Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    08/01/2013
Contract ID: 100395   Estimate Number: 0046     Contract No: 610868
Residency: CLAREMORE (08300)   Estimate Type: Progressive     Account No: 400800

Project Number(s): BRFY-058C(235), BRFY-058C(237), STPY-058C(240)
Primary Job Piece No: 08932(04)
Contract Description: GRADE, DRAIN, SURFACE, AND BRIDGE SH-10: FROM THE I-44 INTERCHANGE, EXTEND EAST. PROJECT LENGTH = 3.566 MILES.
Primary County: OTTAWA              
Name of Road: SH-10              
Prime Contractor: BECCO CONTRACTORS, INC.              
    P.O. BOX 9159              
    TULSA , OK   74157              
Surety Company: MID-CONTINENT CASUALTY COMPANY              

Date Let: 11/18/2010 NTP Effective Date: 04/04/2011 Pay Period: 07/01/2013  TO  07/31/2013
Date Awarded: 12/06/2010 Date Work Began: 04/04/2011 Original Contract Time: 650
Date Contract Executed: 12/22/2010 Date Time Stopped: 07/29/2013 Current Time Charged: 848.00
Date NTP Issued: 01/04/2011 Completion Date: 07/29/2013 Current Time Allowed: 860.00
General Liability Expires: 03/01/2014 Workman's Comp Expires: 02/01/2014 Percent Time Used: 98.60 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $19,653,425.46 Total to Date Prev to Date This Estimate
Bid Amount: $19,695,764.93 Participating: $19,105,816.43 $19,101,375.04 $4,441.39
Percent Complete: 98.48 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $299,708.77 Total Earnings: $19,105,816.43 $19,101,375.04 $4,441.39
Unearned Balance: $342,048.24 Stockpiled Materials: $0.02 $0.02 $0.00
Gross Earnings: $19,105,816.45 $19,101,375.06 $4,441.39
Other Adjustments: $247,900.24 $247,900.24 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $19,353,716.69 $19,349,275.30 $4,441.39

Estimate Adjustment Detail

Contract ID: 100395   Estimate Number: 0046     Primary JP: 08932(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Supplemental agreement to remove light pole. Approved 07/07/2011 0.0 $2,625.00
003 Penelty due to impropper timed work on I-44 Approved 12/10/2012 0.0 $-75,000.00
004 Concrete pavement removal Pending 0 0.0 $18,424.26
005 Days recovered from Utility Conflicts Approved 04/11/2013 110.0 $0.00
006 Add Milestone to SH-137 construction Approved 04/29/2013 0.0 $30,000.00
007 Failing material deduction Approved 11/26/2012 0.0 $-1,447.74
008 FAILING MATERIAL DEDUCTION Approved 06/25/2013 0.0 $-3,675.98
009 Pay plan plus on line 108 Approved 04/17/2013 0.0 $5,159.25
010 Remobilization Pending 0 0.0 $1,800.00


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
08932(04) 0022 dowel bar baskets Stockpiled Material Adjustment 0032 $-608.93
08932(04) 0022 dowel bar baskets Stockpiled Material Adjustment 0025 $-11,327.11
08932(04) 0022 dowel bar baskets Stockpiled Material Adjustment 0024 $-26,051.68
08932(04) 0022 dowel bar baskets Stockpiled Material Adjustment 0022 $-3,229.81
08932(04) 0022 dowel bar baskets Stockpiled Material Adjustment 0021 $-2,515.51
08932(04) 0022 dowel bar baskets Stockpiled Material Initial Payment 0005 $43,733.04
08932(04) 0022 DURO PLAIN PAD Stockpiled Material Adjustment 0021 $-20,720.00
08932(04) 0022 DURO PLAIN PAD Stockpiled Material Initial Payment 0006 $20,720.00
08932(04) 0035 frm & cvr Stockpiled Material Adjustment 0038 $-1,474.49
08932(04) 0035 frm & cvr Stockpiled Material Adjustment 0025 $-2,948.98
08932(04) 0035 frm & cvr Stockpiled Material Adjustment 0022 $-421.28
08932(04) 0035 frm & cvr Stockpiled Material Initial Payment 0020 $4,844.75
08932(04) 0035 Stockpiled Material Adjustment 0038 $-1,895.60
08932(04) 0035 Stockpiled Material Initial Payment 0030 $1,895.60
08932(04) 0036 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0028 $-89.80
08932(04) 0036 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $898.00
08932(04) 0036 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0017 $-808.20
08932(04) 0037 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0028 $-689.00
08932(04) 0037 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,378.00
08932(04) 0037 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0017 $-689.00
08932(04) 0042 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0015 $-1,035.00
08932(04) 0042 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,035.00
08932(04) 0045 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $2,217.00
08932(04) 0045 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0014 $-2,217.00
08932(04) 0048 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,315.00
08932(04) 0048 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0015 $-1,315.00
08932(04) 0049 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $7,775.00
08932(04) 0049 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0011 $-1,555.00
08932(04) 0049 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0010 $-6,220.00
08932(04) 0052 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $2,275.00
08932(04) 0052 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0012 $-2,275.00
08932(04) 0053 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $616.00
08932(04) 0053 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0022 $-616.00
08932(04) 0054 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $616.00
08932(04) 0054 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0037 $-616.00
08932(04) 0055 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0037 $-146.64
08932(04) 0055 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $146.64
08932(04) 0059 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0025 $-1,634.57
08932(04) 0059 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $3,473.96
08932(04) 0059 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0024 $-1,839.39
08932(04) 0061 frm & grt Stockpiled Material Adjustment 0024 $-1,365.47
08932(04) 0061 frm & grt Stockpiled Material Adjustment 0025 $-8,192.79
08932(04) 0061 frm & grt Stockpiled Material Initial Payment 0020 $14,109.81
08932(04) 0061 frm & grt Stockpiled Material Adjustment 0034 $-3,641.24
08932(04) 0061 frm & grt Stockpiled Material Adjustment 0022 $-910.31
08932(04) 0061 Stockpiled Material Adjustment 0034 $-8,663.90
08932(04) 0061 Stockpiled Material Initial Payment 0030 $8,663.90
08932(04) 0062 inlets Stockpiled Material Adjustment 0022 $-660.50
08932(04) 0062 inlets Stockpiled Material Adjustment 0024 $-1,100.84
08932(04) 0062 inlets Stockpiled Material Adjustment 0034 $-3,963.02
08932(04) 0062 inlets Stockpiled Material Adjustment 0025 $-9,687.39
08932(04) 0062 inlets Stockpiled Material Initial Payment 0020 $15,411.76
08932(04) 0062 Stockpiled Material Initial Payment 0030 $5,834.50
08932(04) 0062 Stockpiled Material Adjustment 0034 $-5,834.50
08932(04) 0070 Stockpiled Material Initial Payment 0009 $7,115.72
08932(04) 0070 Stockpiled Material Adjustment 0020 $-1,522.08
08932(04) 0070 Stockpiled Material Closure 0042 $-5,593.64
10430(04) 0158 dowel bar baskets Stockpiled Material Adjustment 0023 $-1,096.32
10430(04) 0158 dowel bar baskets Stockpiled Material Adjustment 0033 $-7,917.47
10430(04) 0158 dowel bar baskets Stockpiled Material Initial Payment 0005 $28,932.80
10430(04) 0158 dowel bar baskets Stockpiled Material Adjustment 0021 $-19,919.02
10430(04) 0176 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0007 $-1,418.00
10430(04) 0176 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,418.00
10430(04) 0177 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,315.00
10430(04) 0177 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0024 $-1,315.00
10430(04) 0180 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $232.05
10430(04) 0180 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0022 $-232.05
10430(04) 0182 Stockpiled Material Closure 0042 $-1,663.90
10430(04) 0182 Stockpiled Material Adjustment 0040 $-700.00
10430(04) 0182 Stockpiled Material Adjustment 0036 $-6,300.00
10430(04) 0182 Stockpiled Material Initial Payment 0030 $8,663.90
10430(04) 0183 Stockpiled Material Adjustment 0036 $-5,834.50
10430(04) 0183 Stockpiled Material Initial Payment 0030 $5,834.50
10430(04) 0187 Stockpiled Material Adjustment 0023 $-475.65
10430(04) 0187 Stockpiled Material Adjustment 0018 $-570.78
10430(04) 0187 Stockpiled Material Closure 0042 $-38.05
