Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    08/02/2013
Contract ID: 090587   Estimate Number: 0040     Contract No: 510450
Residency: CRAIG & KEITHLINE, INC. (08007)   Estimate Type: Progressive     Account No: 400800

Project Number(s): NHY-014N(019)SS
Primary Job Piece No: 17387(04)
Contract Description: GRADE, DRAIN, SURFACE, AND BRIDGE US-75: AT THE 111TH STREET JUNCTION IN THE CITY OF JENKS. PROJECT LENGTH = 2.738 MILES.
Primary County: TULSA              
Name of Road: US-75              
Prime Contractor: MANHATTAN ROAD & BRIDGE COMPANY              
    5601 S. 122ND E. AVE.              
    TULSA , OK   74146              
Surety Company: FEDERAL INSURANCE COMPANY              

Date Let: 09/17/2009 NTP Effective Date: 03/01/2010 Pay Period: 04/16/2013  TO  07/31/2013
Date Awarded: 10/05/2009 Date Work Began: 11/10/2009 Original Contract Time: 365
Date Contract Executed: 10/20/2009 Date Time Stopped: Current Time Charged: 1360.00
Date NTP Issued: 10/23/2009 Completion Date: Current Time Allowed: 1396.00
General Liability Expires: 10/01/2013 Workman's Comp Expires: 10/01/2013 Percent Time Used: 97.42 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $11,810,859.89 Total to Date Prev to Date This Estimate
Bid Amount: $11,243,505.69 Participating: $11,815,470.63 $11,807,779.82 $7,690.81
Percent Complete: 100 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $10.76 Total Earnings: $11,815,470.63 $11,807,779.82 $7,690.81
Unearned Balance: $-567,343.44 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $11,815,470.63 $11,807,779.82 $7,690.81
Other Adjustments: $-4,621.50 $0.00 $-4,621.50
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $11,810,849.13 $11,807,779.82 $3,069.31

Estimate Adjustment Detail

Contract ID: 090587   Estimate Number: 0040     Primary JP: 17387(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Adds 30" RCP Cl. IV and 48" RCP Cl. IV & V to the contract. Approved 04/08/2010 0.0 $32,482.74
002 Adds 6" Perf. & 6" Non-Perf. Pipe Underdrain. Approved 05/03/2010 0.0 $90,902.40
003 Overrun Uncl. Borrow & underrun T.B.S.C. Approved 07/11/2011 0.0 $43,111.40
004 Adds Fence Style SWF (5 Barbed Wire) to the contract. Approved 02/08/2011 0.0 $56,565.00
005 Adds guardrail items and removal of overhead sign structure. Approved 02/08/2011 0.0 $14,522.50
006 Adds 107 Days for work added by prev. C.O.s. Approved 03/28/2011 107.0 $0.00
007 Reimburses subcontractor for payment of elec. service. Approved 06/04/2012 0.0 $21,546.00
008 Funds asphalt binder adjustments Approved 07/11/2011 0.0 $40,394.56
009 Changes method of payment for Aggregate Base. Approved 05/08/2012 0.0 $20,061.13
010 Deletes "Pay Plan Qty" note on drainage str. items. Approved 03/05/2012 0.0 $31,827.36
011 Overrun Plastic Stripe, Uncl. Exc. & 16.0 - 32.99 SF Signs Approved 06/04/2012 0.0 $51,922.73
012 Adds pay item Re-Mobilization, for permanent signs added. Approved 09/11/2012 0.0 $16,555.20
013 Repair existing High Mast and Underpass Lighting Approved 04/01/2013 0.0 $9,790.20
014 F-Shaped Barrier on 111th Approved 04/01/2013 21.0 $131,111.98
015 Additional funding for payment of electricity for lights Approved 04/03/2013 0.0 $6,561.00


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Initial Payment 0005 $22,050.00
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Adjustment 0017 $-1,350.12
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Adjustment 0020 $-11,565.60
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Initial Payment 0010 $22,050.00
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Adjustment 0018 $-3,843.83
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Closure 0008 $-17,956.44
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Adjustment 0007 $-1,234.39
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Adjustment 0006 $-2,859.17
17387(04) 0017 SEPARATOR FABRIC Stockpiled Material Adjustment 0019 $-5,290.45
17387(04) 0029 Drilled Shaft resteel for sound barrier wall Stockpiled Material Closure 0012 $-24,765.06
17387(04) 0029 Drilled Shaft resteel for sound barrier wall Stockpiled Material Initial Payment 0010 $24,765.06
17387(04) 0030 REINFORCING STEEL STR. 10 Stockpiled Material Adjustment 0005 $-3,545.12
17387(04) 0030 REINFORCING STEEL STR. 10 Stockpiled Material Initial Payment 0005 $3,768.32
17387(04) 0030 REINFORCING STEEL STR. 10 Stockpiled Material Closure 0007 $-223.20
17387(04) 0037 MANHOLE (4' DIA.) STR. 11, 13 Stockpiled Material Adjustment 0005 $-308.57
17387(04) 0037 MANHOLE (4' DIA.) STR. 11, 13 Stockpiled Material Initial Payment 0005 $617.14
17387(04) 0037 MANHOLE (4' DIA.) STR. 11, 13 Stockpiled Material Closure 0008 $-308.57
17387(04) 0041 Manhole Frame & Cover Stockpiled Material Initial Payment 0019 $2,864.70
17387(04) 0041 Manhole Frame & Cover Stockpiled Material Adjustment 0020 $-2,864.70
17387(04) 0043 Design 2B Inlet Stockpiled Material Closure 0008 $-1,662.48
17387(04) 0043 Design 2B Inlet Stockpiled Material Initial Payment 0005 $1,662.48
17387(04) 0048 GPI Type A Grate Stockpiled Material Closure 0025 $-195.33
17387(04) 0048 GPI Type A Grate Stockpiled Material Adjustment 0020 $-195.33
17387(04) 0048 GPI Type A Grate Stockpiled Material Initial Payment 0019 $390.66
17387(04) 0049 GPI Type B Grate Stockpiled Material Closure 0025 $-265.86
