Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    05/07/2012
Contract ID: 100511   Estimate Number: 0029     Contract No: 610614
Residency: EL RENO (04200)   Estimate Type: Progressive     Account No: 400400

Project Number(s): SEC1702Y-109A(130)HP, IMY-0040-4(433)139
Primary Job Piece No: 21008(04)
Contract Description: GRADE, DRAIN, SURFACE, AND BRIDGE I-40: AT MORGAN ROAD INTERCHANGE IN OKLAHOMA CITY. PROJECT LENGTH = 2.037 MILES.
Primary County: CANADIAN              
Name of Road: I-40              
Prime Contractor: ALLEN CONTRACTING, INC.              
    1100 South Eastern              
    OKLAHOMA CITY , OK   73129              
Surety Company: FIDELITY & DEPOSIT INSURANCE COMPANY OF MARYLAND              

Date Let: 09/16/2010 NTP Effective Date: 02/07/2011 Pay Period: 04/16/2012  TO  04/30/2012
Date Awarded: 10/04/2010 Date Work Began: 02/14/2011 Original Contract Time: 640
Date Contract Executed: 10/15/2010 Date Time Stopped: Current Time Charged: 449.00
Date NTP Issued: 10/21/2010 Completion Date: Current Time Allowed: 670.00
General Liability Expires: 09/01/2012 Workman's Comp Expires: 09/01/2012 Percent Time Used: 67.01 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $34,056,591.54 Total to Date Prev to Date This Estimate
Bid Amount: $33,963,202.80 Participating: $27,011,545.28 $24,469,366.90 $2,542,178.38
Percent Complete: 84.61 % Non Participating: $1,651,992.42 $1,649,398.92 $2,593.50
Funds Available: $5,240,275.69 Total Earnings: $28,663,537.70 $26,118,765.82 $2,544,771.88
Unearned Balance: $5,146,886.95 Stockpiled Materials: $153,031.73 $274,753.08 $-121,721.35
Gross Earnings: $28,816,569.43 $26,393,518.90 $2,423,050.53
Other Adjustments: $-253.58 $-253.58 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $28,816,315.85 $26,393,265.32 $2,423,050.53

Estimate Adjustment Detail

Contract ID: 100511   Estimate Number: 0029     Primary JP: 21008(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Additional Cost for Prestressed Concrete Beams Approved 04/27/2011 0.0 $9,341.64
002 Substitution Pay Items and New Removal Item Approved 01/10/2012 0.0 $66,528.08
003 Additional temporary traffic control signals Approved 04/02/2012 0.0 $17,519.02
004 Form liner, gate, and precast culvert end sections Pending 0 0.0 $19,179.46


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Initial Payment 0010 $122,946.85
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0013 $-5,050.87
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0014 $-31,484.88
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0015 $-11,425.28
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0029 $-6,164.41
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0017 $-1,262.47
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0019 $-6,339.64
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0025 $-11,972.23
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0028 $-757.33
21008(04) 0013 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0016 $-12,225.48
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0018 $-16,871.76
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Initial Payment 0010 $129,512.62
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0017 $-27,234.77
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0019 $-21,920.48
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0010 $-17,801.37
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0027 $-11,161.46
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0011 $-3,712.69
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0028 $-352.08
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0020 $-7,404.84
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0016 $-9,049.66
21008(04) 0022 (SP)DJ PCCPavt. (Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0026 $-14,003.52
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0017 $-1,233.18
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0016 $-409.77
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0011 $-168.11
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Initial Payment 0010 $6,938.70
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0010 $-806.04
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0029 $-85.25
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0028 $-48.03
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0027 $-505.39
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0026 $-634.08
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0020 $-335.29
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0019 $-992.55
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #4) Stockpiled Material Adjustment 0018 $-763.95
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0028 $-72.42
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0017 $-1,859.30
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Initial Payment 0010 $10,461.63
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0018 $-1,151.82
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0019 $-1,496.49
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0029 $-128.53
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0020 $-505.52
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0027 $-761.98
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0026 $-956.01
