Contract ID: | 090644 | Estimate Number: | 0035 | Contract No: | 510674 | |||
Residency: | ENGINEERING SERVICES & TESTING (08001) | Estimate Type: | Progressive | Account No: | 400800 | |||
Project Number(s): | STP-STIM(284)IG, STP-STIM(286)IG, STP-STIM(482)IG | ||||||||||||
Primary Job Piece No: | 26703(04) | ||||||||||||
Contract Description: | PAVEMENT REHABILITATION CITY STREET (SHERIDAN ROAD): FROM ADMIRAL BOULEVARD EXTEND SOUTH. PROJECT LENGTH = 2.926 MILES. | ||||||||||||
Primary County: | TULSA | ||||||||||||
Name of Road: | CITY STREET | ||||||||||||
Prime Contractor: | BECCO CONTRACTORS, INC. | ||||||||||||
P.O. BOX 9159 | |||||||||||||
TULSA , OK 74157 | |||||||||||||
Surety Company: | MID-CONTINENT CASUALTY COMPANY | ||||||||||||
Date Let: | 11/19/2009 | NTP Effective Date: | 01/04/2010 | Pay Period: | 09/01/2011 TO 09/10/2013 |
Date Awarded: | 12/07/2009 | Date Work Began: | 02/02/2010 | Original Contract Time: | 450 |
Date Contract Executed: | 12/18/2009 | Date Time Stopped: | 10/24/2011 | Current Time Charged: | 630.00 |
Date NTP Issued: | 12/22/2009 | Completion Date: | 10/24/2011 | Current Time Allowed: | 696.00 |
General Liability Expires: | 03/01/2014 | Workman's Comp Expires: | 02/01/2014 | Percent Time Used: | 90.52 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $4,513,724.62 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $4,374,893.50 | Participating: | $3,545,132.08 | $3,477,010.35 | $68,121.73 | ||
Percent Complete: | 99.97 % | Non Participating: | $930,104.82 | $923,500.83 | $6,603.99 | ||
Funds Available: | $1,224.28 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $-137,606.84 | Total Earnings: | $4,475,236.90 | $4,400,511.18 | $74,725.72 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $4,475,236.90 | $4,400,511.18 | $74,725.72 | ||||
Other Adjustments: | $37,263.44 | $17,363.44 | $19,900.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $4,512,500.34 | $4,417,874.62 | $94,625.72 |
Contract ID: | 090644 | Estimate Number: | 0035 | Primary JP: | 26703(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Change to start time | Approved | 05/07/2010 | 30.0 | $0.00 |
002 | Fire extinguisher water lines | Approved | 05/23/2011 | 30.0 | $43,012.33 |
003 | Final Quantity Change Order | Approved | 09/09/2013 | 0.0 | $95,818.79 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
Withhold to Funds Avail(Prog. Est. Only) | 0034 | $-19,900.00 |
Withhold to Funds Avail(Prog. Est. Only) | 0035 | $19,900.00 | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
26705(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $463.84 |
26705(04) | 0006 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | * HMA Deduction as per Sec. 411 | 0032 | 0.00 | $0.00 | $-1,224.30 |
26705(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $15,922.82 |
26705(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Asphalt Binder Adjustment | 0035 | 0.00 | $0.00 | $16.56 |
26705(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0035 | -2.49 | $6.64 | $-16.56 |
26968(04) | 0007 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $1,317.68 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0009 | 0.00 | $0.00 | $58.54 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0025 | 1,114.58 | $2.20 | $2,462.33 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0027 | 157.87 | $2.20 | $348.77 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0032 | 1,251.06 | $7.84 | $9,819.82 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $-5,884.10 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | Asphalt Binder Adjustment | 0035 | -0.84 | $6.64 | $-5.59 |
26703(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | * Asphalt Binder Adjustment | 0035 | 0.00 | $0.00 | $5.59 |
26705(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $7,530.88 |
26705(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0035 | -0.56 | $7.34 | $-4.11 |
26705(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | * Asphalt Binder Adjustment | 0035 | 0.00 | $0.00 | $4.11 |
26968(04) | 0008 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $782.63 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0010 | 0.00 | $0.00 | $1,341.31 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0011 | 0.00 | $0.00 | $1,261.07 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0016 | 0.00 | $0.00 | $904.14 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0017 | 0.00 | $0.00 | $16.91 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0022 | 183.40 | $1.77 | $325.87 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0026 | 227.46 | $2.43 | $554.85 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0027 | 1,069.00 | $2.43 | $2,607.64 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | * Asphalt Binder Adjustment | 0032 | 0.00 | $0.00 | $6,024.75 |
26703(04) | 0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | Asphalt Binder Adjustment | 0032 | -850.60 | $8.66 | $-7,372.01 |
26705(04) | 0012 | FABRIC REINFORCEMENT | * Material Discrepancy Adjustments | 0028 | -23,590.00 | $1.50 | $-35,385.00 |
26705(04) | 0012 | FABRIC REINFORCEMENT | * Material Discrepancy Adjustments | 0032 | 23,590.00 | $1.50 | $35,385.00 |
26968(04) | 0012 | FABRIC REINFORCEMENT | * Material Discrepancy Adjustments | 0028 | -3,700.00 | $2.00 | $-7,400.00 |
26968(04) | 0012 | FABRIC REINFORCEMENT | * Material Discrepancy Adjustments | 0032 | 3,700.00 | $2.00 | $7,400.00 |
26703(04) | 0013 | FABRIC REINFORCEMENT | * Material Discrepancy Adjustments | 0028 | -22,816.00 | $1.50 | $-34,224.00 |
26703(04) | 0013 | FABRIC REINFORCEMENT | * Material Discrepancy Adjustments | 0032 | 22,816.00 | $1.50 | $34,224.00 |
26703(04) | 0017 | INLET CICI DES. 2 (STD) | * Material Discrepancy Adjustments | 0028 | -14.00 | $2,700.00 | $-37,800.00 |
26703(04) | 0017 | INLET CICI DES. 2 (STD) | * Material Discrepancy Adjustments | 0032 | 14.00 | $2,700.00 | $37,800.00 |