17387(04) 0049 GPI Type B Grate Stockpiled Material Initial Payment 0019 $265.86
17387(04) 0050 SMD Type 2 Grate Stockpiled Material Closure 0025 $-439.49
17387(04) 0050 SMD Type 2 Grate Stockpiled Material Initial Payment 0019 $439.49
17387(04) 0053 18"x30" Frame & Grate Stockpiled Material Initial Payment 0019 $14,159.04
17387(04) 0053 18"x30" Frame & Grate Stockpiled Material Adjustment 0021 $-13,147.68
17387(04) 0053 18"x30" Frame & Grate Stockpiled Material Adjustment 0023 $-1,011.36
17387(04) 0054 Cast Iron Curb Inlets Stockpiled Material Initial Payment 0019 $17,773.28
17387(04) 0054 Cast Iron Curb Inlets Stockpiled Material Adjustment 0021 $-15,234.24
17387(04) 0054 Cast Iron Curb Inlets Stockpiled Material Adjustment 0023 $-2,539.04
17387(04) 0055 18" RCP Stockpiled Material Initial Payment 0005 $4,304.40
17387(04) 0055 18" RCP Stockpiled Material Adjustment 0005 $-327.05
17387(04) 0055 18" RCP Stockpiled Material Closure 0008 $-3,977.35
17387(04) 0059 48" RCP Stockpiled Material Closure 0008 $-2,012.64
17387(04) 0059 48" RCP Stockpiled Material Initial Payment 0005 $2,012.64
17387(04) 0059 48" RCP Stockpiled Material Initial Payment 0002 $7,044.24
17387(04) 0059 48" RCP Stockpiled Material Adjustment 0003 $-7,044.24
17387(04) 0087 Prestressed concrete beams Stockpiled Material Adjustment 0015 $-287,395.78
17387(04) 0087 Prestressed concrete beams Stockpiled Material Initial Payment 0011 $287,395.78
17387(04) 0087 Prestressed concrete beams Stockpiled Material Adjustment 0015 $-126,084.75
17387(04) 0087 Prestressed concrete beams Stockpiled Material Initial Payment 0015 $126,084.75
17387(04) 0094 Piers 1-4 Br. A Stockpiled Material Initial Payment 0010 $42,933.44
17387(04) 0094 Piers 1-4 Br. A Stockpiled Material Adjustment 0010 $-107,652.15
17387(04) 0094 Piers 1-4 Br. A Stockpiled Material Closure 0012 $-32,116.92
17387(04) 0094 Piers 1-4 Br. A Stockpiled Material Initial Payment 0010 $107,652.15
17387(04) 0094 Piers 1-4 Br. A Stockpiled Material Adjustment 0011 $-10,816.52
17387(04) 0134 High Mast Luminaires Stockpiled Material Adjustment 0020 $-11,440.00
17387(04) 0134 High Mast Luminaires Stockpiled Material Initial Payment 0011 $13,585.00
17387(04) 0134 High Mast Luminaires Stockpiled Material Adjustment 0023 $-2,145.00
17387(04) 0137 High Mast Pole Stockpiled Material Adjustment 0023 $-6,997.00
17387(04) 0137 High Mast Pole Stockpiled Material Initial Payment 0015 $6,997.00
17387(04) 0138 High Mast Pole Stockpiled Material Adjustment 0020 $-28,560.00
17387(04) 0138 High Mast Pole Stockpiled Material Initial Payment 0015 $28,560.00
17387(04) 0139 Lowering Devices Stockpiled Material Adjustment 0023 $-3,420.40
17387(04) 0139 Lowering Devices Stockpiled Material Adjustment 0020 $-13,681.60
17387(04) 0139 Lowering Devices Stockpiled Material Initial Payment 0015 $17,102.00
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0028 --5.0 $2,000.00 $-10,000.00
System Application of Liquidated Damages 0029 -5.0 $2,000.00 $10,000.00
Subtotals For Liquidated Damages $0.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
17387(04) 0003 UNCLASSIFIED BORROW * Material Discrepancy Adjustments 0011 -8,779.00 $7.30 $-64,086.70
17387(04) 0003 UNCLASSIFIED BORROW * Material Discrepancy Adjustments 0012 8,779.00 $7.30 $64,086.70
17387(04) 0008 TEMPORARY SILT DIKE * Material Discrepancy Adjustments 0016 -84.00 $8.75 $-735.00
17387(04) 0008 TEMPORARY SILT DIKE * Material Discrepancy Adjustments 0025 84.00 $8.75 $735.00
17387(04) 0011 SOLID SLAB SODDING * Permanent Erosion Control-Out of Season 0028 0.00 $0.00 $-14,377.67
17387(04) 0011 SOLID SLAB SODDING * Permanent Erosion Control-Out of Season 0029 0.00 $0.00 $14,377.67
17387(04) 0011 SOLID SLAB SODDING * Overrun 0030 -24,378.00 $1.22 $-29,741.16
17387(04) 0011 SOLID SLAB SODDING * Overrun Re-adjustment 0031 0.00 $0.00 $29,741.16
17387(04) 0020 TACK COAT * Material Discrepancy Adjustments 0016 -2,275.00 $3.15 $-7,166.25
17387(04) 0020 TACK COAT * Material Discrepancy Adjustments 0018 2,275.00 $3.15 $7,166.25
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) * Material Discrepancy Adjustments 0008 0.00 $0.00 $-1,770.00
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0008 0.00 $0.00 $874.58
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0019 0.00 $0.00 $3,728.64
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0020 0.00 $0.00 $5,862.72
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0021 0.00 $0.00 $18,715.85
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0022 0.00 $0.00 $1,963.32
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) * ROADWAY DENSITY 0028 0.00 $0.00 $-22,363.37
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0029 60.14 $1.93 $116.25
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) * Asphalt Binder Adjustment 0029 0.00 $0.00 $51.83
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) * Asphalt Binder Adjustment 0031 0.00 $0.00 $-31,313.19
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) * ROADWAY DENSITY 0031 0.00 $0.00 $24,133.37
17387(04) 0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) Asphalt Binder Adjustment 0032 43.33 $5.92 $256.65
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0007 0.00 $0.00 $602.91
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0008 0.00 $0.00 $302.73
