Contract ID: | 100082 | Estimate Number: | 0001 | Contract No: | 511305 | |||
Residency: | ALTUS (05200) | Estimate Type: | Progressive | Account No: | 555500 | |||
Project Number(s): | STP-STIM(463)EH, STP-STIM(463) PART 3 EH | ||||||||||||
Primary Job Piece No: | 27202(04) | ||||||||||||
Contract Description: | PEDESTRIAN IMPROVEMENTS/RESURFACE (ASPHALT) US-183: FROM 5TH STREET, EXTEND NORTH IN THE TOWN OF HOBART. PROJECT LENGTH = 1.38 MILES | ||||||||||||
Primary County: | KIOWA | ||||||||||||
Name of Road: | US-183 | ||||||||||||
Prime Contractor: | SEWELL BROS., INC. | ||||||||||||
1220 E. MAIN | |||||||||||||
CORDELL , OK 73632 | |||||||||||||
Surety Company: | WESTFIELD INSURANCE COMPANY | ||||||||||||
Date Let: | 04/15/2010 | NTP Effective Date: | 07/05/2010 | Pay Period: | 05/26/2010 TO 07/15/2010 |
Date Awarded: | 05/03/2010 | Date Work Began: | 07/06/2010 | Original Contract Time: | 90 |
Date Contract Executed: | 05/19/2010 | Date Time Stopped: | Current Time Charged: | 10.00 | |
Date NTP Issued: | 05/26/2010 | Completion Date: | Current Time Allowed: | 90.00 | |
General Liability Expires: | 07/01/2011 | Workman's Comp Expires: | 07/01/2011 | Percent Time Used: | 11.11 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $517,232.50 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $517,232.50 | Participating: | $38,848.26 | $0.00 | $38,848.26 | ||
Percent Complete: | 7.42 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $478,829.24 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $478,829.24 | Total Earnings: | $38,848.26 | $0.00 | $38,848.26 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $38,848.26 | $0.00 | $38,848.26 | ||||
Other Adjustments: | $-445.00 | $0.00 | $-445.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $38,403.26 | $0.00 | $38,403.26 |
Contract ID: | 100082 | Estimate Number: | 0001 | Primary JP: | 27202(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
27202(04) | 0021 | CONSTRUCTION TRAFFIC CONTROL | * Material Discrepancy Adjustments | 0001 | -0.10 | $4,450.00 | $-445.00 | Subtotals For Line Item Adjustments | $-445.00 | * = User applied Line Item Adjustments |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 100082 | Estimate Number: | 0001 | Primary JP: | 27202(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(463)EH | Project: 27202(04) | Category: 0100/ROADWAY STP-STIM(463)EH | ||||||||
0001 | TEMPORARY SILT FENCE | 223 2801 | LF | 200.000 | 200.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0002 | AGGREGATE BASE | 303 5912 | TON | 1,854.000 | 1,854.000 | 157.840 | 157.840 | $20.00 | $3,156.80 | $3,156.80 |
0003 | TRAFFIC BOUND SURFACE COURSE TYPE A | 403(A) 0217 | TON | 40.500 | 40.500 | 0.000 | $22.00 | $0.00 | $0.00 | |
0004 | COMBINED CURB & GUTTER (6" BARRIER) | 609(B) 0383 | LF | 1,937.500 | 1,937.500 | 520.000 | 520.000 | $25.00 | $13,000.00 | $13,000.00 |
0005 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 2,199.000 | 2,199.000 | 106.660 | 106.660 | $40.00 | $4,266.40 | $4,266.40 |
0006 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 2,128.500 | 2,128.500 | 23.140 | 23.140 | $50.00 | $1,157.00 | $1,157.00 |
0007 | (PL)TACTILE WARNING DEVICE-NEW | 610(I) 4610 | SF | 208.000 | 208.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0008 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 1.000 | 1.000 | 0.000 | $500.00 | $0.00 | $0.00 | |