26968(04) | 0017 | INLET CICI DES. 2 (STD) | * Material Discrepancy Adjustments | 0028 | -4.00 | $2,700.00 | $-10,800.00 |
26968(04) | 0017 | INLET CICI DES. 2 (STD) | * Material Discrepancy Adjustments | 0032 | 4.00 | $2,700.00 | $10,800.00 |
26705(04) | 0018 | INLET CICI DES. 2 (STD) | * Material Discrepancy Adjustments | 0028 | -4.00 | $3,000.00 | $-12,000.00 |
26705(04) | 0018 | INLET CICI DES. 2 (STD) | * Material Discrepancy Adjustments | 0032 | 4.00 | $3,000.00 | $12,000.00 |
26703(04) | 0019 | INLET FRM&GRT (SSIF-FRM,CIG-GRT-RVG-F) | * Material Discrepancy Adjustments | 0007 | -4.00 | $300.00 | $-1,200.00 |
26703(04) | 0019 | INLET FRM&GRT (SSIF-FRM,CIG-GRT-RVG-F) | * Material Discrepancy Adjustments | 0011 | 4.00 | $300.00 | $1,200.00 |
26703(04) | 0020 | CAST IRON CURB INLETS | * Material Discrepancy Adjustments | 0007 | -4.00 | $250.00 | $-1,000.00 |
26703(04) | 0020 | CAST IRON CURB INLETS | * Material Discrepancy Adjustments | 0011 | 4.00 | $250.00 | $1,000.00 |
26968(04) | 0040 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0028 | -108.00 | $1.10 | $-118.80 |
26968(04) | 0040 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0032 | 108.00 | $1.10 | $118.80 |
26705(04) | 0043 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0007 | -1,787.00 | $1.10 | $-1,965.70 |
26705(04) | 0043 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0028 | 1,787.00 | $1.10 | $1,965.70 |
26703(04) | 0047 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0007 | -630.00 | $1.10 | $-693.00 |
26703(04) | 0047 | REINFORCING STEEL | * Material Discrepancy Adjustments | 0028 | 630.00 | $1.10 | $693.00 |
26703(04) | 0068 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | * Material Discrepancy Adjustments | 0029 | -0.50 | $5,000.00 | $-2,500.00 |
26703(04) | 0068 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | * Material Discrepancy Adjustments | 0030 | 0.50 | $5,000.00 | $2,500.00 | Subtotals For Line Item Adjustments | $37,263.44 | * = User applied Line Item Adjustments |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 090644 | Estimate Number: | 0035 | Primary JP: | 26703(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0100/ROADWAY - STP-STIM(284)IG | ||||||||
0001 | CLEARING AND GRUBBING | 201 0102 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0002 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 1,552.000 | 1,552.000 | 1,552.000 | $10.00 | $0.00 | $15,520.00 | |
0003 | TEMPORARY BALE BARRIER | 222 2801 | LF | 100.000 | 88.000 | 88.000 | $3.00 | $0.00 | $264.00 | |
0004 | TEMPORARY SILT FENCE | 223 2801 | LF | 1,800.000 | 0.000 | 0.000 | $1.00 | $0.00 | $0.00 | |
0005 | SOLID SLAB SODDING | 230(A) 2806 | SY | 2,698.000 | 2,563.730 | 25.400 | 2,563.730 | $1.50 | $38.10 | $3,845.60 |
0006 | AGGREGATE BASE | 303 0192 | CY | 1,821.000 | 1,740.200 | 113.040 | 1,740.200 | $45.00 | $5,086.80 | $78,309.00 |
0007 | SUBGRADE, METHOD B | 310(B) 0149 | SY | 6,534.000 | 3,906.910 | 25.610 | 3,906.910 | $0.20 | $5.12 | $781.38 |
0008 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 2,488.000 | 2,535.710 | -0.840 | 2,535.710 | $73.00 | $-61.32 | $185,106.83 |
0009 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | 411(S5) 5975 | TON | 1,244.000 | 1,416.170 | 1,416.170 | $60.00 | $0.00 | $84,970.20 | |
0010 | (SP)FULL DEPTH P.C.C. PATCH(PLACEMENT) | 414(N) 5800 | SY | 5,773.000 | 3,872.910 | -8.390 | 3,872.910 | $38.00 | $-318.82 | $147,170.58 |
0011 | (SP)P.C. CONCRETE FOR PAVEMENT | 414(P) 6000 | CY | 1,294.000 | 864.870 | 37.570 | 864.870 | $120.00 | $4,508.40 | $103,784.40 |
0012 | COLD MILLING PAVEMENT | 417 5267 | SY | 21,638.000 | 27,566.740 | -509.260 | 27,566.740 | $1.65 | $-840.28 | $45,485.12 |
0013 | FABRIC REINFORCEMENT | 420(A) 4242 | SY | 21,638.000 | 21,396.040 | -2,735.960 | 21,396.040 | $1.50 | $-4,103.94 | $32,094.06 |
0014 | COMBINED CURB & GUTTER (6" BARRIER) | 609(B) 0383 | LF | 3,649.000 | 2,600.000 | 28.000 | 2,600.000 | $15.00 | $420.00 | $39,000.00 |
0015 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 943.000 | 1,421.210 | -1.590 | 1,421.210 | $75.00 | $-119.25 | $106,590.75 |
0016 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 167.000 | 774.960 | 4.260 | 774.960 | $66.00 | $281.16 | $51,147.36 |
0017 | INLET CICI DES. 2 (STD) | 611(E) 5112 | EA | 9.000 | 20.000 | 20.000 | $2,700.00 | $0.00 | $54,000.00 | |
0018 | INLET CICI DES. 2 (ADD'L DEPTH) | 611(F) 5325 | VF | 1.000 | 1.000 | 1.000 | $285.00 | $0.00 | $285.00 | |
0019 | INLET FRM&GRT (SSIF-FRM,CIG-GRT-RVG-F) | 611(G) 4489 | EA | 18.000 | 40.000 | 2.000 | 40.000 | $300.00 | $600.00 | $12,000.00 |
0020 | CAST IRON CURB INLETS | 611(K) 4488 | EA | 18.000 | 40.000 | 2.000 | 40.000 | $250.00 | $500.00 | $10,000.00 |
0021 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 25.000 | 27.000 | -2.000 | 27.000 | $1,000.00 | $-2,000.00 | $27,000.00 |
0022 | INLETS ADJUST TO GRADE | 612(E) 0645 | EA | 5.000 | 1.000 | 1.000 | $1,500.00 | $0.00 | $1,500.00 | |
0023 | VALVE BOXES ADJUST TO GRADE | 612(G) 0647 | EA | 10.000 | 4.000 | 1.000 | 4.000 | $300.00 | $300.00 | $1,200.00 |
0024 | METER BOXES ADJUST TO GRADE | 612(H) 0648 | EA | 6.000 | 4.000 | -1.000 | 4.000 | $300.00 | $-300.00 | $1,200.00 |
0025 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 3,649.000 | 2,601.000 | 233.000 | 2,601.000 | $3.00 | $699.00 | $7,803.00 |
0026 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 161.000 | 139.390 | -0.010 | 139.390 | $9.00 | $-0.09 | $1,254.51 |
0027 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 323.000 | 101.410 | 0.010 | 101.410 | $9.00 | $0.09 | $912.69 |
0028 | REMOVAL OF DRAINAGE INLETS | 619(B) 4741 | EA | 9.000 | 20.000 | 2.000 | 20.000 | $350.00 | $700.00 | $7,000.00 |
0029 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 167.000 | 846.950 | 4.250 | 846.950 | $9.00 | $38.25 | $7,622.55 |