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0015 0.00 $0.00 $2,009.46
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * ROADWAY DENSITY 0019 0.00 $0.00 $-74,049.20
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0019 0.00 $0.00 $9,715.51
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0020 0.00 $0.00 $1,839.04
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0021 0.00 $0.00 $14,995.19
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0022 0.00 $0.00 $1,983.13
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * ROADWAY DENSITY 0028 0.00 $0.00 $19,354.63
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * Asphalt Binder Adjustment 0029 0.00 $0.00 $320.93
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0029 218.35 $1.93 $422.08
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * Asphalt Binder Adjustment 0031 0.00 $0.00 $-32,190.98
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * HMA Deduction as per Sec. 411 0031 0.00 $0.00 $54,694.57
17387(04) 0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0032 -43.33 $5.92 $-256.65
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0008 0.00 $0.00 $639.42
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * ROADWAY DENSITY 0019 0.00 $0.00 $-4,739.61
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0020 0.00 $0.00 $2,936.42
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0021 0.00 $0.00 $5,086.91
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0022 0.00 $0.00 $17,959.33
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0029 0.00 $0.00 $-578.90
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0029 -536.14 $2.20 $-1,184.44
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * HMA Deduction as per Sec. 411 0031 0.00 $0.00 $4,739.61
17387(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0031 0.00 $0.00 $-24,858.74
17387(04) 0025 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0015 0.00 $0.00 $803.70
17387(04) 0025 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Asphalt Binder Adjustment 0031 0.00 $0.00 $-803.70
17387(04) 0027 CLASS AA CONCRETE * Material Discrepancy Adjustments 0027 0.00 $0.00 $-625.00
17387(04) 0027 CLASS AA CONCRETE * Material Discrepancy Adjustments 0034 0.00 $0.00 $625.00
17387(04) 0029 SOUND BARRIER WALL * Material Discrepancy Adjustments 0027 0.00 $0.00 $-4,180.80
17387(04) 0029 SOUND BARRIER WALL * Material Discrepancy Adjustments 0027 0.00 $0.00 $-2,244.48
17387(04) 0029 SOUND BARRIER WALL * Material Discrepancy Adjustments 0029 0.00 $0.00 $2,246.85
17387(04) 0029 SOUND BARRIER WALL * Material Discrepancy Adjustments 0034 0.00 $0.00 $4,178.43
17387(04) 0039 ADD'L.DEPTH IN MANHOLE (4' DIAMETER) * Material Discrepancy Adjustments 0016 -2.54 $140.00 $-355.60
17387(04) 0039 ADD'L.DEPTH IN MANHOLE (4' DIAMETER) * Material Discrepancy Adjustments 0018 2.54 $140.00 $355.60
17387(04) 0052 INLET CICI DES. 3 (ADD'L DEPTH) * Material Discrepancy Adjustments 0016 -5.94 $440.00 $-2,613.60
17387(04) 0052 INLET CICI DES. 3 (ADD'L DEPTH) * Material Discrepancy Adjustments 0018 5.94 $440.00 $2,613.60
17387(04) 0055 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0016 -277.00 $51.00 $-14,127.00
17387(04) 0055 18" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0018 277.00 $51.00 $14,127.00
17387(04) 0056 24" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0016 -41.00 $60.00 $-2,460.00
17387(04) 0056 24" R.C.PIPE CLASS III * Material Discrepancy Adjustments 0018 41.00 $60.00 $2,460.00
17387(04) 0064 TYPE B4 CULVERT END TREATMENT * Material Discrepancy Adjustments 0027 0.00 $0.00 $-1,456.00
17387(04) 0064 TYPE B4 CULVERT END TREATMENT * Material Discrepancy Adjustments 0034 0.00 $0.00 $1,456.00
17387(04) 0067 36" CORR. GALV. STEEL PIPE * Material Discrepancy Adjustments 0016 -34.00 $38.00 $-1,292.00
17387(04) 0067 36" CORR. GALV. STEEL PIPE * Material Discrepancy Adjustments 0018 34.00 $38.00 $1,292.00
17387(04) 0076 TYPE F4 SLOPED CONCRETE END SECTION * Overrun 0032 -3.00 $4,000.00 $-12,000.00
17387(04) 0076 TYPE F4 SLOPED CONCRETE END SECTION * Overrun Re-adjustment 0035 3.00 $4,000.00 $12,000.00
17387(04) 0088 APPROACH SLAB * Material Discrepancy Adjustments 0027 0.00 $0.00 $-4,310.06
17387(04) 0088 APPROACH SLAB * Material Discrepancy Adjustments 0029 0.00 $0.00 $3,782.17
17387(04) 0088 APPROACH SLAB * Material Discrepancy Adjustments 0034 0.00 $0.00 $527.89
17387(04) 0091 CLASS AA CONCRETE * Material Discrepancy Adjustments 0027 0.00 $0.00 $-9,067.50
17387(04) 0091 CLASS AA CONCRETE * Material Discrepancy Adjustments 0029 0.00 $0.00 $6,731.35
17387(04) 0091 CLASS AA CONCRETE * PCCP Deduction as per Sec. 414 0031 0.00 $0.00 $-2,628.80
17387(04) 0091 CLASS AA CONCRETE * PCCP Deduction as per Sec. 414 0034 0.00 $0.00 $4,964.95
17387(04) 8004 6" PERFORATED PIPE UNDERDRAIN ROUND * Overrun 0040 -450.00 $10.27 $-4,621.50
Subtotals For Line Item Adjustments $-4,621.50
* = User applied Line Item Adjustments


MILESTONE INFORMATION
Milestone Number Milestone Description Start Date End Date Current Time Allowed Rate Milestone Closed
01 TIME 'B' BID 11/10/2009 09/26/2010 320.00 DYS $10,000.00 Y


MILESTONE ADJUSTMENTS
Milestone Number Milestone Adjustment Description Estimate Nbr Total
No milestones adjustments exist for this contract.