10430(04) 0187 Stockpiled Material Initial Payment 0009 $1,084.48
10430(04) 0213 PRESTRESSED J BEAMS Stockpiled Material Adjustment 0013 $-35,096.66
10430(04) 0213 PRESTRESSED J BEAMS Stockpiled Material Adjustment 0012 $-39,732.06
10430(04) 0213 PRESTRESSED J BEAMS Stockpiled Material Initial Payment 0006 $149,657.44
10430(04) 0213 PRESTRESSED J BEAMS Stockpiled Material Adjustment 0032 $-74,828.72
10430(04) 0214 Stockpiled Material Initial Payment 0022 $10,122.09
10430(04) 0214 Stockpiled Material Adjustment 0035 $-9,900.79
10430(04) 0214 Stockpiled Material Closure 0042 $-221.30
10430(04) 0216 Stockpiled Material Initial Payment 0022 $2,105.48
10430(04) 0216 Stockpiled Material Adjustment 0036 $-1,292.55
10430(04) 0216 Stockpiled Material Adjustment 0035 $-812.93
10430(04) 0222 reinforce steel Stockpiled Material Initial Payment 0020 $166.33
10430(04) 0222 reinforce steel Stockpiled Material Adjustment 0028 $-166.33
10430(04) 0223 reinforcing steel Stockpiled Material Initial Payment 0020 $12,416.66
10430(04) 0223 reinforcing steel Stockpiled Material Adjustment 0028 $-5,322.51
10430(04) 0223 reinforcing steel Stockpiled Material Adjustment 0029 $-5,322.51
10430(04) 0223 reinforcing steel Stockpiled Material Adjustment 0030 $-1,771.64
10430(04) 0223 reinforcing steel Stockpiled Material Adjustment 0028 $-95.69
10430(04) 0223 reinforcing steel Stockpiled Material Initial Payment 0020 $95.69
10430(04) 0223 Stockpiled Material Adjustment 0033 $-2,375.78
10430(04) 0223 Stockpiled Material Adjustment 0029 $-5,322.51
10430(04) 0223 Stockpiled Material Adjustment 0034 $-2,899.31
10430(04) 0223 Stockpiled Material Adjustment 0030 $-2,531.32
10430(04) 0223 Stockpiled Material Initial Payment 0022 $18,451.44
10430(04) 0223 Stockpiled Material Adjustment 0028 $-5,322.51
10430(04) 0224 PILES, FURNISHED (10X42) Stockpiled Material Adjustment 0005 $-6,098.40
10430(04) 0224 PILES, FURNISHED (10X42) Stockpiled Material Initial Payment 0001 $6,098.40
10430(04) 0225 PILES, FURNISHED (HP 12X53) Stockpiled Material Initial Payment 0001 $33,037.20
10430(04) 0225 PILES, FURNISHED (HP 12X53) Stockpiled Material Adjustment 0005 $-33,037.20
10430(04) 0229 drill shaft steel Stockpiled Material Adjustment 0028 $-2,615.23
10430(04) 0229 drill shaft steel Stockpiled Material Initial Payment 0020 $5,230.47
10430(04) 0229 drill shaft steel Stockpiled Material Adjustment 0027 $-2,615.23
12573(04) 0302 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0019 $-713.00
12573(04) 0302 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $713.00
12573(04) 0305 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0017 $-2,738.00
12573(04) 0305 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $2,738.00
12573(04) 0308 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,849.00
12573(04) 0308 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0007 $-1,849.00
12573(04) 0312 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,555.00
12573(04) 0312 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0007 $-1,555.00
12573(04) 0315 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0007 $-2,035.00
12573(04) 0315 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $2,035.00
12573(04) 0317 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $326.06
12573(04) 0317 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0024 $-326.06
12573(04) 0318 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $170.20
12573(04) 0318 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0028 $-71.80
12573(04) 0318 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0015 $-55.00
12573(04) 0318 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0024 $-43.40
12573(04) 0321 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $269.99
12573(04) 0321 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0015 $-269.99
12573(04) 0322 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0015 $-946.76
12573(04) 0322 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Initial Payment 0003 $1,242.42
12573(04) 0322 IN SUPPLIERS YARD (MIAMI, OK) Stockpiled Material Adjustment 0028 $-295.66
12573(04) 0323 Stockpiled Material Initial Payment 0030 $17,327.80
12573(04) 0323 Stockpiled Material Adjustment 0031 $-16,800.00
12573(04) 0323 Stockpiled Material Adjustment 0034 $-527.80
12573(04) 0325 Stockpiled Material Initial Payment 0030 $11,669.00
12573(04) 0325 Stockpiled Material Adjustment 0031 $-11,669.00
12573(04) 0331 Stockpiled Material Adjustment 0016 $-951.17
12573(04) 0331 Stockpiled Material Initial Payment 0009 $4,774.89
12573(04) 0331 Stockpiled Material Adjustment 0010 $-808.50
12573(04) 0331 Stockpiled Material Adjustment 0011 $-1,597.97
12573(04) 0331 Stockpiled Material Adjustment 0013 $-447.05
12573(04) 0331 Stockpiled Material Adjustment 0014 $-361.45
12573(04) 0331 Stockpiled Material Closure 0042 $-608.75
Subtotals For Stockpile Payments $0.02


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0043 --3.0 $2,000.00 $-6,000.00
System Application of Liquidated Damages 0044 -3.0 $2,000.00 $6,000.00
Subtotals For Liquidated Damages $0.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
08932(04) 0003 ROCK EXCAVATION * QAQC 0030 3.00 $6,000.00 $18,000.00
08932(04) 0003 ROCK EXCAVATION * QAQC 0031 15.00 $6,000.00 $90,000.00
08932(04) 0003 ROCK EXCAVATION * QAQC 0032 16.00 $6,000.00 $96,000.00
08932(04) 0003 ROCK EXCAVATION * QAQC 0043 -34.00 $6,000.00 $-204,000.00
08932(04) 0006 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0002 -753.00 $1.50 $-1,129.50
08932(04) 0006 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0010 -351.00 $1.50 $-526.50
08932(04) 0006 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0018 1,104.00 $1.50 $1,656.00
08932(04) 0018 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0026 621.83 $4.91 $3,056.33
08932(04) 0018 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0035 61.74 $4.39 $271.04
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0019 299.11 $3.76 $1,124.69
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0020 303.34 $3.76 $1,140.57
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0021 185.47 $3.76 $697.38
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0022 182.28 $3.86 $704.52
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0023 273.88 $3.86 $1,058.56
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0035 238.02 $4.39 $1,044.94
08932(04) 0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0037 72.14 $4.18 $301.55
08932(04) 0020 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0035 720.42 $5.01 $3,614.49
08932(04) 0021 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0023 98.50 $4.41 $435.09
08932(04) 0063 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0005 -52.00 $50.00 $-2,600.00
08932(04) 0063 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0006 52.00 $50.00 $2,600.00
08932(04) 0068 48" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0005 -84.00 $130.00 $-10,920.00
08932(04) 0068 48" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0006 84.00 $130.00 $10,920.00
08932(04) 0071 18" PREFAB. CULVERT END SECTION, ROUND * Material Discrepancy Adjustments 0005 -2.00 $600.00 $-1,200.00
08932(04) 0071 18" PREFAB. CULVERT END SECTION, ROUND * Material Discrepancy Adjustments 0006 2.00 $600.00 $1,200.00
08932(04) 0075 48" PREFAB. CULVERT END SECTION, ROUND * Material Discrepancy Adjustments 0005 -2.00 $1,800.00 $-3,600.00
08932(04) 0075 48" PREFAB. CULVERT END SECTION, ROUND * Material Discrepancy Adjustments 0006 2.00 $1,800.00 $3,600.00
10430(04) 0144 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0010 -345.00 $1.50 $-517.50
10430(04) 0144 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0018 345.00 $1.50 $517.50
10430(04) 0153 (SP)MODIFIED SUBGRADE * Missing Material Certification 0026 -3,104.72 $3.00 $-9,314.18
10430(04) 0153 (SP)MODIFIED SUBGRADE * Missing Material Certification 0027 3,104.72 $3.00 $9,314.16
10430(04) 0153 (SP)MODIFIED SUBGRADE * Material Discrepancy Adjustments 0027 1,034.91 $-0.75 $-776.18
10430(04) 0156 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0023 65.50 $3.86 $253.16
10430(04) 0156 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0035 14.42 $4.39 $63.31
10430(04) 0156 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0037 49.22 $4.18 $205.74
