Oklahoma Department of Transportation
Final Estimate Affidavit

Contract ID: 100385   Estimate Number: 0007 , Final     Spec Year: 1999
Primary JP: 25597(04)   Residency: DUNCAN (07100)     Contract No: 610181
Date Created: 09/19/2013   Contractor FEI: 731557599A     Account No: 432700

Project Number(s): BRO-134D(072)CO
Contract Description: BRIDGE AND APPROACHES COUNTY ROAD (EW-207): OVER A TRIBUTARY TO RED CREEK, 5.4 MILES EAST OF THE US-81 JUNCTION. PROJECT LENGTH = 0.188 MILES.
Primary County: JEFFERSON              
Name of Road: COUNTY ROAD              
Prime Contractor: PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)           Time Charged: 169.00
    1105 FIRST PLACE BLVD.           Time Allowed: 181.00
    YUKON , OK   73099           Percent Time: 93.37 %

  Paid To Date: $246,782.45 Payable This Statement: $3,239.97

CONTRACTOR AFFIDAVIT
STATE OF ___________________ )  
  )     §  
COUNTY OF __________________ )  
The undersigned contractor or duly authorized agent, of lawful age, being first duly sworn, on oath say that this claim is true and correct.
Affiant further states that the work, services or materials as shown by this claim have been completed or supplied in accordance with the plans, specifications, orders, requests and all other terms of the contract. Affiant further states that (s)he is duly authorized agent of the contractor for the purpose of certifying the facts pertaining to the giving of things of value to government personnel in order to procure the contract or obtain payment; that (s)he is fully aware of the facts and circumstances surrounding the making of the contract and has been personally and directly involved in the proceedings leading to the procurement of the contract and the filing of this claim; and, neither the contractor nor anyone subject to the contractor's direction or control has been paid, given or donated or agreed to pay, give or donate to any officer or employee of the State of Oklahoma any money or other thing of value, either directly or
indirectly, in procuring the contract or obtaining payment. The affiant further certifies that all laborers, mechanics, apprentices and trainees employed by him/her or by any subcontractor performing work under the contract on the project have been paid wages at rates not less than those required by the contract provisions, and that the work performed by each such laborer, mechanic, apprentice or trainee conformed to the classifications set forth in the contract or training program provisions applicable to the wage rate paid.
Affiant hereby agrees that Contractor will accept this estimate as full compensation for all money due Contractor by the Department of Transportation, and hereby relinquish all claims, either in contract or in tort, which have arisen or which might arise out of the construction of said project. That to the best of my knowledge and belief, all indebtedness for labor, materials, fuel, equipment, equipment rental, parts, supplies, insurance premiums, and claims for items not specifically mentioned, which are attributable to performance of the work on this project or which were incorporated therein in any manner, have been paid in full, and that there are not now any presently outstanding, unpaid claims for such indebtedness; that my position with the company is such, that if there were any such outstanding claims of the nature specified herein, I would ordinarily be aware of them.
Further affiant sayeth not.                                
PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)                               
 
_________________________________________________
Affiant Signature
 
_________________________________________________
Affiant Printed Name
                          PE Seal
_________________________________________________
Affiant Company Position
Subscribed and sworn to before me this ______ day of ____________, 20____
My Commission Number: ____________ My Commission Expires: ______________
   
_________________________________________________              
_________________________________________________
                    Professional Engineer Signature
              Oklahoma Department of Transportation
Corporate Seal
Notary Seal                  

Oklahoma Department of Transportation
Final Estimate Summary
Created:    09/19/2013
Contract ID: 100385   Estimate Number: 0007     Contract No: 610181
Residency: DUNCAN (07100)   Estimate Type: Final     Account No: 432700

Project Number(s): BRO-134D(072)CO
Primary Job Piece No: 25597(04)
Contract Description: BRIDGE AND APPROACHES COUNTY ROAD (EW-207): OVER A TRIBUTARY TO RED CREEK, 5.4 MILES EAST OF THE US-81 JUNCTION. PROJECT LENGTH = 0.188 MILES.
Primary County: JEFFERSON              
Name of Road: COUNTY ROAD              
Prime Contractor: PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)              
    1105 FIRST PLACE BLVD.              
    YUKON , OK   73099              
Surety Company: FIDELITY & DEPOSIT INSURANCE COMPANY OF MARYLAND              

Date Let: 06/17/2010 NTP Effective Date: 10/04/2010 Pay Period: 01/01/2011  TO  01/25/2011
Date Awarded: 07/06/2010 Date Work Began: 08/10/2010 Original Contract Time: 90
Date Contract Executed: 07/28/2010 Date Time Stopped: 01/25/2011 Current Time Charged: 169.00
Date NTP Issued: 07/29/2010 Completion Date: 01/25/2011 Current Time Allowed: 181.00
General Liability Expires: 04/15/2013 Workman's Comp Expires: 06/30/2013 Percent Time Used: 93.37 %
Specification Year: 1999        

Current Contract Amount: $246,782.43 Total to Date Prev to Date This Estimate
Bid Amount: $280,132.67 Participating: $246,782.45 $246,202.96 $579.49
Percent Complete: 100 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $-0.02 Total Earnings: $246,782.45 $246,202.96 $579.49
Unearned Balance: $33,350.22 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $246,782.45 $246,202.96 $579.49
Other Adjustments: $0.00 $-2,660.48 $2,660.48
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $246,782.45 $243,542.48 $3,239.97

