Contract ID: | 100063 | Estimate Number: | 0007 | Contract No: | 511293 | |||
Residency: | CLINTON (05100) | Estimate Type: | Progressive | Account No: | 555500 | |||
Project Number(s): | STP-STIM(461)EH, STP-STIM(461) PART 3 EH | ||||||||||||
Primary Job Piece No: | 27200(04) | ||||||||||||
Contract Description: | PEDESTRIAN IMPROVEMENTS/RESURFACE (ASPHALT) SH-51/SH-58: SH-51 FROM GRANT ST EXTEND EAST, AND SH-58 FROM PARK ST EXTEND NORTH, IN THE TOWN OF CANTON. PROJECT LENGTH = 0.8224 MILES | ||||||||||||
Primary County: | BLAINE | ||||||||||||
Name of Road: | SH-51/SH-58 | ||||||||||||
Prime Contractor: | K & K CONTRACTING, INC. | ||||||||||||
2019 E. ST. HWY. 152, STE.103 | |||||||||||||
MUSTANG , OK 73064 | |||||||||||||
Surety Company: | GRANITE RE, INC. | ||||||||||||
Date Let: | 04/15/2010 | NTP Effective Date: | 07/05/2010 | Pay Period: | 09/01/2010 TO 09/15/2010 |
Date Awarded: | 05/03/2010 | Date Work Began: | 06/07/2010 | Original Contract Time: | 90 |
Date Contract Executed: | 05/19/2010 | Date Time Stopped: | Current Time Charged: | 101.00 | |
Date NTP Issued: | 05/27/2010 | Completion Date: | Current Time Allowed: | 108.00 | |
General Liability Expires: | 10/01/2010 | Workman's Comp Expires: | 03/05/2011 | Percent Time Used: | 93.52 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $626,582.20 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $626,582.20 | Participating: | $321,542.43 | $296,540.50 | $25,001.93 | ||
Percent Complete: | 51.32 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $305,039.77 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $305,039.77 | Total Earnings: | $321,542.43 | $296,540.50 | $25,001.93 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $321,542.43 | $296,540.50 | $25,001.93 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $321,542.43 | $296,540.50 | $25,001.93 |
Contract ID: | 100063 | Estimate Number: | 0007 | Primary JP: | 27200(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 100063 | Estimate Number: | 0007 | Primary JP: | 27200(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(461)EH | Project: 27200(04) | Category: 0100/ROADWAY STP-STIM(461)EH | ||||||||
0001 | TEMPORARY SILT FENCE | 223 2801 | LF | 200.000 | 200.000 | 0.000 | $2.50 | $0.00 | $0.00 | |
0002 | SOLID SLAB SODDING | 230(A) 2806 | SY | 50.000 | 50.000 | 0.000 | $3.25 | $0.00 | $0.00 | |
0003 | AGGREGATE BASE | 303 0192 | CY | 670.000 | 670.000 | 0.000 | 570.470 | $58.00 | $0.00 | $33,087.26 |
0004 | TRAFFIC BOUND SURFACE COURSE TYPE A | 403(A) 0217 | TON | 25.500 | 25.500 | 0.000 | $45.00 | $0.00 | $0.00 | |
0005 | HANDRAILING | 504(G) 6006 | LF | 201.000 | 201.000 | 134.750 | 218.950 | $150.00 | $20,212.50 | $32,842.50 |
0006 | CLASS A CONCRETE FOR SMALL STRUCTURES | 509(C) 0322 | CY | 30.000 | 30.000 | 0.000 | $525.00 | $0.00 | $0.00 | |
0007 | RETAINING WALL | 510(A) 6333 | SY | 71.000 | 71.000 | 0.000 | 47.220 | $95.00 | $0.00 | $4,485.90 |
0008 | REINFORCING STEEL | 511(A) 0332 | LB | 9,335.000 | 9,335.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
0009 | COMBINED CURB & GUTTER (8" BARRIER) | 609(B) 0384 | LF | 2,472.000 | 2,472.000 | 0.000 | 2,430.890 | $22.00 | $0.00 | $53,479.58 |
0010 | 5" CONCRETE SIDEWALK | 610(A) 0604 | SY | 3,064.000 | 3,064.000 | 0.000 | 2,640.600 | $48.00 | $0.00 | $126,748.80 |
