Contract ID: | 090365 | Estimate Number: | 0001 | Contract No: | 411334 | |||
Residency: | CIRCUIT ENGR. DISTRICT # 7 (05005) | Estimate Type: | Progressive | Account No: | 434500 | |||
Project Number(s): | BRF-STIM(220)CO | ||||||||||||
Primary Job Piece No: | 22359(04) | ||||||||||||
Contract Description: | BRIDGE AND APPROACHES COUNTY ROAD(EW-100): OVER BARNITZ CREEK, 4.0 MILES WEST AND 3.5 MILES NORTH OF CLINTON. PROJECT LENGTH = 0.215 MILES | ||||||||||||
Primary County: | CUSTER | ||||||||||||
Name of Road: | COUNTY ROAD | ||||||||||||
Prime Contractor: | SEWELL BROS., INC. | ||||||||||||
1220 E. MAIN | |||||||||||||
CORDELL , OK 73632 | |||||||||||||
Surety Company: | WESTFIELD INSURANCE COMPANY | ||||||||||||
Date Let: | 05/14/2009 | NTP Effective Date: | 08/03/2009 | Pay Period: | 06/05/2009 TO 09/30/2009 |
Date Awarded: | 05/19/2009 | Date Work Began: | 08/03/2009 | Original Contract Time: | 90 |
Date Contract Executed: | 06/03/2009 | Date Time Stopped: | Current Time Charged: | 59.00 | |
Date NTP Issued: | 06/05/2009 | Completion Date: | Current Time Allowed: | 125.00 | |
General Liability Expires: | 07/01/2010 | Workman's Comp Expires: | 07/01/2010 | Percent Time Used: | 47.20 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $470,544.17 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $470,544.17 | Participating: | $34,738.60 | $0.00 | $34,738.60 | ||
Percent Complete: | 7.38 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $435,805.57 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $435,805.57 | Total Earnings: | $34,738.60 | $0.00 | $34,738.60 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $34,738.60 | $0.00 | $34,738.60 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $34,738.60 | $0.00 | $34,738.60 |
Contract ID: | 090365 | Estimate Number: | 0001 | Primary JP: | 22359(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
No change orders have been created for this contract. |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 090365 | Estimate Number: | 0001 | Primary JP: | 22359(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: BRF-STIM(220)CO | Project: 22359(04) | Category: 0100/ROADWAY | ||||||||
0001 | EARTHWORK | 202(G) 0185 | LSUM | 1.000 | 1.000 | 0.400 | 0.400 | $50,000.00 | $20,000.00 | $20,000.00 |
0002 | TEMPORARY SILT FENCE | 223 2801 | LF | 1,975.000 | 1,975.000 | 2,279.300 | 2,279.300 | $2.00 | $4,558.60 | $4,558.60 |
0003 | SOLID SLAB SODDING | 230(A) 2806 | SY | 13,300.000 | 13,300.000 | 0.000 | $1.70 | $0.00 | $0.00 | |
0004 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 2.900 | 2.900 | 0.000 | $450.00 | $0.00 | $0.00 | |
0005 | TRAFFIC BOUND SURFACE COURSE TYPE E | 403(E) 0225 | TON | 640.000 | 640.000 | 0.000 | $24.00 | $0.00 | $0.00 | |
0006 | CLASS C CONCRETE | 509(D) 0325 | CY | 10.000 | 10.000 | 0.000 | $300.00 | $0.00 | $0.00 | |
0007 | TYPE B4 CULVERT END TREATMENT | 613(CC) 7187 | EA | 2.000 | 2.000 | 0.000 | $900.00 | $0.00 | $0.00 | |
0008 | 28" X 20" CORR. GALV. STEEL PIPE ARCH | 613(D) 4528 | LF | 60.000 | 60.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY | $24,558.60 | $24,558.60 | ||||||||
Fed/State Project Number: BRF-STIM(220)CO | Project: 22359(04) | Category: 0200/BRIDGE 'A' | ||||||||
0009 | SUBSTRUCTURE EXCAVATION COMMON | 501(B) 1307 | CY | 84.000 | 84.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0010 | UNCLASSIFIED BACKFILL | 501(D) 6353 | CY | 82.000 | 82.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0011 | PRESTRESSED CONCRETE BEAMS (TYPE IV) | 503(A) 1313 | LF | 396.670 | 396.670 | 0.000 | $161.00 | $0.00 | $0.00 | |
0012 | CONCRETE RAIL (TR1) | 504(E) 1380 | LF | 265.000 | 265.000 | 0.000 | $45.00 | $0.00 | $0.00 | |
0013 | STRUCTURAL STEEL | 506(A) 1322 | LB | 1,810.000 | 1,810.000 | 0.000 | $4.00 | $0.00 | $0.00 | |
0014 | CLASS AA CONCRETE | 509(A) 1326 | CY | 77.000 | 77.000 | 0.000 | $550.00 | $0.00 | $0.00 | |
0015 | CLASS A CONCRETE | 509(B) 1328 | CY | 53.800 | 53.800 | 0.000 | $600.00 | $0.00 | $0.00 | |
0016 | REINFORCING STEEL | 511(A) 1332 | LB | 24,649.000 | 24,649.000 | 0.000 | $0.70 | $0.00 | $0.00 | |
0017 | PILES, FURNISHED (HP 10X42) | 514(A) 6010 | LF | 900.000 | 900.000 | 0.000 | $20.00 | $0.00 | $0.00 | |
0018 | PILES, DRIVEN (HP 10X42) | 514(B) 6292 | LF | 900.000 | 900.000 | 0.000 | $15.00 | $0.00 | $0.00 | |
0019 | TYPE I-A PLAIN RIPRAP | 601(A-1)1353 | TON | 3,091.000 | 3,091.000 | 0.000 | $34.00 | $0.00 | $0.00 | |
0020 | TYPE I-A FILTER BLANKET | 601(A-2)1355 | TON | 702.000 | 702.000 | 0.000 | $26.00 | $0.00 | $0.00 | |
0021 | GUARD RAIL ANCHOR UNIT (TYPE II) | 623(F) 6033 | EA | 4.000 | 4.000 | 0.000 | $2,300.00 | $0.00 | $0.00 | |
0022 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.400 | 0.400 | $2,200.00 | $880.00 | $880.00 |
Subtotals For Category 0200/BRIDGE 'A' | $880.00 | $880.00 | ||||||||
Fed/State Project Number: BRF-STIM(220)CO | Project: 22359(04) | Category: 0600/STAKING | ||||||||
0023 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.250 | 0.250 | $3,200.00 | $800.00 | $800.00 |
Subtotals For Category 0600/STAKING | $800.00 | $800.00 | ||||||||
Fed/State Project Number: BRF-STIM(220)CO | Project: 22359(04) | Category: 0640/CONSTRUCTION | ||||||||
0024 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.100 | 0.100 | $10,000.00 | $1,000.00 | $1,000.00 |
0025 | MOBILIZATION | 641 1399 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $15,000.00 | $7,500.00 | $7,500.00 |
Subtotals For Category 0640/CONSTRUCTION | $8,500.00 | $8,500.00 | ||||||||
Subtotals For Project BRF-STIM(220)CO /22359(04) | $34,738.60 | $34,738.60 |