0030 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 934.000 | 1,461.840 | -38.860 | 1,461.840 | $7.00 | $-272.02 | $10,232.88 |
8030 | ASPHALT BINDER PRICE ADJUSTMENT | 109 1150 | LSUM | 0.000 | 1.000 | 0.000 | $12,469.89 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY - STP-STIM(284)IG | $5,161.20 | $1,038,079.91 | ||||||||
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0300/TRAFFIC - STP-STIM(284)IG | ||||||||
0031 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 11,547.000 | 11,456.000 | -452.000 | 11,456.000 | $1.00 | $-452.00 | $11,456.00 |
0032 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 2.000 | 2.000 | 2.000 | $100.00 | $0.00 | $200.00 | |
0033 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 856(A) 8839 | LF | 14,463.000 | 43,764.000 | 115.000 | 43,764.000 | $0.16 | $18.40 | $7,002.24 |
0034 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 14,463.000 | 6,884.000 | 6,884.000 | $0.11 | $0.00 | $757.24 | |
0035 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 5,000.000 | 12,389.000 | 28.000 | 12,389.000 | $0.50 | $14.00 | $6,194.50 |
0036 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 5,000.000 | 11,439.000 | 20.000 | 11,439.000 | $0.90 | $18.00 | $10,295.10 |
0037 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 10,000.000 | 16,594.000 | 27.000 | 16,594.000 | $1.10 | $29.70 | $18,253.40 |
0038 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 5,000.000 | 9,789.000 | 20.000 | 9,789.000 | $1.10 | $22.00 | $10,767.90 |
0039 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 20,000.000 | 35,071.000 | 1,086.000 | 35,071.000 | $0.11 | $119.46 | $3,857.81 |
0040 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 12,000.000 | 5,780.000 | 6.000 | 5,780.000 | $0.02 | $0.12 | $115.60 |
0041 | DRUMS | 880(F) 8878 | SD | 12,000.000 | 68,572.000 | 5,932.000 | 68,572.000 | $0.55 | $3,262.60 | $37,714.60 |
Subtotals For Category 0300/TRAFFIC - STP-STIM(284)IG | $3,032.28 | $106,614.39 | ||||||||
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0301/TRAFFIC SIGNALS - STP-STIM(284)IG | ||||||||
0042 | (PL)HDPE CONDUIT BORED | 802(B) 8550 | LF | 407.000 | 718.000 | 311.000 | 718.000 | $11.00 | $3,421.00 | $7,898.00 |
0043 | (PL)HDPE CONDUIT TRENCHED | 802(B) 8555 | LF | 32.000 | 194.000 | 162.000 | 194.000 | $5.50 | $891.00 | $1,067.00 |
0044 | PULL BOX(SIZE II) | 803 8066 | EA | 3.000 | 3.000 | 3.000 | $435.00 | $0.00 | $1,305.00 | |
0045 | PULL BOX(SIZE III) | 803 8067 | EA | 1.000 | 1.000 | 1.000 | $550.00 | $0.00 | $550.00 | |
0046 | STRUCTURAL CONCRETE | 804(A) 2915 | CY | 4.200 | 4.200 | 4.200 | $435.00 | $0.00 | $1,827.00 | |
0047 | REINFORCING STEEL | 804(B) 2916 | LB | 630.000 | 630.000 | 630.000 | $1.10 | $0.00 | $693.00 | |
0048 | 32'MH POLE 25'TS & 8'LMA(G.STL.) | 806(A) 8286 | EA | 4.000 | 4.000 | 4.000 | $4,700.00 | $0.00 | $18,800.00 | |
0049 | SERVICE POLE | 810(A) 3118 | EA | 1.000 | 1.000 | 1.000 | $1,300.00 | $0.00 | $1,300.00 | |
0050 | 1/C NO.6 ELECTRICAL CONDUCTOR | 811 8040 | LF | 290.000 | 644.000 | 151.000 | 644.000 | $0.55 | $83.05 | $354.20 |
0051 | 1/C NO.12 ELECTRICAL CONDUCTOR | 811 8046 | LF | 390.000 | 912.000 | -76.000 | 912.000 | $0.30 | $-22.80 | $273.60 |
0052 | VEH.ACT.SOL.ST.TRAF.SIG.CON.ASM | 825 8550 | EA | 1.000 | 1.000 | 1.000 | $16,500.00 | $0.00 | $16,500.00 | |
0053 | (PL)DETECTION SYSTEM (VIDEO) | 828 8132 | LSUM | 1.000 | 1.000 | 1.000 | $30,500.00 | $0.00 | $30,500.00 | |
0054 | PEDESTRIAN PUSH BUTTON | 830 8000 | EA | 8.000 | 8.000 | 8.000 | $165.00 | $0.00 | $1,320.00 | |
0055 | 1WAY 3SEC. ADJ. SIG. HD. S-6 | 831 8231 | EA | 8.000 | 8.000 | 8.000 | $680.00 | $0.00 | $5,440.00 | |
0056 | 1WAY 2SEC. ADJ. PED. SIG. HD. S-20 | 831 8295 | EA | 8.000 | 8.000 | 8.000 | $800.00 | $0.00 | $6,400.00 | |
0057 | 5/C TRAF.SIG.ELECT.CABLE | 834(A) 8207 | LF | 308.000 | 75.000 | -233.000 | 75.000 | $0.80 | $-186.40 | $60.00 |
0058 | 7/C TRAF.SIG.ELECT.CABLE | 834(A) 8208 | LF | 478.000 | 849.000 | 281.000 | 849.000 | $1.10 | $309.10 | $933.90 |
0059 | 21/C TRAF.SIG.EL.CABLE | 834(A) 8213 | LF | 390.000 | 644.000 | 76.000 | 644.000 | $1.40 | $106.40 | $901.60 |
0060 | 2/C SHIELDED LOOP DETECTOR LEAD-IN CABLE | 834(B) 8220 | LF | 587.000 | 684.000 | 418.000 | 684.000 | $0.55 | $229.90 | $376.20 |
0061 | (PL)E.P.S. OPTICAL DETECTOR | 840(B) 8593 | EA | 2.000 | 2.000 | 2.000 | $980.00 | $0.00 | $1,960.00 | |
0062 | (PL)E.P.S. OPTICAL DETECTOR CABLE | 840(C) 8594 | LF | 190.000 | 279.000 | -11.000 | 279.000 | $1.10 | $-12.10 | $306.90 |
0063 | (PL)E.P.S. 2 CHANNEL PHASE SELECTOR | 840(D) 8595 | EA | 1.000 | 1.000 | 1.000 | $2,200.00 | $0.00 | $2,200.00 | |
0064 | MAST ARM MOUNTED SIGNS(ALUMINUM) | 850(C) 8118 | SF | 42.700 | 50.680 | 7.980 | 50.680 | $16.00 | $127.68 | $810.88 |
0065 | (PL)SPECIAL SIGNS | 850(D) 8121 | EA | 2.000 | 2.000 | 2.000 | $1,800.00 | $0.00 | $3,600.00 | |
0066 | (PL)REMOVAL OF TRAFFIC SIGNAL EQUIPMENT | 890(A) 8726 | LSUM | 1.000 | 1.000 | 1.000 | $1,100.00 | $0.00 | $1,100.00 | |
Subtotals For Category 0301/TRAFFIC SIGNALS - STP-STIM(284)IG | $4,946.83 | $106,477.28 | ||||||||
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0600/STAKING - STP-STIM(284)IG | ||||||||
0067 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 1.000 | $50,000.00 | $0.00 | $50,000.00 | |
Subtotals For Category 0600/STAKING - STP-STIM(284)IG | $0.00 | $50,000.00 | ||||||||
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0640/CONSTRUCTION - STP-STIM(284)IG | ||||||||
0068 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 1.000 | $5,000.00 | $0.00 | $5,000.00 | |
0069 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $140,000.00 | $0.00 | $140,000.00 | |
Subtotals For Category 0640/CONSTRUCTION - STP-STIM(284)IG | $0.00 | $145,000.00 | ||||||||
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0900/NON-PARTICIPATING (WATERLINE) - STP-STIM(284)IG | ||||||||
