Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    06/15/2010
Contract ID: 100086   Estimate Number: 0002     Contract No: 511014
Residency: STILLWATER (04500)   Estimate Type: Progressive     Account No: 555400

Project Number(s): STP-STIM(456)EH
Primary Job Piece No: 27195(04)
Contract Description: PEDESTRIAN IMPROVEMENTS SH-33: FROM CHOCTAW ROAD, EXTEND EAST IN THE TOWN OF LANGSTON. PROJECT LENGTH = 0.893 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED.
Primary County: LOGAN              
Name of Road: SH-33              
Prime Contractor: SAC SERVICES, INC.              
    3600 S. ROSS AVE.              
    OKLAHOMA CITY , OK   73119              
Surety Company: GRANITE RE, INC.              

Date Let: 02/25/2010 NTP Effective Date: 05/03/2010 Pay Period: 06/01/2010  TO  06/14/2010
Date Awarded: 03/01/2010 Date Work Began: Original Contract Time: 90
Date Contract Executed: 03/17/2010 Date Time Stopped: Current Time Charged: 43.00
Date NTP Issued: 03/22/2010 Completion Date: Current Time Allowed: 107.00
General Liability Expires: 08/30/2010 Workman's Comp Expires: 10/01/2010 Percent Time Used: 40.19 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $1,428,547.18 Total to Date Prev to Date This Estimate
Bid Amount: $1,428,547.18 Participating: $191,702.51 $124,121.66 $67,580.85
Percent Complete: 13.42 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $1,236,844.67 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $1,236,844.67 Total Earnings: $191,702.51 $124,121.66 $67,580.85
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $191,702.51 $124,121.66 $67,580.85
Other Adjustments: $0.00 $0.00 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $191,702.51 $124,121.66 $67,580.85

