125,916.18 | Total Earnings: | $33,063,226.64 | $32,953,434.89 | $109,791.75 | ||
Unearned Balance: | $-480,338.68 | Stockpiled Materials: | $0.00 | $272,611.46 | $-272,611.46 | ||
Gross Earnings: | $33,063,226.64 | $33,226,046.35 | $-162,819.71 | ||||
Other Adjustments: | $1,791,600.91 | $-143,399.09 | $1,935,000.00 | ||||
Liq Dam/Disincentive: | $-1,935,000.00 | $-1,935,000.00 | $0.00 | ||||
TOTAL: | $32,919,827.55 | $31,147,647.26 | $1,772,180.29 |
Contract ID: | 100617 | Estimate Number: | 0034 | Primary JP: | 06374(44) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Addendum to (SP) CA000002 | Approved | 07/12/2011 | 0.0 | $0.00 |
002 | Powder Coating Hwy. Lighting | Approved | 09/14/2011 | 0.0 | $57,911.70 |
003 | Class B bridge deck repair | Approved | 05/08/2012 | 0.0 | $63,980.79 |
004 | Structural steel | Approved | 12/06/2011 | 0.0 | $3,184.00 |
005 | Material for Joint repair | Approved | 12/06/2011 | 0.0 | $109,115.89 |
006 | Temporary Roadway Lighting | Approved | 12/06/2011 | 0.0 | $262,500.00 |
007 | Labor & Equipment River Joint | Approved | 03/05/2012 | 0.0 | $21,487.20 |
008 | Median Barrier Light Pole Footing | Approved | 05/08/2012 | 0.0 | $35,737.80 |
009 | Waffle house demolition | Approved | 06/04/2012 | 0.0 | $6,660.00 |
010 | SS Manhole | Approved | 09/11/2012 | 0.0 | $7,989.36 |
011 | Water Vault Royal Arms | Approved | 04/01/2013 | 0.0 | $37,688.12 |
012 | Addition of B-Time and C-Time for Disincentive Only | Approved | 06/10/2013 | 129.0 | $0.00 |
013 | Non-participating precast concrete median barrier, Type I | Approved | 03/19/2013 | 0.0 | $0.00 |
014 | Pavement Smoothness Bonus | Pending | 0 | 0.0 | $31,549.06 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0003 | $-3,555.16 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0028 | $-46,651.19 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0005 | $-1,127.28 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0006 | $-7,594.13 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0007 | $-4,309.60 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0008 | $-10,352.40 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0009 | $-32,073.76 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0012 | $-9,080.08 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0013 | $-28,115.42 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0014 | $-10,892.06 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0015 | $-16,506.13 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0016 | $-2,198.27 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0017 | $-5,269.53 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Closure | 0017 | $-224,223.57 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Initial Payment | 0017 | $224,223.57 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0018 | $-6,815.65 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0019 | $-12,482.98 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0020 | $-27,734.47 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0021 | $-28,881.01 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0022 | $-33,188.29 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0023 | $-6,067.15 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0024 | $-29,033.69 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0025 | $-12,370.42 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0026 | $-7,515.85 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Adjustment | 0027 | $-8,213.34 |
06374(44) | 0019 | Separator Fabric | Stockpiled Material Initial Payment | 0003 | $350,027.86 |
06374(44) | 0028 | Stockpiled Material Closure | 0034 | $0.01 | |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0007 | $-8,844.51 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0008 | $-6,310.70 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0009 | $-18,850.52 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0010 | $-10,478.25 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0013 | $-2,348.49 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0014 | $-4,624.78 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0015 | $-2,636.14 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0016 | $-83.04 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0017 | $-4,650.86 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Closure | 0017 | $-102,813.30 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Closure | 0017 | $-41,906.51 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Initial Payment | 0017 | $144,719.81 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0018 | $-7,177.08 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0019 | $-3,052.37 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0020 | $-9,938.00 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0021 | $-571.72 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0022 | $-1,750.61 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0024 | $-6,062.27 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0025 | $-10,068.52 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0026 | $-10,972.85 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0027 | $-9,384.28 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0028 | $-5,240.41 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0031 | $-66,362.64 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Adjustment | 0032 | $-9,488.21 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Initial Payment | 0003 | $156,989.73 |
06374(44) | 0028 | Dowel (Baskets) | Stockpiled Material Initial Payment | 0006 | $41,906.51 |
06374(44) | 0030 | Stockpiled Material Closure | 0034 | $-0.04 | |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0015 | $-64,739.09 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0016 | $-11,900.30 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0017 | $-54,468.71 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Closure | 0017 | $-333,538.63 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Initial Payment | 0017 | $333,538.63 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0018 | $-49,382.67 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0019 | $-6,854.63 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0020 | $-11,624.03 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0023 | $-127,634.09 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0024 | $-32,020.66 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0025 | $-23,495.41 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0027 | $-2,735.11 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0028 | $-25,323.28 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Initial Payment | 0007 | $483,443.45 |
06374(44) | 0030 | Reinforcing steel | Stockpiled Material Adjustment | 0014 | $-73,265.43 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-2,079.49 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-500.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-2,403.87 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0003 | $0.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0003 | $1,774.78 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0028 | $-5,376.94 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0027 | $-2,150.78 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0005 | $-386.87 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0006 | $-193.43 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0006 | $1,095.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0006 | $5,427.02 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0006 | $500.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0002 | $5,920.59 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0025 | $-2,150.78 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0007 | $2,403.87 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0024 | $-1,075.39 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0008 | $2,234.21 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0008 | $2,079.49 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0009 | $-677.02 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0034 | $-3,123.37 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0023 | $-3,763.86 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0018 | $-3,226.16 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0010 | $5,560.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0012 | $-290.15 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0032 | $-2,150.78 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0015 | $-1,354.04 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Initial Payment | 0017 | $24,093.45 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-5,560.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Adjustment | 0017 | $-1,075.39 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-3,019.08 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-1,774.78 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-1,095.00 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-5,427.02 |
06374(44) | 0057 | Manhole (4') | Stockpiled Material Closure | 0017 | $-2,234.21 |
06374(44) | 0058 | MH 5' | Stockpiled Material Adjustment | 0012 | $-868.74 |
06374(44) | 0058 | MH 5' | Stockpiled Material Adjustment | 0009 | $-1,737.47 |
06374(44) | 0058 | MH 5' | Stockpiled Material Initial Payment | 0006 | $2,266.62 |
06374(44) | 0058 | MH 5' | Stockpiled Material Initial Payment | 0002 | $4,691.20 |
06374(44) | 0058 | MH 5' | Stockpiled Material Closure | 0034 | $-486.52 |
06374(44) | 0058 | MH 5' | Stockpiled Material Adjustment | 0028 | $-2,576.73 |
06374(44) | 0058 | MH 5' | Stockpiled Material Adjustment | 0027 | $-1,288.36 |
06374(44) | 0058 | MH 5' | Stockpiled Material Initial Payment | 0017 | $4,351.61 |
06374(44) | 0058 | MH 5' | Stockpiled Material Closure | 0017 | $-2,266.62 |
06374(44) | 0058 | MH 5' | Stockpiled Material Closure | 0017 | $-2,084.99 |
06374(44) | 0059 | Stockpiled Material Closure | 0034 | $-1.45 | |
06374(44) | 0059 | MH 6' | Stockpiled Material Adjustment | 0016 | $-922.94 |
06374(44) | 0059 | MH 6' | Stockpiled Material Initial Payment | 0017 | $11,806.70 |
06374(44) | 0059 | MH 6' | Stockpiled Material Initial Payment | 0009 | $4,263.56 |
06374(44) | 0059 | MH 6' | Stockpiled Material Adjustment | 0009 | $-720.05 |
06374(44) | 0059 | MH 6' | Stockpiled Material Initial Payment | 0007 | $2,118.08 |
06374(44) | 0059 | MH 6' | Stockpiled Material Initial Payment | 0006 | $304.00 |
06374(44) | 0059 | MH 6' | Stockpiled Material Adjustment | 0004 | $-1,440.10 |
06374(44) | 0059 | MH 6' | Stockpiled Material Closure | 0017 | $-304.00 |
06374(44) | 0059 | MH 6' | Stockpiled Material Closure | 0017 | $-5,121.06 |
06374(44) | 0059 | MH 6' | Stockpiled Material Initial Payment | 0002 | $2,268.00 |
06374(44) | 0059 | MH 6' | Stockpiled Material Closure | 0034 | $-11,806.70 |
06374(44) | 0059 | MH 6' | Stockpiled Material Initial Payment | 0003 | $6,044.00 |
06374(44) | 0059 | MH 6' | Stockpiled Material Adjustment | 0016 | $-106.40 |
06374(44) | 0059 | MH 6' | Stockpiled Material Closure | 0017 | $-2,118.08 |
06374(44) | 0059 | MH 6' | Stockpiled Material Closure | 0017 | $-4,263.56 |
06374(44) | 0062 | Stockpiled Material Closure | 0034 | $-1.80 | |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Adjustment | 0032 | $-3,132.91 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Initial Payment | 0002 | $1,253.16 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Initial Payment | 0017 | $4,976.68 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Initial Payment | 0006 | $2,630.45 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Closure | 0017 | $-1,253.16 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Closure | 0017 | $-1,093.07 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Closure | 0017 | $-2,630.45 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Adjustment | 0020 | $-1,841.97 |
06374(44) | 0062 | Spe. inlet drain | Stockpiled Material Initial Payment | 0003 | $1,093.07 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0018 | $-3,468.90 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0017 | $31,814.55 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0027 | $-2,601.67 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0028 | $-3,468.90 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0032 | $-4,336.12 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0034 | $-15,337.29 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0002 | $9,779.52 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0003 | $4,883.72 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0004 | $-665.29 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0005 | $-887.06 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0006 | $-1,774.11 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0006 | $2,420.72 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0006 | $2,865.16 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0006 | $8,917.47 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0007 | $6,505.59 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Initial Payment | 0008 | $2,873.53 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0009 | $-1,995.88 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0015 | $-1,108.82 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0017 | $-867.22 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-3,348.36 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-4,883.72 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-2,420.72 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-2,865.16 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-8,917.47 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-6,505.59 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Closure | 0017 | $-2,873.53 |
