Contract ID: | 100238 | Estimate Number: | 0043 | Contract No: | 610428 | |||
Residency: | MUSKOGEE (01100) | Estimate Type: | Progressive | Account No: | 400100 | |||
Project Number(s): | BHFY-013N(020) | ||||||||||||
Primary Job Piece No: | 08156(04) | ||||||||||||
Contract Description: | BRIDGE REHABILITATION US-69: OVER THE NORTH CANADIAN RIVER, 7.9 MILES NORTH OF THE PITTSBURG COUNTY LINE. PROJECT LENGTH = 0.276 MILES. | ||||||||||||
Primary County: | MCINTOSH | ||||||||||||
Name of Road: | US-69 | ||||||||||||
Prime Contractor: | JENSEN CONSTRUCTION COMPANY | ||||||||||||
11301 W. 57TH PLACE S. | |||||||||||||
SAND SPRINGS , OK 74063 | |||||||||||||
Surety Company: | WESTERN SURETY COMPANY | ||||||||||||
Date Let: | 07/22/2010 | NTP Effective Date: | 12/06/2010 | Pay Period: | 09/01/2012 TO 09/15/2012 |
Date Awarded: | 08/10/2010 | Date Work Began: | 11/01/2010 | Original Contract Time: | 635 |
Date Contract Executed: | 09/10/2010 | Date Time Stopped: | Current Time Charged: | 685.00 | |
Date NTP Issued: | 09/16/2010 | Completion Date: | Current Time Allowed: | 770.00 | |
General Liability Expires: | 04/01/2013 | Workman's Comp Expires: | 04/01/2013 | Percent Time Used: | 88.96 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $11,944,862.33 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $11,498,787.17 | Participating: | $10,052,810.51 | $9,820,748.88 | $232,061.63 | ||
Percent Complete: | 86.83 % | Non Participating: | $44,845.16 | $44,845.16 | $0.00 | ||
Funds Available: | $1,573,226.02 | Total Earnings: | $10,097,655.67 | $9,865,594.04 | $232,061.63 | ||
Unearned Balance: | $1,127,150.86 | Stockpiled Materials: | $273,980.64 | $397,623.00 | $-123,642.36 | ||
Gross Earnings: | $10,371,636.31 | $10,263,217.04 | $108,419.27 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $10,371,636.31 | $10,263,217.04 | $108,419.27 |
Contract ID: | 100238 | Estimate Number: | 0043 | Primary JP: | 08156(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Roadway and Bridge Deck repair | Approved | 04/05/2011 | 60.0 | $112,516.00 |
002 | Police Traffic Surveillance | Approved | 08/01/2011 | 0.0 | $50,310.00 |
003 | Traffic Surveillance Police July 1, 2011 to Jan. 21, 2012 | Approved | 09/14/2011 | 0.0 | $225,664.00 |
004 | Conduit installation for OG&E | Approved | 01/10/2012 | 0.0 | $21,483.00 |
005 | Traffic Control Const Zone pavement markers | Approved | 01/10/2012 | 0.0 | $11,700.00 |
006 | Conduit Installation for Reach Broad Band | Approved | 02/07/2012 | 0.0 | $21,202.16 |
007 | 80 addit. guardrail 40 Phase I, 40 Phase II | Approved | 07/02/2012 | 0.0 | $3,200.00 |
008 | Correction of Traffic Control Quantities | Pending | 0 | 0.0 | $148,768.20 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Initial Payment | 0007 | $982,492.92 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Adjustment | 0043 | $-123,642.36 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Adjustment | 0014 | $-482,416.93 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Adjustment | 0016 | $-387,434.58 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Initial Payment | 0011 | $982,492.91 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Adjustment | 0042 | $-123,642.36 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Adjustment | 0041 | $-487,923.46 |