10430(04) 0186 30" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0005 -120.00 $55.00 $-6,600.00
10430(04) 0186 30" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0006 120.00 $55.00 $6,600.00
10430(04) 0204 (SP)FENCE-STYLE SWF (5 BARBED WIRE) * Material Discrepancy Adjustments 0002 -467.00 $5.00 $-2,335.00
10430(04) 0204 (SP)FENCE-STYLE SWF (5 BARBED WIRE) * Material Discrepancy Adjustments 0004 467.00 $5.00 $2,335.00
10430(04) 0205 FENCE-STYLE CLF (6'HIGH, CLASS A) * Material Discrepancy Adjustments 0007 -125.00 $50.00 $-6,250.00
10430(04) 0205 FENCE-STYLE CLF (6'HIGH, CLASS A) * Material Discrepancy Adjustments 0018 125.00 $50.00 $6,250.00
10430(04) 0213 PRESTRESSED CONCRETE BEAMS (TYPE J BT) * SUBSTANDARD ITEM 0013 1.00 $-5,000.00 $-5,000.00
10430(04) 0213 PRESTRESSED CONCRETE BEAMS (TYPE J BT) * SUBSTANDARD ITEM 0043 1.00 $5,000.00 $5,000.00
10430(04) 0220 CLASS A CONCRETE * SUBSTANDARD ITEM 0029 2.00 $-10,000.00 $-20,000.00
10430(04) 0220 CLASS A CONCRETE * SUBSTANDARD ITEM 0043 2.00 $10,000.00 $20,000.00
10430(04) 0229 DRILLED SHAFTS 66" DIAMETER * SUBSTANDARD ITEM 0029 1.00 $-50,000.00 $-50,000.00
10430(04) 0229 DRILLED SHAFTS 66" DIAMETER * SUBSTANDARD ITEM 0043 1.00 $50,000.00 $50,000.00
12573(04) 0269 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0005 -1.50 $86.00 $-129.00
12573(04) 0269 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0011 -235.00 $1.50 $-352.50
12573(04) 0269 TEMPORARY SILT FENCE * Material Discrepancy Adjustments 0018 321.00 $1.50 $481.50
12573(04) 0271 SOLID SLAB SODDING * Material Discrepancy Adjustments 0036 -1,777.78 $1.25 $-2,222.23
12573(04) 0278 (SP)MODIFIED SUBGRADE * Material Discrepancy Adjustments 0024 -20.44 $3.00 $-61.33
12573(04) 0278 (SP)MODIFIED SUBGRADE * Material Discrepancy Adjustments 0043 20.44 $3.00 $61.33
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0016 343.48 $3.76 $1,291.50
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0017 1,554.82 $3.76 $5,846.20
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0026 5,164.99 $4.91 $25,386.18
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * HMA Deduction as per Sec. 411 0028 306.86 $-22.20 $-6,812.29
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0028 306.86 $5.75 $1,766.00
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0032 4,836.55 $5.96 $28,850.26
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0034 174.13 $4.91 $855.86
12573(04) 0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0035 101.55 $4.39 $445.81
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0014 2,171.73 $4.49 $9,762.04
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0016 6,759.97 $3.76 $25,417.83
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0019 117.04 $3.76 $440.10
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0020 2,076.71 $3.76 $7,808.53
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0021 447.26 $3.76 $1,681.72
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0022 877.38 $3.86 $3,391.12
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0023 2,483.65 $3.86 $9,599.43
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0024 769.44 $3.86 $2,973.92
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0025 1,974.38 $4.91 $9,704.18
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0026 299.44 $4.91 $1,471.76
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * HMA Deduction as per Sec. 411 0028 915.37 $-3.15 $-2,883.42
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0028 915.37 $5.75 $5,268.00
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0030 5,733.78 $5.96 $34,202.28
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0031 509.07 $5.96 $3,036.63
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0032 3,308.25 $5.96 $19,733.88
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0034 256.55 $4.91 $1,260.96
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0035 49.95 $4.39 $219.31
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0038 66.57 $4.18 $278.27
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * HMA Deduction as per Sec. 411 0043 1,000.00 $-3.50 $-3,500.00
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * HMA Deduction as per Sec. 411 0043 1,000.00 $-4.00 $-4,000.00
12573(04) 0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * HMA Deduction as per Sec. 411 0043 1,000.00 $-1.50 $-1,500.00
12573(04) 0283 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0017 198.94 $4.29 $854.89
12573(04) 0283 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0034 3,576.02 $5.61 $20,087.22
12573(04) 0283 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0035 6,152.64 $5.01 $30,869.03
12573(04) 0283 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * HMA Deduction as per Sec. 411 0043 323.87 $-5.44 $-1,761.85
12573(04) 0284 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0017 1,002.30 $4.29 $4,307.08
12573(04) 0284 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0035 -0.27 $5.01 $-1.36
12573(04) 0284 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0038 120.62 $4.77 $576.23
12573(04) 0293 6" CONCRETE DRIVEWAY * Material Discrepancy Adjustments 0024 40.00 $-9.65 $-386.04
12573(04) 0293 6" CONCRETE DRIVEWAY * Material Discrepancy Adjustments 0024 40.00 $-9.65 $-386.04
12573(04) 0293 6" CONCRETE DRIVEWAY * Material Discrepancy Adjustments 0043 80.00 $9.65 $772.08
12573(04) 0342 FENCE-STYLE WWF * Material Discrepancy Adjustments 0002 1,821.00 $9.00 $16,389.00
12573(04) 0342 FENCE-STYLE WWF * Material Discrepancy Adjustments 0006 -1,821.00 $9.00 $-16,389.00
Subtotals For Line Item Adjustments $247,900.24
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 TIME 'B' BID 04/04/2011 10/15/2012 560.00 DYS $6,000.00 Y


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
01 System Application of Disincentive Adj 0030 $-18,000.00
01 System Application of Disincentive Adj 0031 $-90,000.00
01 System Application of Disincentive Adj 0032 $-96,000.00
01 System Application of Disincentive Adj 0033 $-90,000.00
01 System Application of Disincentive Adj 0034 $-96,000.00
01 System Application of Disincentive Adj 0035 $-90,000.00
01 System Application of Disincentive Adj 0036 $-90,000.00
01 System Application of Disincentive Adj 0037 $-90,000.00
01 System Application of Disincentive Adj 0043 $90,000.00
01 System Application of Disincentive Adj 0043 $18,000.00
01 System Application of Disincentive Adj 0043 $96,000.00
01 System Application of Disincentive Adj 0043 $96,000.00
01 System Application of Disincentive Adj 0043 $90,000.00
01 System Application of Disincentive Adj 0043 $90,000.00
01 System Application of Disincentive Adj 0043 $90,000.00
01 System Application of Disincentive Adj 0043 $90,000.00
Subtotals For Milestones $0.00

Line Item Detail

Contract ID: 100395   Estimate Number: 0046     Primary JP: 08932(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0100/ROADWAY - BRFY-058C(235)
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 65,661.000 65,661.000   65,661.000 $5.00 $0.00 $328,305.00
0003 ROCK EXCAVATION 202(B) 0182 CY 9,988.000 9,988.000   38,384.390 $25.00 $0.00 $959,609.75
0004 UNCLASSIFIED BORROW 202(C) 0184 CY 215.000 215.000   215.000 $5.00 $0.00 $1,075.00
0005 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   1.000 $50,000.00 $0.00 $50,000.00
0006 TEMPORARY SILT FENCE 223 2801 LF 1,600.000 1,600.000   3,266.000 $1.50 $0.00 $4,899.00
0007 TEMPORARY SILT DIKE 227 0100 LF 1,820.000 1,820.000   42.000 $7.00 $0.00 $294.00
0008 SOLID SLAB SODDING 230(A) 2806 SY 39,607.000 39,607.000   46,054.970 $1.25 $0.00 $57,568.71
0009 SEEDING METHOD B 232(B) 2814 AC 16.300 16.300   0.000 $450.00 $0.00 $0.00
0010 VEGETATIVE MULCHING 233(A) 2817 AC 8.200 8.200   0.000 $450.00 $0.00 $0.00
0011 MOWING 241 2832 AC 16.400 16.400   24.250 $50.00 $0.00 $1,212.50
0012 AGGREGATE BASE 303 0192 CY 12,176.000 12,176.000   10,600.600 $28.00 $0.00 $296,816.79
0013 (SP)CEMENT TREATED BASE 317(F) 4270 SY 42,461.000 42,461.000   42,628.090 $14.00 $0.00 $596,793.26
0014 SEPARATOR FABRIC 325 5271 SY 57,517.000 57,517.000   57,544.740 $1.00 $0.00 $57,544.74
0015 (SP)MODIFIED SUBGRADE 327(J) 4290 SY 49,233.000 49,233.000   42,041.630 $3.00 $0.00 $126,124.90