Subtotals For Milestones $

Line Item Detail

Contract ID: 090587   Estimate Number: 0040     Primary JP: 17387(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0100/ROADWAY
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $60,000.00 $0.00 $60,000.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 106,353.000 111,423.000   111,423.000 $3.35 $0.00 $373,267.05
0003 UNCLASSIFIED BORROW 202(C) 0184 CY 142,222.000 162,340.000   162,340.430 $7.30 $0.00 $1,185,085.14
0004 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   1.000 $45,000.00 $0.00 $45,000.00
0005 TEMPORARY SILT FENCE 223 2801 LF 10,670.000 6,800.000   6,800.000 $2.35 $0.00 $15,980.00
0006 TEMPORARY SEDIMENT FILTER 224 2803 EA 2.000 0.000   0.000 $250.00 $0.00 $0.00
0007 TEMPORARY SEDIMENT REMOVAL 226 2805 CY 500.000 280.560   280.560 $10.50 $0.00 $2,945.88
0008 TEMPORARY SILT DIKE 227 0100 LF 320.000 168.000   168.000 $8.75 $0.00 $1,470.00
0009 NYLON EROSION CONTROL MAT 228 4170 SY 3,228.620 0.000   0.000 $3.05 $0.00 $0.00
0010 DITCH LINER PROTECTION 229 4318 LF 2,905.760 0.000   0.000 $1.50 $0.00 $0.00
0011 SOLID SLAB SODDING 230(A) 2806 SY 93,613.000 147,136.000 217.000 147,353.000 $1.22 $264.74 $179,770.66
0012 SEEDING METHOD B 232(B) 2814 AC 19.340 21.250   21.250 $205.00 $0.00 $4,356.25
0013 VEGETATIVE MULCHING 233(A) 2817 AC 19.340 21.250   21.250 $205.00 $0.00 $4,356.25
0014 MOWING 241 2832 AC 77.360 1.000   1.000 $87.50 $0.00 $87.50
0015 (PL)STABILIZED CONSTRUCTION EXIT 242 0400 EA 2.000 2.000   2.000 $1,500.00 $0.00 $3,000.00
0016 AGGREGATE BASE 303 0192 CY 18,370.290 2,597.500   2,597.500 $36.25 $0.00 $94,159.39
0017 SEPARATOR FABRIC 325 5271 SY 106,598.820 106,598.820   106,598.820 $0.85 $0.00 $90,609.01
0018 (SP)STABILIZED SUBGRADE 327(K) 4300 SY 86,129.820 0.000   0.000 $1.55 $0.00 $0.00
0019 TRAFFIC BOUND SURFACE COURSE TYPE A 403(A) 0217 TON 12,569.000 7,569.000   7,220.080 $20.75 $0.00 $149,816.67
0020 TACK COAT 407 0250 GAL 7,100.920 7,100.920   4,400.000 $3.15 $0.00 $13,860.00
0021 PRIME COAT 408 5774 GAL 1,873.420 1,873.420   0.000 $6.80 $0.00 $0.00
0022 (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) 411(S3) 5940 TON 11,017.420 11,017.420   11,646.390 $59.00 $0.00 $687,137.01
0023 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 11,544.870 11,544.870   11,712.760 $54.25 $0.00 $635,417.24
0024 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 7,893.750 7,893.750   8,210.450 $70.25 $0.00 $576,784.11
0025 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 494.000 494.000   270.530 $58.00 $0.00 $15,690.74
0026 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 624.000 111.880   111.880 $22.50 $0.00 $2,517.30
0027 CLASS AA CONCRETE 509(A) 0319 CY 334.790 334.790   334.790 $500.00 $0.00 $167,395.00
0028 CLASS C CONCRETE 509(D) 0325 CY 476.820 413.390   413.390 $235.00 $0.00 $97,146.65
0029 SOUND BARRIER WALL 510(B) 6333 SY 4,322.000 4,322.000   4,322.000 $229.25 $0.00 $990,818.50
0030 REINFORCING STEEL 511(A) 0332 LB 57,946.500 57,946.500   57,946.500 $0.70 $0.00 $40,562.55
0031 TYPE I PLAIN RIPRAP 601(A) 0297 TON 47.630 47.630   67.120 $47.00 $0.00 $3,154.64
0032 2'-8" COMB. CURB & GUTTER (4" MNTBLE) 609(B) 1523 LF 618.000 618.000   618.000 $20.50 $0.00 $12,669.00
0033 2'-8" COMB. CURB & GUTTER (6" BARRIER) 609(B) 1525 LF 10,318.750 10,318.750   10,318.750 $15.00 $0.00 $154,781.25
0034 4" CONCRETE SIDEWALK 610(A) 0602 SY 2,786.110 2,786.110   2,786.110 $31.00 $0.00 $86,369.41
0035 4" CONCRETE DIVIDING STRIP 610(C) 0608 SY 388.000 388.000   388.000 $31.00 $0.00 $12,028.00
0036 (PL)TACTILE WARNING DEVICE-NEW 610(I) 4610 SF 96.000 96.000   104.000 $51.50 $0.00 $5,356.00
0037 MANHOLE (4' DIAMETER) 611(A) 2657 EA 10.000 10.000   10.000 $1,350.00 $0.00 $13,500.00
0038 MANHOLE (5' DIAMETER) 611(A) 2658 EA 1.000 1.000   1.000 $1,525.00 $0.00 $1,525.00
0039 ADD'L.DEPTH IN MANHOLE (4' DIAMETER) 611(B) 2680 VF 4.850 4.850 -1.350 3.500 $140.00 $-189.00 $490.00
0040 ADD'L.DEPTH IN MANHOLE (5' DIAMETER) 611(B) 2681 VF 2.080 2.080 0.750 2.830 $250.00 $187.50 $707.50
0041 MANHOLE FRAME & COVER 611(D) 4215 EA 11.000 11.000   11.000 $390.00 $0.00 $4,290.00