0009 | INLETS ADJUST TO GRADE | 612(E) 0645 | EA | 5.000 | 5.000 | 0.000 | $1,500.00 | $0.00 | $0.00 | |
0010 | VALVE BOXES ADJUST TO GRADE | 612(G) 0647 | EA | 11.000 | 11.000 | 0.000 | $150.00 | $0.00 | $0.00 | |
0011 | METER BOXES ADJUST TO GRADE | 612(H) 0648 | EA | 13.000 | 13.000 | 0.000 | $150.00 | $0.00 | $0.00 | |
0012 | (PL)RESET LIGHT POLES | 612(P) 0674 | EA | 1.000 | 1.000 | 0.000 | $2,750.00 | $0.00 | $0.00 | |
0013 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 619(A) 0920 | LSUM | 1.000 | 1.000 | 0.750 | 0.750 | $3,500.00 | $2,625.00 | $2,625.00 |
0014 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 1,898.000 | 1,898.000 | 595.000 | 595.000 | $5.00 | $2,975.00 | $2,975.00 |
0015 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 716.000 | 716.000 | 45.560 | 45.560 | $3.00 | $136.68 | $136.68 |
0016 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 789.000 | 789.000 | 56.650 | 56.650 | $4.00 | $226.60 | $226.60 |
0017 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 1,240.000 | 1,240.000 | 89.390 | 89.390 | $2.00 | $178.78 | $178.78 |
0018 | REMOVAL OF RAILROAD | 619(B) 4822 | LF | 30.000 | 30.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0019 | SAWING PAVEMENT | 619(C) 0924 | LF | 2,281.000 | 2,281.000 | 389.000 | 389.000 | $4.00 | $1,556.00 | $1,556.00 |
Subtotals For Category 0100/ROADWAY STP-STIM(463)EH | $29,278.26 | $29,278.26 | ||||||||
Fed/State Project Number: STP-STIM(463)EH | Project: 27202(04) | Category: 0300/TRAFFIC STP-STIM(463)EH | ||||||||
0020 | 2 1/4" SQUARE TUBE POST | 851(C) 8327 | LF | 176.000 | 176.000 | 0.000 | $3.50 | $0.00 | $0.00 | |
0021 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.100 | 0.100 | $4,450.00 | $445.00 | $445.00 |
0022 | (PL)REMOVE & RESET EXISTING SIGNS | 890A/B 8756 | EA | 14.000 | 14.000 | 0.000 | $170.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC STP-STIM(463)EH | $445.00 | $445.00 | ||||||||
Fed/State Project Number: STP-STIM(463)EH | Project: 27202(04) | Category: 0600/STAKING STP-STIM(463)EH | ||||||||
0023 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.250 | 0.250 | $6,500.00 | $1,625.00 | $1,625.00 |
Subtotals For Category 0600/STAKING STP-STIM(463)EH | $1,625.00 | $1,625.00 | ||||||||
Fed/State Project Number: STP-STIM(463)EH | Project: 27202(04) | Category: 0640/CONSTRUCTION STP-STIM(463)EH | ||||||||
0024 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $15,000.00 | $7,500.00 | $7,500.00 |
Subtotals For Category 0640/CONSTRUCTION STP-STIM(463)EH | $7,500.00 | $7,500.00 | ||||||||
Subtotals For Project STP-STIM(463)EH /27202(04) | $38,848.26 | $38,848.26 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(463) PART 3 EH | Project: 27202(06) | Category: 0100/ROADWAY STP-STIM(463)PT. 3 EH | ||||||||
0025 | (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 411(S4) 5960 | TON | 1,487.000 | 1,487.000 | 0.000 | $79.00 | $0.00 | $0.00 | |
0026 | COLD MILLING PAVEMENT | 417 5267 | SY | 16,205.000 | 16,205.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
0027 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 6,936.000 | 6,936.000 | 0.000 | $0.75 | $0.00 | $0.00 | |
0028 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 8.000 | 8.000 | 0.000 | $90.00 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY STP-STIM(463)PT. 3 EH | $0.00 | $0.00 | ||||||||
Subtotals For Project STP-STIM(463) PART 3 EH /27202(06) | $0.00 | $0.00 |