0016 (SP)GEOSYNTHETIC SUBGRADE REINFORCEMENT 328 2600 SY 4,923.000 4,923.000   0.000 $4.00 $0.00 $0.00
0017 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 1,073.000 1,073.000   1,245.800 $14.00 $0.00 $17,441.20
0018 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) 411(S3) 5935 TON 694.000 694.000   683.570 $64.00 $0.00 $43,748.48
0019 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 1,919.000 1,919.000   1,554.250 $52.00 $0.00 $80,821.00
0020 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 495.000 495.000   720.420 $70.00 $0.00 $50,429.40
0021 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 128.000 128.000   98.500 $63.00 $0.00 $6,205.50
0022 (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) 414(A1) 5725 SY 40,198.000 40,198.000   40,203.800 $14.00 $0.00 $562,853.21
0023 (SP)P.C. CONCRETE FOR PAVEMENT 414(P) 6000 CY 9,986.000 9,986.000   9,986.600 $95.00 $0.00 $948,727.01
0024 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 15.000 15.000   9.630 $25.00 $0.00 $240.76
0025 CLASS A CONCRETE 509(B) 0321 CY 24.000 24.000   26.570 $500.00 $0.00 $13,285.00
0026 REINFORCING STEEL 511(A) 0332 LB 3,155.000 3,155.000   3,400.220 $1.00 $0.00 $3,400.22
0027 TYPE I PLAIN RIPRAP 601(A) 0297 TON 116.000 116.000   105.840 $30.00 $0.00 $3,175.20
0028 CONCRETE CURB (6" BARRIER-INTEGRAL) 609(A) 0300 LF 10,223.000 10,223.000   9,064.000 $4.00 $0.00 $36,256.00
0029 2'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1525 LF 1,150.000 1,150.000   1,150.000 $17.00 $0.00 $19,550.00
0030 6" CONCRETE DRIVEWAY 610(B) 0604 SY 3,836.000 3,836.000   4,086.410 $40.00 $0.00 $163,456.40
0031 MANHOLE (4' DIAMETER) 611(A) 2657 EA 3.000 3.000   3.000 $2,000.00 $0.00 $6,000.00
0032 MANHOLE (5' DIAMETER) 611(A) 2658 EA 3.000 3.000   3.000 $2,700.00 $0.00 $8,100.00
0033 ADD'L.DEPTH IN MANHOLE (4' DIAMETER) 611(B) 2680 VF 5.000 5.000   3.170 $200.00 $0.00 $634.00
0034 ADD'L.DEPTH IN MANHOLE (5' DIAMETER) 611(B) 2681 VF 9.000 9.000   7.920 $300.00 $0.00 $2,376.00
0035 MANHOLE FRAME & COVER 611(D) 4215 EA 31.000 31.000   31.000 $350.00 $0.00 $10,850.00
0036 INLET CICI DES. 2 (STD) 611(E) 5112 EA 6.000 6.000   6.000 $1,800.00 $0.00 $10,800.00
0037 INLET CICI DES. 2 (B) 611(E) 5113 EA 5.000 5.000   5.000 $2,200.00 $0.00 $11,000.00
0038 INLET CICI DES. 2 (D) 611(E) 5115 EA 2.000 2.000   2.000 $2,400.00 $0.00 $4,800.00
0039 INLET CICI DES. 3 (STD) 611(E) 5120 EA 1.000 1.000   1.000 $2,700.00 $0.00 $2,700.00
0040 INLET CICI DES. 3 (2B) 611(E) 5123 EA 1.000 1.000   1.000 $3,800.00 $0.00 $3,800.00
0041 INLET GPI TYPE 1 (DES. 1) 611(E) 5327 EA 1.000 1.000   1.000 $1,600.00 $0.00 $1,600.00
0042 INLET GPI TYPE 1 (DES. 5) 611(E) 5331 EA 4.000 4.000   4.000 $1,800.00 $0.00 $7,200.00
0043 INLET GPI TYPE 2 (DES. 9) 611(E) 5335 EA 1.000 1.000   1.000 $2,300.00 $0.00 $2,300.00
0044 INLET W/LRG.JCT.BOX,CICI-JB-1,DES.2(B) 611(E) 5872 EA 1.000 1.000   1.000 $5,200.00 $0.00 $5,200.00
0045 INLET W/LRG.JCT.BOX,CICI-JB-1,DES.2(D) 611(E) 5874 EA 1.000 1.000   1.000 $5,600.00 $0.00 $5,600.00
0046 INLET W/LRG.JCT.BOX,CICI-JB-1,DES.3(D) 611(E) 5886 EA 1.000 1.000   1.000 $6,900.00 $0.00 $6,900.00
0047 INLET W/LRG.JCT.BOX,CICI-JB-1,DES.3(2B) 611(E) 5888 EA 1.000 1.000   1.000 $6,900.00 $0.00 $6,900.00
0048 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2 611(E) 5970 EA 3.000 3.000   3.000 $3,800.00 $0.00 $11,400.00
0049 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(B) 611(E) 5972 EA 7.000 7.000   7.000 $4,200.00 $0.00 $29,400.00
0050 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(D) 611(E) 5974 EA 7.000 7.000   7.000 $4,600.00 $0.00 $32,200.00
0051 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.3(D) 611(E) 5986 EA 2.000 2.000   2.000 $5,700.00 $0.00 $11,400.00
0052 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.3(B-D) 611(E) 5990 EA 2.000 2.000   2.000 $6,500.00 $0.00 $13,000.00
0053 INLET CICI DES. 2 (ADD'L DEPTH) 611(F) 5325 VF 43.000 43.000   39.580 $250.00 $0.00 $9,895.00
0054 INLET CICI DES. 3 (ADD'L DEPTH) 611(F) 5330 VF 6.000 6.000   5.330 $450.00 $0.00 $2,398.50
0055 INLET GPI TYPE 1 (ADD'L DEPTH) 611(F) 5374 VF 13.000 13.000   8.590 $300.00 $0.00 $2,577.00
0056 INLET GPI TYPE 2 (ADD'L DEPTH) 611(F) 5375 VF 1.000 1.000   0.270 $350.00 $0.00 $94.50
0057 INLET W/LJB,CICI-JB-1,DES.2(ADD'L DEPTH) 611(F) 5870 VF 7.000 7.000   1.410 $550.00 $0.00 $775.50
0058 INLET W/LJB,CICI-JB-1,DES.3(ADD'L DEPTH) 611(F) 5882 VF 8.000 8.000   2.500 $1,000.00 $0.00 $2,500.00
0059 INLET W/SJB,CICI-JB-1,DES.2(ADD'L DEPTH) 611(F) 5970 VF 77.000 77.000   57.280 $400.00 $0.00 $22,912.00
0060 INLET W/SJB,CICI-JB-1,DES.3(ADD'L DEPTH) 611(F) 5982 VF 16.000 16.000   9.920 $750.00 $0.00 $7,440.00
0061 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 96.000 96.000   96.000 $350.00 $0.00 $33,600.00
0062 CAST IRON CURB INLETS 611(K) 4488 EA 194.000 194.000   194.000 $250.00 $0.00 $48,500.00
0063 18" R.C.PIPE CLASS III 613(B) 0491 LF 1,428.000 1,428.000   1,561.000 $50.00 $0.00 $78,050.00
0064 24" R.C.PIPE CLASS III 613(B) 0492 LF 2,722.000 2,722.000   2,767.500 $55.00 $0.00 $152,212.50
0065 30" R.C.PIPE CLASS III 613(B) 0493 LF 1,049.000 1,049.000   1,050.000 $65.00 $0.00 $68,250.00
0066 36" R.C.PIPE CLASS III 613(B) 0494 LF 545.000 545.000   541.000 $85.00 $0.00 $45,985.00
0067 42" R.C.PIPE CLASS III 613(B) 0495 LF 143.000 143.000   144.000 $110.00 $0.00 $15,840.00
0068 48" R.C.PIPE CLASS III 613(B) 0496 LF 609.000 609.000   623.500 $130.00 $0.00 $81,055.00
0069 TYPE A4 CULVERT END TREATMENT 613(CC) 7186 EA 2.000 2.000   2.000 $900.00 $0.00 $1,800.00
0070 18" CORR. GALV. STEEL PIPE 613(D) 0689 LF 748.000 748.000   160.000 $24.00 $0.00 $3,840.00
0071 18" PREFAB. CULVERT END SECTION, ROUND 613(M) 5726 EA 15.000 15.000   17.000 $600.00 $0.00 $10,200.00
0072 24" PREFAB. CULVERT END SECTION, ROUND 613(M) 5730 EA 2.000 2.000   4.000 $700.00 $0.00 $2,800.00
0073 30" PREFAB. CULVERT END SECTION, ROUND 613(M) 5732 EA 2.000 2.000   2.000 $900.00 $0.00 $1,800.00
0074 36" PREFAB. CULVERT END SECTION, ROUND 613(M) 5734 EA 7.000 7.000   7.000 $1,200.00 $0.00 $8,400.00
0075 48" PREFAB. CULVERT END SECTION, ROUND 613(M) 5738 EA 3.000 3.000   3.000 $1,800.00 $0.00 $5,400.00
0076 TRENCH EXCAVATION 613(S) 1180 CY 6,522.000 6,522.000   7,630.960 $15.00 $0.00 $114,464.43
0077 STANDARD BEDDING MATERIAL 613(T) 1181 CY 3,034.000 3,034.000   3,799.070 $35.00 $0.00 $132,967.48
0078 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $25,000.00 $0.00 $25,000.00
0079 REMOVAL OF FENCE 619(B) 4725 LF 1,288.000 1,288.000   1,382.000 $1.00 $0.00 $1,382.00
0080 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 15,714.000 15,714.000   16,812.990 $2.00 $0.00 $33,625.98
0081 REMOVAL OF CONCRETE DRIVEWAY 619(B) 4766 SY 56.000 56.000   56.000 $10.00 $0.00 $560.00
0082 REMOVAL OF GUARD RAIL 619(B) 4780 LF 94.000 94.000   276.000 $3.00 $0.00 $828.00
0083 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 510.000 510.000   500.000 $17.00 $0.00 $8,500.00
0084 THRIE BEAM BRIDGE CONNECTION-TYPE A 623(E) 7114 EA 2.000 2.000   2.000 $1,800.00 $0.00 $3,600.00
0085 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 2.000 2.000   2.000 $2,500.00 $0.00 $5,000.00
0086 FENCE-STYLE WWF 624(A) 4281 LF 371.000 371.000   344.000 $9.00 $0.00 $3,096.00
0087 GATES-STYLE WWF (4.5'HIGH X 16'LONG) 624(B) 4466 EA 1.000 1.000   1.000 $500.00 $0.00 $500.00
0088 REMOVE AND RESET MAILBOX 629(E) 5048 EA 14.000 14.000   14.000 $100.00 $0.00 $1,400.00
0089 EDGE DRAIN CONDUIT-PERFORATED 653(A) 5915 LF 11,320.000 11,320.000   10,953.000 $5.00 $0.00 $54,765.00
0090 EDGE DRAIN OUTLET LATERAL-NONPERFORATED 653(B) 5916 LF 720.000 720.000   138.000 $5.00 $0.00 $690.00
0091 OUTLET LATERAL HEADWALL 653(C) 5946 EA 48.000 48.000   6.000 $500.00 $0.00 $3,000.00
Subtotals For Category     0100/ROADWAY - BRFY-058C(235)    $0.00 $5,639,696.92
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0200/BRIDGE 'B' - BRFY-058C(235)
0092 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 154.000 154.000   154.000 $15.00 $0.00 $2,310.00
0093 SUBSTRUCTURE EXCAVATION ROCK 501(C) 1308 CY 334.000 334.000   334.000 $25.00 $0.00 $8,350.00
0094 CLSM BACKFILL 501(G) 6309 CY 69.600 69.600   69.600 $85.00 $0.00 $5,916.00
0095 APPROACH SLAB 504(A) 1304 SY 312.000 312.000   312.000 $135.00 $0.00 $42,120.00