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0011 $-253.46
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0010 $-1,215.29
21008(04) 0022 (SP)DJ PCCPAVT.(PLACEMENT)(Tie Bars #5) Stockpiled Material Adjustment 0016 $-617.81
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Initial Payment 0017 $111,801.38
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0027 $-11,161.46
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0018 $-16,871.76
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0029 $-1,882.73
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0028 $-1,060.79
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0026 $-14,003.52
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0020 $-7,404.84
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0017 $-27,234.77
21008(04) 0022 (SP)DJ PCCPav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0019 $-21,920.48
21008(04) 0059 Inlet Frm&Grt (SSIF-FRM,CIG-GRT-VG-F) Stockpiled Material Initial Payment 0007 $7,585.00
21008(04) 0059 Inlet Frm&Grt (SSIF-FRM,CIG-GRT-VG-F) Stockpiled Material Adjustment 0008 $-3,690.00
21008(04) 0059 Inlet Frm&Grt (SSIF-FRM,CIG-GRT-VG-F) Stockpiled Material Adjustment 0013 $-2,255.00
21008(04) 0059 Inlet Frm&Grt (SSIF-FRM,CIG-GRT-VG-F) Stockpiled Material Adjustment 0011 $-820.00
21008(04) 0059 Inlet Frm&Grt (SSIF-FRM,CIG-GRT-VG-F) Stockpiled Material Adjustment 0010 $-820.00
21008(04) 0061 Cast Iron Curb Inlets Stockpiled Material Initial Payment 0007 $7,956.00
21008(04) 0061 Cast Iron Curb Inlets Stockpiled Material Adjustment 0008 $-4,914.00
21008(04) 0061 Cast Iron Curb Inlets Stockpiled Material Adjustment 0013 $-1,638.00
21008(04) 0061 Cast Iron Curb Inlets Stockpiled Material Adjustment 0011 $-1,170.00
21008(04) 0061 Cast Iron Curb Inlets Stockpiled Material Adjustment 0010 $-234.00
21008(04) 0082 Fence-Style CLF (6'High, Class A) Stockpiled Material Initial Payment 0006 $63,410.00
21008(04) 0082 Fence-Style CLF (6'High, Class A) Stockpiled Material Closure 0011 $-63,410.00
21008(04) 0082 FENCE-STYLE CLF (6'HIGH, CLASS A) Stockpiled Material Adjustment 0019 $-10,655.30
21008(04) 0082 FENCE-STYLE CLF (6'HIGH, CLASS A) Stockpiled Material Adjustment 0018 $-13,286.41
21008(04) 0082 FENCE-STYLE CLF (6'HIGH, CLASS A) Stockpiled Material Adjustment 0025 $-12,958.39
21008(04) 0082 FENCE-STYLE CLF (6'HIGH, CLASS A) Stockpiled Material Initial Payment 0013 $63,410.00
21008(04) 0090 Prestressed Concrete Beams (Type IV) Stockpiled Material Initial Payment 0007 $491,918.82
21008(04) 0090 Prestressed Concrete Beams (Type IV) Stockpiled Material Adjustment 0027 $-270,561.17
21008(04) 0090 Prestressed Concrete Beams (Type IV) Stockpiled Material Adjustment 0012 $-221,357.65
21008(04) 0090 Prestressed Concrete Beams (Type IV) Stockpiled Material Initial Payment 0008 $147,575.64
21008(04) 0090 Prestressed Concrete Beams (Type IV) Stockpiled Material Closure 0011 $-147,575.64
21008(04) 0090 PRESTRESSED CONCRETE BEAMS (TYPE IV) Stockpiled Material Initial Payment 0013 $147,575.64
21008(04) 0090 PRESTRESSED CONCRETE BEAMS (TYPE IV) Stockpiled Material Adjustment 0027 $-147,575.64
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Adjustment 0010 $-34,913.67
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Adjustment 0011 $-36,598.99
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Initial Payment 0010 $71,512.66
21008(04) 0099 (PL)MSE RETAINING WALL(Steel Strips) Stockpiled Material Initial Payment 0010 $120,446.39
21008(04) 0099 (PL)MSE RETAINING WALL(Steel Strips) Stockpiled Material Adjustment 0023 $-18,933.20
21008(04) 0099 (PL)MSE RETAINING WALL(Steel Strips) Stockpiled Material Adjustment 0011 $-36,824.54
21008(04) 0099 (PL)MSE RETAINING WALL(Steel Strips) Stockpiled Material Adjustment 0012 $-19,543.40
21008(04) 0099 (PL)MSE RETAINING WALL(Steel Strips) Stockpiled Material Adjustment 0010 $-6,058.45
21008(04) 0099 (PL)MSE RETAINING WALL(Steel Strips) Stockpiled Material Adjustment 0022 $-39,086.80
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Adjustment 0023 $-65,110.11
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Initial Payment 0017 $230,845.37
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Adjustment 0022 $-165,735.26
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Adjustment 0022 $-87,800.84
21008(04) 0099 (PL)MSE RETAINING WALL Stockpiled Material Initial Payment 0019 $87,800.84
21008(04) 0110 (PL) Expansion Bearing Assembly Stockpiled Material Adjustment 0014 $-8,280.00
21008(04) 0110 (PL) Expansion Bearing Assembly Stockpiled Material Initial Payment 0007 $23,920.00
21008(04) 0110 (PL) Expansion Bearing Assembly Stockpiled Material Adjustment 0029 $-15,640.00
21008(04) 0130 32'MH POLE,55'TS & 10' LMA(G.STL.) Stockpiled Material Adjustment 0013 $-5,440.00
21008(04) 0130 32'MH POLE,55'TS & 10' LMA(G.STL.) Stockpiled Material Adjustment 0015 $-5,440.00
21008(04) 0130 32'MH POLE,55'TS & 10' LMA(G.STL.) Stockpiled Material Initial Payment 0008 $16,320.00
21008(04) 0130 32'MH POLE,55'TS & 10' LMA(G.STL.) Stockpiled Material Adjustment 0018 $-5,440.00
21008(04) 0132 POLE & 55'T.S.MST.ARM(G.STL.) Stockpiled Material Adjustment 0013 $-4,726.00
21008(04) 0132 POLE & 55'T.S.MST.ARM(G.STL.) Stockpiled Material Initial Payment 0008 $9,452.00
21008(04) 0139 Veh.Act.Sol.St.Traf.Sig.Con.Asm Stockpiled Material Adjustment 0019 $-26,050.00