06374(44) | 0063 | CICI 2(std) | Stockpiled Material Adjustment | 0025 | $-1,734.45 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0019 | $-3,881.32 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0017 | $39,222.04 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0023 | $-3,881.32 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0024 | $-1,940.66 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0025 | $-2,910.99 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0027 | $-2,910.99 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0028 | $-6,792.32 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0032 | $-3,881.32 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0034 | $-11,082.46 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0002 | $12,597.26 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0003 | $-807.32 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0003 | $5,775.00 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0004 | $-1,076.42 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0005 | $-538.21 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0006 | $-269.11 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0006 | $5,400.51 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0006 | $7,751.82 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0006 | $5,604.16 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0007 | $4,691.54 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Initial Payment | 0008 | $3,591.18 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0009 | $-1,883.74 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0012 | $-538.21 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0015 | $-1,076.42 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-6,407.83 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-5,775.00 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-5,400.51 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-7,751.82 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-5,604.16 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-4,691.54 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Closure | 0017 | $-3,591.18 |
06374(44) | 0064 | CICI 2(B) | Stockpiled Material Adjustment | 0022 | $-1,940.66 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Closure | 0017 | $-962.00 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Closure | 0017 | $-1,924.00 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Closure | 0017 | $-4,482.49 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Initial Payment | 0017 | $14,148.48 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0018 | $-1,187.39 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0024 | $-1,187.39 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0025 | $-1,187.39 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0027 | $-2,374.78 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0028 | $-2,374.78 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0032 | $-1,187.39 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Closure | 0034 | $-4,649.36 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Initial Payment | 0002 | $5,316.15 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0003 | $-369.03 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Initial Payment | 0003 | $4,416.07 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0004 | $-369.03 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Initial Payment | 0006 | $962.00 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Initial Payment | 0006 | $1,924.00 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Initial Payment | 0007 | $4,482.49 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0009 | $-369.03 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0012 | $-369.03 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Adjustment | 0015 | $-1,476.11 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Closure | 0017 | $-2,363.92 |
06374(44) | 0065 | CICI 2(D) | Stockpiled Material Closure | 0017 | $-4,416.07 |
06374(44) | 0066 | INLET CICI DES. 2(2B) | Stockpiled Material Closure | 0017 | $-825.00 |
06374(44) | 0066 | INLET CICI DES. 2(2B) | Stockpiled Material Closure | 0017 | $-2,055.00 |
06374(44) | 0066 | INLET CICI DES. 2(2B) | Stockpiled Material Initial Payment | 0017 | $2,880.00 |
06374(44) | 0066 | INLET CICI DES. 2(2B) | Stockpiled Material Initial Payment | 0009 | $2,055.00 |
06374(44) | 0066 | INLET CICI DES. 2(2B) | Stockpiled Material Adjustment | 0028 | $-2,880.00 |
06374(44) | 0066 | INLET CICI DES. 2(2B) | Stockpiled Material Initial Payment | 0006 | $825.00 |
06374(44) | 0067 | Stockpiled Material Closure | 0034 | $-2.44 | |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Initial Payment | 0006 | $1,276.00 |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Initial Payment | 0006 | $2,634.50 |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Adjustment | 0017 | $-1,446.47 |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Closure | 0017 | $-1,276.00 |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Closure | 0017 | $-2,634.50 |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Initial Payment | 0017 | $3,910.50 |
06374(44) | 0067 | CICI DES. 3 (2B) | Stockpiled Material Adjustment | 0032 | $-2,461.59 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Adjustment | 0022 | $-4,586.04 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Adjustment | 0023 | $-1,528.68 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Initial Payment | 0017 | $9,186.66 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Closure | 0017 | $-5,870.60 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Closure | 0017 | $-951.53 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Closure | 0017 | $-2,364.53 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Adjustment | 0017 | $-1,528.68 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Adjustment | 0015 | $-445.87 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Initial Payment | 0010 | $5,870.60 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Initial Payment | 0009 | $951.53 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Adjustment | 0028 | $-1,528.68 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Closure | 0034 | $-14.58 |
06374(44) | 0068 | GPI TYPE 2(DES. 8) | Stockpiled Material Initial Payment | 0006 | $2,810.40 |
06374(44) | 0069 | Stockpiled Material Closure | 0034 | $-0.45 | |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Adjustment | 0009 | $-443.49 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Adjustment | 0003 | $-1,335.21 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Initial Payment | 0002 | $2,405.00 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Initial Payment | 0017 | $1,166.45 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Closure | 0034 | $-1,166.45 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Adjustment | 0009 | $-1,069.34 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Closure | 0017 | $-1,166.45 |
06374(44) | 0069 | GPI type 2 (des.10) | Stockpiled Material Initial Payment | 0006 | $1,609.94 |
06374(44) | 0070 | GPI Type 2(Des.14) | Stockpiled Material Adjustment | 0009 | $-2,234.79 |
06374(44) | 0070 | GPI Type 2(Des.14) | Stockpiled Material Initial Payment | 0006 | $2,234.79 |
06374(44) | 0071 | Stockpiled Material Closure | 0034 | $1.02 | |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Closure | 0017 | $-729.60 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Closure | 0017 | $-565.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Closure | 0017 | $-565.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Closure | 0017 | $-565.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Initial Payment | 0017 | $2,424.60 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Adjustment | 0024 | $-157.92 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Initial Payment | 0002 | $1,158.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Initial Payment | 0006 | $565.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Initial Payment | 0006 | $565.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Initial Payment | 0007 | $565.00 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Adjustment | 0017 | $-2,267.70 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Adjustment | 0012 | $-142.80 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Adjustment | 0015 | $-142.80 |
06374(44) | 0071 | inlet Median Barr.Des 2 | Stockpiled Material Adjustment | 0016 | $-142.80 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Adjustment | 0014 | $-173.49 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Adjustment | 0017 | $-5,637.54 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Closure | 0017 | $-644.43 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Closure | 0017 | $-3,032.80 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Closure | 0017 | $-4,185.60 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Closure | 0017 | $-1,103.83 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Closure | 0017 | $-6,140.24 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Initial Payment | 0017 | $15,106.94 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Adjustment | 0019 | $-1,409.39 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Closure | 0034 | $-8,060.01 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Initial Payment | 0002 | $2,032.32 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Initial Payment | 0006 | $3,032.80 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Initial Payment | 0006 | $4,185.60 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Initial Payment | 0007 | $1,103.83 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Initial Payment | 0008 | $6,140.24 |
06374(44) | 0072 | inlet median barr des 2-2 | Stockpiled Material Adjustment | 0012 | $-1,214.40 |
06374(44) | 0073 | Inlet W/Lrg.JCT.Box | Stockpiled Material Closure | 0017 | $-2,969.85 |
06374(44) | 0073 | Inlet W/Lrg.JCT.Box | Stockpiled Material Initial Payment | 0006 | $2,969.85 |
06374(44) | 0073 | Inlet W/Lrg.JCT.Box | Stockpiled Material Initial Payment | 0017 | $2,969.85 |
06374(44) | 0073 | Inlet W/Lrg.JCT.Box | Stockpiled Material Adjustment | 0032 | $-2,969.85 |
06374(44) | 0074 | Stockpiled Material Closure | 0034 | $2.56 | |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Closure | 0017 | $-3,182.02 |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Closure | 0017 | $-1,987.84 |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Initial Payment | 0017 | $5,115.86 |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Initial Payment | 0006 | $3,182.02 |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Adjustment | 0028 | $-1,435.49 |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Initial Payment | 0010 | $1,987.84 |
06374(44) | 0074 | Inlet W/small Juc.Box | Stockpiled Material Adjustment | 0032 | $-3,682.93 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0027 | $-1,079.57 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0023 | $-1,079.57 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Initial Payment | 0017 | $9,637.62 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Closure | 0017 | $-2,716.89 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Closure | 0017 | $-3,257.40 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Closure | 0017 | $-2,044.33 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Closure | 0017 | $-1,619.00 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0017 | $-1,079.57 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0015 | $-337.04 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0028 | $-2,159.15 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0009 | $-1,348.16 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Initial Payment | 0008 | $2,716.89 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Initial Payment | 0006 | $3,257.40 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0005 | $-337.04 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Initial Payment | 0003 | $2,044.33 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Initial Payment | 0002 | $3,641.24 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Closure | 0034 | $-3,160.19 |
06374(44) | 0075 | inlet smd-type1 | Stockpiled Material Adjustment | 0032 | $-1,079.57 |
06374(44) | 0076 | Stockpiled Material Closure | 0034 | $-1.84 | |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Adjustment | 0004 | $-186.68 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Initial Payment | 0006 | $560.00 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Initial Payment | 0002 | $560.00 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Adjustment | 0015 | $-184.80 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Initial Payment | 0017 | $1,113.78 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Initial Payment | 0007 | $560.00 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Adjustment | 0015 | $-6.22 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Closure | 0017 | $-553.78 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Adjustment | 0005 | $-186.68 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Closure | 0017 | $-560.00 |
