Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    04/20/2010
Contract ID: 090647   Estimate Number: 0002     Contract No: 510724
Residency: TETRA TECH (08002)   Estimate Type: Progressive     Account No: 400800

Project Number(s): STP-STIM(264)IG, STP-STIM(265)IG, STP-STIM(268)IG
Primary Job Piece No: 26684(04)
Contract Description: RESURFACE (ASPHALT) CITY STREETS(9TH ST/ELM PL/NEW ORLEANS/FLORENCE ST/HOUSTON): AT VARIOUS LOCATIONS IN THE CITY OF BROKEN ARROW. PROJECT LENGTH = 1.682 MILES
Primary County: TULSA              
Name of Road: ELM PLACE              
Prime Contractor: APAC-CENTRAL, INC.              
    4150 S. 100th E Ave, Suite 300              
    Tulsa , OK   74146              
Surety Company: FEDERAL INSURANCE COMPANY              

Date Let: 11/19/2009 NTP Effective Date: 02/01/2010 Pay Period: 03/16/2010  TO  03/31/2010
Date Awarded: 12/07/2009 Date Work Began: 02/01/2010 Original Contract Time: 150
Date Contract Executed: 12/21/2009 Date Time Stopped: Current Time Charged: 59.00
Date NTP Issued: 01/11/2010 Completion Date: Current Time Allowed: 151.00
General Liability Expires: 09/01/2010 Workman's Comp Expires: 09/01/2010 Percent Time Used: 39.07 %
Specification Year: 1999     Date Approved: 04/20/2010

Current Contract Amount: $1,245,715.28 Total to Date Prev to Date This Estimate
Bid Amount: $1,245,715.28 Participating: $98,875.01 $64,682.94 $34,192.07
Percent Complete: 7.94 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $1,146,840.27 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $1,146,840.27 Total Earnings: $98,875.01 $64,682.94 $34,192.07
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $98,875.01 $64,682.94 $34,192.07
Other Adjustments: $0.00 $0.00 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $98,875.01 $64,682.94 $34,192.07

Estimate Adjustment Detail

Contract ID: 090647   Estimate Number: 0002     Primary JP: 26684(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
No line item adjustments have been created on this contract.
Subtotals For Line Item Adjustments $0.00


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090647   Estimate Number: 0002     Primary JP: 26684(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(264)IG Project:    26684(04) Category:    0200/ROADWAY - STP-STIM(264)IG
0001 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) 411(S3) 6210 TON 140.000 140.000   0.000 $97.47 $0.00 $0.00
0002 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 7,200.000 7,200.000   0.000 $62.96 $0.00 $0.00
0003 COLD MILLING PAVEMENT 417 5267 SY 42,580.000 42,580.000   0.000 $1.84 $0.00 $0.00
0004 FABRIC REINFORCEMENT 420(A) 4242 SY 42,580.000 42,580.000   0.000 $2.63 $0.00 $0.00
0005 COMBINED CURB & GUTTER (6" BARRIER) 609(B) 0383 LF 3,620.000 3,620.000 1,228.000 3,559.000 $16.18 $19,869.04 $57,584.62
0006 4" CONCRETE SIDEWALK 610(A) 0602 SY 205.000 205.000 62.340 91.570 $41.27 $2,572.77 $3,779.09
0007 CAST IRON CURB INLETS 611(K) 4488 EA 29.000 29.000 15.000 29.000 $252.48 $3,787.20 $7,321.92
0008 MANHOLES ADJUST TO GRADE 612(A) 0641 EA 2.000 2.000   0.000 $530.73 $0.00 $0.00
0009 VALVE BOXES ADJUST TO GRADE 612(G) 0647 EA 3.000 3.000   0.000 $370.99 $0.00 $0.00
0010 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 3,620.000 3,620.000 1,228.000 3,559.000 $5.15 $6,324.20 $18,328.85
0011 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 140.000 140.000   0.000 $9.47 $0.00 $0.00
0012 REMOVAL OF DRAINAGE INLETS 619(B) 4741 EA 29.000 29.000 15.000 29.000 $63.01 $945.15 $1,827.29
0013 REMOVAL OF SIDEWALK 619(B) 4792 SY 205.000 205.000 31.720 81.580 $13.91 $441.23 $1,134.78
0014 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000   0.000 $26,483.20 $0.00 $0.00
0015 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 23,472.000 23,472.000   0.000 $0.55 $0.00 $0.00
0016 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 27.000 27.000   0.000 $77.29 $0.00 $0.00
0017 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 7.000 7.000   0.000 $180.34 $0.00 $0.00
0018 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.100 0.200 $2,524.82 $252.48 $504.96
Subtotals For Category     0200/ROADWAY - STP-STIM(264)IG    $34,192.07 $90,481.51
Fed/State Project Number:    STP-STIM(264)IG Project:    26684(04) Category:    0640/CONSTRUCTION
0019 MOBILIZATION 641 1552 LSUM 1.000 1.000   0.500 $16,787.00 $0.00 $8,393.50
Subtotals For Category     0640/CONSTRUCTION    $0.00 $8,393.50
Fed/State Project Number:    STP-STIM(264)IG Project:    26684(04) Category:    0900/FEDERAL NON PARTICIPATING
8001 (SP)ASPH.CONC.,TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 0.000 0.000   0.000 $62.96 $0.00 $0.00
8002 COLD MILLING PAVEMENT 417 5267 SY 0.000 0.000   0.000 $1.84 $0.00 $0.00
8003 FABRIC REINFORCEMENT 420(A) 4242 SY 0.000 0.000   0.000 $2.63 $0.00 $0.00
8004 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 0.000 0.000   0.000 $0.55 $0.00 $0.00
Subtotals For Category     0900/FEDERAL NON PARTICIPATING    $0.00 $0.00
Subtotals For Project STP-STIM(264)IG /26684(04) $34,192.07 $98,875.01


