| Contract ID: | 100406 | Estimate Number: | 0013 | Contract No: | 610176 | |||
| Residency: | COBB ENGINEERING CO., INC. (08003) | Estimate Type: | Progressive | Account No: | 400850 | |||
| Project Number(s): | STP-STIM(515)IG | ||||||||||||
| Primary Job Piece No: | 27404(04) | ||||||||||||
| Contract Description: | PAVEMENT REHABILITATION (ASPHALT) CITY STREET (UNION AVE): FROM 71ST STREET TO 81ST STREET IN THE CITY OF TULSA. PROJECT LENGTH = 0.923 MILES. | ||||||||||||
| Primary County: | TULSA | ||||||||||||
| Name of Road: | CITY STREET | ||||||||||||
| Prime Contractor: | ELLSWORTH CONSTRUCTION, LLC | ||||||||||||
| 5141 S. 24TH W. AVE | |||||||||||||
| TULSA , OK 74107 | |||||||||||||
| Surety Company: | OKLAHOMA SURETY COMPANY | ||||||||||||
| Date Let: | 06/17/2010 | NTP Effective Date: | 08/30/2010 | Pay Period: | 05/16/2011 TO 03/01/2012 |
| Date Awarded: | 07/06/2010 | Date Work Began: | 09/13/2010 | Original Contract Time: | 90 |
| Date Contract Executed: | 07/14/2010 | Date Time Stopped: | 05/31/2011 | Current Time Charged: | 275.00 |
| Date NTP Issued: | 07/16/2010 | Completion Date: | 05/31/2011 | Current Time Allowed: | 280.00 |
| General Liability Expires: | 06/10/2011 | Workman's Comp Expires: | 04/08/2011 | Percent Time Used: | 98.21 % |
| Specification Year: | 1999 | Date Approved: | |||
| Current Contract Amount: | $897,862.87 | Total to Date | Prev to Date | This Estimate | |||
| Bid Amount: | $750,464.66 | Participating: | $847,093.08 | $824,050.74 | $23,042.34 | ||
| Percent Complete: | 98.87 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
| Funds Available: | $10,122.84 | Non ARRA: | $50,769.79 | $35,860.73 | $14,909.06 | ||
| Unearned Balance: | $-137,275.37 | Total Earnings: | $897,862.87 | $859,911.47 | $37,951.40 | ||
| Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
| Gross Earnings: | $897,862.87 | $859,911.47 | $37,951.40 | ||||
| Other Adjustments: | $-10,122.84 | $-10,139.57 | $16.73 | ||||
| Liq Dam/Disincentive: | $0.00 | $-5,000.00 | $5,000.00 | ||||
| TOTAL: | $887,740.03 | $844,771.90 | $42,968.13 | ||||
| Contract ID: | 100406 | Estimate Number: | 0013 | Primary JP: | 27404(04) | |||
| CHANGE ORDER HISTORY | |||||
| Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
| 001 | Remove & replace additional roadway section, Asphalt deduct | Approved | 05/02/2011 | 45.0 | $143,011.05 |
| 002 | Deduction for Failing Asphalt Concrete Pavement | Approved | 09/13/2011 | 0.0 | $-1,895.35 |
| 003 | Final Quantity Change Order | Approved | 03/07/2012 | 0.0 | $6,282.51 |
| STOCKPILE PAYMENT HISTORY | |||||
| Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
| 27404(04) | 0016 | Beam Guard Rail-W-Bean Single | Stockpiled Material Adjustment | 0011 | $-5,550.00 |
| 27404(04) | 0016 | Beam Guard Rail-W-Bean Single | Stockpiled Material Initial Payment | 0002 | $5,550.00 |
| 27404(04) | 0017 | Type "A" Anchor - 750 | Stockpiled Material Adjustment | 0011 | $-2,920.00 |
| 27404(04) | 0017 | Type "A" Anchor - 750 | Stockpiled Material Initial Payment | 0002 | $2,920.00 | Subtotals For Stockpile Payments | $0.00 |
| LIQUIDATED DAMAGES HISTORY | ||||
| Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount |
| System Application of Liquidated Damages | 0006 | -5.0 | $500.00 | $-2,500.00 |
| System Application of Liquidated Damages | 0007 | -8.0 | $500.00 | $-4,000.00 |
| System Application of Liquidated Damages | 0008 | -2.0 | $500.00 | $-1,000.00 |
| System Application of Liquidated Damages | 0009 | -7.0 | $500.00 | $-3,500.00 |
| System Application of Liquidated Damages | 0010 | -15.0 | $500.00 | $-7,500.00 |
| System Application of Liquidated Damages | 0011 | -3.0 | $500.00 | $-1,500.00 |
| System Application of Liquidated Damages | 0012 | --30 | $500.00 | $15,000.00 |
| System Application of Liquidated Damages | 0013 | --2.0 | $500.00 | $1,000.00 |
| System Application of Liquidated Damages | 0013 | --15 | $500.00 | $7,500.00 |
| System Application of Liquidated Damages | 0013 | --5.0 | $500.00 | $2,500.00 |
| System Application of Liquidated Damages | 0013 | --8.0 | $500.00 | $4,000.00 |
| System Application of Liquidated Damages | 0013 | --3.0 | $500.00 | $1,500.00 |
| System Application of Liquidated Damages | 0013 | -30.0 | $500.00 | $-15,000.00 |
| System Application of Liquidated Damages | 0013 | --7.0 | $500.00 | $3,500.00 |
| CONTRACT ADJUSTMENTS HISTORY | ||
| Adjustment Description | Estimate Nbr | Adjustment Amount |
| No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
| LINE ITEM ADJUSTMENT HISTORY | |||||||
| Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
| 27404(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0003 | 0.00 | $0.00 | $-760.51 |
| 27404(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0004 | 0.00 | $0.00 | $-1,093.82 |
| 27404(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0008 | 2,056.87 | $-1.90 | $-3,919.88 |
| 27404(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0009 | 337.53 | $-1.38 | $-466.05 |
| 27404(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0013 | -39.83 | $1.48 | $-59.18 |
| 27404(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | Asphalt Binder Adjustment | 0008 | 32.67 | $-1.90 | $-62.26 |
| 27404(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | Asphalt Binder Adjustment | 0009 | 31.60 | $-1.38 | $-43.63 |
| 27404(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | Asphalt Binder Adjustment | 0011 | 5.77 | $-1.38 | $-7.97 |
| 27404(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | Asphalt Binder Adjustment | 0013 | 3.46 | $1.48 | $5.14 |
| 27404(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0010 | 2,057.82 | $-1.57 | $-3,247.24 |
| 27404(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0013 | 41.68 | $1.69 | $70.77 |
| 27404(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 70-28 OK) | Asphalt Binder Adjustment | 0009 | 180.08 | $-1.74 | $-313.77 |
| 27404(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 70-28 OK) | Asphalt Binder Adjustment | 0010 | 128.81 | $-1.74 | $-224.44 | Subtotals For Line Item Adjustments | $-10,122.84 |
| MILESTONE ADJUSTMENTS | |||||||||
| Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
| No milestones exist for this contract. | |||||||||
| Contract ID: | 100406 | Estimate Number: | 0013 | Primary JP: | 27404(04) | |||
| Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
| Fed/State Project Number: STP-STIM(515)IG | Project: 27404(04) | Category: 0100/ROADWAY | ||||||||
| 0001 | CONSTRUCTION MISCELLANEOUS | 104 0700 | LSUM | 1.000 | 1.000 | 1.000 | $9,600.00 | $0.00 | $9,600.00 | |
| 0002 | CLEARING AND GRUBBING | 201 0102 | LSUM | 1.000 | 1.000 | 1.000 | $12,000.00 | $0.00 | $12,000.00 | |
| 0003 | TEMPORARY SILT FENCE | 223 2801 | LF | 10,716.000 | 0.000 | 0.000 | $2.25 | $0.00 | $0.00 | |
| 0004 | SOLID SLAB SODDING | 230(A) 2806 | SY | 10,802.000 | 10,086.390 | 157.240 | 10,086.390 | $1.60 | $251.58 | $16,138.22 |
| 0005 | AGGREGATE BASE | 303 0192 | CY | 2,400.000 | 2,392.510 | -18.750 | 2,392.510 | $46.00 | $-862.50 | $110,055.46 |
| 0006 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 411(S3) 5945 | TON | 2,580.000 | 3,713.150 | -39.830 | 3,713.150 | $56.00 | $-2,230.48 | $207,936.40 |
| 0007 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | 411(S3) 6210 | TON | 50.000 | 73.500 | 3.460 | 73.500 | $100.00 | $346.00 | $7,350.00 |
| 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 2,050.000 | 2,099.500 | 41.680 | 2,099.500 | $72.50 | $3,021.80 | $152,213.75 |
| 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 70-28 OK) | 411(S5) 5970 | TON | 350.000 | 308.890 | 308.890 | $90.00 | $0.00 | $27,800.10 | |
| 0010 | 10" H.E.S. CONCRETE PAVEMENT | 414(B) 0302 | SY | 280.000 | 338.730 | 57.730 | 338.730 | $80.00 | $4,618.40 | $27,098.40 |
| 0011 | FABRIC REINFORCEMENT | 420(A) 4242 | SY | 9,929.000 | 7,061.330 | 7,061.330 | $2.30 | $0.00 | $16,241.06 | |
| 0012 | BITUMINOUS DRIVEWAY (6") | 610(G) 4475 | SY | 414.000 | 419.180 | 2.440 | 419.180 | $55.00 | $134.20 | $23,054.90 |
| 0013 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 619(A) 0920 | LSUM | 1.000 | 1.000 | 1.000 | $6,000.00 | $0.00 | $6,000.00 | |
| 0014 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 10,348.000 | 12,065.540 | 1,697.770 | 12,065.540 | $8.00 | $13,582.16 | $96,524.32 |
| 0015 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 280.000 | 338.730 | 57.730 | 338.730 | $12.00 | $692.76 | $4,064.76 |
| 0016 | BEAM GUARD RAIL-W-BEAM-SINGLE | 623(A) 0932 | LF | 600.000 | 600.000 | 600.000 | $22.50 | $0.00 | $13,500.00 | |
| 0017 | GUARD RAIL ANCHOR UNIT (TYPE A) | 623(F) 4446 | EA | 4.000 | 4.000 | 4.000 | $1,460.00 | $0.00 | $5,840.00 | |
| 0018 | GUIDE POSTS | 623(G) 0936 | EA | 100.000 | 98.000 | 98.000 | $33.00 | $0.00 | $3,234.00 | |
| 0019 | REMOVE AND RESET MAILBOX | 629(E) 5048 | EA | 14.000 | 8.000 | 8.000 | $200.00 | $0.00 | $1,600.00 | |
| 8003 | DEDUCTION FOR FAILING MATERIAL | 105 2100 | LSUM | 0.000 | 0.000 | 0.000 | $784.00 | $0.00 | $0.00 | |
| 8004 | DEDUCTION FOR FAILING MATERIAL | 105 2100 | LSUM | 0.000 | 0.000 | 0.000 | $616.00 | $0.00 | $0.00 | |
| 8005 | DEDUCTION FOR FAILING MATERIAL | 105 2100 | LSUM | 0.000 | -1.000 | -1.000 | -1.000 | $3,295.35 | $-3,295.35 | $-3,295.35 |
| Subtotals For Category 0100/ROADWAY | $16,258.57 | $736,956.02 | ||||||||
| Fed/State Project Number: STP-STIM(515)IG | Project: 27404(04) | Category: 0300/TRAFFIC | ||||||||