0070 | CLEARING AND GRUBBING | 201 0102 | LSUM | 1.000 | 1.000 | 0.250 | 1.000 | $2,000.00 | $500.00 | $2,000.00 |
0071 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 900.000 | 1,140.800 | 2.500 | 1,140.800 | $10.00 | $25.00 | $11,408.00 |
0072 | 6" WATER LINE CONNECTION | 616 0132 | EA | 8.000 | 6.000 | 6.000 | $500.00 | $0.00 | $3,000.00 | |
0073 | 6" DUCTILE IRON PIPE | 616(A) 5121 | LF | 1,861.000 | 1,905.000 | -47.000 | 1,905.000 | $40.00 | $-1,880.00 | $76,200.00 |
0074 | 6" DUCTILE IRON PIPE RESTRAINED JOINT | 616(A) 5810 | LF | 174.000 | 201.000 | -8.000 | 201.000 | $46.00 | $-368.00 | $9,246.00 |
0075 | 3/4" COPPER WATER SERVICE PIPE | 616(C) 0868 | LF | 16.000 | 0.000 | 0.000 | $9.00 | $0.00 | $0.00 | |
0076 | 1" COPPER WATER SERVICE PIPE | 616(C) 0869 | LF | 5.000 | 0.000 | 0.000 | $12.00 | $0.00 | $0.00 | |
0077 | 1 1/2" COPPER WATER SERVICE PIPE | 616(C) 0871 | LF | 6.000 | 0.000 | 0.000 | $17.00 | $0.00 | $0.00 | |
0078 | 6" GATE VALVE | 616(D) 1070 | EA | 12.000 | 14.000 | 14.000 | $1,100.00 | $0.00 | $15,400.00 | |
0079 | 12" GATE VALVE | 616(D) 1100 | EA | 1.000 | 1.000 | 1.000 | $2,800.00 | $0.00 | $2,800.00 | |
0080 | STANDARD VALVE BOX | 616(D) 7051 | EA | 13.000 | 13.000 | -1.000 | 13.000 | $160.00 | $-160.00 | $2,080.00 |
0081 | FIRE HYDRANTS | 616(G) 1192 | EA | 2.000 | 2.000 | 2.000 | $2,300.00 | $0.00 | $4,600.00 | |
0082 | FIRE HYDRANT EXTENSION | 616(G) 1193 | EA | 1.000 | 1.000 | 1.000 | $400.00 | $0.00 | $400.00 | |
0083 | 2" SOLID SLEEVE | 616(I) 0010 | EA | 1.000 | 1.000 | 1.000 | $260.00 | $0.00 | $260.00 | |
0084 | 4" SOLID SLEEVE | 616(I) 0014 | EA | 1.000 | 0.000 | 0.000 | $370.00 | $0.00 | $0.00 | |
0085 | 6" SOLID SLEEVE | 616(I) 0018 | EA | 3.000 | 3.000 | -1.000 | 3.000 | $550.00 | $-550.00 | $1,650.00 |
0086 | 12" SOLID SLEEVE | 616(I) 0024 | EA | 1.000 | 1.000 | 1.000 | 1.000 | $1,200.00 | $1,200.00 | $1,200.00 |
0087 | 6" X 6" X 6" TEE | 616(J) 0022 | EA | 6.000 | 6.000 | 6.000 | $500.00 | $0.00 | $3,000.00 | |
0088 | 12" X 12" X 6" TEE | 616(J) 0030 | EA | 1.000 | 1.000 | 1.000 | $900.00 | $0.00 | $900.00 | |
0089 | 4" 45 DEGREE FITTING | 616(K) 0038 | EA | 2.000 | 0.000 | 0.000 | $250.00 | $0.00 | $0.00 | |
0090 | 6" 45 DEGREE FITTING | 616(K) 0042 | EA | 12.000 | 18.000 | 18.000 | $350.00 | $0.00 | $6,300.00 | |
0091 | 6" X 4" REDUCER | 616(L) 0070 | EA | 2.000 | 1.000 | 1.000 | $250.00 | $0.00 | $250.00 | |
0092 | SHORT WATER SERVICE & RESET METER | 616(N) 0094 | EA | 4.000 | 3.000 | 1.000 | 3.000 | $1,100.00 | $1,100.00 | $3,300.00 |
0093 | LONG WATER SERVICE & RESET METER | 616(N) 0096 | EA | 1.000 | 1.000 | 1.000 | $3,000.00 | $0.00 | $3,000.00 | |
Subtotals For Category 0900/NON-PARTICIPATING (WATERLINE) - STP-STIM(284)IG | $-133.00 | $146,994.00 | ||||||||
Fed/State Project Number: STP-STIM(284)IG | Project: 26703(04) | Category: 0910/NON-PARTICIPATING (SANITARY SEWER ALTERNATE)-STP-STIM(284)IG | ||||||||
0094 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 550.000 | 281.490 | 1.490 | 281.490 | $25.00 | $37.25 | $7,037.25 |
0095 | (SP)FULL DEPTH P.C.C. PATCH(PLACEMENT) | 414(N) 5800 | SY | 348.000 | 238.220 | 2.220 | 238.220 | $38.00 | $84.36 | $9,052.36 |
0096 | (SP)P.C. CONCRETE FOR PAVEMENT | 414(P) 6000 | CY | 78.000 | 44.030 | 1.030 | 44.030 | $120.00 | $123.60 | $5,283.60 |
0097 | COMBINED CURB & GUTTER (6" BARRIER) | 609(B) 0383 | LF | 178.000 | 204.000 | -3.000 | 204.000 | $25.00 | $-75.00 | $5,100.00 |
0098 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 77.000 | 140.000 | 7.000 | 140.000 | $75.00 | $525.00 | $10,500.00 |
0099 | MANHOLE (4' DIAMETER) | 611(A) 2657 | EA | 1.000 | 0.000 | 0.000 | $3,000.00 | $0.00 | $0.00 | |
0100 | MANHOLE (5' DIAMETER) | 611(A) 2658 | EA | 1.000 | 2.000 | 2.000 | $5,000.00 | $0.00 | $10,000.00 | |
0101 | SANITARY SEWER SERVICE CONNECTION | 615(D) 0300 | EA | 9.000 | 6.000 | 6.000 | $1,500.00 | $0.00 | $9,000.00 | |
0102 | 8" DUCTILE IRON PIPE | 616(A) 5122 | LF | 66.000 | 164.500 | 164.500 | $75.00 | $0.00 | $12,337.50 | |
0103 | 12" DUCTILE IRON PIPE | 616(A) 5124 | LF | 190.000 | 212.000 | 212.000 | $100.00 | $0.00 | $21,200.00 | |
0104 | 18" DUCTILE IRON PIPE | 616(A) 5125 | LF | 243.000 | 237.000 | 237.000 | $175.00 | $0.00 | $41,475.00 | |
Subtotals For Category 0910/NON-PARTICIPATING (SANITARY SEWER ALTERNATE)-STP-STIM(284)IG | $695.21 | $130,985.71 | ||||||||
Subtotals For Project STP-STIM(284)IG /26703(04) | $13,702.52 | $1,724,151.29 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(286)IG | Project: 26705(04) | Category: 0100/ROADWAY - STP-STIM(286)IG | ||||||||
0001 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 2,261.000 | 0.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0002 | TEMPORARY BALE BARRIER | 222 2801 | LF | 1,000.000 | 0.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0003 | SOLID SLAB SODDING | 230(A) 2806 | SY | 434.000 | 3,100.050 | -111.040 | 3,100.050 | $1.50 | $-166.56 | $4,650.08 |
0004 | AGGREGATE BASE | 303 0192 | CY | 2,261.000 | 1,244.470 | 27.390 | 1,244.470 | $45.00 | $1,232.55 | $56,001.15 |
0005 | SUBGRADE, METHOD B | 310(B) 0149 | SY | 7,110.000 | 3,033.690 | -2.310 | 3,033.690 | $0.20 | $-0.46 | $606.74 |
0006 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | 411(S3) 6210 | TON | 616.000 | 157.300 | 157.300 | $115.00 | $0.00 | $18,089.50 | |
0007 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 5,761.000 | 4,027.000 | -2.490 | 4,027.000 | $73.00 | $-181.77 | $293,971.00 |
0008 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | 411(S5) 5975 | TON | 1,060.000 | 1,995.650 | -0.560 | 1,995.650 | $60.00 | $-33.60 | $119,739.00 |
0009 | (SP)FULL DEPTH P.C.C. PATCH(PLACEMENT) | 414(N) 5800 | SY | 4,647.000 | 3,033.690 | -4.310 | 3,033.690 | $38.00 | $-163.78 | $115,280.22 |
0010 | (SP)P.C. CONCRETE FOR PAVEMENT | 414(P) 6000 | CY | 1,162.000 | 677.530 | 6.530 | 677.530 | $120.00 | $783.60 | $81,303.60 |
