Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    05/23/2013
Contract ID: 100311   Estimate Number: 0007     Contract No: 511247
Residency: TETRA TECH (08002)   Estimate Type: Progressive     Account No: 400800

Project Number(s): STP-STIM(506)IG
Primary Job Piece No: 27382(04)
Contract Description: RESURFACE (ASPHALT) CITY STREET (MAIN STREET): BEGIN AT 4TH STREET, EXTEND WEST IN THE CITY OF JENKS. PROJECT LENGTH = 0.259 MILES.
Primary County: TULSA              
Name of Road: CITY STREET              
Prime Contractor: BECCO CONTRACTORS, INC.              
    P.O. BOX 9159              
    TULSA , OK   74157              
Surety Company: MID-CONTINENT CASUALTY COMPANY              

Date Let: 04/15/2010 NTP Effective Date: 08/02/2010 Pay Period: 03/01/2011  TO  05/15/2013
Date Awarded: 05/03/2010 Date Work Began: 08/02/2010 Original Contract Time: 90
Date Contract Executed: 05/12/2010 Date Time Stopped: Current Time Charged: 1018.00
Date NTP Issued: 06/24/2010 Completion Date: Current Time Allowed: 1007.00
General Liability Expires: 03/01/2014 Workman's Comp Expires: 02/01/2014 Percent Time Used: 101.09 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $195,279.67 Total to Date Prev to Date This Estimate
Bid Amount: $163,450.00 Participating: $198,077.99 $144,731.96 $53,346.03
Percent Complete: 95.52 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $8,754.65 Non ARRA: $5,412.67 $0.00 $5,412.67
Unearned Balance: $-23,075.02 Total Earnings: $203,490.66 $144,731.96 $58,758.70
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $203,490.66 $144,731.96 $58,758.70
Other Adjustments: $-11,465.64 $-2,314.49 $-9,151.15
Liq Dam/Disincentive: $-5,500.00 $-14,000.00 $8,500.00
TOTAL: $186,525.02 $128,417.47 $58,107.55

Estimate Adjustment Detail

Contract ID: 100311   Estimate Number: 0007     Primary JP: 27382(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Extend project limits Approved 08/08/2012 40.0 $31,829.67


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0003 --17 $500.00 $-8,500.00
System Application of Liquidated Damages 0004 --15 $500.00 $-7,500.00
System Application of Liquidated Damages 0005 -5.0 $500.00 $2,500.00
System Application of Liquidated Damages 0006 --1.0 $500.00 $-500.00
System Application of Liquidated Damages 0007 -17.0 $500.00 $8,500.00
Subtotals For Liquidated Damages $-5,500.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
27382(04) 0005 TACK COAT * Missing Material Certification 0007 0.00 $0.00 $-400.00
27382(04) 0006 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0003 287.83 $-2.17 $-626.89
27382(04) 0006 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0004 774.84 $-2.17 $-1,687.60
27382(04) 0006 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0007 -12.65 $70.00 $-886.15
27382(04) 0006 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0007 294.28 $1.81 $535.00
27382(04) 0006 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0007 -120.00 $70.00 $-8,400.00
Subtotals For Line Item Adjustments $-11,465.64
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
No milestones exist for this contract.


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 100311   Estimate Number: 0007     Primary JP: 27382(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(506)IG Project:    27382(04) Category:    0100/ROADWAY - STP-STIM(506)IG
0001 CONSTRUCTION MISCELLANEOUS 104 0600 EA 13.000 13.000   18.000 $150.00 $0.00 $2,700.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 70.000 115.000 88.620 138.400 $15.00 $1,329.30 $2,076.00
0003 UNCLASSIFIED BORROW 202(C) 0184 CY 40.000 40.000   0.000 $10.00 $0.00 $0.00
0004 SUBGRADE, METHOD B 310(B) 0149 SY 175.000 616.000 709.200 896.070 $2.00 $1,418.40 $1,792.14
0005 TACK COAT 407 0250 GAL 475.000 475.000 200.000 607.570 $2.00 $400.00 $1,215.14
0006 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 1,200.000 1,300.000 294.280 1,356.950 $70.00 $20,599.60 $94,986.50
0007 6" H.E.S. CONCRETE PAVEMENT 414(B) 0288 SY 20.000 420.000 396.810 398.570 $55.00 $21,824.55 $21,921.35
0008 8" H.E.S. CONCRETE PAVEMENT 414(B) 0290 SY 160.000 160.000 0.000 185.110 $60.00 $0.00 $11,106.60
0009 COLD MILLING BITUMINOUS PAVEMENT 417 4267 SY 9,700.000 10,200.000 2,749.670 11,355.850 $2.50 $6,874.18 $28,389.64
0010 MANHOLES ADJUST TO GRADE 612(A) 0641 EA 1.000 1.000 1.000 2.000 $500.00 $500.00 $1,000.00
0011 INLETS ADJUST TO GRADE 612(E) 0645 EA 5.000 5.000   2.000 $500.00 $0.00 $1,000.00
0012 VALVE BOXES ADJUST TO GRADE 612(G) 0647 EA 7.000 7.000 2.000 12.000 $200.00 $400.00 $2,400.00
0013 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 19,400.000 11,700.000   11,186.600 $0.70 $0.00 $7,830.62
0014 TRAFFIC STRIPE(PLASTIC)(SYMBOLS) 855(B) 8824 EA 12.000 12.000   12.000 $385.00 $0.00 $4,620.00
0015 PAVEMENT MARKERS CLASS C TYPE 2-D 857(A) 8950 EA 30.000 30.000   26.000 $40.00 $0.00 $1,040.00
0016 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $6,000.00 $0.00 $6,000.00
Subtotals For Category     0100/ROADWAY - STP-STIM(506)IG    $53,346.03 $188,077.99
Fed/State Project Number:    STP-STIM(506)IG Project:    27382(04) Category:    0640/CONSTRUCTION - STP-STIM(506)IG
0017 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
Subtotals For Category     0640/CONSTRUCTION - STP-STIM(506)IG    $0.00 $10,000.00
Fed/State Project Number:    STP-STIM(506)IG Project:    27382(04) Category:    0850/NON ARRA FUNDING
8101 (PL)RE-MOBILIZATION 641 1400 EA 0.000 1.000 1.000 1.000 $2,746.00 $2,746.00 $2,746.00
8102 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 0.000 1.000 1.000 1.000 $2,666.67 $2,666.67 $2,666.67
Subtotals For Category     0850/NON ARRA FUNDING    $5,412.67 $5,412.67
Subtotals For Project STP-STIM(506)IG /27382(04) $58,758.70 $203,490.66