0042 INLET CICI DES. 2 (STD) 611(E) 5112 EA 4.000 5.000   5.000 $1,630.00 $0.00 $8,150.00
0043 INLET CICI DES. 2 (B) 611(E) 5113 EA 2.000 2.000   2.000 $2,165.00 $0.00 $4,330.00
0044 INLET CICI DES. 2 (2D) 611(E) 5119 EA 2.000 2.000   2.000 $3,360.00 $0.00 $6,720.00
0045 INLET CICI DES. 3 (STD) 611(E) 5120 EA 3.000 3.000   3.000 $2,165.00 $0.00 $6,495.00
0046 INLET CICI DES. 3 (B) 611(E) 5121 EA 4.000 4.000   4.000 $2,450.00 $0.00 $9,800.00
0047 INLET CICI DES. 3 (D) 611(E) 5122 EA 1.000 1.000   1.000 $3,030.00 $0.00 $3,030.00
0048 INLET CICI DES. 3 (2B) 611(E) 5123 EA 2.000 2.000   2.000 $2,725.00 $0.00 $5,450.00
0049 INLET GPI TYPE 2 (DES. 10) 611(E) 5336 EA 1.000 1.000   1.000 $2,550.00 $0.00 $2,550.00
0050 INLET (SMD-TYPE 2) 611(E) 6002 EA 1.000 1.000   1.000 $2,600.00 $0.00 $2,600.00
0051 INLET CICI DES. 2 (ADD'L DEPTH) 611(F) 5325 VF 14.180 14.180 -2.600 11.330 $315.00 $-819.00 $3,568.95
0052 INLET CICI DES. 3 (ADD'L DEPTH) 611(F) 5330 VF 16.900 16.900 -1.320 15.580 $440.00 $-580.80 $6,855.20
0053 INLET FRM&GRT (SSIF-FRM,CIG-GRT-VG-F) 611(G) 4488 EA 56.000 57.000   57.000 $360.00 $0.00 $20,520.00
0054 CAST IRON CURB INLETS 611(K) 4488 EA 98.000 94.000   94.000 $305.00 $0.00 $28,670.00
0055 18" R.C.PIPE CLASS III 613(B) 0491 LF 2,266.000 2,272.000   2,272.000 $51.00 $0.00 $115,872.00
0056 24" R.C.PIPE CLASS III 613(B) 0492 LF 1,726.000 1,782.000   1,782.000 $60.00 $0.00 $106,920.00
0057 30" R.C.PIPE CLASS III 613(B) 0493 LF 630.000 515.000   515.000 $75.00 $0.00 $38,625.00
0058 36" R.C.PIPE CLASS III 613(B) 0494 LF 6.000 6.000   6.000 $100.00 $0.00 $600.00
0059 48" R.C.PIPE CLASS III 613(B) 0496 LF 400.000 195.000   195.000 $120.00 $0.00 $23,400.00
0060 28" X 18" R.C.PIPE ARCH CLASS A-III 613(B) 4496 LF 91.000 136.000   136.000 $100.00 $0.00 $13,600.00
0061 58" X 36" R.C.PIPE ARCH CLASS A-III 613(B) 4500 LF 35.000 35.000   35.000 $195.00 $0.00 $6,825.00
0062 22" X 13" R.C.PIPE ARCH CLASS A-IV 613(B) 4511 LF 28.000 28.000   28.000 $85.00 $0.00 $2,380.00
0063 TYPE A4 CULVERT END TREATMENT 613(CC) 7186 EA 25.000 21.000   21.000 $580.00 $0.00 $12,180.00
0064 TYPE B4 CULVERT END TREATMENT 613(CC) 7187 EA 14.000 16.000   16.000 $700.00 $0.00 $11,200.00
0065 TYPE C4 CULVERT END TREATMENT 613(CC) 7188 EA 2.000 2.000   2.000 $1,000.00 $0.00 $2,000.00
0066 24" CORR. GALV. STEEL PIPE 613(D) 0690 LF 232.000 472.000   472.000 $32.50 $0.00 $15,340.00
0067 36" CORR. GALV. STEEL PIPE 613(D) 0692 LF 183.000 233.000   233.000 $38.00 $0.00 $8,854.00
0068 21" X 15" CORR. GALV. STEEL PIPE ARCH 613(D) 4527 LF 141.000 141.000   141.000 $36.00 $0.00 $5,076.00
0069 18" PREFAB. CULVERT END SECTION, ROUND 613(M) 5726 EA 4.000 3.000   3.000 $625.00 $0.00 $1,875.00
0070 24" PREFAB. CULVERT END SECTION, ROUND 613(M) 5730 EA 1.000 1.000   1.000 $800.00 $0.00 $800.00
0071 30" PREFAB. CULVERT END SECTION, ROUND 613(M) 5732 EA 3.000 1.000   1.000 $900.00 $0.00 $900.00
0072 36" PREFAB. CULVERT END SECTION, ROUND 613(M) 5734 EA 1.000 1.000   1.000 $1,350.00 $0.00 $1,350.00
0073 TYPE A4 SLOPED CONCRETE END SECTION 613(MM) 7500 EA 2.000 0.000   0.000 $1,000.00 $0.00 $0.00
0074 TYPE B4 SLOPED CONCRETE END SECTION 613(MM) 7501 EA 2.000 0.000   0.000 $1,500.00 $0.00 $0.00
0075 TYPE C4 SLOPED CONCRETE END SECTION 613(MM) 7502 EA 4.000 4.000   4.000 $2,500.00 $0.00 $10,000.00
0076 TYPE F4 SLOPED CONCRETE END SECTION 613(MM) 7505 EA 4.000 8.000   8.000 $4,000.00 $0.00 $32,000.00
0077 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   1.000 $35,000.00 $0.00 $35,000.00
0078 REMOVAL OF HEADWALL 619(B) 0291 EA 2.000 2.000   2.000 $1,500.00 $0.00 $3,000.00
0079 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 598.000 598.000   598.000 $5.50 $0.00 $3,289.00
0080 REMOVAL OF CONCRETE PAVEMENT 619(B) 4727 SY 408.000 408.000   408.000 $5.50 $0.00 $2,244.00
0081 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 33,463.000 33,463.000   33,463.000 $1.00 $0.00 $33,463.00
0082 REMOVAL OF CURB 619(B) 4791 LF 244.000 244.000   244.000 $4.50 $0.00 $1,098.00
0083 GATES-STYLE CLF (6'HIGH X 4'LONG) 624(E) 5950 EA 2.000 2.000   0.000 $1,500.00 $0.00 $0.00
8001 30" R.C.PIPE CLASS IV 613(B) 0584 LF 0.000 115.000   115.000 $148.91 $0.00 $17,124.77