21008(04) 0139 Veh.Act.Sol.St.Traf.Sig.Con.Asm Stockpiled Material Adjustment 0028 $-13,025.00
21008(04) 0139 Veh.Act.Sol.St.Traf.Sig.Con.Asm Stockpiled Material Initial Payment 0006 $39,075.00
21008(04) 0140 (PL)Detection System (Video) Stockpiled Material Initial Payment 0006 $51,725.00
21008(04) 0140 (PL)Detection System (Video) Stockpiled Material Adjustment 0015 $-12,931.25
21008(04) 0140 (PL)Detection System (Video) Stockpiled Material Adjustment 0023 $-12,931.25
21008(04) 0186 40' MTG.HT.HL.PTP.(G.STL.) Stockpiled Material Initial Payment 0008 $37,565.00
21008(04) 0186 40' MTG.HT.HL.PTP.(G.STL.) Stockpiled Material Adjustment 0018 $-14,343.00
21008(04) 0186 40' MTG.HT.HL.PTP.(G.STL.) Stockpiled Material Adjustment 0028 $-10,245.00
21008(04) 0186 40' MTG.HT.HL.PTP.(G.STL.) Stockpiled Material Adjustment 0019 $-9,562.00
21008(04) 0187 Breakaway Base (Des. B) Stockpiled Material Adjustment 0019 $-3,780.00
21008(04) 0187 Breakaway Base (Des. B) Stockpiled Material Adjustment 0018 $-5,670.00
21008(04) 0187 Breakaway Base (Des. B) Stockpiled Material Adjustment 0028 $-4,050.00
21008(04) 0187 Breakaway Base (Des. B) Stockpiled Material Initial Payment 0008 $14,850.00
21008(04) 0188 (PL)ROADWAY LUMINAIRE Stockpiled Material Adjustment 0029 $-6,375.00
21008(04) 0188 (PL)ROADWAY LUMINAIRE Stockpiled Material Initial Payment 0014 $23,375.00
21008(04) 0188 (PL)ROADWAY LUMINAIRE Stockpiled Material Adjustment 0018 $-8,925.00
21008(04) 0188 (PL)ROADWAY LUMINAIRE Stockpiled Material Adjustment 0019 $-5,950.00
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0027 $-7,173.25
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0028 $-19,250.42
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Initial Payment 0010 $119,080.10
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0026 $-8,851.02
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0010 $-30,459.41
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0023 $-13,811.28
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0013 $-9,423.37
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0012 $-8,874.38
24424(09) 0299 (SP)CEMENT TR BASE(Seperator Fabric) Stockpiled Material Adjustment 0011 $-21,236.98
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0012 $-1,982.94
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Dowel Bar Basket Stockpiled Material Initial Payment 0010 $39,943.49
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Dowel Bar Basket Stockpiled Material Adjustment 0013 $-37,960.55
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Adjustment 0013 $-1,947.77
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Adjustment 0029 $-2,929.48
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Adjustment 0024 $-898.46
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Adjustment 0014 $-1,434.22
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Adjustment 0028 $-256.12
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Adjustment 0012 $-89.79
24424(09) 0307 (SP)DJ PCCPAVT.(Placement)(Tie Bars #4) Stockpiled Material Initial Payment 0010 $7,555.85
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Initial Payment 0010 $11,392.13
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Adjustment 0024 $-1,354.64
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Adjustment 0028 $-386.16
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Adjustment 0029 $-4,416.85
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Adjustment 0014 $-2,162.41
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Adjustment 0013 $-2,936.70
24424(09) 0307 (SP)DJ PCCPAVT(Placement)(Tie Bars #5) Stockpiled Material Adjustment 0012 $-135.37
24424(09) 0307 (SP)DJPCC PAVT.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0024 $-18,924.35
24424(09) 0307 (SP)DJPCC PAVT.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0014 $-31,674.77
24424(09) 0307 (SP)DJPCC PAVT.(Placement)(Dowel Baskets) Stockpiled Material Initial Payment 0014 $50,599.12
24424(09) 0307 (SP)DJ PCC Pav't.(Placement)(Dowel Baskets) Stockpiled Material Initial Payment 0017 $90,196.55
24424(09) 0307 (SP)DJ PCC Pav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0024 $-19,842.57
24424(09) 0307 (SP)DJ PCC Pav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0029 $-64,697.55
24424(09) 0307 (SP)DJ PCC Pav't.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0028 $-5,656.44
24424(09) 0307 (SP)DJPCC PAVT.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0029 $-19,401.55
24424(09) 0307 (SP)DJPCC PAVT.(Placement)(Dowel Baskets) Stockpiled Material Initial Payment 0026 $25,057.99
24424(09) 0307 (SP)DJPCC PAVT.(Placement)(Dowel Baskets) Stockpiled Material Adjustment 0028 $-5,656.44
24424(09) 0350 36' MTG.HT.HL.PTP.(G.STL.) Stockpiled Material Initial Payment 0008 $18,018.00
24424(09) 0351 (PL)ROADWAY LUMINAIRE Stockpiled Material Initial Payment 0014 $22,100.00
Subtotals For Stockpile Payments $153,031.73


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
21008(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0020 8.04 $2.46 $19.80
21008(04) 0062 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0022 -88.00 $31.00 $-2,728.00
21008(04) 0062 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0023 88.00 $31.00 $2,728.00