06374(44) | 0076 | inlet smd-type2 | Stockpiled Material Closure | 0034 | $-1,113.78 |
06374(44) | 0077 | Stockpiled Material Closure | 0034 | $-0.34 | |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0017 | $-1,337.03 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0015 | $-985.18 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0014 | $-70.37 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0013 | $-140.74 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0010 | $-2,251.83 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Initial Payment | 0007 | $10,070.38 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0032 | $-1,308.98 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0028 | $-844.44 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0027 | $-633.33 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0025 | $-774.07 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0020 | $-879.63 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0019 | $-703.70 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Adjustment | 0018 | $-140.74 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Initial Payment | 0017 | $6,622.26 |
06374(44) | 0077 | Fram Grate CICI | Stockpiled Material Closure | 0017 | $-6,622.26 |
06374(44) | 0078 | Stockpiled Material Closure | 0034 | $0.15 | |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0014 | $-87.14 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0020 | $-304.98 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0032 | $-2,169.74 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0019 | $-304.98 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0010 | $-2,004.16 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0018 | $-87.14 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0028 | $-784.23 |
06374(44) | 0078 | CICI | Stockpiled Material Initial Payment | 0017 | $5,742.19 |
06374(44) | 0078 | CICI | Stockpiled Material Closure | 0017 | $-5,742.19 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0017 | $-479.25 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0013 | $-217.84 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0027 | $-697.09 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0015 | $-1,045.65 |
06374(44) | 0078 | CICI | Stockpiled Material Initial Payment | 0007 | $9,096.98 |
06374(44) | 0078 | CICI | Stockpiled Material Adjustment | 0025 | $-914.93 |
06374(44) | 0106 | Impact att. | Stockpiled Material Initial Payment | 0008 | $98,970.24 |
06374(44) | 0106 | Impact att. | Stockpiled Material Adjustment | 0029 | $-36,651.99 |
06374(44) | 0106 | Impact att. | Stockpiled Material Closure | 0017 | $-98,970.24 |
06374(44) | 0106 | Impact att. | Stockpiled Material Initial Payment | 0017 | $98,970.24 |
06374(44) | 0106 | Impact att. | Stockpiled Material Adjustment | 0031 | $-18,325.99 |
06374(44) | 0106 | Impact att. | Stockpiled Material Adjustment | 0020 | $-36,651.99 |
06374(44) | 0106 | Impact att. | Stockpiled Material Closure | 0034 | $-7,340.27 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0007 | $-17,414.19 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0006 | $-14,177.03 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0005 | $-12,608.76 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Initial Payment | 0004 | $164,950.23 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Initial Payment | 0004 | $82,097.58 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Closure | 0034 | $-175,921.98 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Initial Payment | 0017 | $175,921.98 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Closure | 0017 | $-164,950.23 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Closure | 0017 | $-10,971.75 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0015 | $-1,482.45 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0014 | $-3,033.05 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0009 | $-5,689.30 |
06374(44) | 0116 | 18" ductileiron pipe | Stockpiled Material Adjustment | 0008 | $-16,721.05 |
06374(44) | 0119 | 6" DIP | Stockpiled Material Initial Payment | 0004 | $23,665.37 |
06374(44) | 0119 | 6" DIP | Stockpiled Material Adjustment | 0012 | $-22,562.27 |
06374(44) | 0119 | 6" DIP | Stockpiled Material Adjustment | 0006 | $-1,026.14 |
06374(44) | 0119 | 6" DIP | Stockpiled Material Adjustment | 0007 | $-76.96 |
06374(44) | 0121 | 12" DIP | Stockpiled Material Adjustment | 0006 | $-9,829.46 |
06374(44) | 0121 | 12" DIP | Stockpiled Material Initial Payment | 0004 | $43,503.44 |
06374(44) | 0121 | 12" DIP | Stockpiled Material Adjustment | 0012 | $-13,876.89 |
06374(44) | 0121 | 12" DIP | Stockpiled Material Closure | 0017 | $-19,797.09 |
06374(44) | 0122 | 16" DIP | Stockpiled Material Initial Payment | 0004 | $53,273.95 |
06374(44) | 0122 | 16" DIP | Stockpiled Material Adjustment | 0012 | $-10,615.79 |
06374(44) | 0122 | 16" DIP | Stockpiled Material Closure | 0017 | $-42,658.16 |
06374(44) | 0122 | 16" DIP | Stockpiled Material Initial Payment | 0017 | $42,658.16 |
06374(44) | 0122 | 16" DIP | Stockpiled Material Adjustment | 0033 | $-42,658.16 |
06374(44) | 0124 | 6" PVC | Stockpiled Material Adjustment | 0004 | $-11,191.36 |
06374(44) | 0124 | 6" PVC | Stockpiled Material Initial Payment | 0017 | $5,115.29 |
06374(44) | 0124 | 6" PVC | Stockpiled Material Adjustment | 0033 | $-5,115.29 |
06374(44) | 0124 | 6" PVC | Stockpiled Material Closure | 0017 | $-5,115.29 |
06374(44) | 0124 | 6" PVC | Stockpiled Material Adjustment | 0007 | $-1,119.14 |
06374(44) | 0124 | 6" PVC | Stockpiled Material Initial Payment | 0004 | $17,425.79 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Closure | 0034 | $-1,792.12 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Adjustment | 0033 | $796.34 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Initial Payment | 0017 | $995.78 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Closure | 0017 | $-995.78 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Adjustment | 0012 | $-7,566.86 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Adjustment | 0007 | $-398.26 |
06374(44) | 0126 | 6" Gate Valve | Stockpiled Material Initial Payment | 0004 | $8,960.90 |
06374(44) | 0139 | P.C. Beams Br. A | Stockpiled Material Adjustment | 0017 | $-238,751.22 |
06374(44) | 0139 | P.C. Beams Br. A | Stockpiled Material Initial Payment | 0003 | $376,455.15 |
06374(44) | 0139 | P.C. Beams Br. A | Stockpiled Material Adjustment | 0013 | $-137,703.93 |
06374(44) | 0139 | P.C. Beams Br. A | Stockpiled Material Initial Payment | 0017 | $238,751.22 |
06374(44) | 0139 | P.C. Beams Br. A | Stockpiled Material Closure | 0017 | $-238,751.22 |
06374(44) | 0168 | Stockpiled Material Closure | 0034 | $0.06 | |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Adjustment | 0026 | $-232,119.30 |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Initial Payment | 0017 | $396,373.17 |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Initial Payment | 0004 | $237,537.27 |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Adjustment | 0020 | $-164,253.93 |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Initial Payment | 0003 | $158,835.90 |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Closure | 0017 | $-237,537.27 |
06374(44) | 0168 | P.C.Beams Br. B | Stockpiled Material Closure | 0017 | $-158,835.90 |
06374(44) | 0171 | Reinf. steel for F-shape par. | Stockpiled Material Initial Payment | 0023 | $10,860.92 |
06374(44) | 0171 | Reinf. steel for F-shape par. | Stockpiled Material Adjustment | 0029 | $-10,860.92 |
06374(44) | 0176 | Br. | Stockpiled Material Closure | 0020 | $-94,069.50 |
06374(44) | 0176 | Br. | Stockpiled Material Closure | 0017 | $-94,069.50 |
06374(44) | 0176 | Br. | Stockpiled Material Initial Payment | 0017 | $94,069.50 |
06374(44) | 0176 | Br. | Stockpiled Material Initial Payment | 0012 | $94,069.50 |
06374(44) | 0180 | Epox. Reinf. Br. B | Stockpiled Material Adjustment | 0028 | $-27,118.45 |
06374(44) | 0180 | Epox. Reinf. Br. B | Stockpiled Material Adjustment | 0031 | $-3,665.44 |
06374(44) | 0180 | Epox. Reinf. Br. B | Stockpiled Material Adjustment | 0025 | $-9,500.88 |
06374(44) | 0180 | Epox. Reinf. Br. B | Stockpiled Material Closure | 0034 | $-4,045.18 |
06374(44) | 0180 | Epox. Reinf. Br. B | Stockpiled Material Initial Payment | 0023 | $61,667.98 |
06374(44) | 0180 | Epox. Reinf. Br. B | Stockpiled Material Adjustment | 0023 | $-17,338.03 |
06374(44) | 0200 | Stru. steel | Stockpiled Material Initial Payment | 0017 | $335,527.10 |
06374(44) | 0200 | Stru. steel | Stockpiled Material Initial Payment | 0006 | $830,070.00 |
06374(44) | 0200 | Stru. steel | Stockpiled Material Closure | 0017 | $-335,527.10 |
06374(44) | 0200 | Stru. steel | Stockpiled Material Adjustment | 0024 | $-335,527.10 |
06374(44) | 0200 | Stru. steel | Stockpiled Material Adjustment | 0012 | $-494,542.90 |
06374(44) | 0212 | Abut. bearing assembly | Stockpiled Material Initial Payment | 0017 | $3,676.12 |
06374(44) | 0212 | Abut. bearing assembly | Stockpiled Material Closure | 0034 | $-2,225.03 |
06374(44) | 0212 | Abut. bearing assembly | Stockpiled Material Adjustment | 0024 | $-1,451.09 |
06374(44) | 0212 | Abut. bearing assembly | Stockpiled Material Initial Payment | 0013 | $2,829.69 |
06374(44) | 0212 | Abut. bearing assembly | Stockpiled Material Closure | 0017 | $-3,676.12 |
06374(44) | 0212 | Abut. bearing assembly | Stockpiled Material Adjustment | 0013 | $846.43 |
06374(44) | 0213 | expansion bearing assembly | Stockpiled Material Closure | 0017 | $-20,506.81 |
06374(44) | 0213 | expansion bearing assembly | Stockpiled Material Initial Payment | 0017 | $20,506.81 |
06374(44) | 0213 | expansion bearing assembly | Stockpiled Material Closure | 0034 | $-7,372.34 |
06374(44) | 0213 | expansion bearing assembly | Stockpiled Material Adjustment | 0024 | $-13,134.47 |
06374(44) | 0213 | expansion bearing assembly | Stockpiled Material Initial Payment | 0013 | $25,613.70 |
06374(44) | 0213 | expansion bearing assembly | Stockpiled Material Adjustment | 0013 | $-5,106.89 |
06374(44) | 0245 | Extruded Panel groundmount | Stockpiled Material Adjustment | 0030 | $-2,580.48 |
06374(44) | 0245 | Extruded Panel groundmount | Stockpiled Material Initial Payment | 0020 | $2,580.48 |
06374(44) | 0246 | Extruded Panel overhead | Stockpiled Material Adjustment | 0030 | $-21,046.00 |
06374(44) | 0246 | Extruded Panel overhead | Stockpiled Material Initial Payment | 0020 | $21,046.00 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Initial Payment | 0013 | $54,358.00 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Initial Payment | 0015 | $12,727.86 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Initial Payment | 0008 | $42,497.00 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Initial Payment | 0008 | $15,080.00 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Initial Payment | 0012 | $56,989.29 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Closure | 0017 | $-14,577.33 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Closure | 0017 | $-42,497.00 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Closure | 0017 | $-56,989.29 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Closure | 0017 | $-54,358.00 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Closure | 0017 | $-12,727.86 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Initial Payment | 0017 | $181,149.48 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Closure | 0034 | $-13,910.50 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0026 | $-20,150.08 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0022 | $-16,118.95 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0031 | $-20,150.08 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0030 | $-20,150.08 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0028 | $-30,225.13 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0024 | $-60,444.66 |
06374(44) | 0267 | Ped. heads | Stockpiled Material Adjustment | 0014 | $-502.67 |
06374(44) | 0276 | Stockpiled Material Closure | 0034 | $1.90 | |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0028 | $-4,814.79 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0030 | $-19,259.16 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0031 | $-28,888.74 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0033 | $-21,958.67 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Initial Payment | 0015 | $131,734.00 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Closure | 0017 | $-131,734.00 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Initial Payment | 0017 | $131,734.00 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0020 | $-6,740.71 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0022 | $-33,703.54 |
06374(44) | 0276 | 40' MTG.Ht.Hl.PTP. | Stockpiled Material Adjustment | 0026 | $-16,370.29 |
06374(44) | 0277 | Stockpiled Material Closure | 0034 | $-0.01 | |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0016 | $-6,194.09 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0030 | $-5,946.65 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0028 | $-1,238.88 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0022 | $-1,734.44 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Initial Payment | 0015 | $25,422.00 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0020 | $-2,477.77 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0031 | $-644.64 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0026 | $-3,716.65 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0018 | $-1,238.88 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Adjustment | 0024 | $-2,229.99 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Initial Payment | 0017 | $19,227.91 |