08156(04) | 0063 | MOH for Structural Steel | Stockpiled Material Adjustment | 0027 | $-112,641.42 |
08156(04) | 0072 | MOH for Drilled Shafts 66" Diameter | Stockpiled Material Adjustment | 0034 | $-58,244.16 |
08156(04) | 0072 | MOH for Drilled Shafts 66" Diameter | Stockpiled Material Initial Payment | 0019 | $58,244.16 |
08156(04) | 0072 | MOH For Drilled Shafts 66" Diameter | Stockpiled Material Adjustment | 0034 | $-37,955.20 |
08156(04) | 0072 | MOH For Drilled Shafts 66" Diameter | Stockpiled Material Initial Payment | 0021 | $37,955.20 |
08156(04) | 0072 | MOH for Drilled Shafts 66"Diameter | Stockpiled Material Adjustment | 0034 | $-37,518.08 |
08156(04) | 0072 | MOH for Drilled Shafts 66"Diameter | Stockpiled Material Initial Payment | 0022 | $37,518.08 |
08156(04) | 0099 | MOH for Impact Attenuators | Stockpiled Material Initial Payment | 0018 | $26,695.92 | Subtotals For Stockpile Payments | $273,980.64 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 100238 | Estimate Number: | 0043 | Primary JP: | 08156(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0100/ROADWAY | ||||||||
0001 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 4,320.000 | 4,320.000 | 0.000 | 2,944.000 | $12.00 | $0.00 | $35,328.00 |
0002 | UNCLASSIFIED BORROW | 202(C) 0184 | CY | 3,180.000 | 3,180.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
0003 | TEMPORARY SILT FENCE | 223 2801 | LF | 2,500.000 | 2,500.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0004 | TEMPORARY SILT DIKE | 227 0100 | LF | 40.000 | 40.000 | 0.000 | $18.00 | $0.00 | $0.00 | |
0005 | SOLID SLAB SODDING | 230(A) 2806 | SY | 2,067.000 | 2,067.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0006 | AGGREGATE BASE | 303 0192 | CY | 1,284.000 | 1,284.000 | 0.000 | 644.950 | $48.00 | $0.00 | $30,957.60 |
0007 | (SP)CEMENT TREATED BASE | 317(F) 4270 | SY | 5,489.000 | 5,489.000 | 2,751.110 | $13.00 | $0.00 | $35,764.43 | |
0008 | SEPARATOR FABRIC | 325 5271 | SY | 6,200.000 | 6,200.000 | 3,283.890 | $2.00 | $0.00 | $6,567.78 | |
0009 | (SP)STABILIZED SUBGRADE | 327(K) 4300 | SY | 6,067.000 | 6,067.000 | 1,498.330 | $5.00 | $0.00 | $7,491.65 | |
0010 | TRAFFIC BOUND SURFACE COURSE TYPE E | 403(E) 0225 | TON | 979.000 | 979.000 | 170.080 | $28.00 | $0.00 | $4,762.24 | |
0011 | PRIME COAT | 408 5774 | GAL | 2,578.000 | 2,578.000 | 0.000 | $7.10 | $0.00 | $0.00 | |
0012 | (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 411(S4) 5960 | TON | 107.000 | 107.000 | 0.000 | $239.00 | $0.00 | $0.00 | |
0013 | (SP)RUMBLE STRIP-METHOD PCC-CON | 413(D) 4868 | LF | 2,400.000 | 2,400.000 | 0.000 | $2.50 | $0.00 | $0.00 | |
0014 | (SP)P.C.CONCRETE PAVEMENT(PLACEMENT) | 414(A) 0210 | SY | 3,571.000 | 3,571.000 | 2,932.840 | $19.00 | $0.00 | $55,723.96 | |
0015 | (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 414(A1) 5725 | SY | 3,600.000 | 3,600.000 | 1,762.230 | $40.00 | $0.00 | $70,489.20 | |