21008(04) 0064 30" R.C.PIPE CLASS III * Missing Material Certification 0013 -129.00 $51.00 $-6,579.00
21008(04) 0064 30" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0015 129.00 $51.00 $6,579.00
21008(04) 0065 36" R.C.PIPE CLASS III * Missing Material Certification 0010 -48.00 $69.00 $-3,312.00
21008(04) 0065 36" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0011 48.00 $69.00 $3,312.00
21008(04) 0112 6" NON-PERF.PIPE UNDERDRAIN RND. * Material Discrepancy Adjustments 0017 -40.00 $10.00 $-400.00
21008(04) 0112 6" NON-PERF.PIPE UNDERDRAIN RND. * Material Discrepancy Adjustments 0018 40.00 $10.00 $400.00
21008(04) 0126 PULL BOX(SIZE II) * Missing Material Certification 0010 -1.00 $273.39 $-273.39
24424(09) 0294 TEMPORARY SILT DIKE * Missing Material Certification 0007 -160.00 $6.43 $-1,028.80
24424(09) 0294 TEMPORARY SILT DIKE * Material Discrepancy Adjustments 0008 22.50 $6.43 $144.68
24424(09) 0294 TEMPORARY SILT DIKE * Material Discrepancy Adjustments 0010 137.50 $6.43 $884.13
24424(09) 0318 42" R.C.PIPE CLASS III * Missing Material Certification 0010 -30.00 $91.00 $-2,730.00
24424(09) 0318 42" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0011 30.00 $91.00 $2,730.00
24424(09) 0318 42" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0017 -66.00 $91.00 $-6,006.00
24424(09) 0318 42" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0018 66.00 $91.00 $6,006.00
24424(09) 0319 43" X 26" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0006 -348.00 $93.00 $-32,364.00
24424(09) 0319 43" X 26" R.C.PIPE ARCH CLASS A-III * Missing Material Certification 0007 -742.00 $93.00 $-69,006.00
24424(09) 0319 43" X 26" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0008 830.00 $93.00 $77,190.00
24424(09) 0319 43" X 26" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0009 172.00 $93.00 $15,996.00
24424(09) 0319 43" X 26" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0010 88.00 $93.00 $8,184.00
24424(09) 0320 51" X 31" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0006 -398.00 $120.00 $-47,760.00
24424(09) 0320 51" X 31" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0008 398.00 $120.00 $47,760.00
24424(09) 0321 58" X 36" R.C.PIPE ARCH CLASS A-III * Missing Material Certification 0010 -8.00 $150.00 $-1,200.00
24424(09) 0321 58" X 36" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0011 8.00 $150.00 $1,200.00
24424(09) 0322 73" X 45" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0006 -866.00 $200.00 $-173,200.00
24424(09) 0322 73" X 45" R.C.PIPE ARCH CLASS A-III * Missing Material Certification 0007 -754.00 $200.00 $-150,800.00
24424(09) 0322 73" X 45" R.C.PIPE ARCH CLASS A-III * Material Discrepancy Adjustments 0008 1,620.00 $200.00 $324,000.00
Subtotals For Line Item Adjustments $-253.58
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 TIME 'B' BID NOT ENTERED NOT ENTERED 500.00 DYS $15,000.00 N


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 100511   Estimate Number: 0029     Primary JP: 21008(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SEC1702Y-109A(130)HP Project:    21008(04) Category:    0100/ROADWAY - SEC1702Y-109A(130)HP
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 72,662.000 72,662.000   72,662.120 $5.00 $0.00 $363,310.60
0003 UNCLASSIFIED BORROW 202(C) 0184 CY 185,577.000 185,577.000   119,822.080 $6.70 $0.00 $802,807.94
0004 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000 0.250 1.000 $88,000.00 $22,000.00 $88,000.00
0005 TEMPORARY SILT FENCE 223 2801 LF 23,004.000 23,004.000   24,491.100 $1.39 $0.00 $34,042.63
0006 TEMPORARY SEDIMENT FILTER 224 2803 EA 91.000 91.000   25.000 $80.41 $0.00 $2,010.25
0007 TEMPORARY SILT DIKE 227 0100 LF 1,190.000 1,190.000   363.500 $6.43 $0.00 $2,337.31
0008 DITCH LINER PROTECTION 229 4318 LF 7,424.000 7,424.000   0.000 $1.34 $0.00 $0.00
0009 SOLID SLAB SODDING 230(A) 2806 SY 208,720.000 208,720.000   101,148.910 $1.16 $0.00 $117,332.74
0010 VEGETATIVE MULCHING 233(A) 2817 AC 43.000 43.000   0.000 $107.21 $0.00 $0.00
0011 MOWING 241 2832 AC 86.000 86.000   0.000 $53.61 $0.00 $0.00
0012 SAND CUSHION 308 1423 CY 445.000 445.000   315.830 $20.00 $0.00 $6,316.60
0013 (SP)CEMENT TREATED BASE 317(F) 4270 SY 23,652.000 23,652.000 5,246.310 96,736.390 $9.50 $49,839.95 $918,995.72
0014 (SP)FLY ASH 327(A) 4200 TON 6,004.000 3,396.000   3,570.330 $32.00 $0.00 $114,250.56
0015 (SP)CEMENTITIOUS STABILIZED SUBGRADE 327(E) 4240 SY 111,178.000 111,178.000 4,001.110 101,747.990 $1.40 $5,601.55 $142,447.19
0016 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 6,726.000 6,726.000 89.670 2,336.180 $18.00 $1,614.06 $42,051.24
0017 TACK COAT 407 0250 GAL 2,191.000 2,191.000 0.000 7.000 $4.00 $0.00 $28.00
0018 PRIME COAT 408 5774 GAL 19,752.000 19,752.000   0.000 $4.00 $0.00 $0.00
0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 27,792.000 27,792.000   8.040 $50.00 $0.00 $402.00
0020 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 2,665.000 2,665.000   0.000 $31.00 $0.00 $0.00
0021 (SP)P.C.CONCRETE PAVEMENT(PLACEMENT) 414(A) 0210 SY 17,662.000 17,662.000   28,036.300 $8.00 $0.00 $224,290.40
0022 (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) 414(A1) 5725 SY 80,202.000 80,202.000 822.870 67,278.840 $12.50 $10,285.88 $840,985.53
0023 (SP)P.C. CONCRETE FOR PAVEMENT 414(P) 6000 CY 28,390.000 28,390.000 264.000 26,333.000 $82.00 $21,648.00 $2,159,306.00