06374(44) | 0277 | Breakaway base | Stockpiled Material Closure | 0017 | $-19,227.91 |
06374(44) | 0278 | Stockpiled Material Closure | 0034 | $-0.50 | |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Adjustment | 0033 | $-5,766.88 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Adjustment | 0031 | $-14,973.24 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Adjustment | 0030 | $-16,082.37 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Adjustment | 0028 | $-3,327.39 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Adjustment | 0026 | $-52,683.62 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Initial Payment | 0017 | $92,834.00 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Closure | 0017 | $-92,834.00 |
06374(44) | 0278 | Roadway Luminaire | Stockpiled Material Initial Payment | 0012 | $92,834.00 |
06374(44) | 0279 | Stockpiled Material Closure | 0034 | $-0.17 | |
06374(44) | 0279 | Underpass Luminaire | Stockpiled Material Closure | 0017 | $-6,560.00 |
06374(44) | 0279 | Underpass Luminaire | Stockpiled Material Initial Payment | 0012 | $6,560.00 |
06374(44) | 0279 | Underpass Luminaire | Stockpiled Material Adjustment | 0033 | $-183.27 |
06374(44) | 0279 | Underpass Luminaire | Stockpiled Material Adjustment | 0030 | $-6,376.56 |
06374(44) | 0279 | Underpass Luminaire | Stockpiled Material Initial Payment | 0017 | $6,560.00 |
06374(44) | 0281 | Stockpiled Material Closure | 0034 | $0.01 | |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0018 | $-282.20 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0030 | $-6,128.64 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0020 | $-7,186.88 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0022 | $-2,671.00 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0028 | $-1,949.28 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0031 | $-3,644.59 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Initial Payment | 0017 | $33,339.95 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Closure | 0017 | $-33,339.95 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0026 | $-3,964.88 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0024 | $-2,958.85 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Initial Payment | 0008 | $37,601.14 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0016 | $-4,261.19 |
06374(44) | 0281 | 1/C no.4 ele.conduit | Stockpiled Material Adjustment | 0033 | $-4,553.64 | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
Milstone Adjust. (C/O) | 0034 | $1,935,000.00 | Subtotals For Contract Adjustments | $1,935,000.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0005 | -796.00 | $1.50 | $-1,194.00 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0014 | -150.00 | $1.50 | $-225.00 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0017 | -96.00 | $1.50 | $-144.00 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0019 | -425.00 | $1.50 | $-637.50 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Material Discrepancy Adjustments | 0020 | 246.00 | $1.50 | $369.00 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0023 | -100.00 | $1.50 | $-150.00 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0027 | -210.00 | $1.50 | $-315.00 |
06374(44) | 0005 | TEMPORARY SILT FENCE | * Missing Material Certification | 0032 | 1,815.00 | $1.50 | $2,722.50 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0004 | 1,001.02 | $0.42 | $426.06 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0007 | 663.89 | $2.80 | $1,859.31 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0008 | 1,318.72 | $2.80 | $3,693.25 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0009 | 1,625.11 | $2.80 | $4,551.33 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0010 | 303.59 | $2.80 | $850.24 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0013 | 4,056.04 | $2.80 | $11,359.47 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0014 | 1,804.27 | $2.80 | $5,053.09 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0015 | 514.01 | $2.67 | $1,375.30 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0016 | 406.32 | $2.67 | $1,087.16 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0017 | 3,168.40 | $2.23 | $7,091.29 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0018 | 1,103.97 | $2.23 | $2,470.83 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0019 | 43.94 | $2.23 | $98.34 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | * Material Discrepancy Adjustments | 0019 | -43.94 | $38.00 | $-1,669.72 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | * Material Discrepancy Adjustments | 0020 | 43.94 | $38.00 | $1,669.72 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0020 | 685.39 | $2.23 | $1,533.99 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0021 | 237.08 | $2.23 | $530.62 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0022 | 4,197.08 | $2.23 | $9,393.61 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0023 | 977.57 | $2.30 | $2,249.03 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0024 | 2,520.07 | $2.30 | $5,797.75 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0025 | 32.61 | $2.30 | $75.02 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0026 | 214.92 | $2.30 | $494.45 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0027 | 2,705.94 | $2.92 | $7,916.58 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0028 | 1,259.33 | $2.92 | $3,684.33 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0029 | 1,028.75 | $3.42 | $3,524.12 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0030 | 1,560.30 | $3.42 | $5,345.01 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | Asphalt Binder Adjustment | 0031 | 739.68 | $3.55 | $2,626.33 |
06374(44) | 0018 | OPEN GRADED BITUMINOUS BASE | * HMA Deduction as per Sec. 411 | 0031 | 0.00 | $0.00 | $-46,280.00 |
06374(44) | 0023 | (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) | Asphalt Binder Adjustment | 0016 | 1,089.45 | $3.95 | $4,314.15 |
06374(44) | 0023 | (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) | Asphalt Binder Adjustment | 0021 | 132.58 | $3.31 | $439.16 |
06374(44) | 0023 | (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) | Asphalt Binder Adjustment | 0025 | 567.98 | $3.40 | $1,933.93 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0012 | 246.89 | $4.70 | $1,161.63 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0015 | 44.65 | $4.49 | $200.70 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0016 | 1,005.06 | $4.49 | $4,517.80 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0021 | 117.47 | $3.76 | $441.69 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0023 | 13.41 | $3.86 | $51.83 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0025 | 388.03 | $3.86 | $1,499.76 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0026 | 30.77 | $3.86 | $118.93 |
06374(44) | 0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | Asphalt Binder Adjustment | 0029 | 114.18 | $5.75 | $657.11 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | * Asphalt Binder Adjustment | 0006 | 0.00 | $0.00 | $-37.97 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0006 | 30.14 | $1.97 | $59.53 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0007 | 43.77 | $4.70 | $205.94 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0008 | 103.52 | $4.70 | $487.07 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0009 | 187.16 | $4.70 | $880.60 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0010 | 375.96 | $4.70 | $1,768.91 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0012 | 147.47 | $4.70 | $693.85 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0014 | 210.35 | $4.70 | $989.71 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0015 | 113.90 | $4.49 | $511.99 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0016 | 1,377.01 | $4.49 | $6,189.73 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0018 | 29.50 | $3.76 | $110.92 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0020 | 106.40 | $3.76 | $400.07 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0021 | 371.60 | $3.76 | $1,397.24 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0022 | 125.85 | $3.76 | $473.20 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0023 | 104.71 | $3.86 | $404.71 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0025 | 425.15 | $3.86 | $1,643.23 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0027 | 226.90 | $4.91 | $1,115.23 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0030 | 127.38 | $5.75 | $733.08 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | * Missing Material Certification | 0030 | -127.38 | $48.00 | $-6,114.24 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | * Missing Material Certification | 0032 | -57.64 | $48.00 | $-2,766.72 |
06374(44) | 0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0032 | 57.64 | $5.96 | $343.83 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Asphalt Binder Adjustment | 0006 | 0.00 | $0.00 | $-6,152.78 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0006 | 2,774.83 | $2.25 | $6,263.35 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0008 | 56.20 | $5.37 | $302.20 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0009 | 177.24 | $5.37 | $953.06 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0010 | 363.63 | $5.37 | $1,955.31 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0011 | 160.99 | $5.37 | $865.68 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0012 | 183.28 | $5.37 | $985.53 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0014 | 14.06 | $5.37 | $75.60 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0015 | 126.96 | $5.13 | $652.22 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0016 | 883.08 | $5.13 | $4,536.56 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0018 | 15.31 | $4.29 | $65.79 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0020 | 108.34 | $4.29 | $465.56 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Material Discrepancy Adjustments | 0021 | -230.92 | $66.00 | $-15,240.72 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0021 | 528.44 | $4.29 | $2,270.81 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0022 | 67.08 | $4.29 | $288.26 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0023 | 56.58 | $4.41 | $249.93 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0025 | 281.19 | $4.41 | $1,242.07 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0027 | 4.10 | $5.61 | $23.03 |
06374(44) | 0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0029 | 95.18 | $6.57 | $626.02 |
06374(44) | 0042 | SOUND BARRIER WALL | * Missing Material Certification | 0019 | -1,337.22 | $155.00 | $-207,269.10 |
06374(44) | 0042 | SOUND BARRIER WALL | * Material Discrepancy Adjustments | 0020 | 1,337.22 | $155.00 | $207,269.10 |
06374(44) | 0048 | 1'-8" COMB. CURB & GUTTER (6" BARRIER) | * Missing Material Certification | 0032 | -730.00 | $17.00 | $-12,410.00 |
06374(44) | 0054 | 6" CONCRETE DIVIDING STRIP | * Missing Material Certification | 0026 | -268.36 | $38.00 | $-10,197.68 |
06374(44) | 0054 | 6" CONCRETE DIVIDING STRIP | * Missing Material Certification | 0030 | 268.36 | $38.00 | $10,197.68 |
06374(44) | 0056 | (PL)TACTILE WARNING DEVICE-NEW | * Missing Material Certification | 0025 | -173.00 | $35.00 | $-6,055.00 |
06374(44) | 0056 | (PL)TACTILE WARNING DEVICE-NEW | * Missing Material Certification | 0028 | -16.00 | $35.00 | $-560.00 |
06374(44) | 0056 | (PL)TACTILE WARNING DEVICE-NEW | * Missing Material Certification | 0030 | -40.00 | $35.00 | $-1,400.00 |
06374(44) | 0056 | (PL)TACTILE WARNING DEVICE-NEW | * Missing Material Certification | 0031 | 189.00 | $35.00 | $6,615.00 |
06374(44) | 0056 | (PL)TACTILE WARNING DEVICE-NEW | * Missing Material Certification | 0032 | -139.00 | $35.00 | $-4,865.00 |
06374(44) | 0061 | MANHOLE FRAME & COVER | * Missing Material Certification | 0017 | -2.00 | $350.00 | $-700.00 |
06374(44) | 0061 | MANHOLE FRAME & COVER | * Missing Material Certification | 0018 | -4.00 | $350.00 | $-1,400.00 |
06374(44) | 0061 | MANHOLE FRAME & COVER | * Missing Material Certification | 0019 | -3.00 | $350.00 | $-1,050.00 |
06374(44) | 0061 | MANHOLE FRAME & COVER | * Material Discrepancy Adjustments | 0020 | -14.00 | $350.00 | $-4,900.00 |
06374(44) | 0061 | MANHOLE FRAME & COVER | * Material Discrepancy Adjustments | 0027 | 23.00 | $350.00 | $8,050.00 |
06374(44) | 0062 | (PL)SPECIAL INLET DRAIN | * Material Discrepancy Adjustments | 0020 | -1.00 | $5,000.00 | $-5,000.00 |
06374(44) | 0062 | (PL)SPECIAL INLET DRAIN | * Missing Material Certification | 0032 | -2.00 | $5,000.00 | $-10,000.00 |
06374(44) | 0063 | INLET CICI DES. 2 (STD) | * Missing Material Certification | 0032 | -2.00 | $2,300.00 | $-4,600.00 |
06374(44) | 0064 | INLET CICI DES. 2 (B) | * Missing Material Certification | 0028 | -7.00 | $2,800.00 | $-19,600.00 |
06374(44) | 0064 | INLET CICI DES. 2 (B) | * Missing Material Certification | 0032 | -4.00 | $2,800.00 | $-11,200.00 |
06374(44) | 0071 | INLET MEDIAN BARRIER DES. 2 | * Missing Material Certification | 0024 | -1.00 | $3,100.00 | $-3,100.00 |
06374(44) | 0071 | INLET MEDIAN BARRIER DES. 2 | * Missing Material Certification | 0027 | -2.00 | $3,100.00 | $-6,200.00 |
06374(44) | 0071 | INLET MEDIAN BARRIER DES. 2 | * Missing Material Certification | 0032 | -1.00 | $1,500.00 | $-1,500.00 |
