Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    03/23/2011
Contract ID: 100517   Estimate Number: 0003     Contract No: 610648
Residency: BUFFALO (06100)   Estimate Type: Progressive     Account No: 404600

Project Number(s): SBR-123B(059)SB
Primary Job Piece No: 24850(04)
Contract Description: BRIDGE REPAIR US-60: OVER RED BLUFF CREEK, 2.7 MILES EAST OF THE US-283 JUNCTION.
Primary County: ELLIS              
Name of Road: US-60              
Prime Contractor: PBX CORPORATION              
    P.O. BOX 644              
    SAPULPA , OK   74067              
Surety Company: WESTFIELD INSURANCE COMPANY              

Date Let: 09/16/2010 NTP Effective Date: 02/07/2011 Pay Period: 03/01/2011  TO  03/15/2011
Date Awarded: 10/04/2010 Date Work Began: 02/07/2011 Original Contract Time: 45
Date Contract Executed: 10/27/2010 Date Time Stopped: Current Time Charged: 37.00
Date NTP Issued: 10/28/2010 Completion Date: Current Time Allowed: 48.00
General Liability Expires: 10/05/2011 Workman's Comp Expires: 10/05/2011 Percent Time Used: 77.08 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $200,188.30 Total to Date Prev to Date This Estimate
Bid Amount: $200,188.30 Participating: $0.00 $0.00 $0.00
Percent Complete: 73.38 % Non Participating: $146,891.25 $77,166.25 $69,725.00
Funds Available: $53,297.05 Total Earnings: $146,891.25 $77,166.25 $69,725.00
Unearned Balance: $53,297.05 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $146,891.25 $77,166.25 $69,725.00
Other Adjustments: $0.00 $0.00 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $146,891.25 $77,166.25 $69,725.00

Estimate Adjustment Detail

Contract ID: 100517   Estimate Number: 0003     Primary JP: 24850(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 100517   Estimate Number: 0003     Primary JP: 24850(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SBR-123B(059)SB Project:    24850(04) Category:    0200/BRIDGE REHABILITATION
0001 CLSM BACKFILL 501(G) 6309 CY 10.000 10.000 4.000 4.000 $350.00 $1,400.00 $1,400.00
0002 (PL)FALSEWORK JACKING 502 6116 LSUM 1.000 1.000   0.600 $10,000.00 $0.00 $6,000.00
0003 RAPID CURE JOINT SEALANT 504(H) 6390 LF 91.200 91.200   0.000 $20.00 $0.00 $0.00
0004 ELASTOMERIC MORTAR 504(I) 6389 CF 6.200 6.200 3.100 3.100 $550.00 $1,705.00 $1,705.00
0005 CLASS C BRIDGE DECK REPAIR 505(C) 6020 SY 33.200 33.200 15.400 15.400 $600.00 $9,240.00 $9,240.00
0006 CLASS AA CONCRETE 509(A) 1326 CY 4.600 4.600 3.800 3.800 $3,000.00 $11,400.00 $11,400.00
0007 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 2,740.000 2,740.000   1,900.500 $1.50 $0.00 $2,850.75
0008 PREPARATION OF CRACKS ABOVE WATER 520(A) 6058 LF 31.800 31.800   20.000 $31.00 $0.00 $620.00
0009 EPOXY RESIN ABOVE WATER 520(C) 6060 GAL 2.500 2.500 0.250 0.250 $65.00 $16.25 $16.25
0010 PNEUMATICALLY PLACED MORTAR 521(A) 6210 SY 36.900 36.900 41.300 41.300 $610.00 $25,193.00 $25,193.00
0011 (SP)FIBER-REINFORCED EPOXY COMPOSITE MATERIAL 524 6410 SF 139.000 139.000   27.000 $40.00 $0.00 $1,080.00
0012 (SP)CORROSION INHIBITOR(SURFACE APPLIED) 535 6130 SY 37.000 37.000   37.000 $62.00 $0.00 $2,294.00
0013 (PL)REPAIR BRIDGE ITEM (TYPE A) 540 4515 EA 30.000 30.000   18.000 $1,600.00 $0.00 $28,800.00
0014 (PL)REPAIR BRIDGE ITEM (TYPE B) 540 4525 EA 10.000 10.000 10.000 10.000 $1,000.00 $10,000.00 $10,000.00
0015 (PL)REMOVAL OF BRIDGE ITEMS 619(B) 2500 LSUM 1.000 1.000   0.500 $8,000.00 $0.00 $4,000.00
Subtotals For Category     0200/BRIDGE REHABILITATION    $58,954.25 $104,599.00
Fed/State Project Number:    SBR-123B(059)SB Project:    24850(04) Category:    0300/TRAFFIC
0016 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $13,000.00 $0.00 $13,000.00
Subtotals For Category     0300/TRAFFIC    $0.00 $13,000.00
Fed/State Project Number:    SBR-123B(059)SB Project:    24850(04) Category:    0640/CONSTRUCTION
0017 (PL)PORTABLE TRAFFIC SIGNAL SYSTEM 823 8478 SD 20.000 20.000 15.000 32.000 $250.00 $3,750.00 $8,000.00
0018 TRAFFIC STRIPE(PAINT)(4" WIDE) 854(A) 8800 LF 430.000 430.000 100.000 530.000 $1.00 $100.00 $530.00
0019 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.750 $27,683.00 $6,920.75 $20,762.25
Subtotals For Category     0640/CONSTRUCTION    $10,770.75 $29,292.25
Subtotals For Project SBR-123B(059)SB /24850(04) $69,725.00 $146,891.25