0096 CONCRETE RAIL (TR4) 504(E) 6245 LF 320.000 320.000   320.000 $65.00 $0.00 $20,800.00
0097 CLASS AA CONCRETE 509(A) 1326 CY 492.800 492.800   492.800 $425.00 $0.00 $209,440.00
0098 CLASS A CONCRETE 509(B) 1328 CY 172.600 172.600   172.600 $410.00 $0.00 $70,766.00
0099 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 171,698.000 171,698.000   171,698.000 $0.80 $0.00 $137,358.40
0100 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 436.000 436.000   436.000 $3.50 $0.00 $1,526.00
0101 DRILLED SHAFTS 30" DIAMETER 516(A) 6091 LF 80.000 80.000   80.000 $550.00 $0.00 $44,000.00
0102 DRILLED SHAFTS 36" DIAMETER 516(A) 6092 LF 156.000 156.000   156.120 $685.00 $0.00 $106,942.20
0103 TYPE I PLAIN RIPRAP 601(A) 1351 TON 1,513.000 1,513.000   529.230 $27.00 $0.00 $14,289.21
0104 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 142.000 142.000   142.000 $27.00 $0.00 $3,834.00
0105 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 38.000 38.000   42.000 $15.00 $0.00 $630.00
0106 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
Subtotals For Category     0200/BRIDGE 'B' - BRFY-058C(235)    $0.00 $688,281.81
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0201/BRIDGE 'C' - BRFY-058C(235)
0107 UNCLASSIFIED EXCAVATION 202(A) 1301 CY 358.600 358.600   558.860 $17.00 $0.00 $9,500.62
0108 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 1306 CY 128.300 334.670   334.670 $25.00 $0.00 $8,366.75
0109 CLASS AA CONCRETE 509(A) 1326 CY 284.800 284.800   284.800 $285.00 $0.00 $81,168.00
0110 REINFORCING STEEL 511(A) 1332 LB 43,678.000 43,678.000   43,678.000 $0.70 $0.00 $30,574.60
0111 TYPE I PLAIN RIPRAP 601(A) 1351 TON 213.900 213.900   476.820 $30.00 $0.00 $14,304.60
0112 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
Subtotals For Category     0201/BRIDGE 'C' - BRFY-058C(235)    $0.00 $153,914.57
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0300/TRAFFIC PERMANENT - BRFY-058C(235)
0113 SHEET ALUMINUM SIGNS 850(A) 8110 SF 78.180 78.180   66.180 $12.00 $0.00 $794.16
0114 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 291.000 291.000   192.920 $8.00 $0.00 $1,543.36
0115 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) 854(C) 8525 EA 47.000 47.000   14.000 $270.00 $0.00 $3,780.00
0116 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 854(C) 8530 LF 17,210.000 17,210.000   17,062.000 $0.65 $0.00 $11,090.30
0117 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) 854(C) 8540 LF 229.000 229.000   390.000 $2.15 $0.00 $838.51
0118 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) 854(C) 8555 LF 155.000 155.000   61.000 $13.00 $0.00 $793.00
0119 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 1,900.000 1,900.000   0.000 $0.65 $0.00 $0.00
0120 TRAFFIC STRIPE(PLASTIC)(8" WIDE) 855(A) 8814 LF 125.000 125.000   0.000 $2.15 $0.00 $0.00
0121 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 928.000 928.000   974.000 $1.10 $0.00 $1,071.40
0122 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8724 EA 5.000 5.000   5.000 $55.00 $0.00 $275.00
0123 (PL)REMOVE & RESET EXISTING SIGNS 890A/B 8756 EA 14.000 14.000   13.000 $110.00 $0.00 $1,430.00
Subtotals For Category     0300/TRAFFIC PERMANENT - BRFY-058C(235)    $0.00 $21,615.73
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0301/TRAFFIC TEMPORARY - BRFY-058C(235)
0124 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 14,051.000 14,051.000   18,779.000 $0.25 $0.00 $4,694.75
0125 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 856(G) 8887 EA 760.000 760.000   0.000 $1.10 $0.00 $0.00
0126 (PL)CONST.ZONE IMPACT ATTEN. 871 8705 SD 180.000 180.000   0.000 $11.00 $0.00 $0.00
0127 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 8,500.000 8,500.000   4,172.000 $0.55 $0.00 $2,294.60
0128 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 4,320.000 4,320.000   4,285.000 $0.55 $0.00 $2,356.75
0129 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 6,230.000 6,230.000   4,765.000 $1.60 $0.00 $7,624.00
0130 BARRICADES(TYPE III) 880(C) 8842 SD 8,240.000 8,240.000   3,413.000 $0.30 $0.00 $1,023.90
0131 WING BARRICADES 880(C) 8848 SD 2,920.000 2,920.000   0.000 $0.30 $0.00 $0.00
0132 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 25,770.000 25,770.000   8,797.000 $0.11 $0.00 $967.67
0133 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 24,700.000 24,700.000   24,690.000 $0.02 $0.00 $493.80
0134 DRUMS 880(F) 8878 SD 24,700.000 24,700.000   39,091.000 $0.16 $0.00 $6,254.56
0135 FLAGGER 880(I) 8902 SD 8.000 8.000   0.000 $150.00 $0.00 $0.00
Subtotals For Category     0301/TRAFFIC TEMPORARY - BRFY-058C(235)    $0.00 $25,710.03
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0600/STAKING - BRFY-058C(235)
0136 STAKING 642 0098 LSUM 1.000 1.000   1.000 $125,000.00 $0.00 $125,000.00
Subtotals For Category     0600/STAKING - BRFY-058C(235)    $0.00 $125,000.00
Fed/State Project Number:    BRFY-058C(235) Project:    08932(04) Category:    0640/CONSTRUCTION - BRFY-058C(235)
0137 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0138 FIELD OFFICE 640 1426 EA 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
0139 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $600,000.00 $0.00 $600,000.00
Subtotals For Category     0640/CONSTRUCTION - BRFY-058C(235)    $0.00 $615,000.00
Subtotals For Project BRFY-058C(235) /08932(04) $0.00 $7,269,219.06


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BRFY-058C(237) Project:    10430(04) Category:    0100/ROADWAY - BRFY-058C(237)
0140 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
0141 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 13,892.000 13,892.000   13,892.000 $5.00 $0.00 $69,460.01
0142 UNCLASSIFIED BORROW 202(C) 0184 CY 160,807.000 160,807.000   160,807.000 $4.50 $0.00 $723,631.50
0143 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
0144 TEMPORARY SILT FENCE 223 2801 LF 6,383.000 6,383.000   926.000 $1.50 $0.00 $1,389.00
0145 TEMPORARY SILT DIKE 227 0100 LF 370.000 370.000   56.000 $7.00 $0.00 $392.00
0146 SOLID SLAB SODDING 230(A) 2806 SY 39,868.000 39,868.000 2,634.000 71,019.328 $1.25 $3,292.50 $88,774.17
0147 SEEDING METHOD B 232(B) 2814 AC 16.600 16.600   0.000 $450.00 $0.00 $0.00
0148 VEGETATIVE MULCHING 233(A) 2817 AC 8.300 8.300   0.000 $450.00 $0.00 $0.00
0149 MOWING 241 2832 AC 16.600 16.600   15.190 $50.00 $0.00 $759.50
0150 AGGREGATE BASE 303 0192 CY 7,280.000 7,280.000   6,583.700 $28.00 $0.00 $184,343.59
0151 (SP)CEMENT TREATED BASE 317(F) 4270 SY 26,155.000 26,155.000   26,614.550 $14.00 $0.00 $372,603.70
0152 SEPARATOR FABRIC 325 5271 SY 35,014.000 35,014.000   34,273.620 $1.00 $0.00 $34,273.63
0153 (SP)MODIFIED SUBGRADE 327(J) 4290 SY 29,057.000 29,057.000   26,512.550 $3.00 $0.00 $79,537.65
0154 (SP)GEOSYNTHETIC SUBGRADE REINFORCEMENT 328 2600 SY 2,905.000 2,905.000   1,484.060 $4.00 $0.00 $5,936.24
0155 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 543.000 543.000   1,889.680 $14.00 $0.00 $26,455.52
0156 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 143.000 143.000   129.140 $75.00 $0.00 $9,685.50
0157 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 26.000 26.000   0.000 $85.00 $0.00 $0.00
0158 (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) 414(A1) 5725 SY 24,613.000 24,613.000   24,879.900 $14.00 $0.00 $348,318.60
0159 (SP)P.C. CONCRETE FOR PAVEMENT 414(P) 6000 CY 6,057.000 6,057.000   6,126.220 $90.00 $0.00 $551,359.80
0160 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 82.000 82.000   188.100 $25.00 $0.00 $4,702.51
0161 CLASS AA CONCRETE 509(A) 0319 CY 164.000 164.000   216.190 $330.00 $0.00 $71,342.70
0162 CLASS A CONCRETE 509(B) 0321 CY 44.000 44.000   49.610 $325.00 $0.00 $16,123.25
0163 CLASS C CONCRETE 509(D) 0325 CY 2.000 2.000   2.429 $300.00 $0.00 $728.70
0164 REINFORCING STEEL 511(A) 0332 LB 32,555.000 32,555.000   51,258.580 $1.00 $0.00 $51,258.58
0165 TYPE I PLAIN RIPRAP 601(A) 0297 TON 57.000 57.000   260.610 $30.00 $0.00 $7,818.30
0166 CONCRETE CURB (6" BARRIER-INTEGRAL) 609(A) 0300 LF 6,536.000 6,536.000   5,968.000 $4.00 $0.00 $23,872.00
0167 6" CONCRETE DRIVEWAY 610(B) 0604 SY 1,058.000 1,058.000   1,073.740 $40.00 $0.00 $42,949.60
0168 MANHOLE (4' DIAMETER) 611(A) 2657 EA 1.000 1.000   1.000 $2,000.00 $0.00 $2,000.00