Estimate Adjustment Detail

Contract ID: 100385   Estimate Number: 0007     Primary JP: 25597(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Final Quantity Change Order Approved 09/18/2013 0.0 $-33,350.24


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.
Subtotals For Liquidated Damages $


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
25597(04) 0022 TYPE I-A FILTER BLANKET * TEST CODE 0002 0.00 $0.00 $1,337.72
25597(04) 0022 TYPE I-A FILTER BLANKET * TEST CODE 0003 0.00 $0.00 $-2,675.44
25597(04) 0022 TYPE I-A FILTER BLANKET * TEST CODE 0005 0.00 $0.00 $-1,322.76
25597(04) 0022 TYPE I-A FILTER BLANKET * TEST CODE 0007 0.00 $0.00 $2,660.48
Subtotals For Line Item Adjustments $0.00
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 100385   Estimate Number: 0007     Primary JP: 25597(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BRO-134D(072)CO Project:    25597(04) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $3,255.00 $0.00 $3,255.00
0002 EARTHWORK 202(G) 0185 LSUM 1.000 1.000   1.000 $27,533.10 $0.00 $27,533.11
0003 TEMPORARY SILT FENCE 223 2801 LF 2,000.000 673.000   673.000 $1.63 $0.00 $1,096.99
0004 TEMPORARY SILT DIKE 227 0100 LF 450.000 252.000   252.000 $7.35 $0.00 $1,852.20
0005 SOLID SLAB SODDING 230(A) 2806 SY 8,660.000 8,478.220   8,478.220 $1.68 $0.00 $14,243.41
0006 VEGETATIVE MULCHING 233(A) 2817 AC 4.000 0.000   0.000 $262.50 $0.00 $0.00
0007 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 900.000 897.350   897.350 $24.74 $0.00 $22,200.44
0008 PRIME COAT 408 5774 GAL 706.000 0.000   0.000 $4.99 $0.00 $0.00
0009 CLASS C CONCRETE 509(D) 0325 CY 10.000 0.000   0.000 $322.79 $0.00 $0.00
0010 TYPE I PLAIN RIPRAP 601(A) 0297 TON 425.000 273.860   273.860 $43.43 $0.00 $11,893.74
Subtotals For Category     0100/ROADWAY    $0.00 $82,074.89
Fed/State Project Number:    BRO-134D(072)CO Project:    25597(04) Category:    0200/BRIDGE 'A'
0011 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 80.000 80.000   80.000 $8.40 $0.00 $672.00
0012 UNCLASSIFIED BACKFILL 501(D) 6353 CY 50.000 50.000   50.000 $10.50 $0.00 $525.00
0013 PRESTRESSED CONCRETE BEAMS (TYPE II) 503(A) 1311 LF 196.670 196.670   196.670 $158.84 $0.00 $31,239.06
0014 CONCRETE RAIL (TR1) 504(E) 1380 LF 157.000 157.000   157.000 $54.67 $0.00 $8,583.20
0015 STRUCTURAL STEEL 506(A) 1322 LB 1,490.000 1,490.000   1,490.000 $3.90 $0.00 $5,811.00
0016 CLASS AA CONCRETE 509(A) 1326 CY 39.700 39.700   39.700 $398.07 $0.00 $15,803.38
0017 CLASS A CONCRETE 509(B) 1328 CY 45.600 45.600   45.600 $388.39 $0.00 $17,710.58
0018 REINFORCING STEEL 511(A) 1332 LB 15,706.000 15,706.000   15,706.000 $0.77 $0.00 $12,093.62
0019 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 526.000 526.000   526.000 $22.32 $0.00 $11,740.32
0020 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 526.000 490.660   490.660 $21.00 $0.00 $10,303.86
0021 TYPE I-A PLAIN RIPRAP 601(A-1)1353 TON 564.000 222.050   222.050 $38.09 $0.00 $8,457.89
0022 TYPE I-A FILTER BLANKET 601(A-2)1355 TON 130.000 88.920 0.000 88.920 $29.92 $0.00 $2,660.48
0023 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $4,200.00 $0.00 $4,200.00
0024 GUARD RAIL ANCHOR UNIT (TYPE II) 623(F) 6033 EA 4.000 4.000   4.000 $2,100.00 $0.00 $8,400.00
0025 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $2,362.50 $0.00 $2,362.50
Subtotals For Category     0200/BRIDGE 'A'    $0.00 $140,562.89
Fed/State Project Number:    BRO-134D(072)CO Project:    25597(04) Category:    0600/STAKING
0026 STAKING 642 0098 LSUM 1.000 1.000 0.050 1.000 $4,620.00 $231.00 $4,620.00
Subtotals For Category     0600/STAKING    $231.00 $4,620.00
Fed/State Project Number:    BRO-134D(072)CO Project:    25597(04) Category:    0640/CONSTRUCTION
0027 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   1.000 $2,100.00 $0.00 $2,100.00
0028 MOBILIZATION 641 1399 LSUM 1.000 1.000 0.020 1.000 $17,424.67 $348.49 $17,424.67
Subtotals For Category     0640/CONSTRUCTION    $348.49 $19,524.67
Subtotals For Project BRO-134D(072)CO /25597(04) $579.49 $246,782.45