8002 48" R.C.PIPE CLASS IV 613(B) 0587 LF 0.000 90.000   90.000 $212.55 $0.00 $19,129.64
8003 48" R.C.PIPE CLASS V 613(B) 0599 LF 0.000 115.000   115.000 $256.11 $0.00 $29,453.34
8004 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 1091 LF 0.000 8,500.000 1,337.000 8,772.000 $10.27 $13,730.99 $90,088.44
8005 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 1096 LF 0.000 120.000   30.000 $10.27 $0.00 $308.10
8006 OUTLET LATERAL HEADWALL 653(C) 5946 EA 0.000 5.000   5.000 $475.00 $0.00 $2,375.00
8008 (SP)FENCE-STYLE SWF (5 BARBED WIRE) 624(C) 4459 LF 0.000 13,500.000   10,363.000 $4.19 $0.00 $43,420.97
8014 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000   1.000 $89,166.61 $0.00 $89,166.61
8015 DEDUCTION FOR FAILING MATERIAL 105 2100 LSUM 0.000 1.000   1.000 $-48,772.05 $0.00 $-48,772.05
8016 DEDUCTION FOR FAILING MATERIAL 105 2100 LSUM 0.000 1.000   1.000 $-9,123.47 $0.00 $-9,123.47
8018 AGGREGATE BASE 303 0192 CY 0.000 23,463.770   23,463.770 $31.42 $0.00 $737,231.65
8019 DEDUCTION FOR FAILING MATERIAL 105 2100 LSUM 0.000 1.000   1.000 $-153.39 $0.00 $-153.39
8022 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 0.000 35.000 0.010 33.440 $40.00 $0.40 $1,337.60
8023 42" F-SHAPED PARAPET 504(F) 6190 LF 0.000 411.000   412.500 $127.15 $0.00 $52,449.38
8024 CLASS AA CONCRETE 509(A) 0319 CY 0.000 15.000 -9.000 7.270 $824.25 $-7,418.25 $5,992.30
8025 EPOXY COATED REINFORCING STEEL 511(B) 4269 LB 0.000 21,343.000 -1,107.000 20,236.000 $1.06 $-1,173.42 $21,450.16
8026 2'-8" COMB.CRB.& GUT.(6" BARRIER) 609(B) 1525 LF 0.000 110.000 2.100 118.400 $20.00 $42.00 $2,368.00
8027 4" CONCRETE SIDEWALK 610(A) 0602 SY 0.000 440.000 0.210 447.500 $70.20 $14.74 $31,414.50
8028 REMOVAL OF CURB AND GUTTER 619(B) 4726 LF 0.000 41.000   41.000 $10.00 $0.00 $410.00
8029 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 0.000 46.000 14.250 60.470 $12.00 $171.00 $725.64
8030 REMOVAL OF SIDEWALK 619(B) 4792 SY 0.000 297.000 0.240 297.240 $8.00 $1.92 $2,377.92
8031 SAWING PAVEMENT 619(C) 0924 LF 0.000 135.000   123.000 $4.00 $0.00 $492.00
8033 (PL)RE-MOBILIZATION 641 1400 EA 0.000 1.000   1.000 $4,500.00 $0.00 $4,500.00
Subtotals For Category     0100/ROADWAY    $4,232.82 $7,422,500.96
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0200/BRIDGE A
0084 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 2,070.000 2,070.000   2,070.000 $12.50 $0.00 $25,875.00
0085 SUBSTRUCTURE EXCAVATION ROCK 501(C) 1308 CY 240.000 240.000   240.000 $50.00 $0.00 $12,000.00
0086 GRANULAR BACKFILL 501(F) 6352 CY 290.000 290.000   290.000 $37.91 $0.00 $10,993.90
0087 PRESTRESSED CONCRETE BEAMS (TYPE IV) 503(A) 1313 LF 3,441.000 3,441.000   3,441.000 $182.50 $0.00 $627,982.50
0088 APPROACH SLAB 504(A) 1304 SY 452.500 452.500   452.500 $157.50 $0.00 $71,268.75
0089 42" F-SHAPED PARAPET 504(F) 6190 LF 865.000 865.000   865.000 $90.00 $0.00 $77,850.00
0090 STRUCTURAL STEEL 506(A) 1322 LB 4,350.000 4,350.000   4,350.000 $4.00 $0.00 $17,400.00
0091 CLASS AA CONCRETE 509(A) 1326 CY 1,192.500 1,192.500   1,192.500 $450.00 $0.00 $536,625.00
0092 CLASS A CONCRETE 509(B) 1328 CY 2,579.900 2,579.900   2,579.900 $400.00 $0.00 $1,031,960.00
0093 SLOPE WALL (5") 510(C) 6138 SY 1,290.000 1,290.000   1,290.000 $80.00 $0.00 $103,200.00
0094 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 560,240.000 560,240.000   560,240.000 $0.80 $0.00 $448,192.00
0095 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 848.000 848.000   848.000 $40.00 $0.00 $33,920.00
0096 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 848.000 848.000   815.000 $15.00 $0.00 $12,225.00
0097 PILE LOAD TEST (DYNAMIC) 514(F) 6354 EA 32.000 32.000   32.000 $750.00 $0.00 $24,000.00
0098 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 3,625.000 3,625.000   3,625.000 $3.00 $0.00 $10,875.00
0099 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 680.000 680.000   680.000 $3.00 $0.00 $2,040.00
0100 (SP) SEALER RESIN 523(B) 6560 GAL 7.500 7.500   7.500 $100.00 $0.00 $750.00
0101 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 18.000 18.000   18.000 $500.00 $0.00 $9,000.00