0016 | TERMINAL JOINT | 414(F) 5262 | EA | 2.000 | 2.000 | 0.000 | $10,000.00 | $0.00 | $0.00 | |
0017 | (SP)P.C. CONCRETE FOR PAVEMENT (ONLY) | 414(I) 5270 | CY | 2,191.000 | 2,191.000 | 1,439.790 | $110.00 | $0.00 | $158,376.90 | |
0018 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 3,200.000 | 3,200.000 | 2,748.030 | $7.00 | $0.00 | $19,236.21 | |
0019 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 3,837.000 | 3,837.000 | 2,088.510 | $8.00 | $0.00 | $16,708.08 | |
0020 | SAWING PAVEMENT | 619(C) 0924 | LF | 3,458.000 | 3,458.000 | 3,964.000 | $4.50 | $0.00 | $17,838.00 | |
0021 | THRIE BEAM BRIDGE CONNECTION-TYPE A | 623(E) 7114 | EA | 4.000 | 4.000 | 2.000 | $1,400.00 | $0.00 | $2,800.00 | |
0022 | (SP)G.E.T. GUARD RAIL END SECTION | 623(H) 8571 | EA | 2.000 | 2.000 | 0.000 | $1,900.00 | $0.00 | $0.00 | |
0023 | REMOVE AND RECONSTRUCT FENCE | 625(B) 1252 | LF | 400.000 | 400.000 | 0.000 | $35.00 | $0.00 | $0.00 | |
0024 | REMOVE AND RECONSTRUCT GUARD RAIL | 625(D) 1254 | LF | 683.000 | 683.000 | 582.500 | $9.25 | $0.00 | $5,388.13 | |
0025 | CONCRETE MEDIAN BARRIER, DESIGN 1 | 627(I) 4317 | LF | 1,842.000 | 1,842.000 | 0.000 | $60.00 | $0.00 | $0.00 | |
8003 | 9" H.E.S. CONCRETE (PATCHING) | 414(B) 5072 | SY | 0.000 | 400.000 | 391.630 | $154.00 | $0.00 | $60,311.02 | |
8006 | TRAFFIC SURVEILLANCE, POLICE | 880(L) 8911 | HOUR | 0.000 | 900.000 | 800.000 | $55.90 | $0.00 | $44,720.00 | |
8007 | TRAFFIC SURVEILLANCE, POLICE | 880(L) 8911 | HOUR | 0.000 | 4,100.000 | 4,395.250 | $55.04 | $0.00 | $241,914.56 | |
8010 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS | 856(G) 8881 | EA | 0.000 | 6,500.000 | 2,968.000 | $1.80 | $0.00 | $5,342.40 | |
8011 | CONSTRUCTION MISCELLANEOUS | 104 0600 | EA | 0.000 | 80.000 | 0.000 | $40.00 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY | $0.00 | $819,720.16 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0201/BRIDGE 'B' - ADD ALT. THIN PLATE | ||||||||
0056 | UNCLASSIFIED BORROW | 202(C) 1302 | CY | 100.000 | 100.000 | 0.000 | $50.00 | $0.00 | $0.00 | |
0057 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 160.000 | 160.000 | 120.000 | $50.00 | $0.00 | $6,000.00 | |
0058 | CLSM BACKFILL | 501(G) 6309 | CY | 80.000 | 80.000 | 136.570 | $120.00 | $0.00 | $16,388.40 | |
0059 | (PL)TUBULAR METAL TRAFFIC RAIL | 504 6143 | LF | 800.500 | 800.500 | 800.500 | $200.00 | $0.00 | $160,100.00 | |
0060 | APPROACH SLAB | 504(A) 1304 | SY | 522.000 | 522.000 | 246.660 | $100.00 | $0.00 | $24,666.00 | |
0061 | SEALED EXPANSION JOINT | 504(C) 6250 | LF | 234.000 | 234.000 | 120.000 | $200.00 | $0.00 | $24,000.00 | |
0062 | CONCRETE PARAPET | 504(F) 1381 | LF | 1,680.000 | 1,680.000 | 840.000 | $55.00 | $0.00 | $46,200.00 | |
0063 | STRUCTURAL STEEL | 506(A) 1322 | LB | 1,686,770.000 | 1,686,770.000 | 106,136.250 | 1,474,497.500 | $2.10 | $222,886.13 | $3,096,444.76 |
0064 | (PL)SPECIAL CONCRETE FINISH | 509 6152 | SY | 1,277.000 | 1,277.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0065 | CLASS AA CONCRETE | 509(A) 1326 | CY | 1,800.000 | 1,800.000 | 878.300 | $485.00 | $0.00 | $425,975.50 | |