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(265)IG Project:    26685(04) Category:    0200/ROADWAY - STP-STIM(265)IG
0001 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) 411(S3) 6210 TON 129.000 129.000   0.000 $98.20 $0.00 $0.00
0002 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 1,650.000 1,650.000   0.000 $71.88 $0.00 $0.00
0003 COLD MILLING PAVEMENT 417 5267 SY 9,750.000 9,750.000   0.000 $2.50 $0.00 $0.00
0004 FABRIC REINFORCEMENT 420(A) 4242 SY 9,750.000 9,750.000   0.000 $2.63 $0.00 $0.00
0005 COMBINED CURB & GUTTER (6" BARRIER) 609(B) 0383 LF 20.000 20.000   0.000 $26.48 $0.00 $0.00
0006 4" CONCRETE SIDEWALK 610(A) 0602 SY 115.000 115.000   0.000 $43.59 $0.00 $0.00
0007 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 225.000 225.000   0.000 $11.79 $0.00 $0.00
0008 REMOVAL OF SIDEWALK 619(B) 4792 SY 115.000 115.000   0.000 $13.91 $0.00 $0.00
0009 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000   0.000 $25,763.47 $0.00 $0.00
0010 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 7,560.000 7,560.000   0.000 $0.58 $0.00 $0.00
0011 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 14.000 14.000   0.000 $77.29 $0.00 $0.00
0012 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 7.000 7.000   0.000 $180.34 $0.00 $0.00
0013 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   0.000 $1,076.92 $0.00 $0.00
Subtotals For Category     0200/ROADWAY - STP-STIM(265)IG    $0.00 $0.00
Fed/State Project Number:    STP-STIM(265)IG Project:    26685(04) Category:    0900/FEDERAL NON PARTICIPATING
Subtotals For Category     0900/FEDERAL NON PARTICIPATING    $0.00 $0.00
Subtotals For Project STP-STIM(265)IG /26685(04) $0.00 $0.00


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(268)IG Project:    26688(04) Category:    0200/ROADWAY - STP-STIM(268)IG
0001 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) 411(S3) 6210 TON 16.000 16.000   0.000 $134.41 $0.00 $0.00
0002 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 1,550.000 1,550.000   0.000 $73.15 $0.00 $0.00
0003 COLD MILLING PAVEMENT 417 5267 SY 9,150.000 9,150.000   0.000 $2.50 $0.00 $0.00
0004 FABRIC REINFORCEMENT 420(A) 4242 SY 9,150.000 9,150.000   0.000 $2.63 $0.00 $0.00
0005 4" CONCRETE SIDEWALK 610(A) 0602 SY 70.000 70.000   0.000 $43.59 $0.00 $0.00
0006 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 35.000 35.000   0.000 $8.90 $0.00 $0.00
0007 REMOVAL OF SIDEWALK 619(B) 4792 SY 70.000 70.000   0.000 $13.91 $0.00 $0.00
0008 (PL)DETECTION SYSTEM (VIDEO) 828 8132 LSUM 1.000 1.000   0.000 $25,763.47 $0.00 $0.00
0009 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 8,493.000 8,493.000   0.000 $0.62 $0.00 $0.00
0010 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 10.000 10.000   0.000 $77.29 $0.00 $0.00
0011 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 5.000 5.000   0.000 $180.34 $0.00 $0.00
0012 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   0.000 $1,030.54 $0.00 $0.00
Subtotals For Category     0200/ROADWAY - STP-STIM(268)IG    $0.00 $0.00
Fed/State Project Number:    STP-STIM(268)IG Project:    26688(04) Category:    0900/FEDERAL NON PARTICIPATING
Subtotals For Category     0900/FEDERAL NON PARTICIPATING    $0.00 $0.00
Subtotals For Project STP-STIM(268)IG /26688(04) $0.00 $0.00