Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    03/01/2010
Contract ID: 090657   Estimate Number: 0002     Contract No: 510691
Residency: PURCELL (03200)   Estimate Type: Progressive     Account No: 400300

Project Number(s): STP-STIM(424)AG
Primary Job Piece No: 26773(04)
Contract Description: TRAFFIC SIGNALS AND STRIPING US-77/SH-74/SH-39: AT VARIOUS LOCATIONS IN DIVISION III. PROJECT LENGTH = 1.5 MILES
Primary County: MCCLAIN              
Name of Road: US-77/SH-74/SH-39              
Prime Contractor: TRAFFIC SIGNALS, INC.              
    P. O. BOX 30067              
    EDMOND , OK   73003-0002              
Surety Company: MID-CONTINENT CASUALTY CO.              

Date Let: 11/19/2009 NTP Effective Date: 02/08/2010 Pay Period: 02/16/2010  TO  02/28/2010
Date Awarded: 12/07/2009 Date Work Began: 02/08/2010 Original Contract Time: 90
Date Contract Executed: 12/18/2009 Date Time Stopped: Current Time Charged: 21.00
Date NTP Issued: 01/05/2010 Completion Date: Current Time Allowed: 92.00
General Liability Expires: 07/01/2010 Workman's Comp Expires: 02/01/2011 Percent Time Used: 22.83 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $171,743.80 Total to Date Prev to Date This Estimate
Bid Amount: $171,743.80 Participating: $161,473.10 $79,480.00 $81,993.10
Percent Complete: 94.02 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $10,270.70 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $10,270.70 Total Earnings: $161,473.10 $79,480.00 $81,993.10
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $161,473.10 $79,480.00 $81,993.10
Other Adjustments: $0.00 $0.00 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $161,473.10 $79,480.00 $81,993.10

Estimate Adjustment Detail

Contract ID: 090657   Estimate Number: 0002     Primary JP: 26773(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090657   Estimate Number: 0002     Primary JP: 26773(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(424)AG Project:    26773(04) Category:    0300/TRAFFIC
0001 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000 0.500 1.000 $123,680.00 $61,840.00 $123,680.00
0002 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 5,825.000 5,825.000   0.000 $0.60 $0.00 $0.00
0003 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.500 1.000 $1,500.00 $750.00 $1,500.00
Subtotals For Category     0300/TRAFFIC    $62,590.00 $125,180.00
Fed/State Project Number:    STP-STIM(424)AG Project:    26773(04) Category:    0301/ADD ALTERNATE 1
0004 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000 0.500 1.000 $13,675.00 $6,837.50 $13,675.00
0005 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $450.00 $0.00 $450.00
Subtotals For Category     0301/ADD ALTERNATE 1    $6,837.50 $14,125.00
Fed/State Project Number:    STP-STIM(424)AG Project:    26773(04) Category:    0302/ADD ALTERNATE 2
0006 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000 0.500 1.000 $13,675.00 $6,837.50 $13,675.00
0007 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $450.00 $0.00 $450.00
Subtotals For Category     0302/ADD ALTERNATE 2    $6,837.50 $14,125.00
Fed/State Project Number:    STP-STIM(424)AG Project:    26773(04) Category:    0303/ADD ALTERNATE 3
0008 1" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8334 LF 100.000 100.000   0.000 $3.00 $0.00 $0.00
0009 PULL BOX(SIZE III) 803 8067 EA 2.000 2.000   0.000 $280.00 $0.00 $0.00
0010 STRUCTURAL CONCRETE 804(A) 2915 CY 0.800 0.800 0.800 0.800 $580.00 $464.00 $464.00
0011 REINFORCING STEEL 804(B) 2916 LB 56.000 56.000 53.000 53.000 $1.70 $90.10 $90.10
0012 SERVICE POLE 810(A) 3118 EA 2.000 2.000   0.000 $1,470.00 $0.00 $0.00
0013 1/C NO.10 ELECTRICAL CONDUCTOR 811 8044 LF 600.000 600.000 28.000 28.000 $0.80 $22.40 $22.40
0014 SOLID STATE FLASHER CONTROLLER(TYPE II) 827 8623 EA 2.000 2.000 2.000 2.000 $1,380.00 $2,760.00 $2,760.00
0015 1WAY 1SEC. ADJ. SIG. HD. S-22 831 8301 EA 4.000 4.000   4.000 $185.00 $0.00 $740.00
0016 SHEET ALUMINUM SIGNS 850(A) 8110 SF 82.000 82.000 16.000 16.000 $14.00 $224.00 $224.00
0017 4"@10.79 GALV.STEEL PIPE POST 851(B) 3220 LF 24.000 24.000 24.000 24.000 $27.40 $657.60 $657.60
0018 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 104.000 104.000   0.000 $10.00 $0.00 $0.00
0019 TRAFFIC STRIPE(PLASTIC)(24" WIDE) 855(A) 8825 LF 192.000 192.000   0.000 $2.00 $0.00 $0.00
0020 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.400 0.900 $650.00 $260.00 $585.00
0021 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8724 EA 2.000 2.000   0.000 $50.00 $0.00 $0.00
Subtotals For Category     0303/ADD ALTERNATE 3    $4,478.10 $5,543.10
Fed/State Project Number:    STP-STIM(424)AG Project:    26773(04) Category:    0640/CONSTRUCTION
0022 MOBILIZATION 641 1552 LSUM 1.000 1.000 0.500 1.000 $2,500.00 $1,250.00 $2,500.00
Subtotals For Category     0640/CONSTRUCTION    $1,250.00 $2,500.00
Subtotals For Project STP-STIM(424)AG /26773(04) $81,993.10 $161,473.10