06374(44) | 0072 | INLET MEDIAN BARRIER DES. 2-2 | * Missing Material Certification | 0019 | -1.00 | $5,100.00 | $-5,100.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Material Discrepancy Adjustments | 0012 | -1,227.00 | $50.00 | $-61,350.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Material Discrepancy Adjustments | 0013 | 1,227.00 | $50.00 | $61,350.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Missing Material Certification | 0015 | -347.00 | $50.00 | $-17,350.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Missing Material Certification | 0016 | -55.00 | $50.00 | $-2,750.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Missing Material Certification | 0017 | -797.00 | $50.00 | $-39,850.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Missing Material Certification | 0018 | -350.00 | $50.00 | $-17,500.00 |
06374(44) | 0082 | 18" R.C.PIPE CLASS III | * Material Discrepancy Adjustments | 0022 | 1,549.00 | $50.00 | $77,450.00 |
06374(44) | 0083 | 24" R.C.PIPE CLASS III | * Missing Material Certification | 0018 | -274.00 | $55.00 | $-15,070.00 |
06374(44) | 0083 | 24" R.C.PIPE CLASS III | * Missing Material Certification | 0023 | 274.00 | $55.00 | $15,070.00 |
06374(44) | 0103 | EDGE DRAIN CONDUIT-PERFORATED | * Missing Material Certification | 0015 | -788.00 | $5.00 | $-3,940.00 |
06374(44) | 0103 | EDGE DRAIN CONDUIT-PERFORATED | * Missing Material Certification | 0016 | -1,709.00 | $5.00 | $-8,545.00 |
06374(44) | 0103 | EDGE DRAIN CONDUIT-PERFORATED | * Missing Material Certification | 0017 | -225.00 | $5.00 | $-1,125.00 |
06374(44) | 0103 | EDGE DRAIN CONDUIT-PERFORATED | * Missing Material Certification | 0019 | -450.00 | $5.00 | $-2,250.00 |
06374(44) | 0103 | EDGE DRAIN CONDUIT-PERFORATED | * Missing Material Certification | 0023 | 15,860.00 | $5.00 | $79,300.00 |
06374(44) | 0103 | EDGE DRAIN CONDUIT-PERFORATED | * Material Discrepancy Adjustments | 0024 | -12,688.00 | $5.00 | $-63,440.00 |
06374(44) | 0109 | MANHOLE (4' DIAMETER) | * Missing Material Certification | 0031 | -4.00 | $2,500.00 | $-10,000.00 |
06374(44) | 0109 | MANHOLE (4' DIAMETER) | * Material Discrepancy Adjustments | 0032 | 1.00 | $2,500.00 | $2,500.00 |
06374(44) | 0109 | MANHOLE (4' DIAMETER) | * Material Discrepancy Adjustments | 0033 | 3.00 | $2,500.00 | $7,500.00 |
06374(44) | 0140 | APPROACH SLAB | * Missing Material Certification | 0019 | -248.00 | $130.00 | $-32,240.00 |
06374(44) | 0140 | APPROACH SLAB | * Material Discrepancy Adjustments | 0025 | 124.00 | $130.00 | $16,120.00 |
06374(44) | 0140 | APPROACH SLAB | * Material Discrepancy Adjustments | 0027 | 124.00 | $130.00 | $16,120.00 |
06374(44) | 0141 | SEALED EXPANSION JOINT | * Missing Material Certification | 0019 | -84.30 | $215.00 | $-18,124.50 |
06374(44) | 0141 | SEALED EXPANSION JOINT | * Material Discrepancy Adjustments | 0025 | 84.30 | $215.00 | $18,124.50 |
06374(44) | 0142 | 42" F-SHAPED PARAPET | * Missing Material Certification | 0019 | -981.60 | $47.00 | $-46,135.20 |
06374(44) | 0142 | 42" F-SHAPED PARAPET | * Material Discrepancy Adjustments | 0025 | 490.80 | $47.00 | $23,067.60 |
06374(44) | 0142 | 42" F-SHAPED PARAPET | * Material Discrepancy Adjustments | 0027 | 490.80 | $47.00 | $23,067.60 |
06374(44) | 0143 | STRUCTURAL STEEL | * Missing Material Certification | 0017 | -2,710.00 | $1.50 | $-4,065.00 |
06374(44) | 0143 | STRUCTURAL STEEL | * Missing Material Certification | 0023 | 2,710.00 | $1.50 | $4,065.00 |
06374(44) | 0147 | SLOPE WALL (5") | * Material Discrepancy Adjustments | 0025 | -387.00 | $70.00 | $-27,090.00 |
06374(44) | 0147 | SLOPE WALL (5") | * Material Discrepancy Adjustments | 0026 | 387.00 | $70.00 | $27,090.00 |
06374(44) | 0154 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0029 | -2,474.00 | $3.00 | $-7,422.00 |
06374(44) | 0154 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0031 | 24,740.00 | $3.00 | $74,220.00 |
06374(44) | 0154 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0032 | -22,266.00 | $3.00 | $-66,798.00 |
06374(44) | 0158 | (SP) SEALER RESIN | * Material Discrepancy Adjustments | 0020 | -17.50 | $80.00 | $-1,400.00 |
06374(44) | 0158 | (SP) SEALER RESIN | * Material Discrepancy Adjustments | 0031 | 17.50 | $80.00 | $1,400.00 |
06374(44) | 0162 | 6" NON-PERF.PIPE UNDERDRAIN RND. | * Missing Material Certification | 0017 | -25.00 | $15.00 | $-375.00 |
06374(44) | 0162 | 6" NON-PERF.PIPE UNDERDRAIN RND. | * Material Discrepancy Adjustments | 0019 | 25.00 | $15.00 | $375.00 |
06374(44) | 0167 | CLSM BACKFILL | * Missing Material Certification | 0026 | -278.00 | $75.00 | $-20,850.00 |
06374(44) | 0167 | CLSM BACKFILL | * Material Discrepancy Adjustments | 0027 | 178.00 | $75.00 | $13,350.00 |
06374(44) | 0167 | CLSM BACKFILL | * Material Discrepancy Adjustments | 0032 | 100.00 | $75.00 | $7,500.00 |
06374(44) | 0171 | 42" F-SHAPED PARAPET | * Material Discrepancy Adjustments | 0029 | -1,082.00 | $47.00 | $-50,854.00 |
06374(44) | 0171 | 42" F-SHAPED PARAPET | * Material Discrepancy Adjustments | 0030 | 1,082.00 | $47.00 | $50,854.00 |
06374(44) | 0174 | STRUCTURAL STEEL | * Missing Material Certification | 0026 | -3,000.00 | $1.50 | $-4,500.00 |
06374(44) | 0174 | STRUCTURAL STEEL | * Material Discrepancy Adjustments | 0028 | 2,807.00 | $1.50 | $4,210.50 |
06374(44) | 0180 | EPOXY COATED REINFORCING STEEL | * Missing Material Certification | 0028 | -109,348.60 | $0.80 | $-87,478.88 |
06374(44) | 0180 | EPOXY COATED REINFORCING STEEL | * Missing Material Certification | 0031 | 109,348.60 | $0.80 | $87,478.88 |
06374(44) | 0185 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0029 | -2,971.00 | $3.00 | $-8,913.00 |
06374(44) | 0185 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0031 | 2,971.00 | $3.00 | $8,913.00 |
06374(44) | 0189 | (SP) SEALER RESIN | * Material Discrepancy Adjustments | 0029 | -19.50 | $80.00 | $-1,560.00 |
06374(44) | 0189 | (SP) SEALER RESIN | * Material Discrepancy Adjustments | 0031 | 2.50 | $80.00 | $200.00 |
06374(44) | 0199 | 42" F-SHAPED PARAPET | * Missing Material Certification | 0017 | -337.00 | $47.00 | $-15,839.00 |
06374(44) | 0199 | 42" F-SHAPED PARAPET | * Material Discrepancy Adjustments | 0025 | 337.00 | $47.00 | $15,839.00 |
06374(44) | 0208 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0029 | -2,121.00 | $3.00 | $-6,363.00 |
06374(44) | 0208 | WATER REPELLENT (VISUALLY INSPECTED) | * Material Discrepancy Adjustments | 0031 | 2,121.00 | $3.00 | $6,363.00 |
06374(44) | 0211 | (SP) SEALER RESIN | * Material Discrepancy Adjustments | 0029 | -23.00 | $80.00 | $-1,840.00 |
06374(44) | 0222 | REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | * Missing Material Certification | 0027 | -5,552.00 | $0.45 | $-2,498.40 |
06374(44) | 0222 | REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | * Material Discrepancy Adjustments | 0029 | -80.00 | $0.45 | $-36.00 |
06374(44) | 0222 | REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | * Missing Material Certification | 0031 | -5,602.00 | $0.45 | $-2,520.90 |
06374(44) | 0243 | REINFORCING STEEL | * Missing Material Certification | 0031 | -7,952.00 | $1.20 | $-9,542.40 |
06374(44) | 0243 | REINFORCING STEEL | * Missing Material Certification | 0033 | -468.00 | $1.20 | $-561.60 |
06374(44) | 0244 | SHEET ALUMINUM SIGNS | * Missing Material Certification | 0030 | -210.25 | $12.00 | $-2,523.00 |
06374(44) | 0244 | SHEET ALUMINUM SIGNS | * Missing Material Certification | 0031 | -294.91 | $12.00 | $-3,538.92 |
06374(44) | 0244 | SHEET ALUMINUM SIGNS | * Missing Material Certification | 0032 | -173.73 | $12.00 | $-2,084.76 |
06374(44) | 0245 | EXTRUDED ALUMINUM PANEL SIGNS | * Missing Material Certification | 0030 | -401.50 | $20.00 | $-8,030.00 |
06374(44) | 0246 | EXTRUDED ALUMINUM PANEL SIGNS(OVERHEAD SIGNS) | * Missing Material Certification | 0030 | -1,916.55 | $20.00 | $-38,331.00 |
06374(44) | 0248 | 3"@7.58 GALV.STEEL PIPE POST | * Missing Material Certification | 0031 | -175.50 | $25.00 | $-4,387.50 |
06374(44) | 0248 | 3"@7.58 GALV.STEEL PIPE POST | * Missing Material Certification | 0032 | -58.50 | $25.00 | $-1,462.50 |
06374(44) | 0250 | 1 3/4" SQUARE TUBE POST | * Missing Material Certification | 0031 | -45.50 | $7.00 | $-318.50 |
06374(44) | 0250 | 1 3/4" SQUARE TUBE POST | * Missing Material Certification | 0032 | -25.66 | $7.00 | $-179.62 |
06374(44) | 0251 | 2" SQUARE TUBE POST | * Missing Material Certification | 0031 | -116.92 | $11.00 | $-1,286.12 |
06374(44) | 0251 | 2" SQUARE TUBE POST | * Material Discrepancy Adjustments | 0032 | 116.92 | $11.00 | $1,286.12 |
06374(44) | 0252 | 2 1/4" SQUARE TUBE POST | * Missing Material Certification | 0031 | -326.96 | $11.00 | $-3,596.56 |
06374(44) | 0252 | 2 1/4" SQUARE TUBE POST | * Material Discrepancy Adjustments | 0032 | 326.96 | $11.00 | $3,596.56 |
06374(44) | 0257 | TRAFFIC STRIPE(PAINT)(4" WIDE) | * Material Discrepancy Adjustments | 0029 | -13,283.00 | $0.30 | $-3,984.90 |
06374(44) | 0257 | TRAFFIC STRIPE(PAINT)(4" WIDE) | * Material Discrepancy Adjustments | 0030 | 13,283.00 | $0.30 | $3,984.90 |
06374(44) | 0259 | (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | * Missing Material Certification | 0027 | -4.00 | $160.00 | $-640.00 |
06374(44) | 0259 | (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | * Material Discrepancy Adjustments | 0028 | 4.00 | $160.00 | $640.00 |
06374(44) | 0259 | (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | * Missing Material Certification | 0033 | -29.00 | $160.00 | $-4,640.00 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Missing Material Certification | 0026 | -3,000.00 | $0.65 | $-1,950.00 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Material Discrepancy Adjustments | 0028 | 3,000.00 | $0.65 | $1,950.00 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Material Discrepancy Adjustments | 0029 | -14,993.00 | $0.65 | $-9,745.45 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Missing Material Certification | 0030 | 9,745.45 | $0.65 | $6,334.54 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Missing Material Certification | 0031 | -22,648.75 | $0.65 | $-14,721.69 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Material Discrepancy Adjustments | 0032 | 27,896.30 | $0.65 | $18,132.60 |
06374(44) | 0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | * Missing Material Certification | 0033 | -3,615.70 | $0.65 | $-2,350.21 |
06374(44) | 0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | * Missing Material Certification | 0026 | -1,848.00 | $0.88 | $-1,626.24 |
06374(44) | 0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | * Material Discrepancy Adjustments | 0028 | 1,280.00 | $0.88 | $1,126.40 |
06374(44) | 0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | * Material Discrepancy Adjustments | 0029 | -8,784.00 | $0.88 | $-7,729.92 |
06374(44) | 0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | * Missing Material Certification | 0030 | 7,729.92 | $0.88 | $6,802.33 |
06374(44) | 0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | * Missing Material Certification | 0031 | -7,224.00 | $0.88 | $-6,357.12 |
06374(44) | 0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | * Material Discrepancy Adjustments | 0032 | 8,846.08 | $0.88 | $7,784.55 |
06374(44) | 0262 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) | * Missing Material Certification | 0026 | -1,347.00 | $2.15 | $-2,896.05 |
06374(44) | 0262 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) | * Material Discrepancy Adjustments | 0029 | -2,912.00 | $2.15 | $-6,260.80 |
06374(44) | 0262 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) | * Missing Material Certification | 0030 | 9,156.85 | $2.15 | $19,687.23 |
06374(44) | 0262 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) | * Missing Material Certification | 0031 | -6,399.75 | $2.15 | $-13,759.46 |
06374(44) | 0262 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) | * Material Discrepancy Adjustments | 0032 | 1,501.90 | $2.15 | $3,229.09 |
06374(44) | 0263 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) | * Missing Material Certification | 0031 | -292.75 | $16.00 | $-4,684.00 |
06374(44) | 0263 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) | * Missing Material Certification | 0033 | -182.50 | $16.00 | $-2,920.00 |
06374(44) | 0263 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) | * Material Discrepancy Adjustments | 0033 | 292.75 | $16.00 | $4,684.00 |
06374(44) | 0272 | JUNCTION BOX(6" X 6" X 4") | * Material Discrepancy Adjustments | 0020 | -1.00 | $450.00 | $-450.00 |
06374(44) | 0272 | JUNCTION BOX(6" X 6" X 4") | * Missing Material Certification | 0033 | -3.00 | $450.00 | $-1,350.00 |
06374(44) | 0273 | PULL BOX(SIZE I) | * Missing Material Certification | 0030 | -9.00 | $515.00 | $-4,635.00 |
06374(44) | 0273 | PULL BOX(SIZE I) | * Missing Material Certification | 0033 | -4.00 | $515.00 | $-2,060.00 |
06374(44) | 0275 | REINFORCING STEEL | * Missing Material Certification | 0016 | -400.80 | $1.40 | $-561.12 |
06374(44) | 0275 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0020 | -467.60 | $1.40 | $-654.64 |
06374(44) | 0275 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0022 | 868.40 | $1.40 | $1,215.76 |
06374(44) | 0275 | REINFORCING STEEL | * Missing Material Certification | 0030 | -647.00 | $1.40 | $-905.80 |
06374(44) | 0275 | REINFORCING STEEL | * Missing Material Certification | 0031 | -100.20 | $1.40 | $-140.28 |
06374(44) | 0275 | REINFORCING STEEL | * Missing Material Certification | 0033 | -334.00 | $1.40 | $-467.60 |