Estimate Adjustment Detail

Contract ID: 100086   Estimate Number: 0002     Primary JP: 27195(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 100086   Estimate Number: 0002     Primary JP: 27195(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(456)EH Project:    27195(04) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   0.500 $7,685.00 $0.00 $3,842.50
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 382.000 382.000 69.340 69.340 $7.00 $485.38 $485.38
0003 UNCLASSIFIED BORROW 202(C) 0184 CY 4,072.000 4,072.000   0.000 $14.50 $0.00 $0.00
0004 TEMPORARY BALE BARRIER 222 2801 LF 827.000 827.000   0.000 $6.25 $0.00 $0.00
0005 TEMPORARY SILT FENCE 223 2801 LF 9,067.000 9,067.000 0.000 3,911.000 $1.95 $0.00 $7,626.45
0006 TEMPORARY SILT DIKE 227 0100 LF 286.000 286.000   0.000 $7.50 $0.00 $0.00
0007 SOLID SLAB SODDING 230(A) 2806 SY 9,906.000 9,906.000   0.000 $1.95 $0.00 $0.00
0008 SEEDING METHOD B 232(B) 2814 AC 2.000 2.000   0.000 $850.00 $0.00 $0.00
0009 AGGREGATE BASE 303 0192 CY 1,754.000 1,754.000   0.000 $45.55 $0.00 $0.00
0010 TACK COAT 407 0250 GAL 692.000 692.000   0.000 $5.00 $0.00 $0.00
0011 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 3,181.000 3,181.000   0.000 $70.00 $0.00 $0.00
0012 8" H.E.S. CONCRETE PAVEMENT 414(B) 0290 SY 2,294.000 2,294.000   0.000 $46.95 $0.00 $0.00
0013 10" H.E.S. CONCRETE PAVEMENT 414(B) 0302 SY 307.000 307.000   0.000 $62.00 $0.00 $0.00
0014 COLD MILLING PAVEMENT 417 5267 SY 12,573.000 12,573.000   0.000 $3.45 $0.00 $0.00
0015 FABRIC REINFORCEMENT 420(A) 4242 SY 6,287.000 6,287.000   0.000 $8.60 $0.00 $0.00
0016 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 7.000 7.000 8.830 8.830 $50.00 $441.50 $441.50
0017 HANDRAILING 504(G) 6006 LF 172.000 172.000   0.000 $77.00 $0.00 $0.00
0018 CLASS A CONCRETE 509(B) 0321 CY 64.000 64.000 39.700 39.700 $480.00 $19,056.00 $19,056.00
0019 CLASS C CONCRETE 509(D) 0325 CY 14.000 14.000   0.000 $335.00 $0.00 $0.00
0020 REINFORCING STEEL 511(A) 0332 LB 5,222.000 5,222.000 4,779.990 4,779.990 $1.00 $4,779.99 $4,779.99
0021 2'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1525 LF 7,486.000 7,486.000   0.000 $12.98 $0.00 $0.00
0022 4" CONCRETE SIDEWALK 610(A) 0602 SY 5,648.000 5,648.000   0.000 $35.75 $0.00 $0.00
0023 8" CONCRETE DRIVEWAY (H.E.S.) 610(B) 0400 SY 3,135.000 3,135.000   0.000 $47.27 $0.00 $0.00
0024 (PL)TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 1,208.000 1,208.000   0.000 $18.50 $0.00 $0.00
0025 MANHOLE (4' DIAMETER) 611(A) 2657 EA 2.000 2.000 1.000 1.000 $1,500.00 $1,500.00 $1,500.00
0026 MANHOLE FRAME & COVER 611(D) 4215 EA 2.000 2.000   0.000 $310.00 $0.00 $0.00
0027 INLET CICI DES. 2 (STD) 611(E) 5112 EA 1.000 1.000 1.000 1.000 $2,000.00 $2,000.00 $2,000.00
0028 INLET CICI DES. 3 (STD) 611(E) 5120 EA 4.000 4.000 5.000 5.000 $2,600.00 $13,000.00 $13,000.00
0029 INLET CICI DES. 3 (B) 611(E) 5121 EA 2.000 2.000   0.000 $3,100.00 $0.00 $0.00
0030 INLET (SMD-TYPE 2) 611(E) 6002 EA 1.000 1.000   0.000 $3,375.00 $0.00 $0.00
0031 ADDITIONAL DEPTH IN INLET 611(F) 5196 VF 7.000 7.000   0.000 $210.00 $0.00 $0.00
0032 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 26.000 26.000   0.000 $367.00 $0.00 $0.00
0033 CAST IRON CURB INLETS 611(K) 4488 EA 30.000 30.000   0.000 $150.00 $0.00 $0.00
0034 18" R.C.PIPE CLASS III 613(B) 0491 LF 223.000 223.000 60.000 60.000 $37.25 $2,235.00 $2,235.00
0035 24" R.C.PIPE CLASS III 613(B) 0492 LF 148.000 148.000 16.000 16.000 $47.80 $764.80 $764.80
0036 18" R.C.PIPE CLASS IV 613(B) 0582 LF 1,428.000 1,428.000   1,394.000 $35.80 $0.00 $49,905.20
0037 TRENCH EXCAVATION 613(S) 1180 CY 1,096.000 1,096.000 23.570 575.000 $3.50 $82.50 $2,012.51
0038 STANDARD BEDDING MATERIAL 613(T) 1181 CY 560.000 560.000 45.330 399.080 $21.00 $951.93 $8,380.68
0039 (PL)SLOTTED DRAIN 615(H) 0200 LF 17.000 17.000   0.000 $65.00 $0.00 $0.00
0040 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   0.000 $4,785.00 $0.00 $0.00
0041 REMOVAL OF HEADWALL 619(B) 0291 EA 6.000 6.000 1.000 3.000 $350.00 $350.00 $1,050.00
0042 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 200.000 200.000   0.000 $5.00 $0.00 $0.00
0043 REMOVAL OF CONCRETE PAVEMENT 619(B) 4727 SY 256.000 256.000   0.000 $7.00 $0.00 $0.00
0044 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 5,576.000 5,576.000   4,725.000 $6.00 $0.00 $28,350.00
0045 REMOVAL OF CONCRETE DRIVEWAY 619(B) 4766 SY 662.000 662.000   0.000 $6.00 $0.00 $0.00
0046 REMOVAL OF SIDEWALK 619(B) 4792 SY 17.000 17.000   0.000 $15.00 $0.00 $0.00
0047 REMOVAL OF EXISTING PIPE 619(B) 5918 LF 210.000 210.000 45.000 45.000 $10.00 $450.00 $450.00
0048 SAWING PAVEMENT 619(C) 0924 LF 414.000 414.000   383.000 $2.00 $0.00 $766.00
0049 4" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8350 LF 1,439.000 1,439.000   0.000 $5.75 $0.00 $0.00
0050 TRAFFIC STRIPE(PAINT)(4" WIDE) 854(A) 8800 LF 9,430.000 9,430.000   0.000 $0.75 $0.00 $0.00
0051 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   0.200 $8,895.00 $0.00 $1,779.00
0052 (PL)REMOVE & RESET GROUND MOUNTED SIGN 890A/B 8760 EA 35.000 35.000   0.000 $180.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY    $46,097.10 $148,425.01
Fed/State Project Number:    STP-STIM(456)EH Project:    27195(04) Category:    0600/STAKING
0053 STAKING 642 0098 LSUM 1.000 1.000 0.250 0.500 $15,735.00 $3,933.75 $7,867.50
Subtotals For Category     0600/STAKING    $3,933.75 $7,867.50
Fed/State Project Number:    STP-STIM(456)EH Project:    27195(04) Category:    0640/CONSTRUCTION
0054 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.100 $3,100.00 $0.00 $310.00
0055 MOBILIZATION 641 1552 LSUM 1.000 1.000 0.500 1.000 $35,100.00 $17,550.00 $35,100.00
Subtotals For Category     0640/CONSTRUCTION    $17,550.00 $35,410.00
Subtotals For Project STP-STIM(456)EH /27195(04) $67,580.85 $191,702.51