0011 | COLD MILLING BITUMINOUS PAVEMENT | 417 4267 | SY | 34,291.000 | 32,685.930 | -417.940 | 32,685.930 | $1.65 | $-689.60 | $53,931.78 |
0012 | FABRIC REINFORCEMENT | 420(A) 4242 | SY | 34,291.000 | 34,705.110 | -618.890 | 34,705.110 | $1.50 | $-928.34 | $52,057.66 |
0013 | CLSM BACKFILL | 501(G) 6315 | CY | 274.000 | 119.020 | -0.980 | 119.020 | $60.00 | $-58.80 | $7,141.20 |
0014 | CONCRETE CURB (8" BARRIER-INTEGRAL) | 609(A) 0380 | LF | 1,912.000 | 2,039.750 | 9.750 | 2,039.750 | $8.00 | $78.00 | $16,318.00 |
0015 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 258.000 | 1,439.560 | 61.460 | 1,439.560 | $120.00 | $7,375.20 | $172,747.20 |
0016 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 645.000 | 1,429.060 | 16.460 | 1,429.060 | $65.00 | $1,069.90 | $92,888.90 |
0017 | BITUMINOUS DRIVEWAY (6") | 610(G) 4475 | SY | 57.000 | 0.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0018 | INLET CICI DES. 2 (STD) | 611(E) 5112 | EA | 7.000 | 9.000 | 9.000 | $3,000.00 | $0.00 | $27,000.00 | |
0019 | INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) | 611(G) 4488 | EA | 16.000 | 38.000 | 38.000 | $400.00 | $0.00 | $15,200.00 | |
0020 | CAST IRON CURB INLETS | 611(K) 4488 | EA | 9.000 | 35.000 | 35.000 | $450.00 | $0.00 | $15,750.00 | |
0021 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 7.000 | 9.000 | 9.000 | $1,000.00 | $0.00 | $9,000.00 | |
0022 | VALVE BOXES ADJUST TO GRADE | 612(G) 0647 | EA | 1.000 | 16.000 | 16.000 | $300.00 | $0.00 | $4,800.00 | |
0023 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 813.000 | 1,429.060 | 13.460 | 1,429.060 | $9.00 | $121.14 | $12,861.54 |
0024 | REMOVAL OF CURB | 619(B) 4791 | LF | 1,912.000 | 1,861.750 | 46.750 | 1,861.750 | $3.00 | $140.25 | $5,585.25 |
0025 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 325.000 | 621.850 | 29.850 | 621.850 | $7.00 | $208.95 | $4,352.95 |
0026 | REMOVAL OF CONCRETE MEDIAN BARRIER | 619(B) 4915 | LF | 682.000 | 682.000 | 682.000 | $6.00 | $0.00 | $4,092.00 | |
8031 | ASPHALT BINDER PRICE ADJUSTMENT | 109 1150 | LSUM | 0.000 | 1.000 | 0.000 | $23,917.54 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY - STP-STIM(286)IG | $8,786.68 | $1,183,367.77 | ||||||||
Fed/State Project Number: STP-STIM(286)IG | Project: 26705(04) | Category: 0300/TRAFFIC - STP-STIM(286)IG | ||||||||
0027 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 26,257.000 | 24,388.000 | -1,143.000 | 24,388.000 | $1.00 | $-1,143.00 | $24,388.00 |
0028 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 16.000 | 14.000 | 14.000 | $90.00 | $0.00 | $1,260.00 | |
0029 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 856(G) 8887 | EA | 10,000.000 | 519.000 | 13.000 | 519.000 | $0.40 | $5.20 | $207.60 |
0030 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 3,500.000 | 1,502.000 | 1,502.000 | $0.11 | $0.00 | $165.22 | |
0031 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 20,000.000 | 10,389.000 | 32.000 | 10,389.000 | $0.02 | $0.64 | $207.78 |
0032 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 20,000.000 | 11,659.000 | 41.000 | 11,659.000 | $0.40 | $16.40 | $4,663.60 |
0033 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 40,000.000 | 10,276.000 | 34.000 | 10,276.000 | $0.02 | $0.68 | $205.52 |
0034 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 20,000.000 | 9,825.000 | 40.000 | 9,825.000 | $0.30 | $12.00 | $2,947.50 |
0035 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 80,000.000 | 29,066.000 | 98.000 | 29,066.000 | $0.02 | $1.96 | $581.32 |
0036 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 50,000.000 | 3,113.000 | -189.000 | 3,113.000 | $0.02 | $-3.78 | $62.26 |
0037 | DRUMS | 880(F) 8878 | SD | 50,000.000 | 77,692.000 | -56.000 | 77,692.000 | $0.16 | $-8.96 | $12,430.72 |
Subtotals For Category 0300/TRAFFIC - STP-STIM(286)IG | $-1,118.86 | $47,119.52 | ||||||||
Fed/State Project Number: STP-STIM(286)IG | Project: 26705(04) | Category: 0301/TRAFFIC SIGNAL - STP-STIM(286)IG | ||||||||
0038 | 3" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 802(B) 8346 | LF | 115.000 | 165.000 | 50.000 | 165.000 | $5.50 | $275.00 | $907.50 |
0039 | (PL)HDPE CONDUIT BORED | 802(B) 8550 | LF | 365.000 | 892.000 | 527.000 | 892.000 | $16.00 | $8,432.00 | $14,272.00 |
0040 | PULL BOX(SIZE II) | 803 8066 | EA | 3.000 | 3.000 | 3.000 | $435.00 | $0.00 | $1,305.00 | |
0041 | PULL BOX(SIZE III) | 803 8067 | EA | 1.000 | 1.000 | 1.000 | $550.00 | $0.00 | $550.00 | |
0042 | STRUCTURAL CONCRETE | 804(A) 2915 | CY | 11.800 | 9.270 | -2.530 | 9.270 | $435.00 | $-1,100.55 | $4,032.45 |
0043 | REINFORCING STEEL | 804(B) 2916 | LB | 1,787.000 | 1,348.210 | -438.790 | 1,348.210 | $1.10 | $-482.67 | $1,483.04 |
0044 | POLE & 35' TS MST.ARM(G.STL.) | 806(A) 8730 | EA | 3.000 | 3.000 | 3.000 | $5,400.00 | $0.00 | $16,200.00 | |
0045 | POLE & 40' TS MST.ARM(G.STL.) | 806(A) 8732 | EA | 1.000 | 1.000 | 1.000 | $6,700.00 | $0.00 | $6,700.00 | |
0046 | SERVICE POLE | 810(A) 3118 | EA | 1.000 | 1.000 | 1.000 | $1,300.00 | $0.00 | $1,300.00 | |
0047 | 1/C NO.6 ELECTRICAL CONDUCTOR | 811 8040 | LF | 435.000 | 666.000 | 41.000 | 666.000 | $0.55 | $22.55 | $366.30 |
0048 | 1/C NO.12 ELECTRICAL CONDUCTOR | 811 8046 | LF | 515.000 | 1,057.000 | 111.000 | 1,057.000 | $0.30 | $33.30 | $317.10 |
0049 | (PL)TRAFFIC SIGNAL SPAN WIRE EQUIPMENT | 823 8482 | LSUM | 1.000 | 1.000 | 1.000 | $2,700.00 | $0.00 | $2,700.00 | |
0050 | VEH.ACT.SOL.ST.TRAF.SIG.CON.ASM | 825 8550 | EA | 1.000 | 1.000 | 1.000 | $16,000.00 | $0.00 | $16,000.00 | |
0051 | (PL)DETECTION SYSTEM (VIDEO) | 828 8132 | LSUM | 1.000 | 1.000 | 1.000 | $31,000.00 | $0.00 | $31,000.00 | |
0052 | PEDESTRIAN PUSH BUTTON | 830 8000 | EA | 8.000 | 8.000 | 8.000 | $135.00 | $0.00 | $1,080.00 | |
0053 | 1WAY 3SEC. ADJ. SIG. HD. S-6 | 831 8231 | EA | 8.000 | 8.000 | 8.000 | $680.00 | $0.00 | $5,440.00 | |
0054 | 1WAY 5SEC. ADJ. SIG. HD. S-19 | 831 8286 | EA | 5.000 | 5.000 | 5.000 | $980.00 | $0.00 | $4,900.00 | |