0011 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 409.000 | 409.000 | 0.000 | 131.550 | $62.00 | $0.00 | $8,156.10 |
0012 | (PL)TACTILE WARNING DEVICE-NEW | 610(I) 4610 | SF | 160.000 | 160.000 | 8.000 | 144.000 | $21.21 | $169.68 | $3,054.24 |
0013 | VALVE BOXES ADJUST TO GRADE | 612(G) 0647 | EA | 1.000 | 1.000 | 0.000 | $300.00 | $0.00 | $0.00 | |
0014 | METER BOXES ADJUST TO GRADE | 612(H) 0648 | EA | 19.000 | 19.000 | 0.000 | $250.00 | $0.00 | $0.00 | |
0015 | FIRE HYDRANTS | 616(G) 1192 | EA | 1.000 | 1.000 | 0.000 | $5,000.00 | $0.00 | $0.00 | |
0016 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 1,631.000 | 1,631.000 | 4.500 | 1,659.000 | $3.00 | $13.50 | $4,977.00 |
0017 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 284.000 | 284.000 | 107.680 | 485.560 | $10.00 | $1,076.80 | $4,855.60 |
0018 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 403.000 | 403.000 | -25.000 | 194.600 | $10.00 | $-250.00 | $1,946.00 |
0019 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 2,212.000 | 2,212.000 | 395.200 | 2,295.200 | $8.00 | $3,161.60 | $18,361.60 |
0020 | SAWING PAVEMENT | 619(C) 0924 | LF | 2,655.000 | 2,655.000 | 224.000 | 2,282.000 | $2.50 | $560.00 | $5,705.00 |
0021 | REMOVE AND RESET MAILBOX | 629(E) 5048 | EA | 1.000 | 1.000 | 1.000 | $10.00 | $0.00 | $10.00 | |
Subtotals For Category 0100/ROADWAY STP-STIM(461)EH | $24,944.08 | $297,709.58 | ||||||||
Fed/State Project Number: STP-STIM(461)EH | Project: 27200(04) | Category: 0300/TRAFFIC STP-STIM(461)EH | ||||||||
0022 | 2 1/4" SQUARE TUBE POST | 851(C) 8327 | LF | 160.000 | 160.000 | 13.000 | 13.000 | $4.45 | $57.85 | $57.85 |
0023 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.750 | $7,700.00 | $0.00 | $5,775.00 | |
0024 | (PL)REMOVE & RESET EXISTING SIGNS | 890A/B 8756 | EA | 3.000 | 3.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC STP-STIM(461)EH | $57.85 | $5,832.85 | ||||||||
Fed/State Project Number: STP-STIM(461)EH | Project: 27200(04) | Category: 0600/STAKING STP-STIM(461)EH | ||||||||
0025 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.750 | $4,000.00 | $0.00 | $3,000.00 | |
Subtotals For Category 0600/STAKING STP-STIM(461)EH | $0.00 | $3,000.00 | ||||||||
Fed/State Project Number: STP-STIM(461)EH | Project: 27200(04) | Category: 0640/CONSTRUCTION STP-STIM(461)EH | ||||||||
0026 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $15,000.00 | $0.00 | $15,000.00 | |
Subtotals For Category 0640/CONSTRUCTION STP-STIM(461)EH | $0.00 | $15,000.00 | ||||||||
Subtotals For Project STP-STIM(461)EH /27200(04) | $25,001.93 | $321,542.43 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(461) PART 3 EH | Project: 27200(06) | Category: 0100/ROADWAY STP-STIM(461)PART 3 EH | ||||||||
0027 | (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 411(S4) 5960 | TON | 1,316.000 | 1,316.000 | 0.000 | $114.85 | $0.00 | $0.00 | |
0028 | COLD MILLING PAVEMENT | 417 5267 | SY | 12,760.000 | 12,760.000 | 0.000 | $4.25 | $0.00 | $0.00 | |
0029 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 12,200.000 | 12,200.000 | 0.000 | $0.78 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY STP-STIM(461)PART 3 EH | $0.00 | $0.00 | ||||||||
Subtotals For Project STP-STIM(461) PART 3 EH /27200(06) | $0.00 | $0.00 |