06374(44) | 0281 | 1/C NO.4 ELECTRICAL CONDUCTOR | * Missing Material Certification | 0016 | -6,040.00 | $1.75 | $-10,570.00 |
06374(44) | 0281 | 1/C NO.4 ELECTRICAL CONDUCTOR | * Missing Material Certification | 0018 | -400.00 | $1.75 | $-700.00 |
06374(44) | 0281 | 1/C NO.4 ELECTRICAL CONDUCTOR | * Material Discrepancy Adjustments | 0019 | 6,440.00 | $1.75 | $11,270.00 |
06374(44) | 0283 | 1/C NO.12 ELECTRICAL CONDUCTOR | * Material Discrepancy Adjustments | 0020 | -1,000.00 | $0.65 | $-650.00 |
06374(44) | 0283 | 1/C NO.12 ELECTRICAL CONDUCTOR | * Material Discrepancy Adjustments | 0022 | -4,750.00 | $0.65 | $-3,087.50 |
06374(44) | 0283 | 1/C NO.12 ELECTRICAL CONDUCTOR | * Material Discrepancy Adjustments | 0025 | 5,750.00 | $0.65 | $3,737.50 |
06374(44) | 8001 | RAPID CURE JOINT SEALANT | * Missing Material Certification | 0031 | -318.92 | $10.00 | $-3,189.20 |
06374(44) | 8003 | ELASTOMERIC MORTAR | * Missing Material Certification | 0031 | -91.49 | $200.00 | $-18,298.00 | Subtotals For Line Item Adjustments | $-143,399.09 | * = User applied Line Item Adjustments |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
01 | TIME 'B' BID | 03/01/2011 | 07/12/2012 | 499.00 DYS | $15,000.00 | Y | |||
02 | TIME 'C' BID | 08/17/2011 | 07/12/2012 | 330.00 DYS | $15,000.00 | Y |
MILESTONE ADJUSTMENTS | |||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total |
01 | System Application of Disincentive Adj | 0029 | $-165,000.00 |
01 | System Application of Disincentive Adj | 0030 | $-240,000.00 |
01 | System Application of Disincentive Adj | 0031 | $-450,000.00 |
01 | System Application of Disincentive Adj | 0032 | $-180,000.00 |
02 | System Application of Disincentive Adj | 0029 | $-30,000.00 |
02 | System Application of Disincentive Adj | 0030 | $-240,000.00 |
02 | System Application of Disincentive Adj | 0031 | $-450,000.00 |
02 | System Application of Disincentive Adj | 0032 | $-180,000.00 | Subtotals For Milestones | $-1,935,000.00 |
Contract ID: | 100617 | Estimate Number: | 0034 | Primary JP: | 06374(44) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0100/ROADWAY | ||||||||
0001 | CLEARING AND GRUBBING | 201 0102 | LSUM | 1.000 | 1.000 | 1.000 | $100,000.00 | $0.00 | $100,000.00 | |
0002 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 132,993.000 | 132,993.000 | 132,993.000 | $4.00 | $0.00 | $531,972.00 | |
0003 | UNCLASSIFIED BORROW | 202(C) 0184 | CY | 73,890.000 | 73,890.000 | 59,041.920 | $4.00 | $0.00 | $236,167.68 | |
0004 | TYPE A-SALVAGED TOPSOIL | 205 4229 | LSUM | 1.000 | 1.000 | 1.000 | $200,000.00 | $0.00 | $200,000.00 | |
0005 | TEMPORARY SILT FENCE | 223 2801 | LF | 5,685.000 | 5,685.000 | 9,007.000 | $1.50 | $0.00 | $13,510.50 | |
0006 | TEMPORARY SEDIMENT FILTER | 224 2803 | EA | 50.000 | 50.000 | 11.000 | $50.00 | $0.00 | $550.00 | |
0007 | TEMPORARY SEDIMENT BASIN | 225 2804 | EA | 5.000 | 5.000 | 0.000 | $300.00 | $0.00 | $0.00 | |
0008 | SOLID SLAB SODDING | 230(A) 2806 | SY | 159,003.000 | 159,003.000 | 148,239.640 | $1.10 | $0.00 | $163,063.61 | |
0009 | WATERING | 230(F) 2812 | MGAL | 6,360.000 | 6,360.000 | 67.300 | 4,095.140 | $3.00 | $201.90 | $12,285.42 |
0010 | SEEDING METHOD A | 232(A) 2813 | AC | 32.840 | 32.840 | 0.000 | $200.00 | $0.00 | $0.00 | |
0011 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 68.000 | 68.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
0012 | FERTILIZING (10-20-10) | 234(A) 2824 | TON | 20.850 | 20.850 | 18.810 | $600.00 | $0.00 | $11,286.00 | |
0013 | FERTILIZING (0-46-0) | 234(A) 4406 | TON | 2.470 | 2.470 | 0.000 | $600.00 | $0.00 | $0.00 | |
0014 | MOWING | 241 2832 | AC | 68.000 | 68.000 | 71.010 | $50.00 | $0.00 | $3,550.50 | |
0015 | (PL)STABILIZED CONSTRUCTION EXIT | 242 0400 | EA | 4.000 | 4.000 | 4.000 | $1,500.00 | $0.00 | $6,000.00 | |
0016 | (PL)TEMPORARY INLET SEDIMENT FILTER | 243 0450 | EA | 137.000 | 137.000 | 0.000 | $50.00 | $0.00 | $0.00 | |
0017 | AGGREGATE BASE | 303 0192 | CY | 65,184.000 | 65,184.000 | 65,184.000 | $27.00 | $0.00 | $1,759,968.00 | |
0018 | OPEN GRADED BITUMINOUS BASE | 319 5190 | TON | 32,168.000 | 32,168.000 | 32,168.000 | $38.00 | $0.00 | $1,222,384.00 | |
0019 | SEPARATOR FABRIC | 325 5271 | SY | 547,681.000 | 547,681.000 | 547,681.000 | $0.85 | $0.00 | $465,528.88 | |
0020 | (SP)MODIFIED SUBGRADE | 327(J) 4290 | SY | 191,576.000 | 191,576.000 | 191,576.000 | $2.80 | $0.00 | $536,412.80 | |
0021 | (SP)GEOSYNTHETIC SUBGRADE REINFORCEMENT | 328 2600 | SY | 1,000.000 | 1,000.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0022 | TRAFFIC BOUND SURFACE COURSE TYPE E | 403(E) 0225 | TON | 500.000 | 500.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
0023 | (SP)ASPHALT CONCRETE TYPE S2(PG 64-22 OK) | 411(S2) 5930 | TON | 1,722.000 | 1,722.000 | 1,790.010 | $47.00 | $0.00 | $84,130.47 | |
0024 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | 411(S3) 5940 | TON | 1,672.000 | 1,672.000 | 1,960.460 | $62.00 | $0.00 | $121,548.52 | |
0025 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 411(S3) 5945 | TON | 2,477.000 | 2,477.000 | 4,164.410 | $48.00 | $0.00 | $199,891.68 | |
0026 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 6,811.000 | 6,811.000 | 0.000 | 8,682.340 | $66.00 | $0.00 | $573,034.44 |
0027 | (SP)P.C.CONCRETE PAVEMENT(PLACEMENT) | 414(A) 0210 | SY | 31,341.000 | 31,341.000 | 31,341.000 | $9.00 | $0.00 | $282,069.00 | |
0028 | (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 414(A1) 5725 | SY | 84,191.000 | 84,191.000 | 0.000 | 84,191.000 | $15.00 | $0.00 | $1,262,865.00 |
0029 | 9" H.E.S. CONCRETE (PATCHING) | 414(B) 5072 | SY | 1,000.000 | 1,000.000 | 390.360 | $65.00 | $0.00 | $25,373.40 | |
0030 | (SP)CONT. REINF. P.C.C. PAVEMENT(PLACEMENT) | 414(D) 4425 | SY | 49,230.000 | 49,230.000 | 0.000 | 49,230.000 | $23.00 | $0.00 | $1,132,290.00 |
0031 | TERMINAL JOINT | 414(F) 5262 | EA | 14.000 | 14.000 | 14.000 | $5,000.00 | $0.00 | $70,000.00 | |
0032 | TERMINAL JOINT SLEEPER SLAB | 414(G) 5263 | SY | 733.320 | 733.320 | 733.320 | $55.00 | $0.00 | $40,332.61 | |
0033 | (SP)P.C. CONCRETE FOR PAVEMENT | 414(P) 6000 | CY | 47,923.000 | 47,923.000 | 45,631.560 | $82.00 | $0.00 | $3,741,787.92 | |
0034 | COLD MILLING PAVEMENT | 417 5267 | SY | 38,878.000 | 38,878.000 | 49,064.000 | $1.00 | $0.00 | $49,064.00 | |
0035 | STRUCTURAL EXCAVATION UNCLASSIFIED | 501(A) 0313 | CY | 477.000 | 477.000 | 474.000 | $40.00 | $0.00 | $18,960.00 | |
0036 | 42" F-SHAPED PARAPET | 504(F) 6190 | LF | 515.000 | 515.000 | 515.000 | $55.00 | $0.00 | $28,325.00 | |
0037 | CLASS A CONCRETE | 509(B) 0321 | CY | 1,486.730 | 1,486.730 | 1,484.170 | $325.00 | $0.00 | $482,355.25 | |
0038 | CLASS A CONCRETE (MEDIAN BARRIER, DES.1-A) | 509(B) 4153 | CY | 288.940 | 288.940 | 224.420 | 368.890 | $200.00 | $44,884.00 | $73,778.00 |
0039 | CLASS A CONCRETE FOR SMALL STRUCTURES | 509(C) 0322 | CY | 16.420 | 16.420 | 16.420 | $285.00 | $0.00 | $4,679.70 | |
0040 | CLASS C CONCRETE | 509(D) 0325 | CY | 128.710 | 128.710 | 126.720 | $250.00 | $0.00 | $31,680.00 | |
0041 | RETAINING WALL | 510(A) 6333 | SY | 2,623.200 | 2,623.200 | 2,623.100 | $340.00 | $0.00 | $891,854.00 | |
0042 | SOUND BARRIER WALL | 510(B) 6334 | SY | 10,768.700 | 10,768.700 | 0.000 | 10,941.690 | $155.00 | $0.00 | $1,695,961.95 |
0043 | REINFORCING STEEL | 511(A) 0332 | LB | 239,269.000 | 239,269.000 | 5,701.410 | 232,738.660 | $0.40 | $2,280.56 | $93,095.46 |
0044 | DRILLED SHAFTS 30" DIAMETER | 516(A) 6091 | LF | 5,735.000 | 5,735.000 | 5,820.000 | $95.00 | $0.00 | $552,900.00 | |
0045 | CONCRETE CURB (4" MNTBLE-INTEGRAL) | 609(A) 0287 | LF | 3,508.000 | 3,508.000 | 2,649.200 | $3.00 | $0.00 | $7,947.60 | |
0046 | CONCRETE CURB (6" BARRIER-INTEGRAL) | 609(A) 0300 | LF | 20,140.000 | 20,140.000 | 20,440.350 | $4.00 | $0.00 | $81,761.40 | |
0047 | CONCRETE CURB (8" BARRIER-INTEGRAL) | 609(A) 0380 | LF | 14,015.000 | 14,015.000 | 0.000 | 11,289.000 | $5.00 | $0.00 | $56,445.00 |
0048 | 1'-8" COMB. CURB & GUTTER (6" BARRIER) | 609(B) 1513 | LF | 1,197.000 | 1,197.000 | 1,512.000 | $17.00 | $0.00 | $25,704.00 | |
0049 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 4,131.000 | 4,131.000 | 1,554.200 | $28.00 | $0.00 | $43,517.60 | |
0050 | (PL)4" DECORATIVE CONCRETE SIDEWALK | 610(A) 0650 | SY | 16.000 | 16.000 | 0.000 | $75.00 | $0.00 | $0.00 | |
0051 | (PL)6" DECORATIVE CONCRETE SIDEWALK | 610(A) 0654 | SY | 187.000 | 187.000 | 604.790 | $80.00 | $0.00 | $48,383.20 | |
0052 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 3,499.000 | 3,499.000 | 3,916.840 | $40.00 | $0.00 | $156,673.60 | |
0053 | 4" CONCRETE DIVIDING STRIP | 610(C) 0608 | SY | 241.000 | 241.000 | 254.620 | 254.620 | $25.00 | $6,365.50 | $6,365.50 |
0054 | 6" CONCRETE DIVIDING STRIP | 610(C) 0609 | SY | 394.000 | 394.000 | 417.080 | $38.00 | $0.00 | $15,849.04 | |
0055 | DECORATIVE MEDIAN CONCRETE | 610(C) 5824 | SY | 877.000 | 877.000 | 0.000 | 4,144.910 | $80.00 | $0.00 | $331,592.80 |
0056 | (PL)TACTILE WARNING DEVICE-NEW | 610(I) 4610 | SF | 208.000 | 208.000 | 432.000 | $35.00 | $0.00 | $15,120.00 | |
0057 | MANHOLE (4' DIAMETER) | 611(A) 2657 | EA | 68.000 | 68.000 | 0.000 | 69.000 | $2,000.00 | $0.00 | $138,000.00 |
0058 | MANHOLE (5' DIAMETER) | 611(A) 2658 | EA | 6.000 | 6.000 | 0.000 | 6.000 | $3,200.00 | $0.00 | $19,200.00 |
0059 | MANHOLE (6' DIAMETER) | 611(A) 2659 | EA | 7.000 | 7.000 | 0.000 | 7.000 | $5,600.00 | $0.00 | $39,200.00 |
0060 | SPECIAL MANHOLE | 611(C) 0484 | CF | 6,805.000 | 6,805.000 | -2,731.410 | 4,073.440 | $17.00 | $-46,433.97 | $69,248.48 |
0061 | MANHOLE FRAME & COVER | 611(D) 4215 | EA | 112.000 | 112.000 | 112.000 | $350.00 | $0.00 | $39,200.00 | |
0062 | (PL)SPECIAL INLET DRAIN | 611(E) 4012 | EA | 3.000 | 3.000 | 0.000 | 3.000 | $5,000.00 | $0.00 | $15,000.00 |
0063 | INLET CICI DES. 2 (STD) | 611(E) 5112 | EA | 49.000 | 49.000 | 0.000 | 48.000 | $2,300.00 | $0.00 | $110,400.00 |
0064 | INLET CICI DES. 2 (B) | 611(E) 5113 | EA | 52.000 | 52.000 | 0.000 | 52.000 | $2,800.00 | $0.00 | $145,600.00 |
0065 | INLET CICI DES. 2 (D) | 611(E) 5115 | EA | 16.000 | 16.000 | 0.000 | 16.000 | $3,200.00 | $0.00 | $51,200.00 |
0066 | INLET CICI DES. 2 (2B) | 611(E) 5117 | EA | 1.000 | 1.000 | 1.000 | $3,200.00 | $0.00 | $3,200.00 | |
0067 | INLET CICI DES. 3 (2B) | 611(E) 5123 | EA | 3.000 | 3.000 | 0.000 | 3.000 | $5,200.00 | $0.00 | $15,600.00 |
0068 | INLET GPI TYPE 2 (DES. 8) | 611(E) 5334 | EA | 7.000 | 7.000 | 0.000 | 7.000 | $3,800.00 | $0.00 | $26,600.00 |
0069 | INLET GPI TYPE 2 (DES. 10) | 611(E) 5336 | EA | 2.000 | 2.000 | 0.000 | 2.000 | $4,100.00 | $0.00 | $8,200.00 |
0070 | INLET GPI TYPE 2 (DES. 14) | 611(E) 5340 | EA | 1.000 | 1.000 | 1.000 | $4,300.00 | $0.00 | $4,300.00 | |
0071 | INLET MEDIAN BARRIER DES. 2 | 611(E) 5692 | EA | 9.000 | 9.000 | 0.000 | 9.000 | $3,100.00 | $0.00 | $27,900.00 |
0072 | INLET MEDIAN BARRIER DES. 2-2 | 611(E) 5693 | EA | 13.000 | 13.000 | 0.000 | 13.000 | $5,100.00 | $0.00 | $66,300.00 |
0073 | INLET W/LRG.JCT.BOX,CICI-JB-1,DES.2 | 611(E) 5870 | EA | 1.000 | 1.000 | 1.000 | $7,600.00 | $0.00 | $7,600.00 | |
0074 | INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(B) | 611(E) 5972 | EA | 4.000 | 4.000 | 0.000 | 4.000 | $6,100.00 | $0.00 | $24,400.00 |
0075 | INLET (SMD-TYPE 1) | 611(E) 6000 | EA | 12.000 | 12.000 | 0.000 | 12.000 | $3,100.00 | $0.00 | $37,200.00 |
0076 | INLET (SMD-TYPE 2) | 611(E) 6002 | EA | 3.000 | 3.000 | 0.000 | 3.000 | $2,800.00 | $0.00 | $8,400.00 |
0077 | INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) | 611(G) 4488 | EA | 318.000 | 318.000 | 0.000 | 316.000 | $350.00 | $0.00 | $110,600.00 |
0078 | CAST IRON CURB INLETS | 611(K) 4488 | EA | 464.000 | 464.000 | 0.000 | 462.000 | $255.00 | $0.00 | $117,810.00 |
0079 | DROP INLET GRATE (24" SPDI) | 611(L) 4479 | EA | 1.000 | 1.000 | 0.000 | 1.000 | $1,500.00 | $0.00 | $1,500.00 |
0080 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 8.000 | 8.000 | 8.000 | $800.00 | $0.00 | $6,400.00 | |
0081 | INLETS ADJUST TO GRADE | 612(E) 0645 | EA | 1.000 | 1.000 | 1.000 | $1,100.00 | $0.00 | $1,100.00 | |
0082 | 18" R.C.PIPE CLASS III | 613(B) 0491 | LF | 8,731.000 | 8,731.000 | 8,533.000 | $50.00 | $0.00 | $426,650.00 | |
0083 | 24" R.C.PIPE CLASS III | 613(B) 0492 | LF | 2,778.000 | 2,778.000 | 2,985.000 | $55.00 | $0.00 | $164,175.00 | |
0084 | 30" R.C.PIPE CLASS III | 613(B) 0493 | LF | 149.000 | 149.000 | 0.000 | 149.000 | $63.00 | $0.00 | $9,387.00 |
0085 | 36" R.C.PIPE CLASS III | 613(B) 0494 | LF | 1,351.000 | 1,351.000 | 1,351.000 | $75.00 | $0.00 | $101,325.00 | |
0086 | 48" R.C.PIPE CLASS III | 613(B) 0496 | LF | 226.000 | 226.000 | 226.000 | $98.00 | $0.00 | $22,148.00 | |
0087 | 24" X 38" R.C.PIPE ELLIPTICAL CLASS HE-III | 613(B) 4505 | LF | 198.000 | 198.000 | 198.000 | $86.00 | $0.00 | $17,028.00 | |
0088 | 18" CORR. GALV. STEEL PIPE | 613(D) 0689 | LF | 6.000 | 6.000 | 0.000 | $24.00 | $0.00 | $0.00 | |
0089 | 24" CORR. GALV. STEEL PIPE | 613(D) 0690 | LF | 4.000 | 4.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0090 | 18" PREFAB. CULVERT END SECTION, ROUND | 613(M) 5726 | EA | 1.000 | 1.000 | 1.000 | $900.00 | $0.00 | $900.00 | |
0091 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 619(A) 0920 | LSUM | 1.000 | 1.000 | 1.000 | $300,000.00 | $0.00 | $300,000.00 | |
0092 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 33,795.000 | 33,795.000 | 33,795.000 | $3.00 | $0.00 | $101,385.00 | |
0093 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 99,350.000 | 99,350.000 | 99,350.000 | $2.50 | $0.00 | $248,375.01 | |
0094 | REMOVAL OF DRAINAGE INLETS | 619(B) 4741 | EA | 40.000 | 40.000 | 40.000 | $300.00 | $0.00 | $12,000.00 | |