0066 | CLASS A CONCRETE | 509(B) 1328 | CY | 293.500 | 293.500 | 258.700 | $490.00 | $0.00 | $126,763.00 | |
0067 | REINFORCING STEEL | 511(A) 1332 | LB | 20,340.000 | 20,340.000 | 19,080.000 | $0.90 | $0.00 | $17,172.00 | |
0068 | EPOXY COATED REINFORCING STEEL | 511(B) 6010 | LB | 437,930.000 | 437,930.000 | 1,080.000 | 220,062.000 | $0.98 | $1,058.40 | $215,660.76 |
0069 | PILES, FURNISHED (HP 12X53) | 514(A) 6011 | LF | 832.000 | 832.000 | 834.000 | $20.00 | $0.00 | $16,680.00 | |
0070 | PILES, DRIVEN (HP 12X53) | 514(B) 6294 | LF | 832.000 | 832.000 | 827.670 | $10.00 | $0.00 | $8,276.70 | |
0071 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 4,190.000 | 4,190.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0072 | DRILLED SHAFTS 66" DIAMETER | 516(A) 6097 | LF | 1,357.000 | 1,357.000 | 1,357.000 | $2,400.00 | $0.00 | $3,256,800.00 | |
0073 | CROSSHOLE SONIC LOGGING | 516(C) 6200 | EA | 14.000 | 14.000 | 14.000 | $2,000.00 | $0.00 | $28,000.00 | |
0074 | CSL ACCESS TUBES | 516(D) 6400 | LF | 8,298.000 | 8,298.000 | 8,298.000 | $10.00 | $0.00 | $82,980.00 | |
0075 | PNEUMATICALLY PLACED MORTAR | 521(A) 6210 | SY | 18.000 | 18.000 | 0.000 | $992.00 | $0.00 | $0.00 | |
0076 | (PL)CONSTRUCT PEDESTALS | 535 6160 | EA | 72.000 | 72.000 | 64.000 | $5,000.00 | $0.00 | $320,000.00 | |
0077 | TYPE I-A PLAIN RIPRAP | 601(A-1)1353 | TON | 405.000 | 405.000 | 47.910 | $35.00 | $0.00 | $1,676.85 | |
0078 | TYPE I-A FILTER BLANKET | 601(A-2)1355 | TON | 135.000 | 135.000 | 27.480 | $35.00 | $0.00 | $961.80 | |
0079 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(P) 6204 | LF | 208.000 | 208.000 | 0.000 | 154.000 | $45.00 | $0.00 | $6,930.00 |
0080 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(Q) 6207 | LF | 100.000 | 100.000 | 0.000 | 75.000 | $45.00 | $0.00 | $3,375.00 |
0081 | (PL)REMOVAL OF BRIDGE ITEM (TYPE A) | 619(B) 2510 | LSUM | 1.000 | 1.000 | 0.750 | $20,000.00 | $0.00 | $15,000.00 | |
0082 | (PL)REMOVAL OF BRIDGE ITEM (TYPE B) | 619(B) 2520 | LSUM | 1.000 | 1.000 | 0.875 | $180,000.00 | $0.00 | $157,500.00 | |
0083 | (PL)REMOVAL OF BRIDGE ITEM (TYPE C) | 619(B) 2535 | EA | 2.000 | 2.000 | 1.500 | $15,000.00 | $0.00 | $22,500.00 | |
0084 | (PL)REMOVAL OF BRIDGE ITEM (TYPE D) | 619(B) 2540 | LSUM | 1.000 | 1.000 | 0.750 | $10,000.00 | $0.00 | $7,500.00 | |
0085 | CONCRETE MEDIAN BARRIER, DESIGN 1 | 627(I) 4317 | LF | 860.000 | 860.000 | 0.000 | $60.00 | $0.00 | $0.00 | |
8000 | APPROACH SLAB | 504(A) 1304 | SY | 0.000 | 80.000 | 0.000 | 80.000 | $220.00 | $0.00 | $17,600.00 |
8001 | CLASS B BRIDGE DECK REPAIR | 505(B) 6019 | SY | 0.000 | 127.800 | 86.990 | $500.00 | $0.00 | $43,495.00 | |
8002 | CLASS C BRIDGE DECK REPAIR | 505(C) 6020 | SY | 0.000 | 40.400 | 6.430 | $800.00 | $0.00 | $5,144.00 | |
Subtotals For Category 0201/BRIDGE 'B' - ADD ALT. THIN PLATE | $223,944.53 | $8,153,789.77 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0202/UTILITY (RB3) | ||||||||
0086 | (PL)INSERTS | 504 6176 | EA | 108.000 | 108.000 | 108.000 | $20.00 | $0.00 | $2,160.00 | |