0024 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 538.000 538.000   440.170 $12.00 $0.00 $5,282.04
0025 CLASS A CONCRETE 509(B) 0321 CY 1,449.000 1,449.000 0.000 1,436.120 $325.00 $0.00 $466,739.00
0026 CLASS A CONCRETE FOR SMALL STRUCTURES 509(C) 0322 CY 22.000 22.000 0.000 21.340 $580.00 $0.00 $12,377.20
0027 CLASS C CONCRETE 509(D) 0325 CY 1,072.000 1,072.000   1,668.750 $215.00 $0.00 $358,781.25
0028 RETAINING WALL 510(A) 6333 SY 275.000 275.000   44.440 $260.00 $0.00 $11,554.40
0029 REINFORCING STEEL 511(A) 0332 LB 260,855.000 260,855.000   249,799.820 $0.85 $0.00 $212,329.85
0030 TYPE I-A PLAIN RIPRAP 601A-1 0536 TON 141.000 141.000   0.000 $44.00 $0.00 $0.00
0031 TYPE I-A FILTER BLANKET 601A-2 0538 TON 45.000 45.000   0.000 $37.00 $0.00 $0.00
0032 CONCRETE CURB (6" MNTBLE-INTEGRAL) 609(A) 0288 LF 3,106.000 3,106.000   2,775.200 $2.50 $0.00 $6,938.00
0033 CONCRETE CURB (8" BARRIER-INTEGRAL) 609(A) 0380 LF 11,895.000 11,895.000   9,118.870 $3.00 $0.00 $27,356.61
0034 2'-8" COMB. CURB & GUTTER (8" BARRIER) 609(B) 1526 LF 6,225.000 6,225.000   3,673.810 $16.00 $0.00 $58,780.96
0035 4" CONCRETE SIDEWALK 610(A) 0602 SY 3,999.000 3,999.000   3,214.340 $32.00 $0.00 $102,858.88
0036 8" CONCRETE DRIVEWAY (H.E.S.) 610(B) 0400 SY 8,933.000 8,933.000   7,343.940 $46.00 $0.00 $337,821.24
0037 6" CONCRETE DIVIDING STRIP 610(C) 0609 SY 2,888.000 2,888.000   2,199.040 $30.00 $0.00 $65,971.20
0038 (PL)TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 432.000 432.000   380.000 $28.00 $0.00 $10,640.00
0039 MANHOLE (4' DIAMETER) 611(A) 2657 EA 16.000 16.000   16.000 $1,900.00 $0.00 $30,400.00
0040 MANHOLE (5' DIAMETER) 611(A) 2658 EA 6.000 6.000   6.000 $2,200.00 $0.00 $13,200.00
0041 MANHOLE FRAME & COVER 611(D) 4215 EA 25.000 25.000   25.000 $300.00 $0.00 $7,500.00
0042 INLET CICI DES. 2 (STD) 611(E) 5112 EA 9.000 9.000   9.000 $1,900.00 $0.00 $17,100.00
0043 INLET CICI DES. 2 (B) 611(E) 5113 EA 22.000 22.000   21.000 $2,100.00 $0.00 $44,100.00
0044 INLET CICI DES. 2 (D) 611(E) 5115 EA 11.000 11.000   10.000 $2,900.00 $0.00 $29,000.00
0045 INLET CICI DES. 2 (2B) 611(E) 5117 EA 1.000 1.000   1.000 $2,300.00 $0.00 $2,300.00
0046 INLET CICI DES. 2 (2D) 611(E) 5119 EA 3.000 3.000   3.000 $3,400.00 $0.00 $10,200.00
0047 INLET CICI DES. 3 (B) 611(E) 5121 EA 1.000 1.000   1.000 $4,200.00 $0.00 $4,200.00
0048 INLET CICI DES. 3 (D) 611(E) 5122 EA 7.000 7.000   7.000 $4,300.00 $0.00 $30,100.00
0049 INLET GPI TYPE 1 (DES. 3) 611(E) 5329 EA 2.000 2.000   2.000 $1,800.00 $0.00 $3,600.00
0050 INLET CDI 24" RCP 611(E) 5705 EA 1.000 1.000   1.000 $1,200.00 $0.00 $1,200.00
0051 INLET (SMD-TYPE 2) 611(E) 6002 EA 8.000 8.000   8.000 $1,400.00 $0.00 $11,200.00
0052 INLET (SMD-TYPE 2B) 611(E) 6006 EA 1.000 1.000   1.000 $1,600.00 $0.00 $1,600.00
0053 INLET MEDIAN BARRIER, TYPE I, DES.1 611(E) 7126 EA 6.000 6.000   6.000 $1,800.00 $0.00 $10,800.00
0054 INLET CICI DES. 2 (ADD'L DEPTH) 611(F) 5325 VF 119.000 119.000   118.690 $320.00 $0.00 $37,980.80
0055 INLET CICI DES. 3 (ADD'L DEPTH) 611(F) 5330 VF 22.000 22.000   21.650 $500.00 $0.00 $10,825.00
0056 INLET GPI TYPE 1 (ADD'L DEPTH) 611(F) 5374 VF 1.000 1.000   0.770 $240.00 $0.00 $184.80
0057 INLET MED. BAR. DES. 1 (ADD'L DEPTH) 611(F) 5695 VF 47.000 47.000   46.680 $320.00 $0.00 $14,937.60
0058 INLET CDI 24" RCP,(ADD'L DEPTH) 611(F) 5790 VF 5.000 5.000   4.500 $200.00 $0.00 $900.00
0059 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 124.000 124.000   124.000 $360.00 $0.00 $44,640.00
0060 JUNCTION BOXES 611(J) 0487 CF 653.000 653.000   652.600 $25.00 $0.00 $16,315.00
0061 CAST IRON CURB INLETS 611(K) 4488 EA 270.000 270.000   270.000 $210.00 $0.00 $56,700.00
0062 18" R.C.PIPE CLASS III 613(B) 0491 LF 2,410.000 2,410.000   2,456.000 $31.00 $0.00 $76,136.00
0063 24" R.C.PIPE CLASS III 613(B) 0492 LF 2,034.000 2,034.000   2,028.000 $40.00 $0.00 $81,120.00
0064 30" R.C.PIPE CLASS III 613(B) 0493 LF 1,834.000 1,834.000   1,673.000 $51.00 $0.00 $85,323.00
0065 36" R.C.PIPE CLASS III 613(B) 0494 LF 588.000 588.000   632.000 $69.00 $0.00 $43,608.00
0066 36" X 22" R.C.PIPE ARCH CLASS A-III 613(B) 4497 LF 148.000 148.000   1,002.000 $83.00 $0.00 $83,166.00
0067 51" X 31" R.C.PIPE ARCH CLASS A-III 613(B) 4499 LF 90.000 90.000   90.000 $115.00 $0.00 $10,350.00
0068 58" X 36" R.C.PIPE ARCH CLASS A-III 613(B) 4500 LF 306.000 306.000   306.000 $150.00 $0.00 $45,900.00
0069 73" X 45" R.C.PIPE ARCH CLASS A-III 613(B) 4502 LF 122.000 122.000   122.000 $205.00 $0.00 $25,010.00
0070 TYPE A4 CULVERT END TREATMENT 613(CC) 7186 EA 3.000 3.000   3.000 $600.00 $0.00 $1,800.00
0071 18" CORR. GALV. STEEL PIPE 613(D) 0689 LF 82.000 82.000   260.000 $27.00 $0.00 $7,020.00
0072 51" X 31" PREFAB. CULVERT END SECTION, ARCH 613(M) 4540 EA 1.000 1.000   1.000 $1,400.00 $0.00 $1,400.00
0073 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 1091 LF 2,100.000 2,100.000   0.000 $6.00 $0.00 $0.00
0074 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 1096 LF 700.000 700.000   0.000 $6.00 $0.00 $0.00
0075 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $25,000.00 $0.00 $25,000.00
0076 REMOVAL OF FENCE 619(B) 4725 LF 16,569.000 16,569.000   8,759.920 $2.20 $0.00 $19,271.82
0077 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 6,382.000 6,382.000   8,829.000 $6.50 $0.00 $57,388.50