0095 | REMOVAL OF MANHOLES | 619(B) 4742 | EA | 27.000 | 27.000 | 27.000 | $300.00 | $0.00 | $8,100.00 | |
0096 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 1,297.000 | 1,297.000 | 1,297.000 | $7.00 | $0.00 | $9,079.00 | |
0097 | REMOVAL OF GUARD RAIL | 619(B) 4780 | LF | 321.000 | 321.000 | 321.000 | $3.00 | $0.00 | $963.00 | |
0098 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 1,569.000 | 1,569.000 | 1,569.000 | $5.00 | $0.00 | $7,845.00 | |
0099 | REMOVAL OF CONCRETE MEDIAN BARRIER | 619(B) 4915 | LF | 7,196.000 | 7,196.000 | 7,196.000 | $4.00 | $0.00 | $28,784.00 | |
0100 | REMOVAL OF 6" CONCRETE DIVIDING STRIP | 619(B) 6132 | SY | 990.000 | 990.000 | 990.000 | $7.00 | $0.00 | $6,930.00 | |
0101 | PRECAST CONCRETE MEDIAN BARRIER, TYPE I | 627(A) 4310 | LF | 3,721.000 | 0.000 | 0.000 | 3,103.000 | $25.00 | $0.00 | $77,575.00 |
0102 | CONCRETE MEDIAN BARRIER, DESIGN 1 | 627(I) 4317 | LF | 5,473.000 | 5,473.000 | 4,922.780 | $40.00 | $0.00 | $196,911.20 | |
0103 | EDGE DRAIN CONDUIT-PERFORATED | 653(A) 5915 | LF | 36,547.000 | 36,547.000 | 0.000 | 37,103.000 | $5.00 | $0.00 | $185,515.00 |
0104 | EDGE DRAIN OUTLET LATERAL-NONPERFORATED | 653(B) 5916 | LF | 285.000 | 285.000 | 135.000 | $5.00 | $0.00 | $675.00 | |
0105 | OUTLET LATERAL HEADWALL | 653(C) 5946 | EA | 13.000 | 13.000 | 0.000 | 4.000 | $400.00 | $0.00 | $1,600.00 |
0106 | (PL)IMPACT ATTENUATOR | 871 8325 | EA | 6.000 | 6.000 | 0.000 | 5.000 | $20,000.00 | $0.00 | $100,000.00 |
0107 | (PL)REMOVAL OF HIGH MAST TOWER | 890(A) 8708 | EA | 2.000 | 2.000 | 2.000 | $3,000.00 | $0.00 | $6,000.00 | |
Subtotals For Category 0100/ROADWAY | $7,297.99 | $20,635,524.22 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0101/SANITARY SEWER | ||||||||
0108 | FILTER FABRIC | 602(C) 4205 | SY | 19,059.000 | 19,059.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0109 | MANHOLE (4' DIAMETER) | 611(A) 2657 | EA | 7.000 | 7.000 | 0.000 | 7.000 | $2,500.00 | $0.00 | $17,500.00 |
0110 | MANHOLE (5' DIAMETER) | 611(A) 2658 | EA | 21.000 | 21.000 | 21.000 | $5,500.00 | $0.00 | $115,500.00 | |
0111 | ADD'L.DEPTH IN MANHOLE (4' DIAMETER) | 611(B) 2680 | VF | 14.000 | 14.000 | 14.140 | $200.00 | $0.00 | $2,828.00 | |
0112 | ADD'L.DEPTH IN MANHOLE (5' DIAMETER) | 611(B) 2681 | VF | 213.000 | 213.000 | 213.140 | $550.00 | $0.00 | $117,227.00 | |
0113 | MANHOLE FRAME & COVER | 611(D) 4215 | EA | 28.000 | 28.000 | 28.000 | $400.00 | $0.00 | $11,200.00 | |
0114 | 8" POLYVINYL CHLORIDE (PVC) PIPE | 615(C) 6120 | LF | 284.000 | 284.000 | 299.000 | $60.00 | $0.00 | $17,940.00 | |
0115 | SANITARY SEWER SERVICE CONNECTION | 615(D) 0300 | EA | 4.000 | 4.000 | 7.000 | $3,000.00 | $0.00 | $21,000.00 | |
0116 | 18" DUCTILE IRON PIPE | 616(A) 5125 | LF | 5,113.000 | 5,113.000 | 0.000 | 5,113.000 | $170.00 | $0.00 | $869,210.00 |
0117 | (PL)36" STEEL CASING | 616(I) 5273 | LF | 295.000 | 295.000 | 473.000 | $55.00 | $0.00 | $26,015.00 | |
0118 | BORE AND JACK 36" CASING | 616(U) 6230 | LF | 220.000 | 220.000 | 400.000 | $400.00 | $0.00 | $160,000.00 | |
8008 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 0.000 | 2.000 | 0.000 | $3,994.68 | $0.00 | $0.00 | |
Subtotals For Category 0101/SANITARY SEWER | $0.00 | $1,358,420.00 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0102/WATERLINE | ||||||||
0119 | 6" DUCTILE IRON PIPE | 616(A) 5121 | LF | 2,050.000 | 2,050.000 | 823.210 | $60.00 | $0.00 | $49,392.60 | |
0120 | 8" DUCTILE IRON PIPE | 616(A) 5122 | LF | 89.000 | 89.000 | 49.000 | $90.00 | $0.00 | $4,410.00 | |
0121 | 12" DUCTILE IRON PIPE | 616(A) 5124 | LF | 1,672.000 | 1,672.000 | 1,695.000 | $110.00 | $0.00 | $186,450.00 | |
0122 | 16" DUCTILE IRON PIPE | 616(A) 5894 | LF | 1,394.000 | 1,394.000 | 1,394.000 | $130.00 | $0.00 | $181,220.00 | |
0123 | 2" POLYVINYL CHLORIDE (PVC) PIPE | 616(B) 5218 | LF | 68.000 | 68.000 | 34.000 | $75.00 | $0.00 | $2,550.00 | |
0124 | 6" POLYVINYL CHLORIDE (PVC) PIPE | 616(B) 5223 | LF | 3,564.000 | 3,564.000 | 4,997.000 | $70.00 | $0.00 | $349,790.00 | |
0125 | 8" POLYVINYL CHLORIDE (PVC) PIPE | 616(B) 5225 | LF | 153.000 | 153.000 | 193.000 | $100.00 | $0.00 | $19,300.00 | |
0126 | 6" GATE VALVE | 616(D) 1070 | EA | 25.000 | 25.000 | 0.000 | 20.000 | $1,000.00 | $0.00 | $20,000.00 |
0127 | 8" GATE VALVE | 616(D) 1080 | EA | 4.000 | 4.000 | 3.000 | $1,500.00 | $0.00 | $4,500.00 | |
0128 | 12" GATE VALVE | 616(D) 1100 | EA | 5.000 | 5.000 | 4.000 | $2,500.00 | $0.00 | $10,000.00 | |
0129 | 16" GATE VALVE | 616(D) 1125 | EA | 2.000 | 2.000 | 2.000 | $6,500.00 | $0.00 | $13,000.00 | |
0130 | FIRE HYDRANTS | 616(G) 1192 | EA | 8.000 | 8.000 | 8.000 | $2,500.00 | $0.00 | $20,000.00 | |
0131 | (PL)18" STEEL CASING | 616(I) 5264 | LF | 181.000 | 181.000 | 181.000 | $20.00 | $0.00 | $3,620.00 | |
0132 | (PL)30" STEEL CASING | 616(I) 5272 | LF | 64.000 | 64.000 | 64.000 | $30.00 | $0.00 | $1,920.00 | |
0133 | SERVICE CONNECTION (SHORT) | 616(N) 0090 | EA | 11.000 | 11.000 | 21.000 | $1,200.00 | $0.00 | $25,200.00 | |
0134 | SHORT WATER SERVICE & RESET METER | 616(N) 0094 | EA | 13.000 | 13.000 | 15.000 | $1,000.00 | $0.00 | $15,000.00 | |
0135 | BORE AND JACK 18" CASING | 616(U) 6205 | LF | 181.000 | 181.000 | 181.000 | $240.00 | $0.00 | $43,440.00 | |
0136 | BORE AND JACK 30" CASING | 616(U) 6220 | LF | 64.000 | 64.000 | 64.000 | $340.00 | $0.00 | $21,760.00 | |
8013 | 24" CONCRETE TO DUCTILE IRON ADAPTER | 616(L) 0300 | EA | 0.000 | 2.000 | 2.000 | $6,521.00 | $0.00 | $13,042.00 | |
Subtotals For Category 0102/WATERLINE | $0.00 | $984,594.60 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0200/BRIDGE 'A' | ||||||||
0137 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 120.000 | 120.000 | 120.000 | $15.00 | $0.00 | $1,800.00 | |
0138 | CLSM BACKFILL | 501(G) 6309 | CY | 227.000 | 227.000 | 227.000 | $75.00 | $0.00 | $17,025.00 | |
0139 | PRESTRESSED CONCRETE BEAMS (TYPE IV) | 503(A) 1313 | LF | 2,692.800 | 2,692.800 | 2,692.800 | $160.00 | $0.00 | $430,848.00 | |
0140 | APPROACH SLAB | 504(A) 1304 | SY | 248.000 | 248.000 | 248.000 | $130.00 | $0.00 | $32,240.00 | |
0141 | SEALED EXPANSION JOINT | 504(C) 6250 | LF | 84.300 | 84.300 | 84.300 | $215.00 | $0.00 | $18,124.50 | |
0142 | 42" F-SHAPED PARAPET | 504(F) 6190 | LF | 981.600 | 981.600 | 981.600 | $47.00 | $0.00 | $46,135.20 | |
0143 | STRUCTURAL STEEL | 506(A) 1322 | LB | 2,710.000 | 2,710.000 | 2,710.000 | $1.50 | $0.00 | $4,065.00 | |
0144 | (PL)SPECIAL CONCRETE FINISH | 509 6152 | SY | 307.000 | 307.000 | 307.000 | $32.00 | $0.00 | $9,824.00 | |
0145 | CLASS AA CONCRETE | 509(A) 1326 | CY | 640.200 | 640.200 | 640.200 | $360.00 | $0.00 | $230,472.00 | |
0146 | CLASS A CONCRETE | 509(B) 1328 | CY | 447.200 | 447.200 | 447.200 | $360.00 | $0.00 | $160,992.00 | |
0147 | SLOPE WALL (5") | 510(C) 6138 | SY | 387.000 | 387.000 | -100.720 | 487.720 | $70.00 | $-7,050.40 | $34,140.40 |
0148 | REINFORCING STEEL | 511(A) 1332 | LB | 3,420.000 | 3,420.000 | 3,420.000 | $0.70 | $0.00 | $2,394.00 | |
0149 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 224,550.000 | 224,550.000 | 224,550.000 | $0.80 | $0.00 | $179,640.00 | |
0150 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 50.000 | 50.000 | 50.000 | $21.00 | $0.00 | $1,050.00 | |
0151 | PILES, FURNISHED (HP 12X53) | 514(A) 6011 | LF | 618.000 | 618.000 | 618.000 | $28.00 | $0.00 | $17,304.00 | |
0152 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 50.000 | 50.000 | 49.500 | $10.00 | $0.00 | $495.00 | |
0153 | PILES, DRIVEN (HP 12X53) | 514(B) 6294 | LF | 618.000 | 618.000 | 615.940 | $10.00 | $0.00 | $6,159.40 | |
0154 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 2,474.000 | 2,474.000 | 2,474.000 | $3.00 | $0.00 | $7,422.00 | |
0155 | DRILLED SHAFTS 60" DIAMETER | 516(A) 6096 | LF | 88.000 | 88.000 | 0.000 | 88.000 | $450.00 | $0.00 | $39,600.00 |
0156 | DRILLED SHAFTS 72" DIAMETER | 516(A) 6098 | LF | 202.000 | 202.000 | 0.000 | 202.000 | $650.00 | $0.00 | $131,300.00 |
0157 | (SP) SEALER CRACK PREPARATION | 523(A) 6550 | LF | 783.000 | 783.000 | 783.000 | $3.00 | $0.00 | $2,349.00 | |
0158 | (SP) SEALER RESIN | 523(B) 6560 | GAL | 17.500 | 17.500 | 17.500 | $80.00 | $0.00 | $1,400.00 | |
0159 | (PL)FIXED BEARING ASSEMBLY | 535 6164 | EA | 32.000 | 32.000 | 32.000 | $550.00 | $0.00 | $17,600.00 | |
0160 | (PL)EXPANSION BEARING ASSEMBLY | 535 6165 | EA | 22.000 | 22.000 | 22.000 | $700.00 | $0.00 | $15,400.00 | |
0161 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(P) 6204 | LF | 75.000 | 75.000 | 75.000 | $30.00 | $0.00 | $2,250.00 | |
0162 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(Q) 6207 | LF | 25.000 | 25.000 | 25.000 | $15.00 | $0.00 | $375.00 | |
0163 | (PL)REMOVAL OF BRIDGE ITEMS | 619(B) 2500 | LSUM | 1.000 | 1.000 | 1.000 | $70,000.00 | $0.00 | $70,000.00 | |
0164 | (PL)REMOVAL OF BRIDGE ITEM (TYPE A) | 619(B) 2510 | LSUM | 1.000 | 1.000 | 1.000 | $5,000.00 | $0.00 | $5,000.00 | |
8014 | CONSTRUCTION MISCELLANEOUS | 104 0700 | LSUM | 0.000 | 1.000 | 0.000 | $14,405.59 | $0.00 | $0.00 | |
Subtotals For Category 0200/BRIDGE 'A' | $-7,050.40 | $1,485,404.50 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0201/BRIDGE 'B' | ||||||||
0165 | SELECT BORROW | 202(D) 1303 | CY | 95.000 | 95.000 | 0.000 | 95.000 | $25.00 | $0.00 | $2,375.00 |
0166 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 315.000 | 315.000 | 315.000 | $15.00 | $0.00 | $4,725.00 | |
0167 | CLSM BACKFILL | 501(G) 6309 | CY | 278.000 | 278.000 | 278.000 | $75.00 | $0.00 | $20,850.00 | |
0168 | PRESTRESSED CONCRETE BEAMS (TYPE IV) | 503(A) 1313 | LF | 2,892.100 | 2,892.100 | 0.000 | 2,892.100 | $160.00 | $0.00 | $462,736.00 |
0169 | APPROACH SLAB | 504(A) 1304 | SY | 248.000 | 248.000 | 248.000 | $130.00 | $0.00 | $32,240.00 | |
0170 | SEALED EXPANSION JOINT | 504(C) 6250 | LF | 70.000 | 70.000 | 70.000 | $215.00 | $0.00 | $15,050.00 | |
0171 | 42" F-SHAPED PARAPET | 504(F) 6190 | LF | 1,082.100 | 1,082.100 | 1,082.100 | $47.00 | $0.00 | $50,858.70 | |
0172 | RAPID CURE JOINT SEALANT | 504(H) 6390 | LF | 70.500 | 70.500 | 70.500 | $30.00 | $0.00 | $2,115.00 | |
0173 | ELASTOMERIC MORTAR | 504(I) 6389 | CF | 18.700 | 18.700 | 18.700 | $400.00 | $0.00 | $7,480.00 | |
0174 | STRUCTURAL STEEL | 506(A) 1322 | LB | 3,000.000 | 3,000.000 | 3,000.000 | $1.50 | $0.00 | $4,500.00 | |
0175 | (PL)SPECIAL CONCRETE FINISH | 509 6152 | SY | 546.000 | 546.000 | 546.000 | $32.00 | $0.00 | $17,472.00 | |
0176 | CLASS AA CONCRETE | 509(A) 1326 | CY | 867.100 | 867.100 | 867.100 | $360.00 | $0.00 | $312,156.00 | |
0177 | CLASS A CONCRETE | 509(B) 1328 | CY | 501.200 | 501.200 | 501.200 | $360.00 | $0.00 | $180,432.00 | |
0178 | SLOPE WALL (5") | 510(C) 6138 | SY | 386.000 | 386.000 | -100.720 | 486.720 | $70.00 | $-7,050.40 | $34,070.40 |
0179 | REINFORCING STEEL | 511(A) 1332 | LB | 4,130.000 | 4,130.000 | 4,130.000 | $0.70 | $0.00 | $2,891.00 | |
0180 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 276,850.000 | 276,850.000 | 0.000 | 276,850.000 | $0.80 | $0.00 | $221,480.00 |
0181 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 50.000 | 50.000 | 50.000 | $21.00 | $0.00 | $1,050.00 | |
0182 | PILES, FURNISHED (HP 12X53) | 514(A) 6011 | LF | 618.000 | 618.000 | 618.000 | $28.00 | $0.00 | $17,304.00 | |
0183 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 50.000 | 50.000 | 51.500 | $10.00 | $0.00 | $515.00 | |
0184 | PILES, DRIVEN (HP 12X53) | 514(B) 6294 | LF | 618.000 | 618.000 | 614.040 | $10.00 | $0.00 | $6,140.40 | |
0185 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 2,971.000 | 2,971.000 | 2,971.000 | $3.00 | $0.00 | $8,913.00 | |
0186 | DRILLED SHAFTS 60" DIAMETER | 516(A) 6096 | LF | 80.000 | 80.000 | 80.000 | $450.00 | $0.00 | $36,000.00 | |
0187 | DRILLED SHAFTS 72" DIAMETER | 516(A) 6098 | LF | 238.000 | 238.000 | 238.000 | $650.00 | $0.00 | $154,700.00 | |
0188 | (SP) SEALER CRACK PREPARATION | 523(A) 6550 | LF | 915.000 | 915.000 | 915.000 | $3.00 | $0.00 | $2,745.00 | |
0189 | (SP) SEALER RESIN | 523(B) 6560 | GAL | 19.500 | 19.500 | 19.500 | $80.00 | $0.00 | $1,560.00 | |
0190 | (PL)FIXED BEARING ASSEMBLY | 535 6164 | EA | 36.000 | 36.000 | 36.000 | $550.00 | $0.00 | $19,800.00 | |
0191 | (PL)EXPANSION BEARING ASSEMBLY | 535 6165 | EA | 22.000 | 22.000 | 22.000 | $700.00 | $0.00 | $15,400.00 | |
0192 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(P) 6204 | LF | 75.000 | 75.000 | 75.000 | $30.00 | $0.00 | $2,250.00 | |
0193 | (PL)REMOVAL OF BRIDGE ITEMS | 619(B) 2500 | LSUM | 1.000 | 1.000 | 1.000 | $70,000.00 | $0.00 | $70,000.00 | |
0194 | (PL)REMOVAL OF BRIDGE ITEM (TYPE A) | 619(B) 2510 | LSUM | 1.000 | 1.000 | 1.000 | $5,000.00 | $0.00 | $5,000.00 | |
Subtotals For Category 0201/BRIDGE 'B' | $-7,050.40 | $1,712,808.50 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0202/BRIDGE 'C' | ||||||||
0195 | SELECT BORROW | 202(D) 1303 | CY | 80.000 | 80.000 | 0.000 | 80.000 | $25.00 | $0.00 | $2,000.00 |
0196 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 400.000 | 400.000 | 400.000 | $15.00 | $0.00 | $6,000.00 | |
0197 | CLSM BACKFILL | 501(G) 6309 | CY | 583.000 | 583.000 | 583.000 | $75.00 | $0.00 | $43,725.00 | |
0198 | APPROACH SLAB | 504(A) 1304 | SY | 765.000 | 765.000 | 765.000 | $130.00 | $0.00 | $99,450.00 | |
0199 | 42" F-SHAPED PARAPET | 504(F) 6190 | LF | 674.000 | 674.000 | 674.000 | $47.00 | $0.00 | $31,678.00 | |
0200 | STRUCTURAL STEEL | 506(A) 1322 | LB | 716,890.000 | 716,890.000 | 716,890.000 | $1.30 | $0.00 | $931,957.00 | |
0201 | (PL)SPECIAL CONCRETE FINISH | 509 6152 | SY | 2,871.000 | 2,871.000 | 2,871.000 | $32.00 | $0.00 | $91,872.00 | |