Subtotals For Category 0202/UTILITY (RB3) | $0.00 | $2,160.00 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0203/UTILITY (O.G.&E.) | ||||||||
0087 | (PL)INSTALLATION OF BRIDGE ITEMS(TYPE A) | 542 4615 | EA | 82.000 | 82.000 | 82.000 | $150.00 | $0.00 | $12,300.00 | |
Subtotals For Category 0203/UTILITY (O.G.&E.) | $0.00 | $12,300.00 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0300/TRAFFIC | ||||||||
0088 | PRECAST CONCRETE MEDIAN BARRIER, PORTABLE TYPE | 627(E) 4314 | LF | 4,652.000 | 0.000 | 0.000 | $36.00 | $0.00 | $0.00 | |
0089 | RELOCATION OF PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER | 627(G) 4316 | LF | 4,652.000 | 0.000 | 0.000 | $6.00 | $0.00 | $0.00 | |
0090 | DELIVER PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER | 627(H) 5856 | LF | 8,320.000 | 0.000 | 0.000 | $8.00 | $0.00 | $0.00 | |
0091 | SHEET ALUMINUM SIGNS | 850(A) 8110 | SF | 10.500 | 10.500 | 0.000 | $12.00 | $0.00 | $0.00 | |
0092 | 1 3/4" SQUARE TUBE POST | 851(C) 8321 | LF | 26.000 | 26.000 | 0.000 | $9.50 | $0.00 | $0.00 | |
0093 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 16,232.000 | 16,232.000 | 0.000 | $0.57 | $0.00 | $0.00 | |
0094 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 856(A) 8839 | LF | 1,000.000 | 1,000.000 | 2,147.000 | $0.25 | $0.00 | $536.75 | |
0095 | REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 856(C) 8851 | LF | 27,772.000 | 27,772.000 | 0.000 | $0.25 | $0.00 | $0.00 | |
0096 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 856(G) 8887 | EA | 250.000 | 250.000 | 315.000 | $1.00 | $0.00 | $315.00 | |
0097 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-2 | 856(G) 8890 | EA | 250.000 | 250.000 | 1,645.000 | $1.00 | $0.00 | $1,645.00 | |
0098 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 16,232.000 | 16,232.000 | 5,714.000 | $0.25 | $0.00 | $1,428.50 | |
0099 | (PL)IMPACT ATTENUATOR | 871 8325 | EA | 2.000 | 2.000 | 0.000 | $25,000.00 | $0.00 | $0.00 | |
0100 | (PL)CONST.ZONE IMPACT ATTEN. | 871 8705 | SD | 1,268.000 | 1,268.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
0101 | MODULAR GLARE SCREEN | 878(C) 8487 | SD | 50,720.000 | 50,720.000 | 1,800.000 | 77,112.000 | $0.50 | $900.00 | $38,556.00 |
0102 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 1,268.000 | 1,268.000 | 30.000 | 1,370.000 | $10.00 | $300.00 | $13,700.00 |
0103 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 128,068.000 | 128,068.000 | 3,675.000 | 163,918.000 | $0.01 | $36.75 | $1,639.18 |
0104 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 1,268.000 | 1,268.000 | 1,185.000 | 52,414.000 | $5.00 | $5,925.00 | $262,070.00 |
0105 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 49,452.000 | 49,452.000 | 510.000 | 24,081.000 | $0.01 | $5.10 | $240.81 |
0106 | CONSTRUCTION SIGNS 33.0 SF & OVER | 880(B) 8827 | SD | 7,608.000 | 7,608.000 | 240.000 | 10,499.000 | $2.50 | $600.00 | $26,247.50 |
0107 | BARRICADES(TYPE II) | 880(C) 8836 | SD | 1,100.000 | 1,100.000 | 54.000 | $0.10 | $0.00 | $5.40 | |
0108 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 15,850.000 | 15,850.000 | 360.000 | 15,396.000 | $0.01 | $3.60 | $153.96 |