0055 | 1WAY 2SEC. ADJ. PED. SIG. HD. S-20 | 831 8295 | EA | 8.000 | 8.000 | 8.000 | $780.00 | $0.00 | $6,240.00 | |
0056 | BACKPLATE | 833 3030 | EA | 13.000 | 13.000 | 13.000 | $11.00 | $0.00 | $143.00 | |
0057 | 5/C TRAF.SIG.ELECT.CABLE | 834(A) 8207 | LF | 340.000 | 264.000 | -76.000 | 264.000 | $0.80 | $-60.80 | $211.20 |
0058 | 7/C TRAF.SIG.ELECT.CABLE | 834(A) 8208 | LF | 270.000 | 293.000 | 23.000 | 293.000 | $1.10 | $25.30 | $322.30 |
0059 | 9/C TRAF.SIG.EL.CABLE | 834(A) 8209 | LF | 600.000 | 805.000 | 180.000 | 805.000 | $1.35 | $243.00 | $1,086.75 |
0060 | 21/C TRAF.SIG.EL.CABLE | 834(A) 8213 | LF | 515.000 | 701.000 | 76.000 | 701.000 | $1.35 | $102.60 | $946.35 |
0061 | 2/C SHIELDED LOOP DETECTOR LEAD-IN CABLE | 834(B) 8220 | LF | 45.000 | 40.000 | -5.000 | 40.000 | $0.55 | $-2.75 | $22.00 |
0062 | (PL)E.P.S. OPTICAL DETECTOR | 840(B) 8593 | EA | 2.000 | 2.000 | 2.000 | $980.00 | $0.00 | $1,960.00 | |
0063 | (PL)E.P.S. OPTICAL DETECTOR CABLE | 840(C) 8594 | LF | 245.000 | 339.000 | 54.000 | 339.000 | $1.10 | $59.40 | $372.90 |
0064 | (PL)E.P.S. 2 CHANNEL PHASE SELECTOR | 840(D) 8595 | EA | 2.000 | 2.000 | 2.000 | $2,200.00 | $0.00 | $4,400.00 | |
0065 | MAST ARM MOUNTED SIGNS(ALUMINUM) | 850(C) 8118 | SF | 72.000 | 72.000 | 72.000 | $16.00 | $0.00 | $1,152.00 | |
0066 | (PL)REMOVAL OF TRAFFIC SIGNAL EQUIPMENT | 890(A) 8726 | LSUM | 1.000 | 1.000 | 1.000 | $1,100.00 | $0.00 | $1,100.00 | |
Subtotals For Category 0301/TRAFFIC SIGNAL - STP-STIM(286)IG | $7,546.38 | $126,509.89 | ||||||||
Fed/State Project Number: STP-STIM(286)IG | Project: 26705(04) | Category: 0900/NON-PARTICIPATING (WATERLINE) - STP-STIM(286)IG | ||||||||
0067 | CLEARING AND GRUBBING | 201 0102 | LSUM | 1.000 | 1.000 | 1.000 | $2,000.00 | $0.00 | $2,000.00 | |
0068 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 1,396.000 | 3,400.110 | -120.890 | 3,400.110 | $10.00 | $-1,208.90 | $34,001.10 |
0069 | SOLID SLAB SODDING | 230(A) 2806 | SY | 867.000 | 1,139.430 | 2.430 | 1,139.430 | $1.50 | $3.65 | $1,709.15 |
0070 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | 411(S3) 6210 | TON | 54.000 | 0.000 | 0.000 | $120.00 | $0.00 | $0.00 | |
0071 | (SP)FULL DEPTH P.C.C. PATCH(PLACEMENT) | 414(N) 5800 | SY | 349.000 | 423.040 | -17.960 | 423.040 | $50.00 | $-898.00 | $21,152.00 |
0072 | (SP)P.C. CONCRETE FOR PAVEMENT | 414(P) 6000 | CY | 88.000 | 94.500 | -3.500 | 94.500 | $120.00 | $-420.00 | $11,340.00 |
0073 | 8" PLUG | 616 0110 | EA | 2.000 | 2.000 | 2.000 | $330.00 | $0.00 | $660.00 | |
0074 | 8" DUCTILE IRON PIPE | 616(A) 5122 | LF | 145.000 | 179.000 | 3.000 | 179.000 | $46.00 | $138.00 | $8,234.00 |
0075 | 12" DUCTILE IRON PIPE | 616(A) 5124 | LF | 3,588.000 | 3,466.000 | -76.000 | 3,466.000 | $58.00 | $-4,408.00 | $201,028.00 |
0076 | 6" DUCTILE IRON PIPE RESTRAINED JOINT | 616(A) 5810 | LF | 175.000 | 240.000 | 240.000 | $46.00 | $0.00 | $11,040.00 | |
0077 | 3/4" COPPER WATER SERVICE PIPE | 616(C) 0868 | LF | 430.000 | 37.000 | 37.000 | $9.00 | $0.00 | $333.00 | |
0078 | 1" COPPER WATER SERVICE PIPE | 616(C) 0869 | LF | 205.000 | 21.000 | 21.000 | $12.00 | $0.00 | $252.00 | |
0079 | 1 1/2" COPPER WATER SERVICE PIPE | 616(C) 0871 | LF | 85.000 | 45.000 | 45.000 | $17.00 | $0.00 | $765.00 | |
0080 | 2" COPPER WATER SERVICE PIPE | 616(C) 0872 | LF | 80.000 | 33.000 | 15.000 | 33.000 | $25.00 | $375.00 | $825.00 |
0081 | 2" AIR RELIEF VALVE ASSEMBLY & METER CAN | 616(D) 0767 | EA | 1.000 | 1.000 | 1.000 | $4,000.00 | $0.00 | $4,000.00 | |
0082 | 6" GATE VALVE | 616(D) 1070 | EA | 7.000 | 12.000 | -1.000 | 12.000 | $1,200.00 | $-1,200.00 | $14,400.00 |
0083 | 8" GATE VALVE | 616(D) 1080 | EA | 4.000 | 3.000 | 1.000 | 3.000 | $1,700.00 | $1,700.00 | $5,100.00 |
0084 | 12" GATE VALVE | 616(D) 1100 | EA | 16.000 | 16.000 | 16.000 | $2,900.00 | $0.00 | $46,400.00 | |
0085 | 3/4" CORPORATION STOPS | 616(E) 0878 | EA | 9.000 | 9.000 | 9.000 | $100.00 | $0.00 | $900.00 | |
0086 | 1" CORPORATION STOPS | 616(E) 0879 | EA | 3.000 | 4.000 | 4.000 | $125.00 | $0.00 | $500.00 | |
0087 | 1 1/2" CORPORATION STOPS | 616(E) 0902 | EA | 2.000 | 4.000 | 4.000 | $200.00 | $0.00 | $800.00 | |
0088 | 2" CORPORATION STOPS | 616(E) 0903 | EA | 2.000 | 3.000 | 1.000 | 3.000 | $285.00 | $285.00 | $855.00 |
0089 | (PL)METER INSTALLATION 1" | 616(F) 5208 | EA | 3.000 | 4.000 | 4.000 | $430.00 | $0.00 | $1,720.00 | |
0090 | METER INSTALLATION 1 1/2" | 616(F) 5210 | EA | 2.000 | 4.000 | 4.000 | $1,500.00 | $0.00 | $6,000.00 | |
0091 | METER INSTALLATION 2" | 616(F) 5211 | EA | 2.000 | 3.000 | 1.000 | 3.000 | $1,800.00 | $1,800.00 | $5,400.00 |
0092 | METER INSTALLATION 3/4" | 616(F) 5948 | EA | 9.000 | 5.000 | 5.000 | $680.00 | $0.00 | $3,400.00 | |
0093 | FIRE HYDRANTS | 616(G) 1192 | EA | 5.000 | 7.000 | 7.000 | $2,800.00 | $0.00 | $19,600.00 | |
0094 | 6" SOLID SLEEVE | 616(I) 0018 | EA | 2.000 | 2.000 | 2.000 | $550.00 | $0.00 | $1,100.00 | |
0095 | 8" SOLID SLEEVE | 616(I) 0020 | EA | 4.000 | 3.000 | 3.000 | $725.00 | $0.00 | $2,175.00 | |
0096 | 12" SOLID SLEEVE | 616(I) 0024 | EA | 3.000 | 7.000 | 7.000 | $1,200.00 | $0.00 | $8,400.00 | |
0097 | 12" X 12" X 6" TEE | 616(J) 0030 | EA | 7.000 | 14.000 | 2.000 | 14.000 | $900.00 | $1,800.00 | $12,600.00 |
0098 | 12" X 12" X 8" TEE | 616(J) 0032 | EA | 3.000 | 3.000 | 3.000 | $1,000.00 | $0.00 | $3,000.00 | |
0099 | 6" 45 DEGREE FITTING | 616(K) 0042 | EA | 4.000 | 11.000 | 11.000 | $350.00 | $0.00 | $3,850.00 | |
0100 | 8" 45 DEGREE FITTING | 616(K) 0044 | EA | 6.000 | 6.000 | -2.000 | 6.000 | $450.00 | $-900.00 | $2,700.00 |
0101 | 12" 45 DEGREE FITTING | 616(K) 0047 | EA | 30.000 | 16.000 | 16.000 | $775.00 | $0.00 | $12,400.00 | |
0102 | 12" X 8" REDUCER | 616(L) 0082 | EA | 2.000 | 2.000 | 2.000 | $500.00 | $0.00 | $1,000.00 | |
0103 | 12" X 12" X 12" X 12" CROSS | 616(M) 0082 | EA | 1.000 | 1.000 | 1.000 | $1,500.00 | $0.00 | $1,500.00 | |