0078 REMOVAL OF CONCRETE PAVEMENT 619(B) 4727 SY 33,624.000 33,624.000   26,053.410 $5.00 $0.00 $130,267.05
0079 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 34,824.000 34,824.000   20,532.910 $1.50 $0.00 $30,799.39
0080 REMOVAL OF CONCRETE MEDIAN BARRIER 619(B) 4915 LF 372.000 372.000   0.000 $45.00 $0.00 $0.00
0081 SAWING PAVEMENT 619(C) 0924 LF 11,490.000 11,490.000   4,465.960 $2.00 $0.00 $8,931.92
0082 FENCE-STYLE CLF (6'HIGH, CLASS A) 624(D) 4292 LF 17,148.000 17,148.000   9,892.790 $12.33 $0.00 $121,978.09
0083 CONCRETE MEDIAN BARRIER, DESIGN 1 627(I) 4317 LF 372.000 372.000 100.000 100.000 $70.00 $7,000.00 $7,000.00
0084 MAILBOX INSTALLATION-SINGLE 629(A) 4958 EA 5.000 5.000   5.000 $75.05 $0.00 $375.25
0085 MAILBOX 629(C) 4960 EA 5.000 5.000   5.000 $26.80 $0.00 $134.00
0086 REMOVAL OF MAILBOX INSTALLATION 629(D) 4961 EA 5.000 5.000   4.000 $10.72 $0.00 $42.88
8001 REMOVAL OF CONC.PAV.W/ASPH.OVERLAY 619(B) 4763 SY 0.000 600.000   0.000 $7.00 $0.00 $0.00
8004 (SP)CEMENT KILN DUST 327(B) 4210 TON 0.000 1,304.000 172.120 491.830 $61.35 $10,559.56 $30,173.77
Subtotals For Category     0100/ROADWAY - SEC1702Y-109A(130)HP    $128,549.00 $8,847,524.21
Fed/State Project Number:    SEC1702Y-109A(130)HP Project:    21008(04) Category:    0200/BRIDGE 'B' - SEC1702Y-109A(130)HP
0087 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 2,804.000 2,804.000   2,804.000 $11.00 $0.00 $30,844.00
0088 GRANULAR BACKFILL 501(F) 6352 CY 6,299.000 6,299.000 0.000 6,299.000 $25.00 $0.00 $157,475.00
0089 CLSM BACKFILL 501(G) 6309 CY 5,443.800 5,443.800   4,837.500 $70.00 $0.00 $338,625.00
0090 PRESTRESSED CONCRETE BEAMS (TYPE IV) 503(A) 1313 LF 4,944.300 4,944.300   4,944.300 $188.00 $0.00 $929,528.40
0091 APPROACH SLAB 504(A) 1304 SY 2,238.300 2,238.300   2,238.300 $150.00 $0.00 $335,745.00
0092 SEALED EXPANSION JOINT 504(C) 6250 LF 283.500 283.500 188.300 283.500 $240.00 $45,192.00 $68,040.00
0093 CONCRETE RAIL (TR1) 504(E) 1380 LF 429.500 429.500   0.000 $60.00 $0.00 $0.00
0094 42" F-SHAPED PARAPET 504(F) 6190 LF 4,329.300 4,329.300   4,069.080 $75.00 $0.00 $305,181.00
0095 STRUCTURAL STEEL 506(A) 1322 LB 9,640.000 9,640.000   9,640.000 $6.30 $0.00 $60,732.00
0096 CLASS AA CONCRETE 509(A) 1326 CY 1,652.800 1,652.800 966.050 1,652.800 $520.00 $502,346.00 $859,456.00
0097 CLASS A CONCRETE 509(B) 1328 CY 3,460.400 3,460.400   3,360.000 $400.00 $0.00 $1,344,000.00
0098 (PL)TEMPORARY RETAINING WALL 510(A) 6338 SY 137.400 137.400   137.400 $260.00 $0.00 $35,724.00
0099 (PL)MSE RETAINING WALL 510(A) 6341 SY 5,560.000 5,560.000 0.000 5,560.000 $400.00 $0.00 $2,224,000.00
0100 SLOPE WALL (5") 510(C) 6138 SY 2,139.700 2,139.700   2,139.700 $48.00 $0.00 $102,705.60
0101 REINFORCING STEEL 511(A) 1332 LB 8,480.000 8,480.000   8,480.000 $0.81 $0.00 $6,868.80
0102 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 768,660.000 768,660.000 198,200.000 768,660.000 $0.87 $172,434.00 $668,734.20
0103 PILES, FURNISHED (HP 14X73) 514(A) 6012 LF 12,051.000 12,051.000   12,651.000 $45.00 $0.00 $569,295.00
0104 PILES, DRIVEN (HP 14X73) 514(B) 6296 LF 12,051.000 12,051.000   12,262.500 $15.00 $0.00 $183,937.50
0105 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 2,418.500 2,418.500   261.700 $3.20 $0.00 $837.44
0106 DRILLED SHAFTS 66" DIAMETER 516(A) 6097 LF 454.000 454.000   453.600 $450.00 $0.00 $204,120.00
0107 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 963.300 963.300   192.650 $3.20 $0.00 $616.48
0108 (SP) SEALER RESIN 523(B) 6560 GAL 10.000 10.000   2.000 $110.00 $0.00 $220.00
0109 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 56.000 56.000   56.000 $1,000.00 $0.00 $56,000.00
0110 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 52.000 52.000 34.000 52.000 $1,000.00 $34,000.00 $52,000.00
0111 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 626.000 626.000 0.000 626.000 $10.00 $0.00 $6,260.00
0112 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 120.000 120.000   120.000 $10.00 $0.00 $1,200.00
0113 (PL)REMOVAL OF BRIDGE ITEMS 619(B) 2500 LSUM 1.000 1.000   1.000 $5,200.00 $0.00 $5,200.00
0114 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $200,000.00 $0.00 $200,000.00
8000 CONSTRUCTION MISCELLANEOUS 104 0700 LSUM 0.000 1.000   1.000 $9,341.64 $0.00 $9,341.64
Subtotals For Category     0200/BRIDGE 'B' - SEC1702Y-109A(130)HP    $753,972.00 $8,756,687.06
Fed/State Project Number:    SEC1702Y-109A(130)HP Project:    21008(04) Category:    0300/TRAFFIC SIGNAL - SEC1702Y-109A(130)HP
0115 2" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8310 LF 780.000 780.000   522.000 $11.90 $0.00 $6,211.80
0116 3" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8316 LF 170.000 170.000   0.000 $23.59 $0.00 $0.00
0117 1" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8334 LF 45.000 45.000   78.000 $3.11 $0.00 $242.58
0118 1 1/2" PVC SCH.40 PLASTIC CONDUIT BORED 802(B) 8336 LF 75.000 75.000   0.000 $11.79 $0.00 $0.00
0119 1 1/2" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8338 LF 235.000 235.000   252.000 $3.32 $0.00 $836.64
0120 2" PVC SCH.40 PLASTIC CONDUIT BORED 802(B) 8340 LF 175.000 175.000   0.000 $12.33 $0.00 $0.00
0121 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8342 LF 465.000 465.000   425.000 $4.29 $0.00 $1,823.25
0122 3" PVC SCH.40 PLASTIC CONDUIT BORED 802(B) 8344 LF 1,060.000 1,060.000   1,182.700 $15.01 $0.00 $17,752.33