0109 | WING BARRICADES | 880(C) 8848 | SD | 2,536.000 | 2,536.000 | 90.000 | 4,110.000 | $1.00 | $90.00 | $4,110.00 |
0110 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 31,700.000 | 31,700.000 | 990.000 | 43,905.000 | $0.04 | $39.60 | $1,756.20 |
0111 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 34,236.000 | 34,236.000 | 1,425.000 | 60,386.000 | $0.05 | $71.25 | $3,019.30 |
0112 | DRUMS | 880(F) 8878 | SD | 43,112.000 | 43,112.000 | 2,895.000 | 120,012.000 | $0.04 | $115.80 | $4,800.48 |
0113 | PORT.CHANGEABLE MESSAGE SIGN | 882(B) 8306 | SD | 5,072.000 | 5,072.000 | 15.000 | 1,066.000 | $2.00 | $30.00 | $2,132.00 |
8004 | REL.OF RENTED PORT.PREC.CONC.MED.BARRIER | 627(O) 4410 | LF | 0.000 | 6,812.000 | 7,860.000 | $6.00 | $0.00 | $47,160.00 | |
8005 | RENTED PORT.TYPE PREC.CONC.MED. BARR. | 627(P) 4425 | LF | 0.000 | 4,652.000 | 4,620.000 | $34.00 | $0.00 | $157,080.00 | |
Subtotals For Category 0300/TRAFFIC | $8,117.10 | $566,596.08 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0304/CABLE BARRIER | ||||||||
0114 | CLASS AA CONCRETE | 509(A) 0319 | CY | 8.000 | 8.000 | 0.000 | 7.410 | $450.00 | $0.00 | $3,334.50 |
0115 | INLETS ADJUST TO GRADE | 612(E) 0645 | EA | 1.000 | 1.000 | 0.000 | $2,000.00 | $0.00 | $0.00 | |
0116 | (PL)CABLE END ANCHOR UNIT | 628 5110 | EA | 2.000 | 2.000 | 2.000 | $4,300.00 | $0.00 | $8,600.00 | |
0117 | HIGH-TENSION CABLE BARRIER(TL-4) | 628 5125 | LF | 50.000 | 50.000 | 0.000 | $6.00 | $0.00 | $0.00 | |
0118 | INSTALLATION OF CABLE BARRIER SYSTEM | 628 5180 | LF | 100.000 | 100.000 | 0.000 | $6.00 | $0.00 | $0.00 | |
0119 | REMOVAL OF CABLE BARRIER | 628 5190 | LF | 1,875.000 | 1,875.000 | 1,905.000 | $2.00 | $0.00 | $3,810.00 | |
Subtotals For Category 0304/CABLE BARRIER | $0.00 | $15,744.50 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0600/STAKING | ||||||||
0120 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.950 | $150,000.00 | $0.00 | $142,500.00 | |
Subtotals For Category 0600/STAKING | $0.00 | $142,500.00 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0640/CONSTRUCTION | ||||||||
0121 | FIELD OFFICE | 640 1398 | EA | 1.000 | 1.000 | 1.000 | $30,000.00 | $0.00 | $30,000.00 | |
0122 | MOBILIZATION | 641 1399 | LSUM | 1.000 | 1.000 | 1.000 | $310,000.00 | $0.00 | $310,000.00 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $340,000.00 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0900/NON-PARTICIPATING (AT&T) | ||||||||
0123 | (PL)INSERTS | 504 6176 | EA | 108.000 | 108.000 | 108.000 | $20.00 | $0.00 | $2,160.00 | |
Subtotals For Category 0900/NON-PARTICIPATING (AT&T) | $0.00 | $2,160.00 | ||||||||
Fed/State Project Number: BHFY-013N(020) | Project: 08156(04) | Category: 0950/FEDERAL NON PARTICIPATING | ||||||||
9000 | CONSTRUCTION MISCELLANEOUS | 104 0300 | LF | 0.000 | 3,300.000 | 3,300.000 | $6.51 | $0.00 | $21,483.00 | |
9001 | CONSTRUCTION MISCELLANEOUS | 104 0700 | LSUM | 0.000 | 1.000 | 1.000 | $21,202.16 | $0.00 | $21,202.16 | |
Subtotals For Category 0950/FEDERAL NON PARTICIPATING | $0.00 | $42,685.16 | ||||||||
Subtotals For Project BHFY-013N(020) /08156(04) | $232,061.63 | $10,097,655.67 |