0169 MANHOLE (5' DIAMETER) 611(A) 2658 EA 1.000 1.000   1.000 $2,700.00 $0.00 $2,700.00
0170 ADD'L.DEPTH IN MANHOLE (4' DIAMETER) 611(B) 2680 VF 2.000 2.000   1.000 $200.00 $0.00 $200.00
0171 ADD'L.DEPTH IN MANHOLE (5' DIAMETER) 611(B) 2681 VF 15.000 15.000   11.500 $300.00 $0.00 $3,450.00
0172 MANHOLE FRAME & COVER 611(D) 4215 EA 13.000 13.000   13.000 $350.00 $0.00 $4,550.00
0173 INLET CICI DES. 2 (STD) 611(E) 5112 EA 2.000 2.000   2.000 $1,800.00 $0.00 $3,600.00
0174 INLET CICI DES. 2 (B) 611(E) 5113 EA 4.000 4.000   4.000 $2,200.00 $0.00 $8,800.00
0175 INLET CICI DES. 2 (D) 611(E) 5115 EA 1.000 1.000   1.000 $2,400.00 $0.00 $2,400.00
0176 INLET GPI TYPE 2 (DES. 9) 611(E) 5335 EA 1.000 1.000   1.000 $2,300.00 $0.00 $2,300.00
0177 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2 611(E) 5970 EA 1.000 1.000   1.000 $3,800.00 $0.00 $3,800.00
0178 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(B) 611(E) 5972 EA 4.000 4.000   4.000 $4,200.00 $0.00 $16,800.00
0179 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(D) 611(E) 5974 EA 6.000 6.000   6.000 $4,600.00 $0.00 $27,600.00
0180 INLET CICI DES. 2 (ADD'L DEPTH) 611(F) 5325 VF 42.000 42.000   22.080 $250.00 $0.00 $5,520.00
0181 INLET W/SJB,CICI-JB-1,DES.2(ADD'L DEPTH) 611(F) 5970 VF 55.000 55.000   48.890 $400.00 $0.00 $19,556.00
0182 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 36.000 36.000   36.000 $350.00 $0.00 $12,600.00
0183 CAST IRON CURB INLETS 611(K) 4488 EA 80.000 80.000   80.000 $250.00 $0.00 $20,000.00
0184 18" R.C.PIPE CLASS III 613(B) 0491 LF 2,497.000 2,497.000   2,499.500 $35.00 $0.00 $87,482.50
0185 24" R.C.PIPE CLASS III 613(B) 0492 LF 581.000 581.000   583.000 $45.00 $0.00 $26,235.00
0186 30" R.C.PIPE CLASS III 613(B) 0493 LF 171.000 171.000   168.000 $55.00 $0.00 $9,240.00
0187 18" CORR. GALV. STEEL PIPE 613(D) 0689 LF 114.000 114.000   110.000 $24.00 $0.00 $2,640.00
0188 18" PREFAB. CULVERT END SECTION, ROUND 613(M) 5726 EA 12.000 12.000   14.000 $600.00 $0.00 $8,400.00
0189 30" PREFAB. CULVERT END SECTION, ROUND 613(M) 5732 EA 1.000 1.000   1.000 $900.00 $0.00 $900.00
0190 TRENCH EXCAVATION 613(S) 1180 CY 2,441.000 2,441.000   2,554.690 $15.00 $0.00 $38,320.37
0191 STANDARD BEDDING MATERIAL 613(T) 1181 CY 977.000 977.000   1,177.630 $35.00 $0.00 $41,217.06
0192 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
0193 REMOVAL OF FENCE 619(B) 4725 LF 4,645.000 4,645.000   2,821.000 $1.00 $0.00 $2,821.00
0194 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 17,825.000 17,825.000   15,699.670 $2.00 $0.00 $31,399.34
0195 REMOVAL OF GUARD RAIL 619(B) 4780 LF 3,409.000 3,409.000   3,326.000 $3.00 $0.00 $9,978.00
0196 REMOVAL OF CONCRETE MEDIAN BARRIER 619(B) 4915 LF 69.000 69.000   69.000 $15.00 $0.00 $1,035.00
0197 SAWING PAVEMENT 619(C) 0924 LF 405.000 405.000   659.000 $2.00 $0.00 $1,318.00
0198 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 500.000 500.000   500.000 $17.00 $0.00 $8,500.00
0199 THRIE BEAM BRIDGE CONNECTION-TYPE A 623(E) 7114 EA 2.000 2.000   2.000 $1,800.00 $0.00 $3,600.00
0200 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 2.000 2.000   2.000 $2,500.00 $0.00 $5,000.00
0201 FENCE-STYLE WWF 624(A) 4281 LF 659.000 659.000   620.000 $9.00 $0.00 $5,580.00
0202 GATES-STYLE WWF (4.5'HIGH X 12'LONG) 624(B) 4462 EA 1.000 1.000   0.000 $500.00 $0.00 $0.00
0203 GATES-STYLE WWF (4.5'HIGH X 16'LONG) 624(B) 4466 EA 1.000 1.000   1.000 $500.00 $0.00 $500.00
0204 (SP)FENCE-STYLE SWF (5 BARBED WIRE) 624(C) 4459 LF 1,838.000 1,838.000   1,398.000 $5.00 $0.00 $6,990.00
0205 FENCE-STYLE CLF (6'HIGH, CLASS A) 624(D) 4292 LF 125.000 125.000   125.000 $50.00 $0.00 $6,250.00
0206 CONCRETE MEDIAN BARRIER, DESIGN 1 627(I) 4317 LF 21.000 21.000   21.000 $100.00 $0.00 $2,100.00
0207 REMOVE AND RESET MAILBOX 629(E) 5048 EA 1.000 1.000   1.000 $100.00 $0.00 $100.00
0208 EDGE DRAIN CONDUIT-PERFORATED 653(A) 5915 LF 6,703.000 6,703.000   5,734.000 $5.00 $0.00 $28,670.00
0209 EDGE DRAIN OUTLET LATERAL-NONPERFORATED 653(B) 5916 LF 420.000 420.000   42.000 $5.00 $0.00 $210.00
0210 OUTLET LATERAL HEADWALL 653(C) 5946 EA 28.000 28.000   5.000 $500.00 $0.00 $2,500.00
8007 DEDUCTION FOR FAILING MATERIAL 105 2200 SY 0.000 -103.410   -103.410 $14.00 $0.00 $-1,447.74
Subtotals For Category     0100/ROADWAY - BRFY-058C(237)    $3,292.50 $3,231,130.58
Fed/State Project Number:    BRFY-058C(237) Project:    10430(04) Category:    0200/BRIDGE 'A' - BRFY-058C(237)
0211 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 376.000 376.000   376.000 $15.00 $0.00 $5,640.00
0212 CLSM BACKFILL 501(G) 6309 CY 492.200 492.200   492.200 $85.00 $0.00 $41,837.00
0213 PRESTRESSED CONCRETE BEAMS (TYPE J BT) 503(A) 6290 LF 1,808.000 1,808.000   1,808.000 $200.00 $0.00 $361,600.00
0214 APPROACH SLAB 504(A) 1304 SY 631.200 631.200   631.050 $135.00 $0.00 $85,191.75
0215 SEALED EXPANSION JOINT 504(C) 6250 LF 73.000 73.000 0.000 73.000 $200.00 $0.00 $14,600.00
0216 CONCRETE RAIL (TR4) 504(E) 6245 LF 621.600 621.600   621.600 $65.00 $0.00 $40,404.00
0217 STRUCTURAL STEEL 506(A) 1322 LB 2,250.000 2,250.000   2,250.000 $1.50 $0.00 $3,375.00
0218 (PL)SPECIAL CONCRETE FINISH 509 6152 SY 324.000 324.000   327.931 $35.00 $0.00 $11,477.59
0219 CLASS AA CONCRETE 509(A) 1326 CY 547.600 547.600   547.600 $355.00 $0.00 $194,398.00
0220 CLASS A CONCRETE 509(B) 1328 CY 398.100 398.100   398.100 $330.00 $0.00 $131,373.00
0221 SLOPE WALL (4") 510(C) 6137 SY 1,360.000 1,360.000   1,232.336 $55.00 $0.00 $67,778.48
0222 REINFORCING STEEL 511(A) 1332 LB 2,440.000 2,440.000   2,440.000 $0.70 $0.00 $1,708.00
0223 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 135,222.000 135,222.000   135,222.000 $0.80 $0.00 $108,177.60
0224 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 308.000 308.000   308.000 $22.00 $0.00 $6,776.00
0225 PILES, FURNISHED (HP 12X53) 514(A) 6011 LF 1,311.000 1,311.000   1,311.000 $28.00 $0.00 $36,708.00
0226 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 308.000 308.000   300.910 $10.00 $0.00 $3,009.10
0227 PILES, DRIVEN (HP 12X53) 514(B) 6294 LF 1,311.000 1,311.000   1,283.380 $10.00 $0.00 $12,833.80
0228 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 974.000 974.000   974.000 $4.00 $0.00 $3,896.00
0229 DRILLED SHAFTS 66" DIAMETER 516(A) 6097 LF 124.000 124.000   124.330 $1,100.00 $0.00 $136,763.00
0230 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 230.000 230.000   230.000 $1.00 $0.00 $230.00
0231 (SP) SEALER RESIN 523(B) 6560 GAL 2.000 2.000   2.000 $110.00 $0.00 $220.00
0232 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 16.000 16.000   16.000 $1,100.00 $0.00 $17,600.00
0233 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 16.000 16.000   16.000 $1,100.00 $0.00 $17,600.00
0234 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 348.000 348.000   348.000 $30.00 $0.00 $10,440.00
0235 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 94.000 94.000   0.000 $15.00 $0.00 $0.00
0236 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $50,000.00 $0.00 $50,000.00
8003 CONSTRUCTION MISCELLANEOUS 104 0700 LSUM 0.000 1.000   1.000 $-75,000.00 $0.00 $-75,000.00
Subtotals For Category     0200/BRIDGE 'A' - BRFY-058C(237)    $0.00 $1,288,636.32
Fed/State Project Number:    BRFY-058C(237) Project:    10430(04) Category:    0300/TRAFFIC PERMANENT - BRFY-058C(237)
0237 SHEET ALUMINUM SIGNS 850(A) 8110 SF 90.500 90.500   90.500 $12.00 $0.00 $1,086.00
0238 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 304.250 304.250   304.250 $8.00 $0.00 $2,434.00
0239 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) 854(C) 8525 EA 30.000 30.000   17.000 $270.00 $0.00 $4,590.00
0240 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 854(C) 8530 LF 12,507.000 12,507.000   13,096.000 $0.65 $0.00 $8,512.41
0241 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(8" WIDE) 854(C) 8540 LF 400.000 400.000   409.000 $2.15 $0.00 $879.35
0242 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) 854(C) 8555 LF 60.000 60.000   106.000 $13.00 $0.00 $1,378.00
0243 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 530.000 530.000   0.000 $0.65 $0.00 $0.00
0244 TRAFFIC STRIPE(PLASTIC)(6" WIDE) 855(A) 8813 LF 100.000 100.000   0.000 $1.10 $0.00 $0.00
