Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    07/02/2010
Contract ID: 100170   Estimate Number: 0006     Contract No: 510881
Residency: MCALESTER (02400)   Estimate Type: Progressive     Account No: 555200

Project Number(s): STP-STIM(485)EH
Primary Job Piece No: 27244(04)
Contract Description: PEDESTRIAN IMPROVEMENTS US-69: FROM 8TH STREET, EXTEND NORTH IN THE CITY OF KIOWA. PROJECT LENGTH = 0.5675 MILES
Primary County: PITTSBURG              
Name of Road: US-69              
Prime Contractor: RUDY CONSTRUCTION CO.              
    3101 NE 63RD STREET              
    OKLAHOMA CITY , OK   73121              
Surety Company: WESTERN SURETY COMPANY              

Date Let: 01/28/2010 NTP Effective Date: 04/05/2010 Pay Period: 06/15/2010  TO  06/30/2010
Date Awarded: 02/01/2010 Date Work Began: 04/13/2010 Original Contract Time: 120
Date Contract Executed: 02/16/2010 Date Time Stopped: Current Time Charged: 87.00
Date NTP Issued: 02/20/2010 Completion Date: Current Time Allowed: 124.00
General Liability Expires: 08/01/2010 Workman's Comp Expires: 08/01/2010 Percent Time Used: 70.16 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $538,509.53 Total to Date Prev to Date This Estimate
Bid Amount: $538,509.53 Participating: $311,597.64 $261,495.44 $50,102.20
Percent Complete: 57.89 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $226,765.99 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $226,765.99 Total Earnings: $311,597.64 $261,495.44 $50,102.20
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $311,597.64 $261,495.44 $50,102.20
Other Adjustments: $145.90 $145.90 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $311,743.54 $261,641.34 $50,102.20

Estimate Adjustment Detail

Contract ID: 100170   Estimate Number: 0006     Primary JP: 27244(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
27244(04) 0007 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0005 0.00 $0.00 $145.90
Subtotals For Line Item Adjustments $145.90


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 100170   Estimate Number: 0006     Primary JP: 27244(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(485)EH Project:    27244(04) Category:    0100/ROADWAY
0001 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 250.000 250.000 0.000 103.080 $9.00 $0.00 $927.72
0002 UNCLASSIFIED BORROW 202(C) 0184 CY 250.000 250.000 0.000 103.080 $15.00 $0.00 $1,546.20
0003 TEMPORARY BALE BARRIER 222 2801 LF 680.000 680.000   160.000 $3.00 $0.00 $480.00
0004 TEMPORARY SILT FENCE 223 2801 LF 6,993.000 6,993.000 1,397.000 3,170.000 $1.50 $2,095.50 $4,755.00
0005 SOLID SLAB SODDING 230(A) 2806 SY 4,697.750 4,697.750   0.000 $1.75 $0.00 $0.00
0006 AGGREGATE BASE 303 0192 CY 863.700 863.700 85.170 531.930 $48.00 $4,088.16 $25,532.64
0007 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 44.530 44.530   33.420 $115.00 $0.00 $3,843.30
0008 9" H.E.S. CONCRETE (PATCHING) 414(B) 5072 SY 397.600 397.600 36.830 424.450 $61.00 $2,246.63 $25,891.45
0009 CLASS A CONCRETE 509(B) 0321 CY 26.730 26.730   12.000 $630.00 $0.00 $7,560.00
0010 CLASS A CONCRETE FOR SMALL STRUCTURES 509(C) 0322 CY 5.160 5.160 2.450 2.450 $825.00 $2,021.25 $2,021.25
0011 CLASS C CONCRETE 509(D) 1331 CY 1.200 1.200 0.000 2.000 $875.00 $0.00 $1,750.00
0012 CONCRETE CURB (6" BARRIER-INTEGRAL) 609(A) 0300 LF 28.360 28.360 29.300 324.500 $10.00 $293.00 $3,245.00
0013 2'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1525 LF 772.190 772.190   431.500 $22.00 $0.00 $9,493.00
0014 4" CONCRETE SIDEWALK 610(A) 0602 SY 2,710.460 2,710.460 356.110 1,744.270 $50.00 $17,805.50 $87,213.50
0015 6" CONCRETE DRIVEWAY (H.E.S.) 610(B) 0399 SY 2,131.920 2,131.920 188.890 1,108.740 $58.00 $10,955.62 $64,306.92
0016 (PL)TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 288.580 288.580 10.000 140.000 $40.00 $400.00 $5,600.00
0017 MANHOLES ADJUST TO GRADE 612(A) 0641 EA 1.000 1.000   0.000 $800.00 $0.00 $0.00
0018 INLETS REBUILT 612(F) 0646 EA 1.000 1.000   0.000 $3,500.00 $0.00 $0.00
0019 VALVE BOXES ADJUST TO GRADE 612(G) 0647 EA 1.000 1.000   0.000 $200.00 $0.00 $0.00
0020 24" R.C.PIPE CLASS III 613(B) 0492 LF 50.300 50.300 10.000 18.000 $100.00 $1,000.00 $1,800.00
0021 24" CORR. GALV. STEEL PIPE 613(D) 0690 LF 25.900 25.900   25.880 $75.00 $0.00 $1,941.00
0022 24" PREFAB. CULVERT END SECTION, ROUND 613(M) 5730 EA 7.000 7.000 2.000 6.000 $2,000.00 $4,000.00 $12,000.00
0023 REMOVAL OF CONCRETE PAVEMENT 619(B) 4727 SY 403.260 403.260   325.170 $6.00 $0.00 $1,951.02
0024 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 2,084.140 2,084.140 305.090 1,304.940 $6.00 $1,830.54 $7,829.64
0025 REMOVAL OF CURB 619(B) 4791 LF 1,004.230 1,004.230 36.000 485.000 $6.00 $216.00 $2,910.00
0026 PIPE RAILING 622(A) 4746 LF 111.870 111.870   0.000 $90.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY    $46,952.20 $272,597.64
Fed/State Project Number:    STP-STIM(485)EH Project:    27244(04) Category:    0300/TRAFFIC
0027 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   0.500 $7,000.00 $0.00 $3,500.00
0028 (PL)REMOVE & RESET EXISTING SIGNS 890A/B 8756 EA 18.000 18.000 9.000 9.000 $350.00 $3,150.00 $3,150.00
Subtotals For Category     0300/TRAFFIC    $3,150.00 $6,650.00
Fed/State Project Number:    STP-STIM(485)EH Project:    27244(04) Category:    0600/STAKING
0029 STAKING 642 0098 LSUM 1.000 1.000   0.500 $10,000.00 $0.00 $5,000.00
Subtotals For Category     0600/STAKING    $0.00 $5,000.00
Fed/State Project Number:    STP-STIM(485)EH Project:    27244(04) Category:    0640/CONSTRUCTION
0030 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.350 $1,000.00 $0.00 $350.00
0031 MOBILIZATION 641 1552 LSUM 1.000 1.000   0.540 $50,000.00 $0.00 $27,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $27,350.00
Subtotals For Project STP-STIM(485)EH /27244(04) $50,102.20 $311,597.64