0102 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 72.000 72.000   72.000 $1,000.00 $0.00 $72,000.00
0103 (PL)ELASTOMERIC BEARING PADS 535 6282 EA 72.000 72.000   72.000 $425.00 $0.00 $30,600.00
0104 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 360.000 360.000   360.000 $15.00 $0.00 $5,400.00
0105 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 40.000 40.000   40.000 $20.00 $0.00 $800.00
8010 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 1418 LF 0.000 200.000 -48.000 152.000 $18.90 $-907.20 $2,872.80
8011 THRIE BEAM BRIDGE CONNECTION-TYPE A 623(E) 7114 EA 0.000 2.000   2.000 $1,758.75 $0.00 $3,517.50
8012 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 0.000 2.000   2.000 $2,362.50 $0.00 $4,725.00
8017 DEDUCTION FOR CONCRETE PAVING 414 5172 LSUM 0.000 1.000   1.000 $-2,628.80 $0.00 $-2,628.80
Subtotals For Category     0200/BRIDGE A    $-907.20 $3,173,443.65
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0201/BRIDGE B
0106 UNCLASSIFIED EXCAVATION 202(A) 1301 CY 310.000 310.000   310.000 $3.00 $0.00 $930.00
0107 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 1306 CY 100.000 100.000   100.000 $25.00 $0.00 $2,500.00
0108 CLASS AA CONCRETE 509(A) 1326 CY 238.500 238.500   238.500 $400.00 $0.00 $95,400.00
0109 CLASS C CONCRETE 509(D) 1331 CY 28.200 28.200   28.200 $325.00 $0.00 $9,165.00
0110 REINFORCING STEEL 511(A) 1332 LB 37,480.000 37,480.000   37,480.000 $0.70 $0.00 $26,236.00
0111 TYPE I-A PLAIN RIPRAP 601(A-1)1353 TON 130.000 130.000 11.540 191.430 $47.50 $548.15 $9,092.93
0112 TYPE I-A FILTER BLANKET 601(A-2)1355 TON 35.000 35.000   35.740 $42.50 $0.00 $1,518.95
Subtotals For Category     0201/BRIDGE B    $548.15 $144,842.88
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0310/TRAFFIC SIGNING AND STRIPING
0113 STRUCTURAL CONCRETE 804(A) 2915 CY 4.680 8.640   8.640 $415.00 $0.00 $3,585.60
0114 REINFORCING STEEL 804(B) 2916 LB 800.000 1,470.000   1,470.000 $1.55 $0.00 $2,278.50
0115 SHEET ALUMINUM SIGNS 850(A) 8110 SF 283.360 467.980   467.980 $14.55 $0.00 $6,809.11
0116 EXTRUDED ALUMINUM PANEL SIGNS 850(B) 8112 SF 334.000 639.500   639.500 $19.75 $0.00 $12,630.13
0117 4"@13 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3206 LF 73.000 103.000   103.000 $25.00 $0.00 $2,575.00
0118 6"@20 GALV.STEEL WIDE FLANGE BEAM POST 851(A) 3208 LF 81.000 144.500   144.500 $29.00 $0.00 $4,190.50
0119 2 1/2"@5.79 GALV.STEEL PIPE POST 851(B) 3217 LF 30.000 30.000   32.000 $21.00 $0.00 $672.00
0120 1 3/4" SQUARE TUBE POST 851(C) 8321 LF 130.000 130.000   130.000 $6.25 $0.00 $812.50
0121 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 547.000 768.500   768.500 $7.30 $0.00 $5,610.05
0122 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 46,803.000 65,449.000   65,449.000 $0.68 $0.00 $44,505.32
0123 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 19.000 19.000   24.000 $90.00 $0.00 $2,160.00
0124 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 9.000 9.000   12.000 $115.00 $0.00 $1,380.00
0125 (PL)IMPACT ATTENUATOR 871 8325 EA 4.000 4.000   4.000 $20,000.00 $0.00 $80,000.00
0126 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8722 LSUM 1.000 1.000   1.000 $1,100.00 $0.00 $1,100.00
8009 (PL)REMOVAL OF OVERHEAD SIGN STRUCTURE 890(A) 8716 EA 0.000 1.000   1.000 $2,500.00 $0.00 $2,500.00
8020 (PL)RE-MOBILIZATION 641 1400 EA 0.000 1.000   1.000 $945.00 $0.00 $945.00
Subtotals For Category     0310/TRAFFIC SIGNING AND STRIPING    $0.00 $171,753.71
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0320/TRAFFIC LIGHTING
0127 DRILLED SHAFTS 48" DIAMETER 516(A) 6094 LF 81.000 81.000   81.000 $675.00 $0.00 $54,675.00
0128 4" CONCRETE SIDEWALK 610(A) 0602 SY 105.000 105.000   105.000 $52.00 $0.00 $5,460.00
0129 1 1/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED 802(A) 8306 LF 200.000 200.000   297.500 $13.55 $0.00 $4,031.13
0130 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED 802(B) 8342 LF 2,100.000 2,100.000   1,858.500 $5.20 $0.00 $9,664.20
0131 JUNCTION BOX(6" X 6" X 4") 802(D) 8370 EA 1.000 1.000   1.000 $390.00 $0.00 $390.00
0132 PULL BOX(SIZE I) 803 8065 EA 10.000 10.000   9.000 $325.00 $0.00 $2,925.00