0123 3" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8346 LF 235.000 235.000   390.000 $15.01 $0.00 $5,853.90
0124 JUNCTION BOX(6" X 6" X 4") 802(D) 8370 EA 16.000 0.000   0.000 $412.77 $0.00 $0.00
0125 PULL BOX(SIZE I) 803 8065 EA 15.000 15.000   13.000 $219.78 $0.00 $2,857.14
0126 PULL BOX(SIZE II) 803 8066 EA 3.000 3.000   4.000 $273.39 $0.00 $1,093.56
0127 STRUCTURAL CONCRETE 804(A) 2915 CY 33.700 33.700   40.100 $471.73 $0.00 $18,916.38
0128 REINFORCING STEEL 804(B) 2916 LB 4,947.000 4,947.000   4,717.400 $1.30 $0.00 $6,132.62
0129 32'MH POLE 35'TS & 10'LMA(G.STL.) 806(A) 8311 EA 1.000 1.000   1.000 $3,993.64 $0.00 $3,993.64
0130 32'MH POLE,55'TS & 10'LMA(G.STL.) 806(A) 8353 EA 3.000 3.000   3.000 $7,805.03 $0.00 $23,415.09
0131 POLE & 50' TS MST.ARM(G.STL.) 806(A) 8736 EA 1.000 1.000   1.000 $5,823.75 $0.00 $5,823.75
0132 POLE & 55'T.S.MST.ARM(G.STL.) 806(A) 8738 EA 2.000 2.000   1.000 $6,848.70 $0.00 $6,848.70
0133 40' MHP 50' TS & 10' LMA(G.STL.) 806(A) 8872 EA 1.000 1.000   1.000 $6,822.97 $0.00 $6,822.97
0134 10' MTG.HT.TS PED.POLE(G.STL.) 806(B) 8894 EA 15.000 15.000 2.000 12.000 $582.16 $1,164.32 $6,985.92
0135 (PL)ROADWAY LUMINAIRE 809(A) 8090 EA 7.000 7.000 1.000 5.000 $396.68 $396.68 $1,983.40
0136 SERVICE POLE 810(A) 3118 EA 2.000 2.000   3.000 $605.75 $0.00 $1,817.25
0137 1/C NO.6 ELECTRICAL CONDUCTOR 811 8040 LF 800.000 800.000   400.000 $1.72 $0.00 $688.00
0138 1/C NO.10 ELECTRICAL CONDUCTOR 811 8044 LF 4,090.000 4,090.000   2,160.000 $0.96 $0.00 $2,073.60
0139 VEH.ACT.SOL.ST.TRAF.SIG.CON.ASM 825 8550 EA 3.000 3.000   3.000 $25,639.73 $0.00 $76,919.19
0140 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000   0.500 $80,902.10 $0.00 $40,451.06
0141 SOL.STE.DIGITAL IND.VEH.LP.DET. 828(A) 8135 EA 1.000 1.000   0.000 $230.51 $0.00 $0.00
0142 LOOP DETECTOR WIRE 828(B) 8138 LF 2,115.000 2,115.000   0.000 $3.75 $0.00 $0.00
0143 PEDESTRIAN PUSH BUTTON 830 8000 EA 18.000 18.000 2.000 20.000 $146.88 $293.76 $2,937.60
0144 1WAY 3SEC. ADJ. SIG. HD. S-6 831 8231 EA 15.000 15.000   9.000 $605.75 $0.00 $5,451.75
0145 1WAY 3SEC. ADJ. SIG. HD. S-9 831 8252 EA 7.000 7.000   3.000 $566.08 $0.00 $1,698.24
0146 1WAY 3SEC. ADJ. SIG. HD. S-11 831 8270 EA 4.000 4.000   0.000 $566.08 $0.00 $0.00
0147 1WAY 5SEC. ADJ. SIG. HD. S-19 831 8286 EA 3.000 3.000   3.000 $1,034.59 $0.00 $3,103.77
0148 1WAY 2SEC. ADJ. PED. SIG. HD. S-20 831 8295 EA 18.000 18.000 2.000 20.000 $359.16 $718.32 $7,183.20
0149 BACKPLATE 833 3030 EA 29.000 29.000   15.000 $75.05 $0.00 $1,125.75
0150 5/C TRAF.SIG.ELECT.CABLE 834(A) 8207 LF 5,365.000 6,665.000   2,135.000 $1.27 $0.00 $2,711.45
0151 7/C TRAF.SIG.ELECT.CABLE 834(A) 8208 LF 1,295.000 1,295.000   1,190.000 $1.59 $0.00 $1,892.10
0152 21/C TRAF.SIG.EL.CABLE 834(A) 8213 LF 2,690.000 2,690.000   1,430.000 $4.44 $0.00 $6,349.20
0153 2/C SHIELDED LOOP DETECTOR LEAD-IN CABLE 834(B) 8220 LF 1,790.000 1,790.000   0.000 $0.96 $0.00 $0.00
0154 MAST ARM MOUNTED SIGNS(ALUMINUM) 850(C) 8118 SF 145.750 145.750   70.500 $37.52 $0.00 $2,645.16
0155 (PL)TRAFFIC ITEMS(SIGNALS) 890 7706 LSUM 1.000 1.000   0.000 $109,356.13 $0.00 $0.00
0156 (PL)REMOVAL OF TRAFFIC SIGNAL EQUIPMENT 890(A) 8726 LSUM 1.000 1.000   1.000 $7,612.04 $0.00 $7,612.04
0157 (PL)REMOVE & RESET TRAFFIC SIGNAL EQUIPMENT 890A/B 8742 LSUM 1.000 1.000   1.000 $6,218.29 $0.00 $6,218.29
8002 (PL)JUNCTION BOX(SPECIAL) 802(D) 8374 EA 0.000 16.000   5.000 $855.50 $0.00 $4,277.50
8005 (PL)TRAFFIC ITEMS(SIGNALS) 890 7706 LSUM 0.000 1.000   0.000 $15,868.02 $0.00 $0.00
Subtotals For Category     0300/TRAFFIC SIGNAL - SEC1702Y-109A(130)HP    $2,573.08 $292,748.82
Fed/State Project Number:    SEC1702Y-109A(130)HP Project:    21008(04) Category:    0301/TRAFFIC SIGNING AND STRIPING - SEC1702Y-109A(130)HP
0158 STRUCTURAL CONCRETE 804(A) 2915 CY 23.100 23.100   10.890 $1,072.12 $0.00 $11,675.39
0159 REINFORCING STEEL 804(B) 2916 LB 3,800.000 3,800.000   1,534.600 $2.14 $0.00 $3,284.04
0160 SHEET ALUMINUM SIGNS 850(A) 8110 SF 507.270 507.270   0.000 $10.19 $0.00 $0.00
0161 EXTRUDED ALUMINUM PANEL SIGNS 850(B) 8112 SF 1,235.000 1,235.000   0.000 $12.87 $0.00 $0.00
0162 4"@13 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3206 LF 442.000 442.000   0.000 $20.37 $0.00 $0.00
0163 6"@15 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3207 LF 100.000 100.000   0.000 $23.59 $0.00 $0.00
0164 6"@20 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3208 LF 88.000 88.000   0.000 $32.16 $0.00 $0.00
0165 6"@25 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3209 LF 104.000 104.000   0.000 $39.67 $0.00 $0.00
0166 2"@3.65 GALV.STEEL PIPE POST 851(B) 3216 LF 295.000 295.000   0.000 $6.43 $0.00 $0.00
0167 2 1/2"@5.79 GALV.STEEL PIPE POST 851(B) 3217 LF 486.000 486.000   0.000 $10.72 $0.00 $0.00
0168 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 40.000 40.000   0.000 $4.29 $0.00 $0.00
0169 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) 854(C) 8525 EA 134.000 134.000   0.000 $117.93 $0.00 $0.00
0170 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 854(C) 8530 LF 45,605.000 45,605.000   0.000 $0.59 $0.00 $0.00
0171 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) 854(C) 8535 LF 14,714.000 14,714.000   0.000 $1.18 $0.00 $0.00
0172 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) 854(C) 8540 LF 13,520.000 13,520.000   0.000 $1.29 $0.00 $0.00