0245 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 2,200.000 2,200.000   5,301.000 $1.10 $0.00 $5,831.10
0246 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8724 EA 5.000 5.000   5.000 $55.00 $0.00 $275.00
0247 (PL)REMOVE & RESET EXISTING SIGNS 890A/B 8756 EA 25.000 25.000   25.000 $110.00 $0.00 $2,750.00
8000 (PL)REMOVAL OF LIGHT POLE 890(A) 8712 EA 0.000 1.000   1.000 $2,625.00 $0.00 $2,625.00
Subtotals For Category     0300/TRAFFIC PERMANENT - BRFY-058C(237)    $0.00 $30,360.86
Fed/State Project Number:    BRFY-058C(237) Project:    10430(04) Category:    0301/TRAFFIC TEMPORARY - BRFY-058C(237)
0248 RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN 627(O) 4410 LF 6,750.000 6,750.000   4,840.000 $3.00 $0.00 $14,520.00
0249 RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER 627(P) 4425 LF 2,245.000 2,245.000   2,949.600 $20.00 $0.00 $58,992.00
0250 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 9,220.000 9,220.000   18,301.000 $0.25 $0.00 $4,575.25
0251 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 856(G) 8887 EA 1,780.000 1,780.000   0.000 $1.10 $0.00 $0.00
0252 (PL)CONST.ZONE IMPACT ATTEN. 871 8705 SD 565.000 565.000   1,277.000 $11.00 $0.00 $14,047.00
0253 ARROW DISPLAY(TYPE C) 880(A) 8812 SD 214.000 214.000   565.000 $11.00 $0.00 $6,215.00
0254 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 12,295.000 12,295.000   11,903.000 $0.55 $0.00 $6,546.65
0255 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 9,174.000 9,174.000   14,940.000 $0.55 $0.00 $8,217.00
0256 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 15,246.000 15,246.000   21,744.000 $1.60 $0.00 $34,790.40
0257 BARRICADES(TYPE III) 880(C) 8842 SD 4,788.000 4,788.000   7,897.000 $0.30 $0.00 $2,369.10
0258 WING BARRICADES 880(C) 8848 SD 4,266.000 4,266.000   4,277.000 $0.30 $0.00 $1,283.10
0259 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 23,980.000 23,980.000   34,399.000 $0.11 $0.00 $3,783.89
0260 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 45,541.000 45,541.000   39,383.000 $0.02 $0.00 $787.66
0261 DRUMS 880(F) 8878 SD 45,541.000 45,541.000   68,276.000 $0.16 $0.00 $10,924.16
0262 FLAGGER 880(I) 8902 SD 200.000 200.000   16.000 $150.00 $0.00 $2,400.00
0263 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 116.000 116.000   324.250 $60.00 $0.00 $19,455.00
0264 PORT.CHANGEABLE MESSAGE SIGN 882(B) 8306 SD 454.000 454.000   206.000 $22.00 $0.00 $4,532.00
Subtotals For Category     0301/TRAFFIC TEMPORARY - BRFY-058C(237)    $0.00 $193,438.21
Subtotals For Project BRFY-058C(237) /10430(04) $3,292.50 $4,743,565.97


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STPY-058C(240) Project:    12573(04) Category:    0100/ROADWAY - STPY-058C(240)
0265 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $20,000.00 $0.00 $20,000.00
0266 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 134,155.000 134,155.000   134,155.000 $4.00 $0.00 $536,620.00
0267 UNCLASSIFIED BORROW 202(C) 0184 CY 245.000 245.000   245.000 $5.00 $0.00 $1,225.00
0268 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   1.000 $60,000.00 $0.00 $60,000.00
0269 TEMPORARY SILT FENCE 223 2801 LF 1,285.000 1,285.000   1,683.000 $1.50 $0.00 $2,524.50
0270 TEMPORARY SILT DIKE 227 0100 LF 2,320.000 2,320.000   210.000 $7.00 $0.00 $1,470.00
0271 SOLID SLAB SODDING 230(A) 2806 SY 82,510.000 82,510.000 659.110 124,956.110 $1.25 $823.89 $156,195.14
0272 SEEDING METHOD B 232(B) 2814 AC 34.100 34.100   0.000 $450.00 $0.00 $0.00
0273 VEGETATIVE MULCHING 233(A) 2817 AC 17.050 17.050   7.810 $450.00 $0.00 $3,514.50
0274 MOWING 241 2832 AC 34.100 34.100   46.859 $50.00 $0.00 $2,342.95
0275 AGGREGATE BASE 303 0192 CY 25,497.000 25,497.000   21,825.280 $28.00 $0.00 $611,107.84
0276 (SP)CEMENT TREATED BASE 317(F) 4270 SY 3,178.000 3,178.000   3,128.440 $14.00 $0.00 $43,798.16
0277 SEPARATOR FABRIC 325 5271 SY 120,392.000 120,392.000   114,464.633 $1.00 $0.00 $114,464.64
0278 (SP)MODIFIED SUBGRADE 327(J) 4290 SY 109,425.000 109,425.000   49,744.085 $3.00 $0.00 $149,232.26
0279 (SP)GEOSYNTHETIC SUBGRADE REINFORCEMENT 328 2600 SY 10,789.000 10,789.000   2,964.252 $4.00 $0.00 $11,857.01
0280 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 1,548.000 1,548.000   3,949.430 $14.00 $0.00 $55,292.02
0281 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) 411(S3) 5935 TON 14,126.000 14,126.000   12,482.380 $60.00 $0.00 $748,942.80
0282 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 42,885.000 42,885.000   28,816.550 $50.00 $0.00 $1,440,827.50
0283 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 9,895.000 9,895.000   9,927.600 $68.00 $0.00 $675,076.80
0284 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 833.000 833.000   1,122.650 $60.00 $0.00 $67,359.00
0285 (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) 414(A1) 5725 SY 3,054.000 3,054.000   3,054.000 $20.00 $0.00 $61,080.00
0286 (SP)P.C. CONCRETE FOR PAVEMENT 414(P) 6000 CY 765.000 765.000   765.000 $95.00 $0.00 $72,675.00
0287 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 1,106.000 1,106.000   1,208.129 $25.00 $0.00 $30,203.24
0288 CLASS A CONCRETE 509(B) 0321 CY 618.000 618.000 1.000 560.805 $325.00 $325.00 $182,261.63
0289 REINFORCING STEEL 511(A) 0332 LB 104,800.000 104,800.000   87,959.453 $1.00 $0.00 $87,959.46
0290 TYPE I PLAIN RIPRAP 601(A) 0297 TON 656.000 656.000   372.120 $30.00 $0.00 $11,163.60
0291 CONCRETE CURB (6" BARRIER-INTEGRAL) 609(A) 0300 LF 505.000 505.000   1,042.000 $4.00 $0.00 $4,168.00
0292 2'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1525 LF 21,588.000 21,588.000   21,185.980 $13.00 $0.00 $275,417.74
0293 6" CONCRETE DRIVEWAY 610(B) 0604 SY 1,122.000 1,122.000   1,139.118 $40.00 $0.00 $45,564.72
0294 4" CONCRETE DIVIDING STRIP 610(C) 0608 SY 5.000 5.000   4.959 $40.00 $0.00 $198.36
0295 MANHOLE (5' DIAMETER) 611(A) 2658 EA 2.000 2.000   2.000 $2,700.00 $0.00 $5,400.00
0296 MANHOLE (6' DIAMETER) 611(A) 2659 EA 1.000 1.000   1.000 $4,500.00 $0.00 $4,500.00
0297 ADD'L.DEPTH IN MANHOLE (5' DIAMETER) 611(B) 2681 VF 5.000 5.000   4.500 $280.00 $0.00 $1,260.00
0298 ADD'L.DEPTH IN MANHOLE (6' DIAMETER) 611(B) 2682 VF 3.000 3.000   2.417 $400.00 $0.00 $966.80
0299 MANHOLE FRAME & COVER 611(D) 4215 EA 27.000 27.000   27.000 $350.00 $0.00 $9,450.00
0300 INLET CICI DES. 2 (STD) 611(E) 5112 EA 4.000 4.000   4.000 $1,800.00 $0.00 $7,200.00
0301 INLET CICI DES. 2 (B) 611(E) 5113 EA 8.000 8.000   8.000 $2,200.00 $0.00 $17,600.00
0302 INLET CICI DES. 2 (D) 611(E) 5115 EA 9.000 9.000   9.000 $2,400.00 $0.00 $21,600.00
0303 INLET CICI DES. 2 (2B) 611(E) 5117 EA 2.000 2.000   2.000 $2,400.00 $0.00 $4,800.00
0304 INLET CICI DES. 3 (B) 611(E) 5121 EA 1.000 1.000   1.000 $3,300.00 $0.00 $3,300.00
0305 INLET CICI DES. 3 (D) 611(E) 5122 EA 3.000 3.000   3.000 $3,800.00 $0.00 $11,400.00
0306 INLET CICI DES. 3 (2B) 611(E) 5123 EA 1.000 1.000   1.000 $3,800.00 $0.00 $3,800.00
0307 INLET CICI DES. 3 (B-D) 611(E) 5124 EA 1.000 1.000   1.000 $4,500.00 $0.00 $4,500.00
0308 INLET CICI DES. 3 (2D) 611(E) 5125 EA 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0309 INLET GPI TYPE 1 (DES. 1) 611(E) 5327 EA 3.000 3.000   3.000 $1,600.00 $0.00 $4,800.00
0310 INLET W/LRG.JCT.BOX,CICI-JB-1,DES.3(B-D) 611(E) 5891 EA 1.000 1.000   1.000 $7,500.00 $0.00 $7,500.00
0311 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2 611(E) 5970 EA 3.000 3.000   3.000 $3,800.00 $0.00 $11,400.00
0312 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(B) 611(E) 5972 EA 10.000 10.000   10.000 $4,200.00 $0.00 $42,000.00
0313 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.2(D) 611(E) 5974 EA 5.000 5.000   5.000 $4,600.00 $0.00 $23,000.00
0314 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.3(D) 611(E) 5986 EA 1.000 1.000   1.000 $5,700.00 $0.00 $5,700.00
0315 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.3(2B) 611(E) 5988 EA 2.000 2.000   2.000 $5,700.00 $0.00 $11,400.00
0316 INLET W/SMALL JCT.BOX,CICI-JB-1,DES.3(B-D) 611(E) 5990 EA 1.000 1.000   1.000 $6,500.00 $0.00 $6,500.00
0317 INLET CICI DES. 2 (ADD'L DEPTH) 611(F) 5325 VF 74.000 74.000   64.250 $250.00 $0.00 $16,062.50
0318 INLET CICI DES. 3 (ADD'L DEPTH) 611(F) 5330 VF 24.000 24.000   20.667 $450.00 $0.00 $9,300.15
0319 INLET GPI TYPE 1 (ADD'L DEPTH) 611(F) 5374 VF 1.000 1.000   1.167 $300.00 $0.00 $350.10
