Contract ID: | 100132 | Estimate Number: | 0003 | Contract No: | 510986 | |||
Residency: | OKLAHOMA CITY (04600) | Estimate Type: | Progressive | Account No: | 400400 | |||
Project Number(s): | STP-STIM(490)AG | ||||||||||||
Primary Job Piece No: | 27269(04) | ||||||||||||
Contract Description: | RESURFACE (ASPHALT) CITY STREET(SE 44TH STREET): FROM BRYANT AVENUE, EXTEND EAST IN THE CITY OF OKLAHOMA CITY. PROJECT LENGTH = 1.998 MILES | ||||||||||||
Primary County: | OKLAHOMA | ||||||||||||
Name of Road: | SE 44TH STREET | ||||||||||||
Prime Contractor: | T.J. CAMPBELL CONSTRUCTION CO. | ||||||||||||
P. O. BOX 15129 | |||||||||||||
OKLA. CITY , OK 73155 | |||||||||||||
Surety Company: | TRAVELERS INDEMNITY COMPANY | ||||||||||||
Date Let: | 02/18/2010 | NTP Effective Date: | 04/19/2010 | Pay Period: | 05/16/2010 TO 05/31/2010 |
Date Awarded: | 03/01/2010 | Date Work Began: | 04/19/2010 | Original Contract Time: | 30 |
Date Contract Executed: | 03/15/2010 | Date Time Stopped: | Current Time Charged: | 43.00 | |
Date NTP Issued: | 03/22/2010 | Completion Date: | Current Time Allowed: | 43.00 | |
General Liability Expires: | 04/01/2011 | Workman's Comp Expires: | 07/01/2010 | Percent Time Used: | 100.00 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $505,282.10 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $505,282.10 | Participating: | $546,503.50 | $115,219.92 | $431,283.58 | ||
Percent Complete: | 100 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $0.00 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $0.00 | Total Earnings: | $546,503.50 | $115,219.92 | $431,283.58 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $546,503.50 | $115,219.92 | $431,283.58 | ||||
Other Adjustments: | $-41,221.40 | $1,895.29 | $-43,116.69 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $505,282.10 | $117,115.21 | $388,166.89 |
Contract ID: | 100132 | Estimate Number: | 0003 | Primary JP: | 27269(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
Withhold to Funds Avail(Prog. Est. Only) | 0003 | $-46,868.67 | Subtotals For Contract Adjustments | $-46,868.67 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
27269(04) | 0002 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | Asphalt Binder Adjustment | 0001 | 0.00 | $0.00 | $441.79 |
27269(04) | 0002 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | Asphalt Binder Adjustment | 0002 | 0.00 | $0.00 | $4,045.50 |
27269(04) | 0002 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | * QAQC | 0003 | 0.00 | $0.00 | $-1,491.72 |
27269(04) | 0003 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * QAQC | 0003 | 0.00 | $0.00 | $-12,897.67 |
27269(04) | 0003 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0003 | 0.00 | $0.00 | $18,141.37 |
27269(04) | 0007 | (PL)TACTILE WARNING DEVICE-NEW | * Material Discrepancy Adjustments | 0001 | -129.60 | $20.00 | $-2,592.00 | Subtotals For Line Item Adjustments | $5,647.27 | * = User applied Line Item Adjustments |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 100132 | Estimate Number: | 0003 | Primary JP: | 27269(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(490)AG | Project: 27269(04) | Category: 0100/ROADWAY | ||||||||
0001 | SOLID SLAB SODDING | 230(A) 2806 | SY | 532.000 | 532.000 | 0.000 | $2.50 | $0.00 | $0.00 | |
0002 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | 411(S3) 6210 | TON | 1,869.000 | 1,869.000 | 0.000 | 1,576.370 | $64.50 | $0.00 | $101,675.87 |
0003 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 4,179.000 | 4,179.000 | 5,576.470 | 5,576.470 | $65.00 | $362,470.55 | $362,470.55 |
0004 | COLD MILLING BITUMINOUS PAVEMENT | 417 4267 | SY | 37,087.000 | 37,087.000 | 58,225.810 | 58,225.810 | $0.90 | $52,403.23 | $52,403.23 |
0005 | 2'-8" COMB. CURB & GUTTER (8" BARRIER) | 609(B) 1526 | LF | 330.000 | 330.000 | 0.000 | $26.00 | $0.00 | $0.00 | |
0006 | 6" CONCRETE SIDEWALK | 610(A) 0605 | SY | 298.000 | 298.000 | 161.230 | $35.00 | $0.00 | $5,643.05 | |
0007 | (PL)TACTILE WARNING DEVICE-NEW | 610(I) 4610 | SF | 290.000 | 290.000 | 129.600 | $20.00 | $0.00 | $2,592.00 | |
0008 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 6.000 | 6.000 | 0.000 | $375.00 | $0.00 | $0.00 | |
0009 | VALVE BOXES ADJUST TO GRADE | 612(G) 0647 | EA | 2.000 | 2.000 | 0.000 | $250.00 | $0.00 | $0.00 | |
0010 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 330.000 | 330.000 | 0.000 | $4.50 | $0.00 | $0.00 | |
0011 | SAWING PAVEMENT | 619(C) 0924 | LF | 370.000 | 370.000 | 272.000 | $3.25 | $0.00 | $884.00 | |
0012 | LOOP DETECTOR WIRE | 828(B) 8138 | LF | 6,048.000 | 6,048.000 | 0.000 | $4.35 | $0.00 | $0.00 | |
0013 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 37,595.000 | 37,595.000 | 34,817.000 | 34,817.000 | $0.40 | $13,926.80 | $13,926.80 |
0014 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 8.000 | 8.000 | 11.000 | 11.000 | $103.00 | $1,133.00 | $1,133.00 |
0015 | TRAFFIC STRIPE(PLASTIC)(WORDS) | 855(B) 8821 | EA | 4.000 | 4.000 | 5.000 | 5.000 | $180.00 | $900.00 | $900.00 |
0016 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.150 | 1.000 | $3,000.00 | $450.00 | $3,000.00 |
Subtotals For Category 0100/ROADWAY | $431,283.58 | $544,628.50 | ||||||||
Fed/State Project Number: STP-STIM(490)AG | Project: 27269(04) | Category: 0600/STAKING | ||||||||
0017 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.500 | $750.00 | $0.00 | $375.00 | |
Subtotals For Category 0600/STAKING | $0.00 | $375.00 | ||||||||
Fed/State Project Number: STP-STIM(490)AG | Project: 27269(04) | Category: 0640/CONSTRUCTION | ||||||||
0018 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $1,500.00 | $0.00 | $1,500.00 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $1,500.00 | ||||||||
Subtotals For Project STP-STIM(490)AG /27269(04) | $431,283.58 | $546,503.50 |