0133 UNDERPASS LUMINIARE 809(B) 8098 EA 8.000 8.000   8.000 $800.00 $0.00 $6,400.00
0134 HIGH MAST LUMINAIRE 809(E) 8103 EA 19.000 19.000   19.000 $950.00 $0.00 $18,050.00
0135 SERVICE POLE 810(A) 3118 EA 2.000 2.000   2.000 $3,250.00 $0.00 $6,500.00
0136 1/C NO.4 ELECTRICAL CONDUCTOR 811 8038 LF 2,545.000 2,545.000 0.000 4,398.000 $3.25 $0.00 $14,293.50
0137 110' HIGH MAST POLE(G.STL.) 812 8056 EA 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
0138 120' HIGH MAST POLE(G.STL.) 812 8060 EA 4.000 4.000   4.000 $11,500.00 $0.00 $46,000.00
0139 HIGH MAST LOWERING DEVICE TYPE I 813 8074 EA 5.000 5.000   5.000 $7,000.00 $0.00 $35,000.00
8013 (SP)TEMPORARY ROADWAY LIGHTING ASSEMBLY 880(M) 8340 LMDY 0.000 1,041.000 122.000 1,010.000 $27.00 $3,294.00 $27,270.00
8021 CONSTRUCTION MISCELLANEOUS 104 0700 LSUM 0.000 1.000   1.000 $9,790.20 $0.00 $9,790.20
Subtotals For Category     0320/TRAFFIC LIGHTING    $3,294.00 $250,449.03
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0330/TRAFFIC OPERATIONS
0140 RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN 627(O) 4410 LF 2,050.000 2,050.000   80.000 $3.50 $0.00 $280.00
0141 RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER 627(P) 4425 LF 970.000 970.000   740.000 $10.00 $0.00 $7,400.00
0142 (PL)TRAFFIC SIGNAL SPAN WIRE EQUIPMENT 823 8482 LSUM 1.000 1.000   1.000 $22,500.00 $0.00 $22,500.00
0143 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 66,920.000 66,920.000   52,651.000 $0.12 $0.00 $6,318.12
0144 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 856(G) 8887 EA 5,000.000 5,000.000   100.000 $0.52 $0.00 $52.00
0145 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 30,000.000 30,000.000   6,776.000 $0.10 $0.00 $677.60
0146 (PL)SAND FILLED IMPACT ATTENUATION SYSTEM 870(A) 8490 SD 580.000 580.000   436.000 $5.20 $0.00 $2,267.20
0147 (PL)CONST.ZONE IMPACT ATTEN. 871 8705 SD 30.000 30.000   0.000 $26.00 $0.00 $0.00
0148 (PL)TRUCK MOUNTED ATTENUATOR 876(C) 8482 SD 30.000 30.000   0.000 $78.00 $0.00 $0.00
0149 ARROW DISPLAY(TYPE C) 880(A) 8812 SD 30.000 30.000   6.000 $26.00 $0.00 $156.00
0150 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 14,290.000 14,290.000 36.000 24,467.000 $0.22 $7.92 $5,382.74
0151 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 7,860.000 7,860.000 12.000 17,358.000 $0.43 $5.16 $7,463.94
0152 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 11,850.000 33,049.000 48.000 33,097.000 $1.05 $50.40 $34,751.85
0153 BARRICADES(TYPE III) 880(C) 8842 SD 5,190.000 5,190.000 24.000 12,346.000 $0.68 $16.32 $8,395.28
0154 WING BARRICADES 880(C) 8848 SD 4,200.000 4,200.000 12.000 3,870.000 $0.27 $3.24 $1,044.90
0155 VERTICAL PANELS 880(D) 8854 SD 24,565.000 24,565.000   23,823.000 $0.11 $0.00 $2,620.53
0156 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 17,865.000 17,865.000   44,094.000 $0.22 $0.00 $9,700.68
0157 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 53,215.000 53,215.000   91,027.000 $0.02 $0.00 $1,820.54
0158 DRUMS 880(F) 8878 SD 28,650.000 28,650.000   74,362.000 $0.21 $0.00 $15,616.02
0159 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 200.000 200.000 8.000 61.000 $55.00 $440.00 $3,355.00
0160 PORT.CHANGEABLE MESSAGE SIGN 882(B) 8306 SD 1,340.000 1,340.000   706.000 $13.00 $0.00 $9,178.00
8032 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 0.000 1.000   1.000 $1,000.00 $0.00 $1,000.00
Subtotals For Category     0330/TRAFFIC OPERATIONS    $523.04 $139,980.40
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0600/STAKING
0161 STAKING 642 0098 LSUM 1.000 1.000   1.000 $130,000.00 $0.00 $130,000.00
Subtotals For Category     0600/STAKING    $0.00 $130,000.00
Fed/State Project Number:    NHY-014N(019)SS Project:    17387(04) Category:    0640/CONSTRUCTION
0162 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   1.000 $5,000.00 $0.00 $5,000.00
0163 FIELD OFFICE 640 1426 EA 1.000 1.000   1.000 $32,500.00 $0.00 $32,500.00
0164 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $345,000.00 $0.00 $345,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $382,500.00
Subtotals For Project NHY-014N(019)SS /17387(04) $7,690.81 $11,815,470.63