0173 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) 854(C) 8555 LF 231.000 231.000   0.000 $16.08 $0.00 $0.00
0174 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 5,000.000 5,000.000   0.000 $1.07 $0.00 $0.00
0175 (PL)IMPACT ATTENUATOR 871 8325 EA 2.000 2.000   1.000 $18,226.02 $0.00 $18,226.02
0176 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8724 EA 5.000 5.000   21.000 $107.21 $0.00 $2,251.41
0177 (PL)REMOVE & RESET EXISTING SIGNS 890A/B 8756 EA 13.000 13.000   0.000 $107.21 $0.00 $0.00
0178 (PL)REMOVE & RESET OVERHEAD SIGN STRUCTURE 890A/B 8758 EA 1.000 1.000   0.650 $10,721.19 $0.00 $6,968.77
Subtotals For Category     0301/TRAFFIC SIGNING AND STRIPING - SEC1702Y-109A(130)HP    $0.00 $42,405.63
Fed/State Project Number:    SEC1702Y-109A(130)HP Project:    21008(04) Category:    0302/TRAFFIC LIGHTING - SEC1702Y-109A(130)HP
0179 3/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8300 LF 1,310.000 1,310.000   540.000 $8.31 $0.00 $4,487.40
0180 2" PVC SCH.40 PLASTIC CONDUIT BORED 802(B) 8340 LF 530.000 530.000   0.000 $12.33 $0.00 $0.00
0181 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8342 LF 8,780.000 8,780.000 1,390.000 8,451.000 $3.75 $5,212.50 $31,691.25
0182 JUNCTION BOX(6" X 6" X 4") 802(D) 8370 EA 2.000 2.000   0.000 $412.77 $0.00 $0.00
0183 PULL BOX(SIZE I) 803 8065 EA 11.000 11.000 3.000 4.000 $219.78 $659.34 $879.12
0184 STRUCTURAL CONCRETE 804(A) 2915 CY 30.160 30.160 0.800 28.880 $471.73 $377.38 $13,623.56
0185 REINFORCING STEEL 804(B) 2916 LB 1,736.800 1,736.800 52.600 1,822.800 $1.30 $68.38 $2,369.64
0186 40' MTG.HT.HL.PTP.(G.STL.) 806(D) 8989 EA 55.000 55.000   50.000 $1,173.97 $0.00 $58,698.50
0187 BREAKAWAY BASE (DES. B) 807 8092 EA 55.000 55.000   50.000 $455.65 $0.00 $22,782.50
0188 (PL)ROADWAY LUMINAIRE 809(A) 8090 EA 55.000 55.000 15.000 50.000 $820.17 $12,302.55 $41,008.50
0189 UNDERPASS LUMINIARE 809(B) 8098 EA 24.000 24.000 24.000 24.000 $482.45 $11,578.80 $11,578.80
0190 SERVICE POLE 810(A) 3118 EA 1.000 1.000 1.000 1.000 $3,484.39 $3,484.39 $3,484.39
0191 1/C NO.4 ELECTRICAL CONDUCTOR 811 8038 LF 18,440.000 18,440.000 2,410.000 16,300.000 $1.82 $4,386.20 $29,666.00
0192 1/C NO.10 ELECTRICAL CONDUCTOR 811 8044 LF 655.000 655.000 1,080.000 1,080.000 $0.96 $1,036.80 $1,036.80
0193 1/C NO.12 ELECTRICAL CONDUCTOR 811 8046 LF 6,875.000 6,875.000   4,361.000 $0.70 $0.00 $3,052.70
Subtotals For Category     0302/TRAFFIC LIGHTING - SEC1702Y-109A(130)HP    $39,106.34 $224,359.16
Fed/State Project Number:    SEC1702Y-109A(130)HP Project:    21008(04) Category:    0303/CONSTRUCTION TRAFFIC CONTROL - SEC1702Y-109A(130)HP
0194 RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN 627(O) 4410 LF 37,384.000 37,384.000   1,534.000 $3.50 $0.00 $5,369.00
0195 RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER 627(P) 4425 LF 17,825.000 17,825.000   1,594.000 $5.00 $0.00 $7,970.00
0196 (PL)TRAFFIC SIGNAL SPAN WIRE EQUIPMENT 823 8482 LSUM 1.000 1.000   1.000 $76,120.45 $0.00 $76,120.45
0197 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 123,740.000 123,740.000   75,952.920 $0.11 $0.00 $8,354.82
0198 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) 856(C) 8851 LF 21,240.000 21,240.000   746.000 $0.66 $0.00 $492.36
0199 REMOVABLE PAVEMENT MARKING TAPE(8" WIDE) 856(C) 8857 LF 300.000 300.000   0.000 $1.50 $0.00 $0.00
0200 REMOVABLE PAVEMENT MARKING TAPE(ARROWS) 856(D) 8860 EA 18.000 18.000   4.000 $107.21 $0.00 $428.84
0201 REMOVABLE PAVEMENT MARKING TAPE(WORDS) 856(D) 8863 EA 6.000 6.000   0.000 $117.93 $0.00 $0.00
0202 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-2 856(G) 8890 EA 5,265.000 5,265.000   1,000.000 $0.70 $0.00 $700.00
0203 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 47,138.000 47,138.000   12,127.390 $0.13 $0.00 $1,576.56
0204 (PL)CONSTRUCTION ZONE QUADGUARD IMPACT ATTENUATOR 871 8709 SD 7,420.000 7,420.000 15.000 1,211.000 $5.36 $80.40 $6,490.96
0205 (PL)TRUCK MOUNTED ATTENUATOR 876(C) 8482 SD 1,060.000 1,060.000   0.000 $8.58 $0.00 $0.00
0206 ARROW DISPLAY(TYPE A) 880(A) 8800 SD 2,120.000 2,120.000   257.000 $1.07 $0.00 $274.99
0207 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 23,320.000 23,320.000 1,620.000 27,738.000 $0.02 $32.40 $554.76
0208 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 24,380.000 24,380.000 1,140.000 28,153.000 $0.10 $114.00 $2,815.30
0209 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 31,270.000 31,270.000 465.000 12,111.000 $0.02 $9.30 $242.22
0210 BARRICADES(TYPE III) 880(C) 8842 SD 7,420.000 7,420.000 450.000 17,704.000 $5.90 $2,655.00 $104,453.60
0211 WING BARRICADES 880(C) 8848 SD 3,180.000 3,180.000 30.000 829.000 $0.02 $0.60 $16.58
0212 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 46,110.000 46,110.000 1,275.000 46,652.000 $0.05 $63.75 $2,332.60
0213 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 152,110.000 152,110.000 6,000.000 155,386.000 $0.11 $660.00 $17,092.46
0214 DRUMS 880(F) 8878 SD 152,110.000 152,110.000 6,000.000 155,934.000 $0.11 $660.00 $17,152.74
0215 CHANNELIZER CONES 880(G) 8890 SD 6,890.000 6,890.000 300.000 7,252.000 $0.11 $33.00 $797.72
0216 FLAGGER 880(I) 8902 SD 1,060.000 1,060.000   0.000 $175.00 $0.00 $0.00
0217 SURVEILLANCE TRAFFIC CONTROL 880(K) 8908 SD 530.000 530.000 30.000 870.000 $750.48 $22,514.40 $652,917.60
0218