0320 INLET W/LJB,CICI-JB-1,DES.3(ADD'L DEPTH) 611(F) 5882 VF 4.000 4.000   3.083 $1,000.00 $0.00 $3,083.00
0321 INLET W/SJB,CICI-JB-1,DES.2(ADD'L DEPTH) 611(F) 5970 VF 70.000 70.000   66.417 $400.00 $0.00 $26,566.80
0322 INLET W/SJB,CICI-JB-1,DES.3(ADD'L DEPTH) 611(F) 5982 VF 16.000 16.000   16.833 $750.00 $0.00 $12,624.75
0323 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 130.000 130.000   130.000 $350.00 $0.00 $45,500.00
0324 JUNCTION BOXES 611(J) 0487 CF 312.000 312.000   327.872 $35.00 $0.00 $11,475.52
0325 CAST IRON CURB INLETS 611(K) 4488 EA 286.000 286.000   284.000 $250.00 $0.00 $71,000.00
0326 18" R.C.PIPE CLASS III 613(B) 0491 LF 3,614.000 3,614.000   3,662.000 $35.00 $0.00 $128,170.00
0327 24" R.C.PIPE CLASS III 613(B) 0492 LF 2,153.000 2,153.000   2,363.000 $45.00 $0.00 $106,335.00
0328 30" R.C.PIPE CLASS III 613(B) 0493 LF 1,025.000 1,025.000   1,031.000 $55.00 $0.00 $56,705.00
0329 36" R.C.PIPE CLASS III 613(B) 0494 LF 1,248.000 1,248.000   1,223.000 $68.00 $0.00 $83,164.00
0330 TYPE A4 CULVERT END TREATMENT 613(CC) 7186 EA 18.000 18.000   17.000 $900.00 $0.00 $15,300.00
0331 18" CORR. GALV. STEEL PIPE 613(D) 0689 LF 502.000 502.000   632.000 $24.00 $0.00 $15,168.00
0332 18" PREFAB. CULVERT END SECTION, ROUND 613(M) 5726 EA 17.000 17.000   23.000 $600.00 $0.00 $13,800.00
0333 24" PREFAB. CULVERT END SECTION, ROUND 613(M) 5730 EA 2.000 2.000   2.000 $700.00 $0.00 $1,400.00
0334 36" PREFAB. CULVERT END SECTION, ROUND 613(M) 5734 EA 6.000 6.000   6.000 $1,200.00 $0.00 $7,200.00
0335 TRENCH EXCAVATION 613(S) 1180 CY 6,560.000 6,560.000   7,681.222 $15.00 $0.00 $115,218.35
0336 STANDARD BEDDING MATERIAL 613(T) 1181 CY 3,100.000 3,100.000   3,804.962 $35.00 $0.00 $133,173.70
0337 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $25,000.00 $0.00 $25,000.00
0338 REMOVAL OF FENCE 619(B) 4725 LF 14,708.000 14,708.000   8,427.000 $1.00 $0.00 $8,427.00
0339 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 76,589.000 76,589.000   45,035.107 $2.00 $0.00 $90,070.22
0340 REMOVAL OF CONCRETE DRIVEWAY 619(B) 4766 SY 411.000 411.000   317.500 $10.00 $0.00 $3,175.00
0341 (PL) GATE 624 5920 EA 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0342 FENCE-STYLE WWF 624(A) 4281 LF 2,377.000 2,377.000   4,717.000 $9.00 $0.00 $42,453.00
0343 (SP)FENCE-STYLE SWF (5 BARBED WIRE) 624(C) 4459 LF 8,278.000 8,278.000   2,780.000 $5.00 $0.00 $13,900.00
0344 REMOVE AND RESET MAILBOX 629(E) 5048 EA 11.000 11.000   14.000 $100.00 $0.00 $1,400.00
0345 EDGE DRAIN CONDUIT-PERFORATED 653(A) 5915 LF 22,773.000 22,773.000   20,544.000 $5.00 $0.00 $102,720.00
0346 EDGE DRAIN OUTLET LATERAL-NONPERFORATED 653(B) 5916 LF 1,080.000 1,080.000   334.000 $5.00 $0.00 $1,670.00
0347 OUTLET LATERAL HEADWALL 653(C) 5946 EA 72.000 72.000   0.000 $500.00 $0.00 $0.00
8006 EARLY COMPLETION INCENTIVE 108 0175 DAY 0.000 30.000   30.000 $1,000.00 $0.00 $30,000.00
8008 DEDUCTION FOR FAILING MATERIAL 105 2200 SY 0.000 -262.570   -262.570 $14.00 $0.00 $-3,675.98
Subtotals For Category     0100/ROADWAY - STPY-058C(240)    $1,148.89 $6,877,354.78
Fed/State Project Number:    STPY-058C(240) Project:    12573(04) Category:    0300/TRAFFIC PERMANENT - STPY-058C(240)
0348 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8342 LF 44.000 44.000   0.000 $5.00 $0.00 $0.00
0349 3" PVC SCH.40 PLASTIC CONDUIT BORED 802(B) 8344 LF 344.000 344.000   0.000 $19.00 $0.00 $0.00
0350 3" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8346 LF 6.000 6.000 0.000 212.000 $9.00 $0.00 $1,908.00
0351 PULL BOX(SIZE I) 803 8065 EA 3.000 3.000   3.000 $200.00 $0.00 $600.00
0352 PULL BOX(SIZE II) 803 8066 EA 1.000 1.000   1.000 $250.00 $0.00 $250.00
0353 STRUCTURAL CONCRETE 804(A) 2915 CY 11.600 11.600   11.600 $430.00 $0.00 $4,988.00
0354 REINFORCING STEEL 804(B) 2916 LB 1,767.000 1,767.000   1,766.600 $1.00 $0.00 $1,766.60
0355 32'MH POLE 45'TS & 15'LMA(G.STL.) 806(A) 8324 EA 1.000 1.000   1.000 $7,000.00 $0.00 $7,000.00
0356 32'MH POLE 40'TS & 15'LMA(G.STL.) 806(A) 8333 EA 2.000 2.000   2.000 $6,000.00 $0.00 $12,000.00
0357 32'MH POLE 35'TS & 15'LMA(G.STL.) 806(A) 8334 EA 1.000 1.000   1.000 $5,400.00 $0.00 $5,400.00
0358 1/C NO.6 ELECTRICAL CONDUCTOR 811 8040 LF 93.000 93.000   510.000 $2.00 $0.00 $1,020.00
0359 1/C NO.10 ELECTRICAL CONDUCTOR 811 8044 LF 1,556.000 1,556.000   1,146.000 $0.45 $0.00 $515.70
0360 VEH.ACT.SOL.ST.TRAF.SIG.CON.ASM 825 8550 EA 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
0361 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000   1.000 $18,000.00 $0.00 $18,000.00
0362 1WAY 3SEC. ADJ. SIG. HD. S-6 831 8231 EA 8.000 8.000   8.000 $600.00 $0.00 $4,800.00
0363 BACKPLATE 833 3030 EA 8.000 8.000   8.000 $70.00 $0.00 $560.00
0364 5/C TRAF.SIG.ELECT.CABLE 834(A) 8207 LF 384.000 384.000   434.000 $1.30 $0.00 $564.20
0365 7/C TRAF.SIG.ELECT.CABLE 834(A) 8208 LF 260.000 260.000   288.000 $1.50 $0.00 $432.00
0366 12/C TRAF.SIG.ELECT.CABLE 834(A) 8210 LF 570.000 570.000   597.000 $2.30 $0.00 $1,373.10
0367 (PL)E.P.S. OPTICAL DETECTOR 840(B) 8593 EA 4.000 4.000   4.000 $550.00 $0.00 $2,200.00
0368 (PL)E.P.S. OPTICAL DETECTOR CABLE 840(C) 8594 LF 723.000 723.000   220.000 $1.50 $0.00 $330.00
0369 (PL)E.P.S. 4 CHANNEL PHASE SELECTOR 840(D) 8598 EA 1.000 1.000   1.000 $2,600.00 $0.00 $2,600.00
0370 SHEET ALUMINUM SIGNS 850(A) 8110 SF 197.320 197.320   197.320 $12.00 $0.00 $2,367.84
0371 MAST ARM MOUNTED SIGNS(ALUMINUM) 850(C) 8118 SF 25.500 25.500   45.500 $40.00 $0.00 $1,820.00
0372 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 722.000 722.000   722.000 $8.00 $0.00 $5,776.00
0373 2 1/2" SQUARE TUBE POST 851(C) 8330 LF 156.000 156.000   156.000 $9.00 $0.00 $1,404.00
0374 (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) 854(C) 8525 EA 4.000 4.000   34.000 $270.00 $0.00 $9,180.00
0375 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) 854(C) 8530 LF 825.000 825.000 0.000 46,208.000 $0.65 $0.00 $30,035.20
0376 (SP)TRAFFIC STRIPE(MULTI-POLYMER)(24" WIDE) 854(C) 8555 LF 380.000 380.000   232.000 $13.00 $0.00 $3,016.00
0377 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 43,111.000 43,111.000   0.000 $0.65 $0.00 $0.00
0378 TRAFFIC STRIPE(PLASTIC)(8" WIDE) 855(A) 8814 LF 1,079.000 1,079.000   0.000 $2.15 $0.00 $0.00
0379 TRAFFIC STRIPE(PLASTIC)(24" WIDE) 855(A) 8825 LF 101.000 101.000   0.000 $5.00 $0.00 $0.00
0380 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 92.000 92.000   0.000 $70.00 $0.00 $0.00
0381 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 9.000 9.000   0.000 $130.00 $0.00 $0.00
0382 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 1,294.000 1,294.000   1,426.000 $1.10 $0.00 $1,568.60
0383 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8724 EA 13.000 13.000   12.000 $55.00 $0.00 $660.00
0384 (PL)REMOVE & RESET EXISTING SIGNS 890A/B 8756 EA 73.000 73.000   73.000 $110.00 $0.00 $8,030.00
Subtotals For Category     0300/TRAFFIC PERMANENT - STPY-058C(240)    $0.00 $140,165.24
Fed/State Project Number:    STPY-058C(240) Project:    12573(04) Category:    0301/TRAFFIC TEMPORARY - STPY-058C(240)
0385 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 38,828.000 38,828.000   48,263.000 $0.25 $0.00 $12,065.75
0386 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 12,370.000 12,370.000   19,374.000 $0.55 $0.00 $10,655.70
0387 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 11,670.000 11,670.000   12,575.000 $0.55 $0.00 $6,916.25
0388 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 17,400.000 17,400.000   15,766.000 $1.35 $0.00 $21,284.10
0389 BARRICADES(TYPE III) 880(C) 8842 SD 8,610.000 8,610.000   10,242.000 $0.30 $0.00 $3,072.60
0390 WING BARRICADES 880(C) 8848 SD 4,240.000 4,240.000   2,716.000 $0.30 $0.00 $814.80
0391 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 32,190.000 32,190.000   31,470.000 $0.11 $0.00 $3,461.70
0392 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 85,630.000 85,630.000   67,624.000 $0.02 $0.00 $1,352.48
0393 DRUMS 880(F) 8878 SD 85,630.000 85,630.000   105,920.000 $0.15 $0.00 $15,888.00
0394 FLAGGER 880(I) 8902 SD 6.000 6.000   0.000 $150.00 $0.00 $0.00
Subtotals For Category     0301/TRAFFIC TEMPORARY - STPY-058C(240)    $0.00 $75,511.38
Subtotals For Project STPY-058C(240) /12573(04) $1,148.89 $7,093,031.40