| 0020 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 19,572.000 | 19,142.000 | -91.000 | 19,142.000 | $0.73 | $-66.43 | $13,973.66 |
| 0021 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 856(A) 8839 | LF | 10,000.000 | 19,602.000 | 19,602.000 | 19,602.000 | $0.14 | $2,744.28 | $2,744.28 |
| 0022 | ARROW DISPLAY(TYPE A) | 880(A) 8803 | EA | 240.000 | 0.000 | 0.000 | $1.15 | $0.00 | $0.00 | |
| 0023 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 240.000 | 3,341.000 | -12.000 | 3,341.000 | $2.30 | $-27.60 | $7,684.30 |
| 0024 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 240.000 | 5,155.000 | -25.000 | 5,155.000 | $3.40 | $-85.00 | $17,527.00 |
| 0025 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 240.000 | 3,546.000 | 29.000 | 3,546.000 | $3.40 | $98.60 | $12,056.40 |
| 0026 | BARRICADES(TYPE II) | 880(C) 8836 | SD | 480.000 | 150.000 | 150.000 | $0.12 | $0.00 | $18.00 | |
| 0027 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 480.000 | 1,525.000 | 0.000 | 1,525.000 | $2.30 | $0.00 | $3,507.50 |
| 0028 | VERTICAL PANELS | 880(D) 8854 | SD | 480.000 | 4,500.000 | 120.000 | 4,500.000 | $0.12 | $14.40 | $540.00 |
| 0029 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 240.000 | 6,100.000 | -34.000 | 6,100.000 | $0.30 | $-10.20 | $1,830.00 |
| 0030 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 240.000 | 23,817.000 | 20,477.000 | 23,817.000 | $0.30 | $6,143.10 | $7,145.10 |
| 0031 | DRUMS | 880(F) 8881 | EA | 2,400.000 | 19,317.000 | 22.000 | 19,317.000 | $0.46 | $10.12 | $8,885.82 |
| 0032 | TUBE CHANNELIZERS | 880(G) 8887 | EA | 6,000.000 | 0.000 | 0.000 | $0.46 | $0.00 | $0.00 | |
| 0033 | FLAGGER | 880(I) 8902 | SD | 240.000 | 69.000 | -91.500 | 69.000 | $25.00 | $-2,287.50 | $1,725.00 |
| Subtotals For Category 0300/TRAFFIC | $6,533.77 | $77,637.06 | ||||||||
| Fed/State Project Number: STP-STIM(515)IG | Project: 27404(04) | Category: 0600/STAKING | ||||||||
| 0034 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 1.000 | $15,000.00 | $0.00 | $15,000.00 | |
| Subtotals For Category 0600/STAKING | $0.00 | $15,000.00 | ||||||||
| Fed/State Project Number: STP-STIM(515)IG | Project: 27404(04) | Category: 0640/CONSTRUCTION | ||||||||
| 0035 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.100 | 1.000 | $2,500.00 | $250.00 | $2,500.00 |
| 0036 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $15,000.00 | $0.00 | $15,000.00 | |
| Subtotals For Category 0640/CONSTRUCTION | $250.00 | $17,500.00 | ||||||||
| Fed/State Project Number: STP-STIM(515)IG | Project: 27404(04) | Category: 0850/NON ARRA FUNDING | ||||||||
| 8001 | REMOVAL OF GUARD RAIL | 619(B) 4780 | LF | 0.000 | 764.000 | 14.000 | 764.000 | $4.00 | $56.00 | $3,056.00 |
| 8002 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 0.000 | 1,395.140 | 434.300 | 1,395.140 | $34.20 | $14,853.06 | $47,713.79 |
| Subtotals For Category 0850/NON ARRA FUNDING | $14,909.06 | $50,769.79 | ||||||||
| Fed/State Project Number: STP-STIM(515)IG | Project: 27404(04) | Category: 0900/NON PARTICIPATING | ||||||||
| Subtotals For Category 0900/NON PARTICIPATING | $0.00 | $0.00 | ||||||||
| Subtotals For Project STP-STIM(515)IG /27404(04) | $37,951.40 | $897,862.87 | ||||||||