Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    11/09/2010
Contract ID: 090495   Estimate Number: 0004     Contract No: 510183
Residency: EDMOND (04400)   Estimate Type: Progressive     Account No: 400400

Project Number(s): STP-STIM(403)AG
Primary Job Piece No: 26741(04)
Contract Description: RESURFACE (ASPHALT) CITY STREET: S. MUSTANG RD FROM SW 89TH STREET, EXT NORTH. N. SARA RD FROM SH-152, EXT NORTH. PROJECT LENGTH = 1.90 MILES.
Primary County: CANADIAN              
Name of Road: CITY STREET              
Prime Contractor: MARKWELL PAVING COMPANY, INC.              
    P.O. BOX 82005              
    OKLAHOMA CITY , OK   73148              
Surety Company: LIBERTY MUTUAL INSURANCE COMPANY              

Date Let: 07/23/2009 NTP Effective Date: 10/30/2009 Pay Period: 10/01/2010  TO  10/31/2010
Date Awarded: 08/03/2009 Date Work Began: 10/16/2009 Original Contract Time: N/A
Date Contract Executed: 08/18/2009 Date Time Stopped: 10/02/2010 Current Time Charged: N/A
Date NTP Issued: 08/19/2009 Completion Date: 10/02/2010 Current Time Allowed: N/A
General Liability Expires: 04/01/2011 Workman's Comp Expires: 04/01/2011 Percent Time Used: N/A
Specification Year: 1999 FIXED COMPLETION DATE: 10/30/2010 Date Approved:

Current Contract Amount: $294,688.75 Total to Date Prev to Date This Estimate
Bid Amount: $282,444.00 Participating: $287,919.31 $283,140.72 $4,778.59
Percent Complete: 97.70 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $6,769.44 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $-5,475.31 Total Earnings: $287,919.31 $283,140.72 $4,778.59
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $287,919.31 $283,140.72 $4,778.59
Other Adjustments: $0.00 $-696.73 $696.73
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $287,919.31 $282,443.99 $5,475.32

Estimate Adjustment Detail

Contract ID: 090495   Estimate Number: 0004     Primary JP: 26741(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Completion Date Revision Approved 06/28/2010 243.0 $0.00
002 Time Adjustment / Extend Project Limits Approved 08/24/2010 121.0 $0.00
003 Asphalt Overrun Approved 11/05/2010 0.0 $12,244.75


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0002 -10.0 $500.00 $-5,000.00
System Application of Liquidated Damages 0003 --10 $500.00 $5,000.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
Withhold to Funds Avail(Prog. Est. Only) 0003 $-492.72
Withhold to Funds Avail(Prog. Est. Only) 0004 $492.72
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
26741(04) 0002 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $76.32
26741(04) 0002 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) * Asphalt Binder Adjustment 0004 1.00 $-76.32 $-76.32
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $1,042.60
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Material Discrepancy Adjustments 0001 -2,250.00 $68.00 $-153,000.00
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Material Discrepancy Adjustments 0002 2,250.00 $68.00 $153,000.00
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0002 0.00 $0.00 $0.40
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Material Discrepancy Adjustments 0002 -85.63 $68.00 $-5,822.84
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) Asphalt Binder Adjustment 0003 0.00 $0.00 $4,499.51
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Material Discrepancy Adjustments 0004 1.00 $5,822.84 $5,822.84
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0004 1.00 $-1,042.60 $-1,042.60
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0004 1.00 $-0.40 $-0.40
26741(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) * Asphalt Binder Adjustment 0004 1.00 $-4,499.51 $-4,499.51
Subtotals For Line Item Adjustments $0.00
* = User applied Line Item Adjustments


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090495   Estimate Number: 0004     Primary JP: 26741(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(403)AG Project:    26741(04) Category:    0100/ROADWAY
0001 TACK COAT 407 0250 GAL 4,380.000 4,380.000 350.000 2,450.000 $1.00 $350.00 $2,450.00
0002 (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) 411(S3) 6210 TON 200.000 200.000 0.000 199.110 $60.00 $0.00 $11,946.60
0003 (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) 411(S4) 5955 TON 3,250.000 3,433.070 0.000 3,433.070 $68.00 $0.00 $233,448.76
0004 COLD MILLING PAVEMENT 417 5267 SY 28,910.000 28,910.000 543.670 18,969.510 $0.55 $299.02 $10,433.23
0005 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 45,950.000 45,950.000 13,132.060 48,014.340 $0.33 $4,333.58 $15,844.73
0006 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $4,000.00 $0.00 $4,000.00
8001 ASPHALT BINDER PRICE ADJUSTMENT 109 1150 LSUM 0.000 1.000 1.000 1.000 $5,618.83 $5,618.83 $5,618.83
8002 DEDUCTION FOR FAILING MATERIAL 105 2100 LSUM 0.000 1.000 1.000 1.000 $-5,822.84 $-5,822.84 $-5,822.84
Subtotals For Category     0100/ROADWAY    $4,778.59 $277,919.31
Fed/State Project Number:    STP-STIM(403)AG Project:    26741(04) Category:    0640/CONSTRUCTION
0007 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $10,000.00 $0.00 $10,000.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $10,000.00
Subtotals For Project STP-STIM(403)AG /26741(04) $4,778.59 $287,919.31