0104 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 471.000 | 556.100 | 110.100 | 556.100 | $9.00 | $990.90 | $5,004.90 |
8010 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 0.000 | 11.100 | 11.100 | $7.00 | $0.00 | $77.70 | |
8011 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 0.000 | 153.800 | 153.800 | $9.00 | $0.00 | $1,384.20 | |
8012 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 0.000 | 11.100 | 11.100 | $75.00 | $0.00 | $832.50 | |
8013 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 0.000 | 153.800 | 153.800 | $66.00 | $0.00 | $10,150.80 | |
8014 | REMOVAL OF CURB | 619(B) 4791 | LF | 0.000 | 28.000 | 28.000 | $3.00 | $0.00 | $84.00 | |
8015 | CONC.CURB(6" BARRIER-INTEGRAL) | 609(A) 0300 | LF | 0.000 | 28.000 | 28.000 | $15.00 | $0.00 | $420.00 | |
8016 | SOLID SLAB SODDING | 230(A) 2806 | SY | 0.000 | 582.200 | 582.200 | $1.50 | $0.00 | $873.30 | |
8017 | CONSTRUCTION MISCELLANEOUS | 104 0700 | LSUM | 0.000 | 1.000 | 1.000 | $29,189.83 | $0.00 | $29,189.83 | |
Subtotals For Category 0900/NON-PARTICIPATING (WATERLINE) - STP-STIM(286)IG | $-1,942.35 | $499,156.48 | ||||||||
Fed/State Project Number: STP-STIM(286)IG | Project: 26705(04) | Category: 0910/NON-PARTICIPATING (SANITARY SEWER) - STP-STIM(286)IG | ||||||||
0105 | 8" SEWER PIPE | 615(C) 6121 | LF | 65.000 | 90.000 | 90.000 | $200.00 | $0.00 | $18,000.00 | |
Subtotals For Category 0910/NON-PARTICIPATING (SANITARY SEWER) - STP-STIM(286)IG | $0.00 | $18,000.00 | ||||||||
Subtotals For Project STP-STIM(286)IG /26705(04) | $13,271.85 | $1,874,153.66 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-STIM(482)IG | Project: 26968(04) | Category: 0100/ROADWAY - STP-STIM(482)IG | ||||||||
0001 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 3,332.000 | 2,629.020 | 180.020 | 2,629.020 | $10.00 | $1,800.20 | $26,290.20 |
0002 | TEMPORARY BALE BARRIER | 222 2801 | LF | 100.000 | 0.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0003 | TEMPORARY SEDIMENT FILTER | 224 2803 | EA | 25.000 | 0.000 | 0.000 | $50.00 | $0.00 | $0.00 | |
0004 | SOLID SLAB SODDING | 230(A) 2806 | SY | 620.000 | 1,126.350 | 693.350 | 1,126.350 | $1.50 | $1,040.03 | $1,689.53 |
0005 | AGGREGATE BASE | 303 0192 | CY | 1,975.000 | 1,818.010 | -26.690 | 1,818.010 | $45.00 | $-1,201.05 | $81,810.45 |
0006 | SUBGRADE, METHOD B | 310(B) 0149 | SY | 5,913.000 | 4,706.280 | 304.280 | 4,706.280 | $0.20 | $60.86 | $941.26 |
0007 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 275.000 | 479.950 | 479.950 | $90.00 | $0.00 | $43,195.50 | |
0008 | (SP)ASPHALT CONCRETE TYPE S5(PG 64-22 OK) | 411(S5) 5975 | TON | 130.000 | 268.220 | 268.220 | $75.00 | $0.00 | $20,116.50 | |
0009 | 9" P.C. DOWEL JOINTED CONCRETE PAVEMENT | 414(A1) 5754 | SY | 4,000.000 | 3,954.670 | 264.670 | 3,954.670 | $60.00 | $15,880.20 | $237,280.20 |
0010 | H.E.S. CONCRETE (FULL DEPTH PATCHING) | 414(B) 5913 | SY | 915.000 | 751.610 | 39.610 | 751.610 | $75.00 | $2,970.75 | $56,370.75 |
0011 | COLD MILLING BITUMINOUS PAVEMENT | 417 4267 | SY | 2,365.000 | 3,063.110 | 1.450 | 3,063.110 | $1.65 | $2.39 | $5,054.13 |
0012 | FABRIC REINFORCEMENT | 420(A) 4242 | SY | 3,080.000 | 3,942.670 | -363.990 | 3,942.670 | $2.00 | $-727.98 | $7,885.34 |
0013 | CONCRETE CURB (8" BARRIER-INTEGRAL) | 609(A) 0380 | LF | 1,410.000 | 1,216.000 | 1,216.000 | $7.00 | $0.00 | $8,512.00 | |
0014 | 4" CONCRETE SIDEWALK | 610(A) 0602 | SY | 400.000 | 680.730 | 146.730 | 680.730 | $73.00 | $10,711.29 | $49,693.29 |
0015 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 550.000 | 543.340 | -6.660 | 543.340 | $65.00 | $-432.90 | $35,317.10 |
0016 | BITUMINOUS DRIVEWAY (6") | 610(G) 4475 | SY | 80.000 | 0.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0017 | INLET CICI DES. 2 (STD) | 611(E) 5112 | EA | 5.000 | 4.000 | 4.000 | $2,700.00 | $0.00 | $10,800.00 | |
0018 | INLET CICI DES. 2 (B) | 611(E) 5113 | EA | 1.000 | 2.000 | 2.000 | $3,500.00 | $0.00 | $7,000.00 | |
0019 | MANHOLES ADJUST TO GRADE | 612(A) 0641 | EA | 4.000 | 7.000 | 1.000 | 7.000 | $1,000.00 | $1,000.00 | $7,000.00 |
0020 | VALVES RESET | 612(K) 0651 | EA | 1.000 | 2.000 | 2.000 | $300.00 | $0.00 | $600.00 | |
0021 | REMOVAL OF DRAINAGE INLETS | 619(B) 4741 | EA | 6.000 | 6.000 | 6.000 | $350.00 | $0.00 | $2,100.00 | |
0022 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 630.000 | 543.340 | 112.340 | 543.340 | $6.00 | $674.04 | $3,260.04 |
0023 | REMOVAL OF CURB | 619(B) 4791 | LF | 1,410.000 | 1,216.000 | 1,216.000 | $3.00 | $0.00 | $3,648.00 | |
0024 | REMOVAL OF SIDEWALK | 619(B) 4792 | SY | 325.000 | 557.490 | 183.990 | 557.490 | $5.00 | $919.95 | $2,787.45 |
0025 | REMOVAL OF CONCRETE MEDIAN BARRIER | 619(B) 4915 | LF | 480.000 | 811.000 | 811.000 | $6.00 | $0.00 | $4,866.00 | |
8032 | ASPHALT BINDER PRICE ADJUSTMENT | 109 1150 | LSUM | 0.000 | 1.000 | 0.000 | $2,100.31 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY - STP-STIM(482)IG | $32,697.78 | $616,217.74 | ||||||||
Fed/State Project Number: STP-STIM(482)IG | Project: 26968(04) | Category: 0300/TRAFFIC - STP-STIM(482)IG | ||||||||
0026 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 5,785.000 | 9,245.000 | -12.000 | 9,245.000 | $1.00 | $-12.00 | $9,245.00 |
0027 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 8.000 | 8.000 | 8.000 | $100.00 | $0.00 | $800.00 | |
0028 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 2,805.000 | 3,608.000 | 779.000 | 3,608.000 | $0.50 | $389.50 | $1,804.00 |
0029 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 4,198.000 | 4,693.000 | 769.000 | 4,693.000 | $1.00 | $769.00 | $4,693.00 |
0030 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 3,823.000 | 4,282.000 | 149.000 | 4,282.000 | $1.10 | $163.90 | $4,710.20 |
0031 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 8,543.000 | 11,658.000 | 1,728.000 | 11,658.000 | $0.11 | $190.08 | $1,282.38 |
