Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    07/16/2009
Contract ID: 090456   Estimate Number: 0001     Contract No: 411331
Residency: SAND SPRINGS (08400)   Estimate Type: Progressive     Account No: 400800

Project Number(s): STP-STIM(290)3R
Primary Job Piece No: 26709(04)
Contract Description: RESURFACE (ASPHALT) US-60: BEGIN AT THE KAY C/L, EXTEND EAST. PROJECT LENGTH = 4.44 MILES
Primary County: OSAGE              
Name of Road: US-60              
Prime Contractor: EVANS & ASSOCIATES CONSTRUCTION CO., INC.              
    P. O. BOX 30              
    PONCA CITY , OK   74602              
Surety Company: MID-CONTINENT CASUALTY COMPANY              

Date Let: 05/14/2009 NTP Effective Date: 07/06/2009 Pay Period: 06/05/2009  TO  07/15/2009
Date Awarded: 05/19/2009 Date Work Began: 07/01/2009 Original Contract Time: 30
Date Contract Executed: 06/03/2009 Date Time Stopped: Current Time Charged: 15.00
Date NTP Issued: 06/05/2009 Completion Date: Current Time Allowed: 30.00
General Liability Expires: 05/01/2009 Workman's Comp Expires: 05/01/2009 Percent Time Used: 50.00 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $1,313,447.68 Total to Date Prev to Date This Estimate
Bid Amount: $1,313,447.68 Participating: $975,088.18 $0.00 $975,088.18
Percent Complete: 74.02 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $341,239.16 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $341,239.16 Total Earnings: $975,088.18 $0.00 $975,088.18
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $975,088.18 $0.00 $975,088.18
Other Adjustments: $-2,879.66 $0.00 $-2,879.66
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $972,208.52 $0.00 $972,208.52

Estimate Adjustment Detail

Contract ID: 090456   Estimate Number: 0001     Primary JP: 26709(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
26709(04) 0002 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-1,017.95
26709(04) 0012 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-689.34
26709(04) 0019 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-597.13
26709(04) 0024 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-575.24
Subtotals For Line Item Adjustments $-2,879.66


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090456   Estimate Number: 0001     Primary JP: 26709(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(290)3R Project:    26709(04) Category:    0100/ROADWAY STP-STIM(290)3R
0001 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 420.000 420.000   0.000 $20.68 $0.00 $0.00
0002 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 6,062.000 6,062.000 5,770.670 5,770.670 $58.32 $336,545.47 $336,545.47
0003 COLD MILLING PAVEMENT 417 5267 SY 1,478.000 1,478.000 3,238.910 3,238.910 $6.59 $21,344.42 $21,344.42
0004 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 1,760.000 1,760.000   0.000 $15.06 $0.00 $0.00
0005 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 4.000 4.000   0.000 $2,750.00 $0.00 $0.00
0006 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 39,328.000 39,328.000   0.000 $0.38 $0.00 $0.00
0007 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 4.000 4.000   0.000 $130.00 $0.00 $0.00
0008 TRAFFIC STRIPE(PLASTIC)(WORDS) 855(B) 8821 EA 1.000 1.000   0.000 $160.00 $0.00 $0.00
0009 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.250 $3,867.00 $966.75 $966.75
0010 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 360.000 360.000   0.000 $115.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY STP-STIM(290)3R    $358,856.64 $358,856.64
Fed/State Project Number:    STP-STIM(290)3R Project:    26709(04) Category:    0101/ROADWAY ADD ALT 1 STP-STIM(290)3R
0011 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 300.000 300.000   0.000 $20.68 $0.00 $0.00
0012 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 4,144.000 4,144.000 3,907.800 3,907.800 $58.32 $227,902.90 $227,902.90
0013 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 1,760.000 1,760.000   0.000 $15.06 $0.00 $0.00
0014 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 4.000 4.000   0.000 $2,750.00 $0.00 $0.00
0015 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 26,000.000 26,000.000   0.000 $0.38 $0.00 $0.00
0016 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 4.000 4.000   0.000 $130.00 $0.00 $0.00
0017 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.250 $1,000.00 $250.00 $250.00
Subtotals For Category     0101/ROADWAY ADD ALT 1 STP-STIM(290)3R    $228,152.90 $228,152.90
Fed/State Project Number:    STP-STIM(290)3R Project:    26709(04) Category:    0102/ROADWAY ADD ALT 2 STP-STIM(290)3R
0018 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 300.000 300.000   0.000 $20.68 $0.00 $0.00
0019 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 4,201.000 4,201.000 3,385.080 3,385.080 $58.32 $197,417.87 $197,417.87
0020 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 26,000.000 26,000.000   0.000 $0.38 $0.00 $0.00
0021 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 4.000 4.000   0.000 $130.00 $0.00 $0.00
0022 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.250 $1,000.00 $250.00 $250.00
Subtotals For Category     0102/ROADWAY ADD ALT 2 STP-STIM(290)3R    $197,667.87 $197,667.87
Fed/State Project Number:    STP-STIM(290)3R Project:    26709(04) Category:    0103/ROADWAY ADD ALT 3 STP-STIM(290)3R
0023 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 309.000 309.000   0.000 $20.68 $0.00 $0.00
0024 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 4,555.000 4,555.000 3,260.970 3,260.970 $58.32 $190,179.77 $190,179.77
0025 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 26,877.000 26,877.000   0.000 $0.38 $0.00 $0.00
0026 TRAFFIC STRIPE(PLASTIC)(ARROWS) 855(B) 8818 EA 4.000 4.000   0.000 $130.00 $0.00 $0.00
0027 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.250 0.250 $924.00 $231.00 $231.00
Subtotals For Category     0103/ROADWAY ADD ALT 3 STP-STIM(290)3R    $190,410.77 $190,410.77
Subtotals For Project STP-STIM(290)3R /26709(04) $975,088.18 $975,088.18