0202 | CLASS AA CONCRETE | 509(A) 1326 | CY | 1,220.700 | 1,220.700 | 1,220.700 | $360.00 | $0.00 | $439,452.00 | |
0203 | CLASS A CONCRETE | 509(B) 1328 | CY | 847.600 | 847.600 | 847.600 | $360.00 | $0.00 | $305,136.00 | |
0204 | SLOPE WALL (5") | 510(C) 6138 | SY | 1,314.000 | 1,314.000 | 1,314.000 | $70.00 | $0.00 | $91,980.00 | |
0205 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 394,100.000 | 394,100.000 | 394,100.000 | $0.80 | $0.00 | $315,280.00 | |
0206 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 1,530.000 | 1,530.000 | 1,530.000 | $21.00 | $0.00 | $32,130.00 | |
0207 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 1,530.000 | 1,530.000 | 1,471.700 | $10.00 | $0.00 | $14,717.00 | |
0208 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 2,121.000 | 2,121.000 | 2,121.000 | $3.00 | $0.00 | $6,363.00 | |
0209 | DRILLED SHAFTS 60" DIAMETER | 516(A) 6096 | LF | 452.000 | 452.000 | 452.000 | $450.00 | $0.00 | $203,400.00 | |
0210 | (SP) SEALER CRACK PREPARATION | 523(A) 6550 | LF | 1,096.000 | 1,096.000 | 1,096.000 | $3.00 | $0.00 | $3,288.00 | |
0211 | (SP) SEALER RESIN | 523(B) 6560 | GAL | 23.000 | 23.000 | 0.000 | 23.000 | $80.00 | $0.00 | $1,840.00 |
0212 | (PL)FIXED BEARING ASSEMBLY | 535 6164 | EA | 26.000 | 26.000 | 0.000 | 26.000 | $300.00 | $0.00 | $7,800.00 |
0213 | (PL)EXPANSION BEARING ASSEMBLY | 535 6165 | EA | 39.000 | 39.000 | 0.000 | 39.000 | $1,500.00 | $0.00 | $58,500.00 |
0214 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(P) 6204 | LF | 272.000 | 272.000 | 272.000 | $25.00 | $0.00 | $6,800.00 | |
0215 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(Q) 6207 | LF | 36.000 | 36.000 | 36.000 | $15.00 | $0.00 | $540.00 | |
0216 | REMOVAL OF EXISTING BRIDGE STRUCTURE | 619(D) 1397 | LSUM | 1.000 | 1.000 | 1.000 | $50,000.00 | $0.00 | $50,000.00 | |
0217 | CONCRETE MEDIAN BARRIER, DESIGN 1 | 627(I) 4317 | LF | 337.000 | 337.000 | 337.000 | $40.00 | $0.00 | $13,480.00 | |
8010 | CONSTRUCTION MISCELLANEOUS | 104 0700 | LSUM | 0.000 | 1.000 | 1.000 | $3,184.00 | $0.00 | $3,184.00 | |
Subtotals For Category 0202/BRIDGE 'C' | $0.00 | $2,760,572.00 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0300/TRAFFIC CONTROL | ||||||||
0218 | RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN | 627(O) 4410 | LF | 6,809.000 | 6,809.000 | 17,755.500 | $3.00 | $0.00 | $53,266.50 | |
0219 | RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER | 627(P) 4425 | LF | 25,595.000 | 25,595.000 | 11,676.500 | $10.00 | $0.00 | $116,765.00 | |
0220 | (PL)SPECIAL SIGNS | 850(D) 8120 | SF | 166.000 | 166.000 | 0.000 | $11.00 | $0.00 | $0.00 | |
0221 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 856(A) 8839 | LF | 14,108.000 | 14,108.000 | 108,866.450 | $0.30 | $0.00 | $32,659.94 | |
0222 | REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 856(C) 8851 | LF | 52,430.000 | 52,430.000 | 29,118.000 | $0.45 | $0.00 | $13,103.10 | |
0223 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS | 856(G) 8881 | EA | 2,665.000 | 2,665.000 | 2,924.000 | $1.60 | $0.00 | $4,678.40 | |
0224 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 39,205.000 | 39,205.000 | 65,658.500 | $0.16 | $0.00 | $10,505.36 | |
0225 | SAND FILLED IMPACT ATTENUATION MODULE | 870(A) 8485 | SD | 12,150.000 | 12,150.000 | 6,570.000 | $0.30 | $0.00 | $1,971.00 | |
0226 | (PL)TRUCK MOUNTED ATTENUATOR | 876(C) 8482 | SD | 180.000 | 180.000 | 137.000 | $38.00 | $0.00 | $5,206.00 | |
0227 | MODULAR GLARE SCREEN | 878(C) 8487 | SD | 81,420.000 | 81,420.000 | 55,238.000 | $0.11 | $0.00 | $6,076.18 | |
0228 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 1,560.000 | 1,560.000 | 90.000 | $16.00 | $0.00 | $1,440.00 | |
0229 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 29,790.000 | 29,790.000 | 1,058.000 | 46,405.000 | $0.55 | $581.90 | $25,522.75 |
0230 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 24,990.000 | 24,990.000 | 510.000 | 40,447.000 | $0.30 | $153.00 | $12,134.10 |
0231 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 27,090.000 | 27,090.000 | 2,860.000 | 54,988.000 | $1.60 | $4,576.00 | $87,980.80 |
0232 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 22,710.000 | 22,710.000 | 4.000 | 35,821.000 | $0.55 | $2.20 | $19,701.55 |
0233 | WING BARRICADES | 880(C) 8848 | SD | 5,760.000 | 5,760.000 | 506.000 | 5,527.000 | $0.11 | $55.66 | $607.97 |
0234 | VERTICAL PANELS | 880(D) 8854 | SD | 2,760.000 | 2,760.000 | 4,104.000 | $0.30 | $0.00 | $1,231.20 | |
0235 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 39,900.000 | 39,900.000 | 2,346.000 | 87,104.000 | $0.30 | $703.80 | $26,131.20 |
0236 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 204,360.000 | 204,360.000 | 106,760.000 | $0.01 | $0.00 | $1,067.60 | |
0237 | DRUMS | 880(F) 8878 | SD | 201,420.000 | 201,420.000 | 237,270.000 | $0.11 | $0.00 | $26,099.70 | |
0238 | TRAFFIC SURVEILLANCE, POLICE | 880(L) 8911 | HOUR | 500.000 | 500.000 | 1,449.500 | $50.00 | $0.00 | $72,475.00 | |
0239 | PORT.CHANGEABLE MESSAGE SIGN | 882(B) 8306 | SD | 1,680.000 | 1,680.000 | 671.000 | $16.00 | $0.00 | $10,736.00 | |
Subtotals For Category 0300/TRAFFIC CONTROL | $6,072.56 | $529,359.35 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0301/TRAFFIC SIGNING AND STRIPING | ||||||||
0240 | CLASS A CONCRETE | 509(B) 0321 | CY | 216.000 | 216.000 | 168.000 | $520.00 | $0.00 | $87,360.00 | |
0241 | DRILLED SHAFTS 60" DIAMETER | 516(A) 6096 | LF | 140.000 | 140.000 | 140.000 | $600.00 | $0.00 | $84,000.00 | |
0242 | STRUCTURAL CONCRETE | 804(A) 2915 | CY | 17.810 | 17.810 | 17.810 | $400.00 | $0.00 | $7,124.00 | |
0243 | REINFORCING STEEL | 804(B) 2916 | LB | 8,548.000 | 8,548.000 | 8,548.000 | $1.20 | $0.00 | $10,257.60 | |
0244 | SHEET ALUMINUM SIGNS | 850(A) 8110 | SF | 1,145.000 | 1,145.000 | 961.230 | $12.00 | $0.00 | $11,534.76 | |
0245 | EXTRUDED ALUMINUM PANEL SIGNS | 850(B) 8112 | SF | 364.000 | 364.000 | 401.500 | $20.00 | $0.00 | $8,030.00 | |
0246 | EXTRUDED ALUMINUM PANEL SIGNS(OVERHEAD SIGNS) | 850(B) 8114 | SF | 1,875.000 | 1,875.000 | 1,916.550 | $20.00 | $0.00 | $38,331.00 | |
0247 | 4"@13 GALV.STEEL WIDE FLANGE BEAM POST | 851(A) 3206 | LF | 226.000 | 226.000 | 197.670 | $28.00 | $0.00 | $5,534.76 | |
0248 | 3"@7.58 GALV.STEEL PIPE POST | 851(B) 3218 | LF | 32.000 | 32.000 | 264.750 | $25.00 | $0.00 | $6,618.75 | |
0249 | 3 1/2"@9.11 GALV.STEEL PIPE POST | 851(B) 3219 | LF | 114.000 | 114.000 | 116.500 | $28.00 | $0.00 | $3,262.00 | |
0250 | 1 3/4" SQUARE TUBE POST | 851(C) 8321 | LF | 73.000 | 73.000 | 67.660 | $7.00 | $0.00 | $473.62 | |
0251 | 2" SQUARE TUBE POST | 851(C) 8324 | LF | 315.000 | 315.000 | 236.680 | $11.00 | $0.00 | $2,603.48 | |
0252 | 2 1/4" SQUARE TUBE POST | 851(C) 8327 | LF | 1,128.000 | 1,128.000 | 800.130 | $11.00 | $0.00 | $8,801.43 | |
0253 | OVHD.SN.STR., MONOTUBE TYPE A 80' | 852(B) 0110 | EA | 1.000 | 1.000 | 1.000 | $50,000.00 | $0.00 | $50,000.00 | |
0254 | OVHD.SN.STR., MONOTUBE TYPE A 85' | 852(B) 0115 | EA | 1.000 | 1.000 | 1.000 | $53,000.00 | $0.00 | $53,000.00 | |
0255 | OVHD.SN.STR., MONOTUBE TYPE A 100' | 852(B) 0130 | EA | 1.000 | 1.000 | 1.000 | $58,000.00 | $0.00 | $58,000.00 | |
0256 | OVHD.SN.STR., MONOTUBE TYPE C | 852(B) 0500 | EA | 1.000 | 1.000 | 1.000 | $36,500.00 | $0.00 | $36,500.00 | |
0257 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 854(A) 8800 | LF | 18,245.000 | 18,245.000 | 25,358.500 | $0.30 | $0.00 | $7,607.55 | |
0258 | TRAFFIC STRIPE(PAINT)(ARROW) | 854(B) 8803 | EA | 10.000 | 10.000 | 13.000 | $87.00 | $0.00 | $1,131.00 | |
0259 | (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | 854(C) 8525 | EA | 69.000 | 69.000 | 73.000 | $160.00 | $0.00 | $11,680.00 | |
0260 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 854(C) 8530 | LF | 41,481.000 | 41,481.000 | 44,259.630 | $0.65 | $0.00 | $28,768.77 | |
0261 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | 854(C) 8535 | LF | 18,118.000 | 18,118.000 | 17,856.000 | $0.88 | $0.00 | $15,713.28 | |
0262 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) | 854(C) 8540 | LF | 10,918.000 | 10,918.000 | 10,658.750 | $2.15 | $0.00 | $22,916.31 | |
0263 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) | 854(C) 8555 | LF | 512.000 | 512.000 | 475.250 | $16.00 | $0.00 | $7,604.00 | |
0264 | (PL)REMOVAL OF OVERHEAD SIGN STRUCTURE & SIGNS | 890(A) 8718 | LSUM | 1.000 | 1.000 | 1.000 | $2,200.00 | $0.00 | $2,200.00 | |
0265 | (PL)REMOVAL OF GROUND MOUNTED SIGNS | 890(A) 8720 | LSUM | 1.000 | 1.000 | 1.000 | $1,100.00 | $0.00 | $1,100.00 | |
0266 | (PL)REMOVE & RESET OVERHEAD SIGN STRUCTURE | 890A/B 8758 | EA | 1.000 | 1.000 | 0.500 | $2,200.00 | $0.00 | $1,100.00 | |
Subtotals For Category 0301/TRAFFIC SIGNING AND STRIPING | $0.00 | $571,252.31 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0302/TRAFFIC SIGNAL | ||||||||
0267 | (PL)TRAFFIC ITEMS(SIGNALS) | 890 7706 | LSUM | 1.000 | 1.000 | 0.100 | 1.000 | $560,000.00 | $56,000.00 | $560,000.00 |
Subtotals For Category 0302/TRAFFIC SIGNAL | $56,000.00 | $560,000.00 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0303/TRAFFIC LIGHTING | ||||||||
0268 | 3/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED | 802(A) 8300 | LF | 515.000 | 515.000 | 515.000 | $10.00 | $0.00 | $5,150.00 | |
0269 | 1 1/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED | 802(A) 8306 | LF | 1,560.000 | 1,560.000 | 1,556.000 | $10.00 | $0.00 | $15,560.00 | |
0270 | 2" PVC SCH.40 PLASTIC CONDUIT BORED | 802(B) 8340 | LF | 2,155.000 | 2,155.000 | 2,155.000 | $13.00 | $0.00 | $28,015.00 | |
0271 | 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 802(B) 8342 | LF | 24,485.000 | 24,485.000 | 24,485.000 | $4.50 | $0.00 | $110,182.50 | |
0272 | JUNCTION BOX(6" X 6" X 4") | 802(D) 8370 | EA | 4.000 | 4.000 | 4.000 | $450.00 | $0.00 | $1,800.00 | |
0273 | PULL BOX(SIZE I) | 803 8065 | EA | 76.000 | 76.000 | 75.000 | $515.00 | $0.00 | $38,625.00 | |
0274 | STRUCTURAL CONCRETE | 804(A) 2915 | CY | 68.440 | 68.440 | 68.440 | $540.00 | $0.00 | $36,957.60 | |
0275 | REINFORCING STEEL | 804(B) 2916 | LB | 3,941.200 | 3,941.200 | 3,941.200 | $1.40 | $0.00 | $5,517.68 | |
0276 | 40' MTG.HT.HL.PTP.(G.STL.) | 806(D) 8989 | EA | 152.000 | 152.000 | 0.000 | 152.000 | $1,200.00 | $0.00 | $182,400.00 |
0277 | BREAKAWAY BASE (DES. B) | 807 8092 | EA | 114.000 | 114.000 | 0.000 | 114.000 | $510.00 | $0.00 | $58,140.00 |
0278 | (PL)ROADWAY LUMINAIRE | 809(A) 8090 | EA | 186.000 | 186.000 | 0.000 | 186.000 | $760.00 | $0.00 | $141,360.00 |
0279 | UNDERPASS LUMINIARE | 809(B) 8098 | EA | 32.000 | 32.000 | 0.000 | 32.000 | $470.00 | $0.00 | $15,040.00 |
0280 | SERVICE POLE | 810(A) 3118 | EA | 3.000 | 3.000 | 3.000 | $3,400.00 | $0.00 | $10,200.00 | |
0281 | 1/C NO.4 ELECTRICAL CONDUCTOR | 811 8038 | LF | 59,220.000 | 59,220.000 | 0.000 | 59,220.000 | $1.75 | $0.00 | $103,635.00 |
0282 | 1/C NO.10 ELECTRICAL CONDUCTOR | 811 8044 | LF | 1,520.000 | 1,520.000 | 1,520.000 | $0.90 | $0.00 | $1,368.00 | |
0283 | 1/C NO.12 ELECTRICAL CONDUCTOR | 811 8046 | LF | 23,250.000 | 23,250.000 | 23,250.000 | $0.65 | $0.00 | $15,112.50 | |
8002 | (PL)TRAFFIC ITEMS(LIGHTING) | 890 7708 | LSUM | 0.000 | 1.000 | 1.000 | $57,911.70 | $0.00 | $57,911.70 | |
8005 | CLASS A CONCRETE | 509(B) 0321 | CY | 0.000 | 45.360 | 0.000 | 45.360 | $577.50 | $0.00 | $26,195.40 |
8006 | REINFORCING STEEL | 804(B) 2916 | LB | 0.000 | 6,720.000 | 0.000 | 6,720.000 | $1.42 | $0.00 | $9,542.40 |
8012 | (SP)TEMPORARY ROADWAY LIGHTING ASSEMBLY | 880(M) 8340 | LMDY | 0.000 | 50,000.000 | 7,688.000 | 46,786.000 | $5.25 | $40,362.00 | $245,626.50 |
Subtotals For Category 0303/TRAFFIC LIGHTING | $40,362.00 | $1,108,339.28 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0600/STAKING | ||||||||
0284 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.050 | 1.000 | $150,000.00 | $7,500.00 | $150,000.00 |
Subtotals For Category 0600/STAKING | $7,500.00 | $150,000.00 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0640/CONSTRUCTION | ||||||||
0285 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.750 | $10,000.00 | $0.00 | $7,500.00 | |
0286 | FIELD OFFICE | 640 1426 | EA | 1.000 | 1.000 | 1.000 | $15,000.00 | $0.00 | $15,000.00 | |
0287 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $980,000.00 | $0.00 | $980,000.00 | |
0288 | (SP)CONTRACTORS QUALITY CONTROL | 643 0087 | LSUM | 1.000 | 1.000 | 0.250 | $65,000.00 | $0.00 | $16,250.00 | |
8004 | CLASS B BRIDGE DECK REPAIR | 505(B) 6019 | SY | 0.000 | 433.780 | 433.780 | $117.43 | $0.00 | $50,938.79 | |
8007 | (PL)RIGHT-OF-WAY CLEARANCE | 643 0094 | LSUM | 0.000 | 1.000 | 1.000 | 1.000 | $6,660.00 | $6,660.00 | $6,660.00 |
Subtotals For Category 0640/CONSTRUCTION | $6,660.00 | $1,076,348.79 | ||||||||
Fed/State Project Number: IMY-0044-2(396)225 | Project: 06374(44) | Category: 0900/FEDERAL NON PARTICIPATING | ||||||||
8001 | RAPID CURE JOINT SEALANT | 504(H) 6390 | LF | 0.000 | 318.920 | 0.000 | 318.920 | $10.00 | $0.00 | $3,189.20 |
8003 | ELASTOMERIC MORTAR | 504(I) 6389 | CF | 0.000 | 91.490 | 0.000 | 91.490 | $200.00 | $0.00 | $18,298.00 |
8009 | CONSTRUCTION MISCELLANEOUS | 104 0600 | EA | 0.000 | 1.000 | 0.000 | $23,282.53 | $0.00 | $0.00 | |
8011 | CONSTRUCTION MISCELLANEOUS | 104 0700 | LSUM | 0.000 | 1.000 | 1.000 | $109,115.89 | $0.00 | $109,115.89 | |
8015 | PRECAST CONCRETE MEDIAN BARRIER, TYPE I | 627(A) 4310 | LF | 0.000 | 3,721.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
Subtotals For Category 0900/FEDERAL NON PARTICIPATING | $0.00 | $130,603.09 | ||||||||
Subtotals For Project IMY-0044-2(396)225 /06374(44) | $109,791.75 | $33,063,226.64 |