0032 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 8,058.000 | 440.000 | 88.000 | 440.000 | $0.02 | $1.76 | $8.80 |
0033 | DRUMS | 880(F) 8878 | SD | 8,058.000 | 40,059.000 | 4,698.000 | 40,059.000 | $0.55 | $2,583.90 | $22,032.45 |
0034 | TUBE CHANNELIZERS | 880(G) 8884 | SD | 25,942.000 | 0.000 | 0.000 | $0.05 | $0.00 | $0.00 | |
0035 | BARRICADES(TYPE III) | 880(J) 8021 | SD | 3,823.000 | 4,097.000 | 715.000 | 4,097.000 | $1.10 | $786.50 | $4,506.70 |
Subtotals For Category 0300/TRAFFIC - STP-STIM(482)IG | $4,872.64 | $49,082.53 | ||||||||
Fed/State Project Number: STP-STIM(482)IG | Project: 26968(04) | Category: 0301/TRAFFIC SIGNALS - STP-STIM(482)IG | ||||||||
0036 | 3" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 802(B) 8346 | LF | 585.000 | 960.000 | 377.000 | 960.000 | $5.50 | $2,073.50 | $5,280.00 |
0037 | PULL BOX(SIZE I) | 803 8065 | EA | 3.000 | 3.000 | 3.000 | $435.00 | $0.00 | $1,305.00 | |
0038 | PULL BOX(SIZE II) | 803 8066 | EA | 1.000 | 1.000 | 1.000 | $550.00 | $0.00 | $550.00 | |
0039 | STRUCTURAL CONCRETE | 804(A) 2915 | CY | 1.400 | 1.400 | 0.400 | 1.400 | $435.00 | $174.00 | $609.00 |
0040 | REINFORCING STEEL | 804(B) 2916 | LB | 108.000 | 108.000 | 108.000 | $1.10 | $0.00 | $118.80 | |
0041 | 10' MTG.HT.TS PED.POLE(G.STL.) | 806(B) 8894 | EA | 4.000 | 4.000 | 4.000 | $775.00 | $0.00 | $3,100.00 | |
0042 | SERVICE POLE | 810(A) 3118 | EA | 1.000 | 1.000 | 1.000 | $1,300.00 | $0.00 | $1,300.00 | |
0043 | 1/C NO.6 ELECTRICAL CONDUCTOR | 811 8040 | LF | 400.000 | 703.000 | 33.000 | 703.000 | $0.55 | $18.15 | $386.65 |
0044 | 1/C NO.12 ELECTRICAL CONDUCTOR | 811 8046 | LF | 415.000 | 1,051.000 | -57.000 | 1,051.000 | $0.30 | $-17.10 | $315.30 |
0045 | (PL)TRAFFIC SIGNAL SPAN WIRE EQUIPMENT | 823 8482 | LSUM | 1.000 | 1.000 | 1.000 | $2,700.00 | $0.00 | $2,700.00 | |
0046 | VEH.ACT.SOL.ST.TRAF.SIG.CON.ASM | 825 8550 | EA | 1.000 | 1.000 | 1.000 | $16,000.00 | $0.00 | $16,000.00 | |
0047 | (PL)DETECTION SYSTEM (VIDEO) | 828 8132 | LSUM | 1.000 | 1.000 | 1.000 | $30,000.00 | $0.00 | $30,000.00 | |
0048 | PEDESTRIAN PUSH BUTTON | 830 8000 | EA | 8.000 | 8.000 | 8.000 | $135.00 | $0.00 | $1,080.00 | |
0049 | 1WAY 2SEC. ADJ. PED. SIG. HD. S-20 | 831 8295 | EA | 8.000 | 8.000 | 8.000 | $800.00 | $0.00 | $6,400.00 | |
0050 | 5/C TRAF.SIG.ELECT.CABLE | 834(A) 8207 | LF | 140.000 | 155.000 | 5.000 | 155.000 | $0.80 | $4.00 | $124.00 |
0051 | 7/C TRAF.SIG.ELECT.CABLE | 834(A) 8208 | LF | 480.000 | 398.000 | -229.000 | 398.000 | $1.10 | $-251.90 | $437.80 |
0052 | 21/C TRAF.SIG.EL.CABLE | 834(A) 8213 | LF | 830.000 | 714.000 | 74.000 | 714.000 | $1.35 | $99.90 | $963.90 |
0053 | 2/C SHIELDED LOOP DETECTOR LEAD-IN CABLE | 834(B) 8220 | LF | 540.000 | 662.000 | 175.000 | 662.000 | $0.55 | $96.25 | $364.10 |
0054 | (PL)E.P.S. OPTICAL DETECTOR | 840(B) 8593 | EA | 2.000 | 2.000 | 2.000 | $980.00 | $0.00 | $1,960.00 | |
0055 | (PL)E.P.S. OPTICAL DETECTOR CABLE | 840(C) 8594 | LF | 175.000 | 335.000 | 335.000 | $1.10 | $0.00 | $368.50 | |
0056 | (PL)E.P.S. 2 CHANNEL PHASE SELECTOR | 840(D) 8595 | EA | 1.000 | 1.000 | 1.000 | $2,200.00 | $0.00 | $2,200.00 | |
0057 | (PL)REMOVAL OF TRAFFIC SIGNAL EQUIPMENT | 890(A) 8726 | LSUM | 1.000 | 1.000 | 1.000 | $1,100.00 | $0.00 | $1,100.00 | |
Subtotals For Category 0301/TRAFFIC SIGNALS - STP-STIM(482)IG | $2,196.80 | $76,663.05 | ||||||||
Fed/State Project Number: STP-STIM(482)IG | Project: 26968(04) | Category: 0900/NON PARTICIPATING (WATERLINE) - STP-STIM(482)IG | ||||||||
0058 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 300.000 | 636.080 | 22.380 | 636.080 | $10.00 | $223.80 | $6,360.80 |
0059 | 6" CONCRETE DRIVEWAY (H.E.S.) | 610(B) 0399 | SY | 32.000 | 166.590 | 77.590 | 166.590 | $65.00 | $5,043.35 | $10,828.35 |
0060 | 12" PLUG | 616 0118 | EA | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0061 | 12" DUCTILE IRON PIPE | 616(A) 5124 | LF | 443.000 | 493.000 | 30.000 | 493.000 | $60.00 | $1,800.00 | $29,580.00 |
0062 | 12" DUCTILE IRON PIPE REST. JT. W/POLYETHYLENE ENCASEMENT | 616(A) 6090 | LF | 446.000 | 293.500 | -12.000 | 293.500 | $75.00 | $-900.00 | $22,012.50 |
0063 | 6" GATE VALVE | 616(D) 1070 | EA | 4.000 | 3.000 | 3.000 | $1,000.00 | $0.00 | $3,000.00 | |
0064 | 12" GATE VALVE | 616(D) 1100 | EA | 9.000 | 8.000 | 8.000 | $2,700.00 | $0.00 | $21,600.00 | |
0065 | STANDARD VALVE BOX | 616(D) 7051 | EA | 13.000 | 11.000 | 11.000 | $150.00 | $0.00 | $1,650.00 | |
0066 | FIRE HYDRANTS | 616(G) 1192 | EA | 3.000 | 3.000 | 3.000 | $2,800.00 | $0.00 | $8,400.00 | |
0067 | 6" SOLID SLEEVE | 616(I) 0018 | EA | 1.000 | 1.000 | 1.000 | $550.00 | $0.00 | $550.00 | |
0068 | 12" SOLID SLEEVE | 616(I) 0024 | EA | 3.000 | 4.000 | 4.000 | $1,200.00 | $0.00 | $4,800.00 | |
0069 | 12" X 12" X 6" TEE | 616(J) 0030 | EA | 2.000 | 3.000 | 3.000 | $900.00 | $0.00 | $2,700.00 | |
0070 | 12" X 12" X 12" TEE | 616(J) 0035 | EA | 1.000 | 1.000 | 1.000 | $1,200.00 | $0.00 | $1,200.00 | |
0071 | 6" 45 DEGREE FITTING | 616(K) 0042 | EA | 2.000 | 2.000 | 2.000 | $350.00 | $0.00 | $700.00 | |
0072 | 12" 45 DEGREE FITTING | 616(K) 0047 | EA | 8.000 | 14.000 | 14.000 | $775.00 | $0.00 | $10,850.00 | |
0073 | 12" 22 1/2 DEGREE FITTING | 616(K) 0054 | EA | 2.000 | 1.000 | 1.000 | $750.00 | $0.00 | $750.00 | |
0074 | 12" X 6" REDUCER | 616(L) 0081 | EA | 1.000 | 1.000 | 1.000 | $500.00 | $0.00 | $500.00 | |
0075 | 12" X 12" X 12" X 12" CROSS | 616(M) 0082 | EA | 1.000 | 1.000 | 1.000 | $1,500.00 | $0.00 | $1,500.00 | |
0076 | SHORT WATER SERVICE & RESET METER | 616(N) 0094 | EA | 3.000 | 4.000 | 1.000 | 4.000 | $1,500.00 | $1,500.00 | $6,000.00 |
0077 | REMOVAL OF CONCRETE DRIVEWAY | 619(B) 4766 | SY | 32.000 | 165.220 | 35.220 | 165.220 | $9.00 | $316.98 | $1,486.98 |
Subtotals For Category 0900/NON PARTICIPATING (WATERLINE) - STP-STIM(482)IG | $7,984.13 | $134,968.63 | ||||||||
Subtotals For Project STP-STIM(482)IG /26968(04) | $47,751.35 | $876,931.95 |