Contract ID: | 100158 | Estimate Number: | 0001 | Contract No: | 510891 | |||
Residency: | ANADARKO (07300) | Estimate Type: | Progressive | Account No: | 555700 | |||
Project Number(s): | STP-STIM(472)EH | ||||||||||||
Primary Job Piece No: | 27211(04) | ||||||||||||
Contract Description: | PEDESTRIAN IMPROVEMENTS SH-17: FROM COMANCHE AVENUE, EXTEND EAST IN THE TOWN OF RUSH SPRINGS. PROJECT LENGTH = 0.380 MILES | ||||||||||||
Primary County: | GRADY | ||||||||||||
Name of Road: | SH-17 | ||||||||||||
Prime Contractor: | RUDY CONSTRUCTION CO. | ||||||||||||
3101 NE 63RD STREET | |||||||||||||
OKLAHOMA CITY , OK 73121 | |||||||||||||
Surety Company: | WESTERN SURETY COMPANY | ||||||||||||
Date Let: | 01/28/2010 | NTP Effective Date: | 04/05/2010 | Pay Period: | 02/17/2010 TO 03/15/2010 |
Date Awarded: | 02/01/2010 | Date Work Began: | 03/01/2010 | Original Contract Time: | 90 |
Date Contract Executed: | 02/12/2010 | Date Time Stopped: | Current Time Charged: | 15.00 | |
Date NTP Issued: | 02/17/2010 | Completion Date: | Current Time Allowed: | 90.00 | |
General Liability Expires: | 08/01/2010 | Workman's Comp Expires: | 08/01/2010 | Percent Time Used: | 16.67 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $160,458.00 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $160,458.00 | Participating: | $37,571.10 | $0.00 | $37,571.10 | ||
Percent Complete: | 23.41 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $122,886.90 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $122,886.90 | Total Earnings: | $37,571.10 | $0.00 | $37,571.10 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $37,571.10 | $0.00 | $37,571.10 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $37,571.10 | $0.00 | $37,571.10 |
Contract ID: | 100158 | Estimate Number: | 0001 | Primary JP: | 27211(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 100158 | Estimate Number: | 0001 | Primary JP: | 27211(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(472)EH | Project: 27211(04) | Category: 0100/ROADWAY | ||||||||
0001 | TEMPORARY SILT FENCE | 223 2801 | LF | 1,550.000 | 1,550.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
0002 | SOLID SLAB SODDING | 230(A) 2806 | SY | 550.000 | 550.000 | 0.000 | $2.50 | $0.00 | $0.00 | |
0003 | TRAFFIC BOUND SURFACE COURSE TYPE E | 403(E) 0225 | TON | 45.000 | 45.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0004 | TACK COAT | 407 0250 | GAL | 37.000 | 37.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0005 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 175.000 | 175.000 | 0.000 | $110.00 | $0.00 | $0.00 | |
0006 | COLD MILLING PAVEMENT | 417 5267 | SY | 739.000 | 739.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0007 | CLASS A CONCRETE | 509(B) 0321 | CY | 6.000 | 6.000 | 0.000 | $800.00 | $0.00 | $0.00 | |
0008 | REINFORCING STEEL | 511(A) 0332 | LB | 483.000 | 483.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
0009 | CONCRETE CURB (6" BARRIER-INTEGRAL) | 609(A) 0300 | LF | 65.000 | 65.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0010 | COMBINED CURB & GUTTER (6" BARRIER) | 609(B) 0383 | LF | 485.000 | 485.000 | 189.750 | 189.750 | $20.00 | $3,795.00 | $3,795.00 |
0011 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 1,115.000 | 1,115.000 | 356.020 | 356.020 | $50.00 | $17,801.00 | $17,801.00 |
0012 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 95.000 | 95.000 | 39.220 | 39.220 | $50.00 | $1,961.00 | $1,961.00 |
0013 | 8" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0400 | SY | 47.000 | 47.000 | 0.000 | $55.00 | $0.00 | $0.00 | |
0014 | (PL)TACTILE WARNING DEVICE-NEW | 610(I) 4610 | SF | 288.000 | 288.000 | 64.000 | 64.000 | $25.00 | $1,600.00 | $1,600.00 |
0015 | (PL)TACTILE WARNING DEVICE-RETROFIT | 610(I) 4615 | SF | 40.000 | 40.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0016 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 309.000 | 309.000 | 216.000 | 216.000 | $5.00 | $1,080.00 | $1,080.00 |
0017 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 39.000 | 39.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0018 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 22.000 | 22.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0019 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 108.000 | 108.000 | 39.900 | 39.900 | $5.00 | $199.50 | $199.50 |
0020 | REMOVAL OF EXISTING STRUCTURES | 619(B) 4778 | EA | 1.000 | 1.000 | 0.000 | $500.00 | $0.00 | $0.00 | |
0021 | REMOVAL OF CURB | 619(B) 4791 | LF | 163.000 | 163.000 | 104.500 | 104.500 | $5.00 | $522.50 | $522.50 |
0022 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 599.000 | 599.000 | 370.520 | 370.520 | $5.00 | $1,852.60 | $1,852.60 |
0023 | SAWING PAVEMENT | 619(C) 0924 | LF | 1,268.000 | 1,268.000 | 586.500 | 586.500 | $3.00 | $1,759.50 | $1,759.50 |
0024 | 1 1/2" PIPE RAILING | 622(A) 4743 | LF | 110.000 | 110.000 | 0.000 | $70.00 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY | $30,571.10 | $30,571.10 | ||||||||
Fed/State Project Number: STP-STIM(472)EH | Project: 27211(04) | Category: 0300/TRAFFIC | ||||||||
0025 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 306.000 | 306.000 | 0.000 | $12.00 | $0.00 | $0.00 | |
0026 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 202.000 | 202.000 | 0.000 | $2.50 | $0.00 | $0.00 | |
0027 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $6,000.00 | $3,000.00 | $3,000.00 |
0028 | (PL)REMOVE & RESET GROUND MOUNTED SIGN | 890A/B 8760 | EA | 9.000 | 9.000 | 0.000 | $125.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC | $3,000.00 | $3,000.00 | ||||||||
Fed/State Project Number: STP-STIM(472)EH | Project: 27211(04) | Category: 0600/STAKING | ||||||||
0029 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.250 | 0.250 | $6,000.00 | $1,500.00 | $1,500.00 |
Subtotals For Category 0600/STAKING | $1,500.00 | $1,500.00 | ||||||||
Fed/State Project Number: STP-STIM(472)EH | Project: 27211(04) | Category: 0640/CONSTRUCTION | ||||||||
0030 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $5,000.00 | $2,500.00 | $2,500.00 |
Subtotals For Category 0640/CONSTRUCTION | $2,500.00 | $2,500.00 | ||||||||
Subtotals For Project STP-STIM(472)EH /27211(04) | $37,571.10 | $37,571.10 |