Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    07/18/2010
Contract ID: 100175   Estimate Number: 0002     Contract No: 510985
Residency: ENGINEERING SERVICES & TESTING (04001)   Estimate Type: Progressive     Account No: 400400

Project Number(s): STP-STIM(502)AG
Primary Job Piece No: 27290(04)
Contract Description: RESURFACE (ASPHALT) CITY STREET (MERIDAN AVE): BEGIN AT SW 29TH ST EXT SOUTH. PROJECT LENGTH = 1.60 MILES
Primary County: OKLAHOMA              
Name of Road: CITY STREET              
Prime Contractor: MARKWELL PAVING COMPANY, INC.              
    P.O. BOX 82005              
    OKLAHOMA CITY , OK   73148              
Surety Company: LIBERTY MUTUAL INSURANCE COMPANY              

Date Let: 02/18/2010 NTP Effective Date: 06/07/2010 Pay Period: 07/01/2010  TO  07/15/2010
Date Awarded: 03/01/2010 Date Work Began: 06/07/2010 Original Contract Time: 30
Date Contract Executed: 03/15/2010 Date Time Stopped: Current Time Charged: 39.00
Date NTP Issued: 04/26/2010 Completion Date: Current Time Allowed: 47.00
General Liability Expires: 04/01/2011 Workman's Comp Expires: 04/01/2011 Percent Time Used: 82.98 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $508,910.00 Total to Date Prev to Date This Estimate
Bid Amount: $508,910.00 Participating: $438,803.46 $256,951.85 $181,851.61
Percent Complete: 90.00 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $50,876.42 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $50,876.42 Total Earnings: $438,803.46 $256,951.85 $181,851.61
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $438,803.46 $256,951.85 $181,851.61
Other Adjustments: $19,230.12 $11,287.52 $7,942.60
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $458,033.58 $268,239.37 $189,794.21

Estimate Adjustment Detail

Contract ID: 100175   Estimate Number: 0002     Primary JP: 27290(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
27290(04) 0003 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $2,546.40
27290(04) 0003 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) Asphalt Binder Adjustment 0002 0.00 $0.00 $73.72
27290(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $8,741.12
27290(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0002 0.00 $0.00 $7,868.88
Subtotals For Line Item Adjustments $19,230.12


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 100175   Estimate Number: 0002     Primary JP: 27290(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(502)AG Project:    27290(04) Category:    0100/ROADWAY
0001 SOLID SLAB SODDING 230(A) 2806 SY 100.000 100.000   0.000 $2.00 $0.00 $0.00
0002 TACK COAT 407 0250 GAL 5,000.000 5,000.000 1,050.000 1,625.000 $2.00 $2,100.00 $3,250.00
0003 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) 411(S3) 6210 TON 900.000 900.000 26.890 921.430 $61.00 $1,640.29 $56,207.23
0004 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 5,500.000 5,500.000 2,511.450 5,198.380 $67.50 $169,522.88 $350,890.66
0005 (PL)CRACK SEALING P.C.PAVEMENT 414 5169 LF 3,000.000 3,000.000   0.000 $3.15 $0.00 $0.00
0006 COLD MILLING BITUMINOUS PAVEMENT 417 4267 SY 47,750.000 47,750.000 6,006.880 32,551.240 $0.50 $3,003.44 $16,275.62
0007 2'-8" COMB. CURB & GUTTER (8" BARRIER) 609(B) 1526 LF 80.000 80.000   0.000 $10.00 $0.00 $0.00
0008 6" CONCRETE SIDEWALK 610(A) 0605 SY 120.000 120.000   0.000 $35.00 $0.00 $0.00
0009 (PL)TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 40.000 40.000   0.000 $18.00 $0.00 $0.00
0010 MANHOLES ADJUST TO GRADE 612(A) 0641 EA 1.000 1.000   0.000 $100.00 $0.00 $0.00
0011 VALVE BOXES ADJUST TO GRADE 612(G) 0647 EA 1.000 1.000   0.000 $100.00 $0.00 $0.00
0012 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 80.000 80.000   0.000 $1.00 $0.00 $0.00
0013 SAWING PAVEMENT 619(C) 0924 LF 120.000 120.000   0.000 $1.00 $0.00 $0.00
0014 LOOP DETECTOR WIRE 828(B) 8138 LF 2,700.000 2,700.000   0.000 $3.50 $0.00 $0.00
0015 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 18,000.000 18,000.000   0.000 $0.45 $0.00 $0.00
0016 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 5.000 5.000   0.000 $55.00 $0.00 $0.00
0017 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 4.000 4.000   0.000 $155.00 $0.00 $0.00
0018 TRAFFIC STRIPE(PLASTIC)(SYMBOLS) 855(B) 8824 EA 8.000 8.000   0.000 $190.00 $0.00 $0.00
0019 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.750 $2,700.00 $675.00 $2,025.00
0020 (PL) PRECOATED FABRIC MEMBRANE(STRIP) 931.57 5706 LF 2,500.000 2,500.000 1,100.000 2,359.500 $2.10 $2,310.00 $4,954.95
Subtotals For Category     0100/ROADWAY    $179,251.61 $433,603.46
Fed/State Project Number:    STP-STIM(502)AG Project:    27290(04) Category:    0640/CONSTRUCTION
0021 MOBILIZATION 641 1552 LSUM 1.000 1.000 0.500 1.000 $5,200.00 $2,600.00 $5,200.00
Subtotals For Category     0640/CONSTRUCTION    $2,600.00 $5,200.00
Subtotals For Project STP-STIM(502)AG /27290(04) $181,851.61 $438,803.46